ADAM BAK AND AVA POLANSKY BAK VS. ROBERT AND JANET MCEWAN (L-0394-14 AND L-2255-15, MORRIS COUNTY AND STATEWIDE) (CONSOLIDATED) ( 2020 )


Menu:
  •                                  NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited . R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NOS. A-2088-17T3
    A-2149-17T3
    ADAM BAK and AVA
    POLANSKY BAK,
    Plaintiffs-Appellants,
    v.
    ROBERT and JANET MCEWAN,
    BOB MCEWAN CONSTRUCTION
    CORP., TAMKO BUILDING
    PRODUCTS, TRI-STATE
    INSPECTION SERVICES, LLC,
    JOE MAGGIO CONCRETE &
    MASONRY, DENNIS GRANT
    CONSTRUCTION CO., A & A
    EXTERIORS, INC., GIAMIKE,
    INC.,
    Defendants-Respondents,
    and
    DUNN & DUNN, INC., and
    PELLA WINDOWS,
    Defendants.
    ____________________________
    CUMBERLAND MUTUAL
    INSURANCE COMPANY, INC.,
    Plaintiff,
    v.
    ROBERT and JANET MCEWAN,
    BOB MCEWAN CONSTRUCTION
    CORP., TAMKO BUILDING
    PRODUCTS, TRI-STATE
    INSPECTION SERVICES, LLC,
    DUNN & DUNN, INC.,
    JOE MAGGIO CONCRETE &
    MASONRY, DENNIS GRANT
    CONSTRUCTION CO., A & A
    EXTERIORS, INC., GIAMIKE,
    INC., and PELLA WINDOWS,
    Defendants.
    ADAM BAK and AVA POLANSKY
    BAK,
    Plaintiffs,
    v.
    ROBERT and JANET MCEWAN,
    TAMKO BUILDING
    PRODUCTS, TRI-STATE
    INSPECTION SERVICES, LLC,
    DUNN & DUNN, INC., and
    PELLA WINDOWS,
    Defendants,
    A-2088-17T3
    2
    and
    BOB MCEWAN
    CONSTRUCTION CORP.,
    Defendant-Appellant,
    and
    JOE MAGGIO CONCRETE &
    MASONRY, DENNIS GRANT
    CONSTRUCTION CO., A & A
    EXTERIORS, INC., GIAMIKE, INC.,
    Defendants-Respondents.
    CUMBERLAND MUTUAL
    INSURANCE COMPANY, INC.,
    Plaintiff,
    v.
    ROBERT and JANET MCEWAN,
    BOB MCEWAN CONSTRUCTION
    CORP., TAMKO BUILDING
    PRODUCTS, TRI-STATE
    INSPECTION SERVICES, LLC,
    DUNN & DUNN, INC.,
    JOE MAGGIO CONCRETE &
    MASONRY, DENNIS GRANT
    CONSTRUCTION CO., A & A
    EXTERIORS, INC., GIAMIKE,
    INC., and PELLA WINDOWS,
    Defendants.
    A-2088-17T3
    3
    Argued (A-2088-17) and Submitted (A-2149-17)
    February 6, 2020 – Decided June 24, 2020
    Before Judges Alvarez and DeAlmeida.
    On appeal from the Superior Court of New Jersey, Law
    Division, Morris County, Docket Nos. L-0394-14 and
    L-2255-15.
    Francis A. Kirk argued the cause for appellants Adam
    Bak and Ava Polansky Bak in Docket No. A-2088-17
    (Tesser & Cohen, attorneys; Francis A. Kirk, on the
    briefs).
    Robert W. Bannon, II, argued the cause for respondent
    Bob McEwan Construction Corp. in Docket No. A-
    2088-17 (appellant in Docket No. A-2149-17) (Welby,
    Brady & Greenblatt, LLP, attorneys; Robert W.
    Bannon, II, on the briefs).
    Linton W. Turner, Jr., argued the cause for respondents
    Robert and Janet McEwan in Docket No. A-2088-17
    (Mayfield, Turner, O'Mara & Donnelly, PC, attorneys;
    Linton W. Turner, Jr., on the brief).
    Edward J. Fanning, Jr., argued the cause for respondent
    TAMKO Building Products, Inc. in Docket No. A-
    2088-17 (McCarter & English, LLP, attorneys; Edward
    J. Fanning, Jr., of counsel and on the brief; Ryan A.
    Richman, on the brief).
    Elizabeth F. Lorell argued the cause for respondent Tri-
    State Inspection Services, LLC in Docket No. A-2088-
    17 (Gordon Rees Scully Mansukhani LLP, attorneys;
    Elizabeth F. Lorell and JoAnna M. Doherty, of counsel
    and on the brief).
    A-2088-17T3
    4
    Michael F. Brandman argued the cause for respondent
    Joe Maggio, LLC (Weiler & Brandman, attorneys;
    Michael F. Brandman, on the briefs).
    Frank J. Kunzier argued the cause for respondent
    Dennis Grant d/b/a Dennis Grant Construction
    Company (Zimmerer, Murray, Conyngham & Kunzier,
    attorneys; Frank J. Kunzier, of counsel and on the
    briefs; Sidney E. Goldstein, on the briefs).
    Peter A. Gaudioso argued the cause for respondent
    A&A Exteriors, Inc. (McElroy, Deutsch, Mulvaney &
    Carpenter, LLP, attorneys; Peter A. Gaudioso, of
    counsel and on the briefs).
    Marc A. Deitch argued the cause for respondent
    Giamike, Inc. (Kent & McBride, attorneys; Marc A.
    Deitch, on the brief).
    PER CURIAM
    Plaintiffs Adam Bak and Ava Polansky Bak filed suit against defendants
    Robert and Janet McEwan (the McEwans), the general contractor Bob McEwan
    Construction Corporation (BMCC), the subcontractors involved with the
    construction of the home at issue, and the home inspectors. On November 30,
    2017, the trial judge granted summary judgment to some defendants, and on
    December 1, 2017, granted the remaining motions and cross-motions for
    summary judgment. He also dismissed all cross-claims. We now affirm, except
    that we reverse and remand the order granting defendant Giamike, Inc.
    (Giamike) summary judgment against BMCC, and the orders dismissing
    A-2088-17T3
    5
    BMCC's cross-claims against A&A Exteriors, Inc. (A&A), Giamike, Dennis
    Grant d/b/a Dennis P. Grant Construction Company (Grant), and Joe Maggio,
    LLC (Maggio).
    Plaintiffs bought a home from the McEwans for $2.8 million in August
    2012. The McEwans had occupied the premises since 2005. During Superstorm
    Sandy, the roof was damaged and water leaked into the home, although plaintiffs
    alleged they experienced water leaks prior to the storm. After retaining various
    consultants and experts, they eventually gutted the house, ultimately
    demolishing it in May 2015. They have since commenced construction of a new
    23,000 square foot home.
    I.
    Plaintiffs' complaint alleged multiple causes of action, including
    negligence, breach of warranties, misrepresentation, fraudulent concealment,
    product liability, and consumer fraud against the various defendants. BMCC
    filed cross-claims against its subcontractors for indemnification and
    contribution.
    A-2088-17T3
    6
    On April 15, 2015, plaintiffs 1 filed the first amended complaint against
    the following defendants: the McEwans; BMCC; TAMKO Building Products,
    Inc. (Tamko); Tri-State Inspection Services, LLC (Tri-State); Dunn & Dunn,
    Inc. (Dunn);2 Maggio; Grant; A&A; Giamike; and Pella Windows (Pella). The
    complaint specifically alleged the following counts: breach of contract against
    the McEwans (count one); breach of implied warranty of habitability against the
    McEwans and BMCC (count two); breach of implied warranty of workmanlike
    construction against BMCC (count three); breach of implied warranty of fitness
    for intended purpose against BMCC and the McEwans (count four); negligence
    against all defendants (count five); general contractors' negligence against
    BMCC (count six); home inspector's breach of contract against Tri-State (count
    seven); breach of the covenant of good faith and fair dealing against the
    McEwans (count eight); knowing misrepresentation against the McEwans
    (count nine); negligent misrepresentation against the McEwans (count ten);
    fraudulent concealment in the sale of real estate against the McEwans (count
    eleven); product liability in the form of defective design against BMCC and
    1
    For ease of reference, this opinion will use plaintiffs' first names when
    referring to them individually.
    2
    Plaintiffs represent that Dunn became defunct and did not participate in the
    action.
    A-2088-17T3
    7
    Tamko (count twelve); product liability in the form of manufacturing defect
    against Tamko (count thirteen); product liability in the form of breach of
    warranty against BMCC and Tamko (count fourteen); and a violation of the
    Consumer Fraud Act (CFA), N.J.S.A. 56:8-1 to -224, against all defendants
    (count fifteen).
    II.
    On September 5, 2014, BMCC filed an order to show cause with
    temporary restraints, seeking to enjoin plaintiffs from altering, modifying, or
    demolishing the home.       On September 15, 2014, the court held a case
    management conference, during which plaintiffs advised that demolition was
    scheduled in approximately thirty days but that they would be able to obtain a
    preliminary expert report identifying the structural and other defects. Once the
    report was prepared, defendants could inspect the residence with their respective
    experts. Plaintiffs also represented that, before demolition, they would provide
    timely notice to defendants, who could be present during demolition. Based
    upon that agreement, BMCC withdrew the order to show cause.
    On September 22, 2014, the trial court memorialized the agreement in an
    order. It stated plaintiffs would produce a preliminary expert report and afford
    A-2088-17T3
    8
    defendants a period of ten days after receipt to inspect the property and
    undertake testing.
    Tamko and BMCC filed motions to dismiss for failure to state a claim
    pursuant to Rule 4:6-2(e). On February 6, 2015, the trial court granted Tamko's
    motion in part, dismissing the negligence claim (count five) with prejudice. The
    trial court granted BMCC's motion to dismiss in part, dismissing plaintiffs'
    claims for breach of implied warranty of habitability (count two), defective
    design product liability (count twelve), and product liability breach of warranty
    (count fourteen), with prejudice. The court also dismissed the CFA claim (count
    fifteen) against Tamko and BMCC without prejudice.
    On February 17, 2015, BMCC filed its answer to the complaint. BMCC
    asserted the following cross-claims against co-defendants Maggio, Grant, A&A,
    and Giamike: contractual indemnification, contribution, and common law
    indemnification.     Subcontractor defendants filed answers in July 2015
    (Giamike), May 2015 (Grant), March 2015 (A&A), and July 2014 (Maggio). By
    February 2017, both Pella and Giamike had settled with plaintiffs.
    After the court rescheduled trial for December 11, 2017, twenty-three
    motions and cross-motions were filed by the parties. The motions were filed
    A-2088-17T3
    9
    over a two-month period and were adjourned by the court to November 17, 2017,
    to be heard simultaneously.
    On September 15, 2017, Tamko filed a motion for summary judgment
    seeking dismissal of plaintiffs' remaining claims for alleged breach of warranty,
    design defect, and manufacturing defects.
    On October 3, 2017, Giamike filed a cross-motion for summary judgment
    dismissing all cross-claims asserted by BMCC. It requested oral argument if
    opposition to the motion was submitted.
    BMCC filed opposition to Giamike's cross-motion for summary judgment
    on November 7, 2017, requesting an order denying Giamike summary judgment
    and also awarding BMCC summary judgment that Giamike was required to
    defend and indemnify. A&A, Grant, and Maggio each submitted a letter to the
    court on November 9, 2017, seeking to be heard on Giamike's indemnification
    motion. Defendants had until October 13, 2017, to file all their motions, a
    deadline set with consent of all counsel.
    On October 10, 2017, the McEwans filed motions for summary judgment
    as to liability, plaintiffs' lack of proof of damages, and plaintiffs' failure to
    mitigate damages. On October 31, 2017, BMCC, Maggio, A&A, and Tamko all
    A-2088-17T3
    10
    filed cross-motions joining the McEwans' motions for summary judgment for
    plaintiffs' lack of proof of damages and plaintiffs' failure to mitigate damages.
    Also on October 10, 2017, BMCC filed a motion for sanctions and
    dismissal based on plaintiffs' spoliation of evidence due to the demolition of the
    structure. Tri-State, Maggio, A&A, and Tamko all filed cross-motions joining
    the spoliation motion. On October 13, 2017, BMCC filed a motion for summary
    judgment based on the statute of limitations and other defenses. Maggio and
    A&A both filed cross-motions on October 31, 2017, joining this motion for
    summary judgment as well.
    On October 13, 2017, Tri-State moved for summary judgment on
    plaintiffs' negligence, breach of contract, and CFA claims. Maggio also filed a
    motion for summary judgment.
    On November 6, 2017, plaintiffs' counsel filed a letter with the trial judge
    requesting, with the consent of defendants' counsel, an adjournment until
    December 1, 2017, or December 15, 2017, of the summary judgment motions
    filed by Maggio, Tri-State, and A&A. Also on that date, plaintiffs' counsel filed
    a letter with the civil presiding judge requesting, with consent of all counsel, an
    adjournment of the December 11, 2017, trial date because of the numerous
    pending summary judgment motions. This request was denied.
    A-2088-17T3
    11
    On November 9, 2017, BMCC submitted a letter to the court noting that
    subcontractor defendants sought relief from BMCC's cross-claims in their
    motions seeking summary judgment relief against plaintiffs. BMCC, as a result,
    requested that its cross-claims be adjudicated at trial or during post-trial motion
    practice to allow "for all parties to be heard on the issues related to the" cross-
    claims.
    On November 15, 2017, Giamike's counsel filed a letter confirming that
    the cross-claim indemnification issues would not be heard during oral argument
    scheduled for November 17, 2017. The letter also confirmed that the trial court
    scheduled argument on the indemnification issues for December 1, 2017, and
    that all briefs must be filed by November 27, 2017.
    On November 17, 2017, the trial judge heard oral argument on all opposed
    motions against plaintiffs. Those motions were: Tamko's motion for summary
    judgment; the McEwans' motions for summary judgment based on plaintiffs'
    lack of proof of damages, failure to mitigate, and liability; and BMCC's
    summary judgment motion pursuant to the statute of limitations and other
    defenses. The court reserved decision.
    On November 22, 2017, plaintiffs filed a motion on short notice to adjourn
    the trial date and reschedule the motions for summary judgment that were not
    A-2088-17T3
    12
    fully briefed.   On November 30, 2017, plaintiffs filed a supplemental
    certification in further opposition to the McEwans' motion for summary
    judgment for failure to prove damages.
    Also on November 30, 2017, the trial judge issued a statement of reasons
    granting summary judgment to all defendants, and entered numerous orders on
    November 30, 2017, and December 1, 2017, reflecting his decision, and also
    dismissing all cross-claims.
    III.
    In this appeal, we focus on the summary judgment dismissals anchored in
    plaintiffs' lack of proof of damages, which are dispositive. We summarize the
    relevant undisputed facts and circumstances from the summary judgment record.
    BMCC purchased the property in 2004 with the intention to build a home
    for the McEwans. The 7000 square-foot residence was located on a 5.4 acre lot.
    Construction began that year and the certificate of occupancy issued on August
    4, 2005.
    BMCC was the general contractor for the construction of the home.
    Robert was the sole shareholder of BMCC. As the general contractor, BMCC
    retained the various subcontractors for construction.
    A-2088-17T3
    13
    Grant was the framing subcontractor for the project and performed the
    rough framing and installation of windows. A&A installed stucco on the house
    and detached three-car garage.     Maggio installed the foundation walls and
    footings.
    Giamike installed Tamko roof shingles on the home in September 2004,
    and on the pool shed and detached garage in September 2005. Tamko had a
    limited warranty for the Lamarite roofing shingles used by Giamike. The limited
    warranty was written on each shingle tile, and permitted the original owner to
    transfer the warranty to subsequent purchasers only once and only during the
    first two years after purchase.
    Janet acquired title to the property from BMCC after the completion, and
    she and Robert lived in the home until its August 21, 2012 sale to plaintiffs.
    Plaintiffs purchased the residence from her in May 2012, in "as is" condition for
    $2,850,000.
    On May 24, 2012, prior to the closing, Tri-State inspected the home on
    plaintiffs' behalf. Tri-State was unable to access the roof during the inspection
    because of overcast and rainy weather, plus the "significant pitch" of the roof .
    Additionally, some areas in the attic were inaccessible because they were too
    small. Ava observed portions of the inspection and remembered that Tri-State
    A-2088-17T3
    14
    inspected the bedrooms, kitchen, and foyer. Tri-State did not observe any water
    leakage even though it was raining at the time, but did observe stains from
    previous water leaks in the unfinished attic above the garage.
    During Superstorm Sandy in late October 2012, approximately 100
    shingles were blown off the roof. On November 5, 2012, Tri-Con Construction,
    Ltd. (Tri-Con) issued a proposal to plaintiffs to replace 100 shingles and roof
    caps.      Tri-Con fixed the roof damage using Lamarite shingles left by the
    McEwans. Tri-Con did not observe any other damage to the roof during the
    repairs.
    Plaintiffs filed a homeowner's insurance claim with their carrier, Chubb
    Insurance Co., on November 6, 2012, claiming that Superstorm Sandy damaged
    the roofing shingles, a window, and some siding. Chubb closed the insurance
    claim file in February 2013, because plaintiffs failed to respond to its inquiries .
    On November 7, 2012, Ava called Tamko to open a claim under Tamko's
    limited warranty, and on April 8, 2013, she submitted a written warranty claim.
    Tamko denied plaintiffs' warranty claim on May 5, 2013, because of the two -
    year non-transferability clause.
    Ava alleged that she "notice[d] potential problems" with the home such as
    "a rotten window and several leaks," in September 2012, before Superstorm
    A-2088-17T3
    15
    Sandy. While living in the home, the McEwans only observed water leakage
    through some windows manufactured by Pella in the unfinished attic area of the
    home and from an opening for a lightning rod through the roof. Tri-Con had
    caulked sealant around the lightning rod in 2011, waterproofed the chimney next
    to it, and replaced small pieces of shingle around it.
    In an April 2013 letter, plaintiffs' counsel notified the McEwans' attorney
    of the alleged defects discovered in the home. In a letter dated April 15, 2013,
    the McEwans' counsel informed plaintiffs "for settlement purposes only" that
    the McEwans were "agreeable to purchasing back" the residence from plaintiffs.
    On August 1, 2013, plaintiffs provided a "settlement book," which consisted of
    a list of cost estimates for the correction of the defects. Settlement discussions
    continued into at least January 2014.
    Plaintiffs rented a townhouse to live in while they started work on the
    home. Plaintiffs allege they attempted to remediate the defects and removed
    sheetrock, most of which had been removed by April 21, 2014. They retained
    additional consultants as exposed areas in the home revealed other conditions
    after sheetrock had been removed.
    In a letter from plaintiffs' counsel dated July 14, 2014, plaintiffs notified
    defendants that they decided to demolish the entire residence "in light of the cost
    A-2088-17T3
    16
    and the discovery of pervasive mold," and build a new home on the site.
    However, in November 2017, Ava certified that they decided to demolish the
    home based on a combination of factors that included mold but also included
    "labor intensive" defects, stigma attached to having to disclose the mold, and
    their architect's "unwillingness" to "stand behind a substantially new structure"
    if built on the old foundation.
    Plaintiffs' July 14, 2014, letter also stated that if defendants wanted to
    conduct inspections of the property, they needed to do so before July 25.
    Plaintiffs would give notice when the stucco and stone work would be removed
    from the façade of the house so that anyone who wished to be present could
    observe that phase of the demolition.
    BMCC's counsel and an expert inspected the home on July 21, 2014. In a
    letter dated July 25, 2014, BMCC stated that the expert was not able to
    "adequately and properly assess plaintiffs' claims based on the limited
    information available from plaintiffs," and that a preliminary report specifically
    identifying alleged construction defects would enable adequate assessment of
    the allegations.    BMCC, therefore, requested that plaintiffs refrain from
    demolishing the home until such a report was produced, and its expert had
    adequate time to review it, otherwise defendants would be prejudiced by
    A-2088-17T3
    17
    destruction of evidence.    Maggio's and Tamko's counsel also sent letters
    notifying plaintiffs that demolition of the home would result in sanctions . By
    August 2014, all of the insulation had been removed.
    In May 2015, plaintiffs demolished the entire home, including the
    concrete basement; only the detached three-car garage remained. Plaintiffs'
    architect, Tomasz Adach, created plans for the new 23,044 square foot
    residence. The plans were filed on October 6, 2015.
    IV.
    Plaintiffs' Experts
    Plaintiffs retained numerous experts and consultants to generate reports
    on the alleged construction defects that existed between 2012 and 2015.
    Frederick Larson, with EnviroVision Consultants, Inc., wrote a report dated
    February 24, 2014, addressing mold remediation procedures. He wrote another
    report, dated April 17, 2014, identifying additional areas of mold after the
    removal of building materials that had previously covered studs, insulation, and
    sheathing. He recommended plaintiffs continue to follow the mold remediation
    procedure identified in the initial report. EnviroVision obtained swab surface
    and bulk material samples on June 13, 2014, at the request of plaintiffs after
    "substantial demolition" had occurred.
    A-2088-17T3
    18
    In a June 23, 2014 report, Larson noted additional areas of moisture and
    fungal growth, and again recommended plaintiffs follow the initial remediation
    plan and hire a professional mold remediation company to perform the required
    abatement and cleanup. A final October 24, 2014 report recommended that
    plaintiffs "look[] into the cost and other benefits of partial or complete
    demolition of the house to see if that option [was] economically feasible or
    reasonable when weighing [their] options." Should plaintiffs choose fungal
    remediation, the use of a professional mold remediation company was
    recommended.
    Anthony    Piccione,   from    Building    Evaluations,   Inc.,   created    a
    "Replacement Cost Estimate" dated December 1, 2014, and a revised report
    dated May 18, 2016.       Piccione initially projected reconstruction costs of
    $3,897,902. His revised report increased the costs to $4,050,535.
    SOR Testing Laboratories, Inc. issued findings on laboratory testing of
    the slate roofing on December 3, 2014.          The company concluded that the
    shingles were prematurely weathered and had completed approximately 66% of
    the service life in nine years, estimating that only two or three years of service
    life remained.
    A-2088-17T3
    19
    A real estate appraiser, Jon Brody, from Appraisal Consultants Corp., on
    April 27, 2015, assessed the subject property's land value as $703,000 . In
    valuing the property, Brody assumed that the residence had no economic value
    and that "even though the structures remain[ed] on the site, they [were not]
    valued." He testified at his deposition that plaintiffs had specifically limited the
    scope of his report to valuing only the land.
    Frederick A. Porcello, on behalf of Porcello Engineering, Inc., on April
    12, 2016, identified fifty-six alleged construction defects in writing. During his
    deposition, Porcello noted that his company did not perform a cost analysis of
    the home deficiencies.
    After oral argument, plaintiffs submitted a certification on November 30,
    2017, acknowledging that the Porcello report named "certain defects" that were
    not previously identified "in all likelihood because not all defects could be
    discovered or confirmed until demolition had occurred." Plaintiffs attached two
    more documents: a July 1, 2014, letter from plaintiffs' architect, Adach; and a
    February 5, 2015 report from Todd Heacock, P.E., of Warren Professional
    Services, L.L.C.
    Adach's letter stated that the "numerous deficiencies to be repaired or
    replaced and their value equate a new construction; hence the cost of materials
    A-2088-17T3
    20
    would be the same for new construction as for reconstruction work." He also
    wrote that "the labor costs for the reconstruction would be substantially higher"
    and recommended they build a new home.
    Heacock's report addressed his observations and opinions about the
    alleged construction deficiencies.    He stated that the effort to replace and
    remediate the various issues with the alleged defects, such as roofing, mold, and
    framing, would be labor intensive.
    Defendants' Experts
    BMCC submitted in support of summary judgment an expert report from
    Jonathon P. Dixon & Associates, P.C., Professional Engineering. This report
    addressed numerous documents, including Larson's EnviroVision reports, the
    SOR report, Porcello's construction defects report, Adach's recommendation
    letter, and Piccione's building replacement cost estimate. The report disputed
    the conclusions and recommendations made by plaintiffs' experts.
    Gerry Ross, a Tamko employee, also prepared an expert report on Tamko's
    behalf. Ross's report opined that the roof shingles were improperly installed in
    numerous locations, that the shingles were not defective, there was no
    manufacturing defect that caused leaks, that if leaks did occur they did not result
    A-2088-17T3
    21
    from any design or manufacturing defect in the shingles, and that the shingles'
    design did not pose a hazard for anyone attempting to walk or stand on the roof .
    In June 2016, Mark Sussman of Lasser Sussman Associates, LLC,
    completed a real estate appraisal of the home as of April 15, 2013, at the request
    of all defendants. He opined that the market value of the property as of that
    2013 date was $2,225,000.
    V.
    In a written statement of reasons, the trial court first addressed the statute
    of limitations issue. It rejected plaintiffs' assertion that the discovery rule
    applied to toll the time from which the statute began to run, reasoning that the
    discovery rule did not apply in contract cases. The trial court found that the
    statute of limitations had expired in 2011, six years after substantial completion
    of the home. It concluded that the statute of limitations was an "absolute bar to
    recovery."
    The court next briefly addressed the product liability claims, holding that
    the Products Liability Act (PLA), N.J.S.A. 2A:58C-1 to -11, subsumed those
    claims. With regard to defendants' spoliation claims, the judge found that
    plaintiffs demolished their home after defense counsel notified them of the
    potential spoliation issue. Doing so "absolutely impaired the ability of the
    A-2088-17T3
    22
    defendants to test the alleged 'mold' to counter the plaintiffs' claim that they
    were forced to demolish their home on this basis," and that it was "crucial
    evidence" that went to the heart of the case. The court held that plaintiffs'
    spoliation of the evidence mandated dismissal of the complaint as the sanction.
    Most significantly, the trial court found that plaintiffs failed to establish
    damages, through expert opinion or otherwise. Specifically, plaintiffs presented
    no evidence as to the cost of repairs, the diminution in value of the home as a
    result of any alleged defects, or even that the house was unrepairable. Plaintiffs'
    "testimony alone as to their reason for demolishing the home [was] insufficient
    as a matter of law." The discovery plaintiffs presented did not support "any
    proper measure of damages," as there was no expert opinions as to the impaired
    property value.
    The "so-called quotes to perform work [were] mere hearsay." It held that
    there were "myriad other legal issues presented by the various defendants which
    [had] been reviewed by the court," but that based upon its analysis of the other
    issues discussed in the statement of reasons, it was "abundantly clear that
    summary judgment" was appropriate.
    Thus, the court concluded that plaintiffs failed to present genuine issues
    of material facts. Furthermore, Robert could not be held personally liable to
    A-2088-17T3
    23
    plaintiffs because he was not an owner of the home. BMCC had no liability to
    plaintiffs as a general contractor because it was not legally responsible for its
    subcontractors. Tamko was entitled to summary judgment because plaintiffs
    failed to present any expert evidence as to the shingles' defects, and failed to file
    suit within the time required by the warranty. Tri-State had no liability based
    upon its contract's express provisions.
    VI.
    Now on appeal, plaintiffs assert the following errors in the grant of
    summary judgment:
    POINT I: THE COURT ERRED IN REFUSING TO
    ADJOURN SUMMARY JUDGMENT MOTIONS
    AND THE TRIAL ON CONSENT OF ALL PARTIES.
    POINT II: THE COURT ERRED IN DECIDING
    SUMMARY JUDGMENT MOTIONS WHEN THE
    OPPOSING        PARTIES      REQUESTED
    ADJOURNMENTS ON CONSENT AND ADVISED
    THAT THEY INTENDED TO FILE FACTUAL AND
    LEGAL OPPOSITION.
    POINT III: THE COURT ERRED IN DECIDING
    SUMMARY JUDGMENT MOTIONS THAT WERE
    RETURNABLE LESS THAN 30 DAYS PRIOR TO
    TRIAL, IN CONTRAVENTION OF R. 4:46-1.
    POINT IV: THE COURT ERRED IN GRANTING
    SEVERAL SUMMARY JUDGMENT MOTIONS
    WITHOUT      CITING  THE   SUPPOSEDLY
    A-2088-17T3
    24
    UNDISPUTED FACTS AND THE APPLICABLE
    LAW SUPPORTING THOSE DECISIONS.
    POINT V: THE COURT ERRED IN GRANTING
    SUMMARY JUDGMENT        MOTIONS   WHEN
    MULTIPLE DISPUTED MATERIAL FACTS
    EXISTED, AND THE COURT FAILED TO AFFORD
    THE BENEFIT OF THE DOUBT TO THE PARTY
    OPPOSING SUMMARY JUDGMENT.
    POINT VI: THE COURT ERRED IN FAILING/
    REFUSING TO CONSIDER SUPPLEMENTAL
    SUBMISSIONS IN OPPOSITION TO MOTIONS
    SEEKING RELIEF REGARDING ALLEGED
    SPOLIATION OF EVIDENCE.
    POINT VII: THE COURT ERRED IN RELYING
    UPON CERTAIN FACTS THAT WERE CONTRARY
    TO FACTS CITED BY EITHER THE MOVING
    PARTY OR OPPOSING PARTY.
    POINT VIII : THE COURT MADE PATENTLY
    INCORRECT RULINGS ON LEGAL ISSUES ON
    SEVERAL MOTIONS.
    POINT IX: SUMMARY     JUDGMENT     WAS
    IMPROPERLY    ENTERED    IN  LIGHT  OF
    CONFLICTING EXPERT OPINIONS.
    POINT X: IN REVERSING AND REMANDING,
    THE APPELLATE DIVISION SHOULD RULE OUT
    THAT SUMMARY JUDGMENT COULD NOT
    HAVE BEEN GRANTED TO THE DEFENDANTS
    AND THEREFORE THE CASE SHOULD BE
    REMANDED FOR TRIAL, NOT FOR FURTHER
    MOTION ARGUMENT.
    A-2088-17T3
    25
    POINT XI: IF THE DECISIONS ARE REVERSED,
    AND THE MOTIONS ARE REMANDED, THEY
    SHOULD BE ASSIGNED TO A DIFFERENT JUDGE.
    POINT XII:  IF  THE   DECISIONS  ARE
    REVERSED, AND THE CASE IS REMANDED, IT
    SHOULD BE REMANDED TO A DIFFERENT
    COUNTY.
    By way of separate appeal, BMCC raises the following points:
    POINT I: THE TRIAL COURT ERRED IN
    GRANTING DEFENDANT GIAMIKE'S MOTION
    FOR SUMMARY JUDGMENT AGAINST BMCC.
    POINT II: THE             SUBCONTRACT
    INDEMNIFICATION CLAUSE IS ENFORCEABLE
    AND       REQUIRED     SUBCONTRACTOR
    DEFENDANTS TO INDEMNIFY BMCC FOR EVEN
    BMCC'S OWN NEGLIGENCE, WHICH AS A
    MATTER OF LAW WAS NONE.
    POINT III: THE TRIAL COURT ERRED IN
    CANCELLING ORAL ARGUMENT AND SUA
    SPONTE DISMISSING BMCC'S CROSS-CLAIMS
    AGAINST        THE     SUBCONTRACTOR
    DEFENDANTS.
    Because plaintiffs failed to produce proof of damages, we only address
    the claim of error regarding that issue. The patchwork of expert reports and
    opinions plaintiffs obtained simply did not fill the void. The remaining issues
    plaintiffs raise are made moot by the disposition.
    A-2088-17T3
    26
    VII.
    "An appellate court reviews an order granting summary judgment in
    accordance with the same standard as the motion judge." Bhagat v. Bhagat, 
    217 N.J. 22
    , 38 (2014). That standard requires the court to "review the competent
    evidential materials submitted by the parties to identify whether there are
    genuine issues of material fact and, if not, whether the moving party is entitled
    to summary judgment as a matter of law." 
    Ibid.
     (citing Brill v. Guardian Life
    Ins. Co. of Am., 
    142 N.J. 520
    , 540 (1995)); R. 4:46-2(c). If "a legal issue is
    involved in the absence of a genuine factual dispute, that standard is de novo,
    and the trial court rulings 'are not entitled to any special deference.'" Henry v.
    N.J. Dep't of Human Servs., 
    204 N.J. 320
    , 330 (2010) (quoting Manalapan
    Realty, LP v. Manalapan Twp. Comm., 
    140 N.J. 366
    , 378 (1995)).
    "An issue of fact is genuine only if, considering the burden of persuasion
    at trial, the evidence submitted by the parties on the motion, together with all
    legitimate inferences therefrom favoring the non-moving party, would require
    submission of the issue to the trier of fact." R. 4:46–2(c). The "'genuine issue
    [of] material fact' standard mandates that the opposing party do more than
    'point[] to any fact in dispute' in order to defeat summary judgment." Globe
    A-2088-17T3
    27
    Motor Co. v. Igdalev, 
    225 N.J. 469
    , 479 (2016) (alterations in original) (quoting
    Brill, 
    142 N.J. at 529
    ).
    N.J.R.E. 101(b)(2) defines the "burden of producing evidence" as "the
    obligation of a party to introduce evidence when necessary to avoid the risk of
    a judgment or peremptory finding against that party on an issue of fact." That
    burden "has been described as so light as to be 'little more than a formality. '"
    State v. Segars, 
    172 N.J. 481
    , 494 (2002) (quotations omitted) (quoting Mogull
    v. CB Commercial Real Estate Co., Inc., 
    162 N.J. 449
    , 469 (2000)). Moreover,
    that burden "is met whether or not the evidence produced is found to be
    persuasive." 
    Ibid.
    Compensatory damages are designed "to put the injured party in as good
    a position as he would have been if performance were rendered as promised."
    St. Louis, L.L.C. v. Final Touch Glass & Mirror, Inc., 
    386 N.J. Super. 177
    , 188
    (App. Div. 2006) (quoting 525 Main St. Corp. v. Eagle Roofing Co., 
    34 N.J. 252
    , 254 (1961)). Generally, the appropriate award of damages is the diminution
    in the value of the property or the reasonable cost of restoring or repairing the
    damage. Velop, Inc. v. Kaplan, 
    301 N.J. Super. 32
    , 64 (App. Div. 1997).
    "Damages for defective construction, whether those damages are the result
    of a breach of contract or negligence of the contractor, are often determined by
    A-2088-17T3
    28
    using the reasonable cost of remedying the defects unless that cost is clearly
    disproportionate to the property's probable loss of value." St. Louis, L.L.C., 
    386 N.J. Super. at 188
    . When "the cost of repairs vastly exceeds . . . the probable
    market value of the property," then it may be unfair to use the restoration-cost
    method of quantifying property damage. Mosteller v. Naiman, 
    416 N.J. Super. 632
    , 638 (App. Div. 2010) (alteration in original) (quoting Correa v. Maggiore,
    
    196 N.J. Super. 273
    , 285 (App. Div. 1984)).
    Moreover, if the cost-of-repairs approach would result in "unreasonable
    economic waste," then that method should not be employed. 
    Ibid.
     (quoting
    Correa, 
    196 N.J. Super. at 285
    ). "However, reasonable repair costs that exceed
    the diminution of the property's value are appropriate 'in some circumstances[,
    such as] where the property owner wishes to use the property rather than sell
    it.'" 
    Ibid.
     (alterations in original) (quoting Velop, Inc., 301 N.J. Super. at 64);
    cf. St. Louis, L.L.C., 
    386 N.J. Super. at 191-92
     (explaining the damages in that
    case would not cause economic waste because the damage award was "not in
    excess of the value of the property, nor would it permit a substantial upgrade of
    the house").
    To evaluate which method of quantifying damages is appropriate, parties
    must present expert opinions providing the value of the impaired property and
    A-2088-17T3
    29
    cost of repairs or restoration. See St. Louis, L.L.C., 
    386 N.J. Super. at 193-94
    (relying on expert opinion when determining that the trial court did not err in
    ruling that the cost of repair was the proper element of consideration for
    determining damages); Velop, Inc., 301 N.J. Super. at 64-66 (holding that the
    proper measure of damages was the difference between the contract price and
    the market value of the property because the expert opinion presented a
    restoration cost that would have resulted in approximately two million dollars
    more than the value of the property).
    VIII.
    Here, the trial court granted defendants' motions for summary judgment
    because plaintiffs did not present proof of damages despite producing many
    expert opinions.    Their discovery "did not support any proper measure of
    damages." Plaintiffs did not present expert testimony as to the value of the
    impaired property. This glaring void in plaintiffs' proofs means there is no
    genuine issue of material fact which is in dispute, and that defendants are
    entitled to judgment as a matter of law. See Brill, 
    142 N.J. at 540
    .
    Plaintiffs on appeal argue that their experts did present evidence as to the
    costs of repairs and appraised value of the home, and that the parties' conflicting
    expert reports should have prevented summary judgment. In support of the
    A-2088-17T3
    30
    argument that summary judgment is not appropriate where there are conflicting
    expert opinions, plaintiffs rely on Davin, LLC v. Daham, 
    329 N.J. Super. 54
    (App. Div. 2000). But Davin was a legal malpractice case in which the trial
    judge granted summary judgment by relying on his prior experience as a
    practicing attorney in knowing that a tenant's lawyer never orders a title search
    before advising a client to enter into a lease. 
    Id. at 71
    . We determined that the
    conflicting certifications created a genuine issue of material fact as to whether
    ordering a title search for a commercial tenancy was necessary competent
    representation. 
    Ibid.
     That fact was certainly material to the dispute between the
    parties. The disputes here are not material.
    Plaintiffs name Porcello, Brody, Piccione, Larson, Ali Gurhan of S OR
    Testing Laboratories, and Greg Gerdes of Pella Construction as "nominated
    experts for whom the defendants did not produce opposing experts[.]"
    None of the experts' reports plaintiffs submitted, however, would enable
    a trier of fact to properly assess construction defect damages. And that is the
    issue—whether those reports would aid a jury in assessing damages. Certainly,
    the experts identified defects, the value of the land, the existence of mold, and
    issues with the roofing shingles, however, none opine as to the financial
    A-2088-17T3
    31
    consequences of plaintiffs' allegations regarding the harm inflicted by
    defendants.3
    Porcello, for example, when asked regarding the cost of remediation of
    foundation walls at deposition, testified that his firm "[did not] do a cost analysis
    on anything." His report did not conclude that the defects required complete
    demolition and reconstruction of the residence.
    Contrary to plaintiffs' contention, Brody did not appraise the value of the
    property and "determine[] that the home itself had zero value, and the only
    positive value to the Property was for the land itself." Brody's letter began with
    the most significant assumption made in the valuation—that "based on extensive
    engineering reports, . . . the single family home and all additional improvements
    on the property, due to various forms of damage over time, have no economic
    value or economic contributory value to the overall property." At deposition,
    Brody testified that plaintiffs defined the limits of his report, and instructed his
    firm not to value the improvements made on the land.
    Piccione's report provided only the estimated cost of reconstructing the
    home. The report did not address any estimate to repair the home prior to
    3
    No reports by Gerdes are included in the appellate record provided to us.
    A-2088-17T3
    32
    demolition or whether the cost to demolish and rebuild would have been less
    than to repair.
    Larson's report related to how the remediation process should occur,
    including ways to prevent the spread of contamination and the required use of
    protective equipment.     No conclusions or opinions as to the level of
    contamination in the residence, the need to demolish the home, or a cost for the
    remediation process were provided. Larson's report detailed the steps necessary
    to remediate the home without demolition. His subsequent reports also only
    identified additional fungal issues, and although his last one recommended
    exploration of the notion of demolition versus remediation expenses, the report
    did not do so and no numbers were included. Indeed, Larson testified that he
    "never told [Ava] that she should" demolish the entire house and learned
    plaintiffs had done so the day before deposition. He never discussed with Ava
    the cost of performing the remediation.
    Gurhan's report did not state that the cost of replacing the roof shingles
    merited demolition of the residence. Rather, the report concluded that some of
    the shingles were improperly installed and prematurely weathered, and
    estimated the remainder of the shingles' life would be only another two or three
    A-2088-17T3
    33
    years. Some of the roofing experienced "early failure" but that does not equate
    to values that would enable a jury to determine damages.
    In their reply brief, plaintiffs contend that Adach's letter warranted denial
    of summary judgment because it indicated demolition was necessary. Even
    though Adach was not designated as an expert, his letter should be considered
    because it was "based on his personal observations at the jobsite." Since it sets
    forth reasons for his recommendation, it is admissible as a lay opinion. This
    argument, however, is raised in a footnote, and thus we do not address it. See
    Almog v. Israel Travel Advisory Serv., Inc., 
    298 N.J. Super. 145
    , 155 (App. Div.
    1997) (stating that courts will not "countenance the raising of additional legal
    issues" in footnotes and "need not respond to oblique hint and assertions made"
    within them). The letter makes no mention of damages, or of any calculations
    contrasting the cost to repair, demolish, or rebuild.
    As consequential damages are the remedy for plaintiffs' claims against
    defendants, and a required element to establish some of the causes of action, the
    order granting summary judgment based on plaintiffs' lack of proper proof of
    damages is legally correct and dispositive.      See, e.g., Globe Motor Co. v.
    Igdalev, 
    225 N.J. 469
    , 482 (2016) (identifying damages as an element for a
    breach of contract claim); D'Agostino v. Maldonado, 
    216 N.J. 168
    , 184-85
    A-2088-17T3
    34
    (2013) (stating that a claim under the CFA requires damages); Carroll v. Cellco
    P'ship, 
    313 N.J. Super. 488
    , 502 (App. Div. 1998) (naming damages as an
    element in a claim for negligent misrepresentation). 4
    Plaintiffs further allege that they presented evidence that they suffered
    damages in the form of alternate living expenses and costs to investigate the
    alleged defects, which did not require expert testimony, and which the court did
    not consider. However, the document plaintiffs cite in support of this assertion
    is a chart they generated that identified alleged costs they incurred, without any
    receipts, invoices, or other supportive evidence.
    Many of the "disputed" facts plaintiffs rely on are just the expert opinions.
    However, even accepting plaintiffs' expert opinions as true for summary
    judgment purposes, they do not establish the facts necessary to support their
    claim. Although an expert provided an estimate of the cost of rebuilding the
    home, they could not give any estimate of what the costs would have been to
    remediate, or even whether demolition was necessary in the first place.
    4
    Plaintiffs also argue the trial court erred in finding no basis for liability against
    BMCC, the McEwans, Tamko, Tri-State, and Maggio in their reply brief. This
    too is improper, however. See In re Bell Atl.-N.J., Inc., 
    342 N.J. Super. 439
    ,
    442 (App. Div. 2001) ("It is improper to introduce new issues in a reply brief.");
    Liebling v. Garden State Indem., 
    337 N.J. Super. 447
    , 465-66 (App. Div. 2001)
    ("[A]n issue not briefed . . . is deemed waived.").
    A-2088-17T3
    35
    Similarly, plaintiffs' real estate expert valued the land only and "assumed" the
    house was of no value, but did not come to his own conclusion. See Igdalev,
    225 N.J. at 479 (stating that the party must do more than point to any fact in
    dispute). Having reviewed the voluminous materials submitted, and drawing all
    inferences in favor of the non-moving parties, we reach the inescapable
    conclusion that defendants are entitled to judgment as a matter of law. See R.
    4:46-2(c).
    IX.
    Having found that plaintiffs' claims were properly dismissed, we now
    reach the issue of BMCC's cross-claims for counsel fees and court costs. BMCC
    entered into subcontractor agreements with Giamike, A&A, Grant, and Maggio
    for the construction of the residence.        These agreements each included
    enumerated paragraphs addressing indemnification:
    1. Subcontractor agrees to defend, indemnify, and hold
    Contractor [BMCC] harmless and, if requested by
    Contractor [BMCC], the Owner, their consultants,
    agents and employees of any of them, from and against
    any and all claims, suits, losses or liability, including
    attorneys' fees and litigation expenses, for or on
    account of injury to or death of persons, including
    subcontractor's employees, or damage to or destruction
    of property, or any bond obtained for the same, arising
    out of or resulting from any act or omission, or alleged
    act or omission, of Subcontractor, its employees or
    A-2088-17T3
    36
    agents, whether caused in part or by a party indemnified
    hereunder.
    BMCC contends that plaintiffs' lawsuit required Giamike to reimburse it
    as called for by the agreement between general and subcontractor, and that it
    was not necessary for BMCC to prove Giamike caused the alleged damage.
    BMCC contends the trial judge erred by granting Giamike's motion for summary
    judgment and dismissing its cross-claims against the other subcontractor
    defendants without either explaining its analysis and without oral argument on
    the issue.
    Maggio and Grant argue that we should exercise original jurisdiction and
    render a decision, while A&A argues the trial court's lack of support is harmless
    error because we review issues of law de novo.
    We rarely exercise original jurisdiction. As our Supreme Court has said,
    our
    [r]esort to original jurisdiction is particularly
    appropriate to avoid unnecessary further litigation, as
    where the record is adequate to terminate the dispute
    and no further fact-finding or administrative expertise
    or discretion is involved, and thus a remand would be
    pointless because the issue to be decided is one of law
    and implicates the public interest.
    [Price v. Himeji, L.L.C., 
    214 N.J. 263
    , 294 (2013)
    (alteration in original) (quoting Vas v. Roberts, 
    418 N.J. Super. 509
    , 523-24 (App. Div. 2011)).]
    A-2088-17T3
    37
    The interpretation and construction of a contract is a matter of law and
    thus we review the trial court's decision de novo. Kaur v. Assured Lending
    Corp., 
    405 N.J. Super. 468
    , 474 (App. Div. 2009); Manalapan Realty, 
    140 N.J. at 378
    .
    Trial courts are required to "find the facts and state its conclusions in
    accordance with R. 1:7-4." R. 4:46-2(c). As such, a "trial judge is obliged to
    set forth factual findings and correlate them to legal conclusions," and " [t]hose
    findings and conclusions must then be measured against the standards set forth
    in [Brill, 
    142 N.J. at 540
    ]." Great Atl. & Pac. Tea Co., Inc. v. Checchio, 
    335 N.J. Super. 495
    , 498 (App. Div. 2000). "Cross-motions for summary judgment
    do not preclude the existence of fact issues." 
    Ibid.
    Moreover, Rule 1:6-2(d) requires that a request for oral argument "shall
    be granted as of right." If a trial court "decides the motion on the papers despite
    a request for oral argument, the trial court should set forth in its opinion its
    reasons for disposing of the motion for summary judgment on the papers in its
    opinion." LVNC Funding, L.L.C. v. Colvell, 
    421 N.J. Super. 1
    , 5 (App. Div.
    2011). We have reversed summary judgment where a trial court did not address
    the movant's request for oral argument and did not provide on the record a basis
    A-2088-17T3
    38
    for its relaxation of Rule 1:6-2. Great Atl. & Pac. Tea Co., 
    335 N.J. Super. at 497-98
    .
    Here, the trial court did not state on the record nor did the orders for
    dismissal set forth factual findings or draw legal conclusions about BMCC's
    cross-claims, making this matter appropriate for a remand. Further aggravating
    this error was the trial court's failure to hold oral argument on Giamike's motion
    for summary judgment on the indemnification issues raised by BMCC's cross-
    claims. It had scheduled argument, but then cancelled it after the parties argued
    the motions against plaintiffs. But the issue was not addressed during that
    November 17, 2017 argument.
    The only reference in the statement of reasons to that cross-claim is a
    sentence that "Giamike filed a motion for summary judgment reciting much of
    the same argument as Tamko but stating that there is no proof that the roof was
    defectively installed and that BMCC indemnified it as a subcontractor." The
    trial court also concluded that BMCC had "no liability to plaintiffs as a general
    contractor is not legally responsible for its subcontractors." The court ended its
    statement of reasons by noting there were "myriad other legal issues presented
    by the various defendants which have been carefully reviewed by the court,
    A-2088-17T3
    39
    however, based upon the above analysis it is abundantly clear that summary
    judgment is appropriate."
    The interpretation of this provision is not purely legal, as the liability of
    the subcontractor defendants and BMCC, and the impact of BMCC's liability, if
    any, are contested. The subcontractor defendants argue the contracts cannot in
    reason require them to indemnify BMCC for its own negligence, while BMCC
    contends the contracts do provide for that contingency, but that it was not
    negligent.
    Giamike also argues that the New Jersey Property-Liability Insurance
    Guaranty Association Act (NJPLIGA), N.J.S.A. 17:30A-1 to -20, precludes
    BMCC from seeking indemnification, because of Giamike's insurance carrier's
    liquidation. Again, the trial court made no findings or conclusions, or even
    addressed this argument in any form, in its statement of reasons or on the record.
    Contrary to the rule, the court neither made factual findings, drew legal
    conclusions, or even allowed oral argument.         Thus, the orders dismissing
    BMCC's cross-claims must be remanded.
    The orders granting summary judgment against plaintiffs are affirmed; the
    order granting Giamike summary judgment against BMCC is reversed; and the
    A-2088-17T3
    40
    orders dismissing BMCC's cross-claims against A&A, Giamike, Grant, and
    Maggio, are remanded for further proceedings on BMCC's cross-claims.
    Affirmed in part; reversed and remanded in part.
    A-2088-17T3
    41