POLO A. PLUMBING & HEATING VS. CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY (L-3656-16, MIDDLESEX COUNTY AND STATEWIDE) ( 2020 )


Menu:
  •                                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-0171-18T2
    POLO A. PLUMBING &
    HEATING, INC.,
    Plaintiff-Respondent,
    v.
    CONRAIL DEVELOPERS
    LIMITED LIABILITY COMPANY,
    a New Jersey Limited Liability
    Company,
    Defendant-Appellant/
    Third-Party Plaintiff,
    and
    WELLNESS and BEAUTY INC.,
    d/b/a MOSAIC WELLNESS and
    BEAUTY and EKATERINA
    ST. ONGE,
    Third-Party Defendants.
    ________________________________
    Submitted May 11, 2020 – Decided August 3, 2020
    Before Judges Messano and Ostrer.
    On appeal from the Superior Court of New Jersey, Law
    Division, Middlesex County, Docket No. L-3656-16.
    Shamy, Shipers & Lonski, PC, attorneys for appellant
    (Darren M. Pfeil, of counsel; Robert J. MacNiven, on
    the briefs).
    Robbins and Robbins, LLP, attorneys for respondent
    (Spencer B. Robbins, on the brief).
    PER CURIAM
    Defendant Conrail Developers, LLC, is a general contractor that
    subcontracted with plaintiff, Polo A. Plumbing & Heating, Inc., to perform
    plumbing work at a construction project in Woodbridge. Originally, defendant's
    principal, Ralph Mocci, also the principal of the property's corporate owner,
    envisioned commercial spaces on the first floor of the proposed building and
    office space on the second. However, third-party defendant Ekaterina St. Onge,
    who owned and ran several day spas, decided to lease the second floor to operate
    a spa and salon of her design.
    It is undisputed that plaintiff prepared two contracts, both dated June 6,
    2012, to supply labor for the necessary plumbing, and the parties executed both
    contracts. The first, executed on July 5, 2012, was for a total of $14,000 , and
    contained a payment schedule that tracked plaintiff's completion of certain work
    items after an initial deposit of $3000. The second contract, executed more than
    A-0171-18T2
    2
    six months later on January 29, 2013, was for a total of $32,000, and contained
    significantly more work items. Defendant was to pay a $5000 deposit, and,
    again, the balance of payment was tied to plaintiff's completion of various stages
    of the work. The contracts excluded all plumbing fixtures, any cutting, repairing
    or removal of the concrete slab for both floors, and any natural gas piping.
    Plaintiff did not begin work until after the second contract was executed .
    In February 2013, defendant made two separate payments to plaintiff of $3000
    and $5000, the deposit amounts under each contract. Defendant made additional
    payments of $2000, the amount due upon completion of the "slab" under the first
    contract, and $6000, the amount due upon completion of the slab under the
    second contract, on May 16 and May 22, 2013, respectively.
    Plaintiff claimed that it continued to work in accordance with the two
    contracts. Its principal, Anthony Polonio, testified there were delays in the
    project attributable to defendant, such that plaintiff could not continue its work
    after March 2014. This was corroborated to some degree by St. Onge. She
    testified that after plaintiff had installed the rough plumbing, other contractors
    working for defendant installed wall studs that were "crooked" and misplaced.
    New cuts in the slab had to be made to address the situation.
    A-0171-18T2
    3
    In June 2014, defendant tendered two checks, partial payments for the
    next amounts due under each contract "after rough" plumbing was complete.
    Ultimately, plaintiff sought assurances that defendant would make full payment
    on the outstanding balances on the two contracts, $8000, plus extra charges of
    $1750 for roof drains plaintiff already installed, before plaintiff would return to
    the job site.
    The record reveals a series of emails and letters exchanged between
    plaintiff and defendant in attempts to reach an accommodation. The testimony
    at trial from Polonio and Mocci diverged. Defendant contended the partial
    payment was made because plaintiff gave assurances it would return to the site
    and complete all the rough plumbing, and, there were documents in the record
    supporting plaintiff's commitment. Polonio claimed he wanted assurances the
    outstanding balance for work already done would be promptly paid before he
    sent a work crew back to the site. He asserted that defendant still did not have
    all the necessary supplies available to complete the job.
    On July 24, 2014, defendant's attorney sent plaintiff a letter
    acknowledging there were two "contracts total[ing] $51,150[] and payments
    A-0171-18T2
    4
    totaling $29,150[] ha[d] already been made."1 Counsel advised plaintiff that it
    would be paid upon completion of the rough plumbing in accordance with the
    contracts and established procedure, but not in advance of its return to the site.
    Counsel told plaintiff unless it returned to the jobsite within two days, defendant
    would declare a breach of the contracts. When plaintiff failed to return, counsel
    sent a second letter terminating the contracts.
    Plaintiff filed suit. It claimed that defendant owed $9750 for work that
    plaintiff completed for which defendant had not paid. Defendant answered and
    counterclaimed, alleging that it incurred additional expense to fix substandard
    work plaintiff had already performed and to complete work that remained
    unfinished. Defendant filed a third-party complaint against St. Onge and her
    business entities, seeking contribution and indemnification against plaintiff's
    claim.
    The case was tried without a jury. A critical issue at trial was whether
    there were two separate contracts, as plaintiff contended, or whether the second
    contract replaced the first, as defendant argued. Another point of contention
    1
    Polonio claimed there might have been extras that accounted for this difference
    from the sum of the original contract amounts, but except for $1750 for roof
    drains, he could not specifically recall. Defense counsel's letter accurately
    reflected the amount of money defendant had paid to plaintiff.
    A-0171-18T2
    5
    was whether plaintiff had performed all the work under both contracts to that
    point and was due payment for having completed the "rough" plumbing.
    Defendant asserted there was only one contract and that plaintiff breached
    the contract by failing to perform. Defendant introduced evidence that it paid
    other contractors more than $30,000 to correct plaintiff's unprofessional work.
    The judge issued an oral opinion in plaintiff's favor and entered judgment
    for plaintiff in the amount of $7250, plus pre-judgment interest. She also
    dismissed defendant's counterclaim and third-party complaint against St. Onge. 2
    The judge subsequently denied defendant's motion for reconsideration, and this
    appeal followed. 3
    Before us, defendant contends the verdict was "clearly against the weight
    of the evidence." Defendant also contends that it established plaintiff breached
    the contract and failed to mitigate defendant's damages. Defendant urges us to
    vacate the judgment and remand the matter for a new trial. We have considered
    these arguments and affirm.
    2
    Defendant does not appeal the dismissal of its third-party complaint.
    3
    We only have defendant's notice of motion for reconsideration, which did not
    request oral argument, and the judge's order denying the motion. The order
    contains no written statement of reasons.
    A-0171-18T2
    6
    Rule 2:10-1 provides: "In both civil and criminal actions, the issue of
    whether a jury verdict was against the weight of the evidence shall not be
    cognizable on appeal unless a motion for a new trial on that ground was made
    in the trial court." (Emphasis added). A challenge to a verdict as being against
    the weight of the evidence is inapplicable to a bench trial.        Fanarjian v.
    Moskowitz, 
    237 N.J. Super. 395
    , 406 (App. Div. 1989).
    Instead, we review defendant's argument using the proper standard of
    review following a non-jury trial.
    Final determinations made by the trial court
    sitting in a non-jury case are subject to a limited and
    well-established scope of review: "we do not disturb
    the factual findings and legal conclusions of the trial
    judge unless we are convinced that they are so
    manifestly unsupported by or inconsistent with the
    competent, relevant and reasonably credible evidence
    as to offend the interests of justice[.]"
    [Seidman v. Clifton Sav. Bank, S.L.A., 
    205 N.J. 150
    ,
    169 (2011) (alteration in original) (quoting In re Trust
    Created By Agreement Dated December 20, 1961, ex.
    rel. Johnson, 
    194 N.J. 276
    , 284 (2008)).]
    "Deference is especially appropriate when the evidence is largely testimonial
    and involves questions of credibility." 
    Ibid.
     (quoting Cesare v. Cesare, 
    154 N.J. 394
    , 412 (1998)).
    A-0171-18T2
    7
    In her oral opinion, the judge found as a fact that the parties entered into
    two valid contracts and "payments were made by [defendant] under each of the
    two contracts." There was ample support for this conclusion, given defendant's
    acknowledgement that it tendered two separate deposits, made two separate
    interim payments, and made two final partial payments with separate checks.
    Additionally, defendant's attorney's letter acknowledged the existence of two
    contracts for a total amount that far surpassed the $32,000 total in the second
    contract which, defendant asserted at trial superseded the first.
    The judge also specifically found that Polonio and his field supervisor,
    Sidney Schumacher, were credible witnesses. Having excluded defendant from
    producing expert testimony because it failed to provide any expert report in
    discovery, the judge rejected defendant's claim that "plaintiff's work was
    deficient."4 There was support for this conclusion, too, in the testimony by St.
    Onge, who was quite critical of the framing inside the proposed spa and the
    erroneous location of walls and partitions by other contractors that led to delays.
    The judge also found that defendant "presented no contemporaneous written
    evidence . . . recording defendant complained about any of plaintiff's plumbing
    work sa[ve] one mislocated pipe." Indeed, there was no claim in the various
    4
    Defendant has not appealed from this in limine evidentiary ruling by the judge.
    A-0171-18T2
    8
    communications in the record between the parties attempting to have plaintiff
    return to the site that the work to that point was unacceptable, except for the roof
    drains, which allegedly did not pass municipal inspection.
    In reviewing the findings by the judge, "[w]e do not weigh the evidence,
    assess the credibility of witnesses, or make conclusions about the evidence."
    Mountain Hill, LLC v. Twp. of Middletown, 
    399 N.J. Super. 486
    , 498 (App.
    Div. 2008) (alteration in original) (quoting State v. Barone, 
    147 N.J. 599
    , 615
    (1997)). The judge believed plaintiff's witnesses who claimed it had already
    performed work for which it had not been paid when negotiations about moving
    forward, broke down. At trial, defendant vigorously cross-examined Polonio as
    to whether the "rough" plumbing had indeed been completed, or whether there
    was additional work to be done before the "rough" plumbing was finished and,
    under the terms of the contract, plaintiff was entitled to the balance of payments.
    The judge found only that plaintiff conceded defendant was entitled to a $2000
    credit for some work which was incomplete, and therefore rendered judgment in
    plaintiff's favor for $7250.
    There is certainly evidence that could support a different result. Polonio's
    testimony was, at times, confused. Correspondence from defendant during June
    and July 2014 repeatedly asserted the rough plumbing was not complete and
    A-0171-18T2
    9
    demanded that plaintiff return to the job site to complete the rou gh plumbing.
    There were discrepancies in the permit plaintiff secured from Woodbridge as to
    the anticipated number of plumbing fixtures that would eventually be installed,
    compared to the amount of work Polonio claimed was completed. However, we
    will not "engage in an independent assessment of the evidence as if [we] were
    the court of first instance."   State v. Locurto, 
    157 N.J. 463
    , 471 (1999).
    "Reversal is reserved only for those circumstances when we determine the
    factual findings and legal conclusions of the trial judge went 'so wide of the
    mark that a mistake must have been made.'" Llewelyn v. Shewchuk, 
    440 N.J. Super. 207
    , 214 (App. Div. 2015) (quoting N.J. Div. of Youth & Family Servs.
    v. M.M., 
    189 N.J. 261
    , 279 (2007)). We do not reach that high threshold in this
    case.
    Affirmed.
    A-0171-18T2
    10