SITE ENTERPRISES, INC. VS. NRG REMA, LLC (L-5651-14, MIDDLESEX COUNTY AND STATEWIDE) ( 2020 )


Menu:
  •                                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-1852-18T4
    SITE ENTERPRISES, INC.,
    Plaintiff-Respondent,
    v.
    NRG REMA, LLC, and BTU
    SOLUTIONS GROUP, INC.,
    Defendants-Appellants.
    ___________________________
    Argued September 29, 2020 – Decided October 8, 2020
    Before Judges Fasciale, Mayer, and Susswein.
    On appeal from the Superior Court of New Jersey, Law
    Division, Middlesex County, Docket No. L-5651-14.
    Thomas J. O'Leary argued the cause for appellants
    (Walsh, Pizzi, O'Reilly, Falanga, LLP, attorneys;
    Thomas J. O'Leary, of counsel and on the briefs;
    Katherine M. Romano, on the briefs).
    Mitchell Malzberg argued the cause for respondent
    (Mitchell J. Malzberg, LLC, attorneys; Mitchell
    Malzberg and Jodelyn S. Malzberg, on the brief).
    PER CURIAM
    This appeal pertains to an action for enforcement of a construction lien.
    BTU Solutions Group, LLC (BTU), and NGR Rema LLC (NGR) (collectively
    defendants) appeal from three written orders entered after a bench trial: an
    August 16, 2018 "opinion and order" entering judgment to the lienholder,
    plaintiff Site Enterprises, Inc. (SEI); a September 28, 2018 order determining
    that SEI is entitled to attorney fees and costs under N.J.S.A. 2A:44A-15(b),
    subject to a certification of services; and a November 21, 2018 order awarding
    those fees and costs. Defendants also challenge a "verbal order" by the judge
    denying their motion to bar SEI's expert, Robert Peña. Judge Arthur Bergman
    conducted the bench trial, entered the orders, and rendered written and oral
    opinions.
    A trial court's factual findings "are binding on appeal if they are supported
    by 'adequate, substantial and credible evidence.'" Diamond Beach, LLC v.
    March Assocs., Inc., 
    457 N.J. Super. 265
    , 281-82 (App. Div. 2018) (quoting
    Rova Farms Resort, Inc. v. Inv'rs Ins. Co., 
    65 N.J. 474
    , 484 (1974)). "Deference
    is especially appropriate 'when the evidence is largely testimonial and involves
    questions of credibility.'" Cesare v. Cesare, 
    154 N.J. 394
    , 412 (1998) (quoting
    In re Return of Weapons to J.W.D., 
    149 N.J. 108
    , 117 (1997)). See State v.
    Locurto, 
    157 N.J. 463
    , 474 (1999) (explaining that credibility findings are "often
    A-1852-18T4
    2
    influenced by matters such as observations of the character and demeanor of
    witnesses and common human experience that are not transmitted by the
    record"). However, "[a] trial court's interpretation of the law and the legal
    consequences that flow from established facts are not entitled to any special
    deference" and warrant de novo review. Manalapan Realty, LP v. Twp. Comm.
    of Manalapan, 
    140 N.J. 366
    , 378 (1995).
    Applying these well-settled standards and other applicable law, we affirm
    SEI's final judgment of $491,379.42, the award of counsel fees and costs totaling
    $80,188.26, and the judge's evidentiary rulings.
    I.
    Pertinent background information concerning the relationships between
    the parties and the long history of this demolition project was explained in NRG
    REMA LLC v. Creative Environmental Solutions Corp., 
    454 N.J. Super. 578
    (App. Div.), certif. denied, 
    235 N.J. 111
    (2018), a related appeal pertaining to
    the value of the lien fund for SEI and another BTU subcontractor, Creative
    Environmental Solutions Corporation. 1
    On April 5, 2012, NRG and Werner entered into a contract for demolition
    of Units 1, 2, and 3 of the Werner Generating Station in South Amboy. Werner
    1
    Creative Environmental Solutions Corporation is not a party in this appeal.
    A-1852-18T4
    3
    paid NRG $250,000 for title to the salvage materials that it anticipated
    recovering during the demolition. Werner immediately received title to the
    salvage that it valued at $13 million. Just four days after it executed the prime
    contract with NRG, Werner subcontracted with BTU and "BTU stepped into
    Werner's shoes to perform the prime contract" for the demolition. NRG REMA
    
    LLC, 454 N.J. Super. at 584
    .
    "BTU initially projected that costs of roughly $4.5 million would generate
    $13 million in salvage-related revenue."
    Ibid. However, "BTU overestimated
    the amount of salvageable metal and equipment, and underestimated the cost of
    recovery."
    Ibid. When Superstorm Sandy
    hit New Jersey in October 2012,
    "[t]he site filled with salt water, destroying otherwise salvageable equipment,
    dispersing asbestos throughout the site, and further complicating remediation."
    Ibid. Several months later,
    on April 25, 2013, BTU subcontracted with SEI
    "which agreed to perform demolition work after the storm in return for $3.7
    million."
    Id. at 584-85.
    According to the contract between BTU and SEI, titled "General Services
    Agreement," SEI "is in the business of providing Demolition, Asbestos
    Remediation, HAZMAT removal and site cleanup." The parties each agreed to
    designate a project manager to coordinate performance of the work, which was
    A-1852-18T4
    4
    to be completed in six months "under a fixed fee engagement" for $3.7 million,
    as noted above. BTU designated Helio Guzman as project manager and SEI
    designated Tom Rock. The scope of the work to be performed by SEI for
    remediation and demolition of the power generating station is described in th e
    Statement of Work attached to the contract.
    Schedule 2 of the Statement of Work lists SEI's responsibilities as follows:
    (1) removal/disposal of universal waste from the building; (2) set up and
    maintenance of silt fence around the property; (3) plating of canals for
    demolition work/installation of steel plates for water intake inlets on West side;
    (4) electrical work, including disconnecting power from the building; (5) power
    panel for misting blowers to be maintained on site to contain airborne dust ; (6)
    set up power in salvage process area; (7) provide power source for and relocation
    of NRG cables and data lines; (8) provide additional power panel for work area;
    (9) complete demolition of existing power plant; (10) demolition of oil tanks,
    water tower, and small buildings around the plant; (11) demolition and
    abatement labor, with all demolition laborers having asbestos licenses plus
    asbestos and lead awareness training and proper personal protective equipment
    (PPE); (12) separating metal and non-ferrous material for salvage; (13) cutting
    of steel to fit into dump trailers; and (14) removal of all concrete, slabs, footing,
    A-1852-18T4
    5
    and foundations to grade. Pursuant to Schedule 2, SEI was also responsible for
    the disposal costs of the first 1,000 tons of asbestos-containing material (ACM).
    In addition to the tasks specified in Schedule 2, Schedule 6 required SEI
    to supply safety information and documentation to BTU. Schedule 7 required
    SEI's project manager or site supervisor to attend various daily and weekly
    meetings and to participate in project conference calls. While Section 5 of the
    contract contained boilerplate language pertaining to the submission of invoices
    to BTU "for services not compensated on a fixed price basis," Schedule 9 of the
    Statement of Work made it clear that SEI was to be paid a lump sum of $3.7
    million for "all work performed." The Statement of Work itself did not require
    SEI to submit any invoices or timesheets to BTU.
    On August 29, 2014, SEI sued defendants for enforcement of a $450,000
    construction lien pursuant to the CLL. The complaint also asserted breach of
    contract and account stated claims, not part of this appeal, that were dismissed
    because the parties' contract required SEI to prosecute those claims in Texas.
    Defendants filed a counterclaim to discharge SEI's lien, alleging that it was
    untimely filed and willfully overstated in violation of the CLL. They also sought
    attorney's fees and costs.
    A-1852-18T4
    6
    On April 10, 2017, defendants filed a motion in limine to preclude SEI's
    expert, Robert Peña, from testifying at the bench trial. Peña opined that SEI had
    completed at least 15% of the required work, valued at $555,000, under its lump
    sum contract with BTU before it demobilized from the project in December
    2013. The judge denied defendants' motion in limine on the record without
    entering a written order. It found that Peña was qualified to give an expert
    opinion based upon over twenty years of experience with estimating and project
    management for demolition projects, and that Peña's opinion was not a net
    opinion because he provided the "why and wherefore" to support his conclusion.
    The case proceeded to trial.
    The four-day bench trial was limited in scope to the timeliness of the lien
    and whether its value was willfully overstated.2 SEI called four witnesses at
    trial: (1) James DiNatale, owner of SEI; (2) Helio Guzman, BTU project
    2
    The parties stipulated that the amount of the lien fund as determined by the
    Appellate Division in NRG REMA LLC v. Creative Environmental Solutions
    Corp., 
    454 N.J. Super. 578
    (App. Div.), certif. denied, 
    235 N.J. 111
    (2018), a
    related case tried in 2013, was sufficient to satisfy SEI's lien claim. See L & W
    Supply Corp. v. DeSilva, 
    429 N.J. Super. 179
    , 184 (App. Div. 2012) (explaining
    that the CLL "limits the lien to the amount available in the 'lien fund,' which
    'shall not exceed the unpaid portion of the contract price of the claimant's
    contract for the work, services, material or equipment provided'") (quoting
    N.J.S.A. 2A:44A-9(a)).
    A-1852-18T4
    7
    manager; (3) Tom Rock, SEI project manager; and (4) Robert Peña, expert in
    demolition cost analysis.    Defendants called three witnesses: (1) Nicholas
    Kemper, Consolidated Asset Management Services; (CAMS) project manager; 3
    (2) Jared Rossi, Chief Financial Officer of BTU; and (3) Barry Brower, expert
    in construction cost analysis.
    The judge issued his written findings of fact and conclusions of law,
    concluding that SEI proved, by a preponderance of the evidence, that the lien
    was timely filed. The judge further determined that SEI was entitled to judgment
    in the amount of $450,000 plus prejudgment interest and costs. He then entered
    judgment for SEI in the amount of $491,379.42, dismissed defendants'
    counterclaim with prejudice, and awarded SEI $75,978 in attorney's fees and
    $4,210.26 in costs under N.J.S.A. 2A:44A-15(b), for a total of $80,188.26.
    II.
    On appeal, defendants argue primarily the judge's factual findings were
    unsupported by the credible evidence adduced at trial. They also contend that
    the judge erred as a matter of law when he concluded the lien was timely filed.
    Defendants assert that the judge abused his discretion by awarding counsel fees
    and costs.
    3
    Werner is a wholly owned subsidiary of CAMS.
    A-1852-18T4
    8
    III.
    Enacted in 1994, the CLL is a remedial statute that "replaced the
    longstanding Mechanic's Lien Law in New Jersey, making it easier for
    contractors, subcontractors and suppliers to place construction liens on property
    in the amount of the work, services or material they have provided, and for
    which they have not been paid." Thomas Grp., Inc. v. Wharton Senior Citizen
    Hous., Inc., 
    163 N.J. 507
    , 509, 517 (2000). "Work" is statutorily defined as "any
    activity, including, but not limited to, labor, performed in connection with the
    improvement of real property." N.J.S.A. 2A:44A-2.
    N.J.S.A. 2A:44A-3 provides:
    that any contractor or subcontractor . . . who provides
    work, services, material or equipment pursuant to a
    contract shall be entitled to a lien for the value of the
    work or services performed, or materials or equipment
    furnished in accordance with the contract and based on
    the contract price.
    [Thomas 
    Grp., 163 N.J. at 513
    .]
    "The lien attaches to the interest of the owner in the real property."
    Ibid. (citing N.J.S.A. 2A:44A-3).
    "The amount of a lien claim shall not exceed the unpaid
    portion of the contract price of the claimant's contract for the work, services,
    material or equipment provided." N.J.S.A. 2A:44A-9.
    A-1852-18T4
    9
    The CLL requires claimants to file lien claims "within 90 days from the
    last date of work, services, material or equipment provided for which payment
    is claimed."    Thomas 
    Grp., 163 N.J. at 513
    (citing N.J.S.A. 2A:44A-6).
    Enforcement actions must be initiated in Superior Court "within one year from
    the date the last work was provided" or the lien will be discharged.
    Id. at 514
    (citing N.J.S.A. 2A:44A-14(a)(1)). If a lien claim is untimely or "willfully
    overstated . . . the claimant shall forfeit all claimed lien rights and rights to file
    subsequent lien claims to the extent of the face amount claimed in the lien
    claim." N.J.S.A. 2A:44A-15(a).
    Additionally, the CLL contains a fee-shifting provision.               N.J.S.A.
    2A:44A-15(a) provides that if the lien claim is untimely or willfully overstat ed,
    the claimant "shall . . . be liable for all court costs, and reasonable legal
    expenses, including, but not limited to, attorneys' fees, incurred by the owner"
    in defending the lien claim. Conversely, N.J.S.A. 2A:44A-15(b) provides:
    If a defense to a lien claim is without basis, the party
    maintaining the defense shall be liable for all court
    costs, and reasonable legal expenses, including, but not
    limited to, attorneys' fees, incurred by any of the parties
    adversely affected by the defense to the lien claim. The
    court shall, in addition, enter judgment against the party
    maintaining this defense for damages to any of the
    parties adversely affected thereby.
    A-1852-18T4
    10
    For purposes of this analysis, "without basis" is defined as "frivolous, false,
    unsupported by a contract, or made with malice or bad faith or for any improper
    purpose." N.J.S.A. 2A:44A-15(d).
    IV.
    We begin by addressing defendants' contention that the judge's findings
    are unsupported by the record. Defendants contend that evidence does not
    support the judge's findings that SEI completed at least 15 percent of the work
    contemplated under the contract and that the value of the work was $450,000.
    Contrary to these assertions, there is ample support in the record for the judge's
    findings of fact.
    A. Whether SEI completed at least 15 percent of the work
    Defendants attack Peña's testimony, which the judge found to be credible,
    on the basis that he was unqualified to testify as an expert under N.J.R.E. 702
    and because his opinion was a net opinion. Here, the judge addressed these
    arguments when he denied defendants' motion in limine to exclude Peña's
    testimony.    He did so by applying applicable law and by not abusing his
    discretion.
    A trial court's decision to admit or exclude expert testimony in a civil case
    is reviewed under "a pure abuse of discretion standard." In re Accutane Litig.,
    A-1852-18T4
    11
    
    234 N.J. 340
    , 391-92 (2018) (citing Townsend v. Pierre, 
    221 N.J. 36
    , 52-53
    (2015)). "Accordingly, the trial court's decision here should not be disturbed on
    appeal unless the decision was 'made without a rational explication, inexplicably
    departed from established practices, or rested on an impermissible basis.'"
    Estate of Kotsovska v. Liebman, 
    221 N.J. 568
    , 588 (2015) (quoting Flagg v.
    Essex Cty. Prosecutor, 
    171 N.J. 561
    , 571 (2002)).
    "New Jersey Rules of Evidence 702 and 703 control the admission of
    expert testimony." In re 
    Accutane, 234 N.J. at 348
    . Pursuant to N.J.R.E. 702,
    "[i]f scientific, technical, or other specialized knowledge will assist the trier of
    fact to understand the evidence or to determine a fact in issue, a witness qualified
    as an expert by knowledge, skill, experience, training, or education may testify
    thereto in the form of an opinion or otherwise."
    Ibid. (quoting N.J.R.E. 703).
    "N.J.R.E. 703 addresses the foundation for expert testimony." 
    Townsend, 221 N.J. at 53
    . Expert opinions must be grounded in "facts or data derived from (1)
    the expert's personal observations, or (2) evidence admitted at the trial, or (3)
    data relied upon by the expert which is not necessarily admissible in evidence
    but which is the type of data normally relied upon by experts."
    Ibid. (quoting Polzo v.
    Cty. of Essex, 
    196 N.J. 569
    , 583 (2008)).
    A-1852-18T4
    12
    "The net opinion rule is a 'corollary of [N.J.R.E. 703] . . . which forbids
    the admission into evidence of an expert's conclusions that are not supported by
    factual evidence or other data.'"
    Id. at 53-54
    (alterations in original) (quoting
    
    Polzo, 196 N.J. at 583
    ). In other words, the expert must "'give the why and
    wherefore' that supports the opinion, 'rather than a mere conclusion.'"
    Id. at 54
    (quoting Borough of Saddle River v. 66 E. Allendale, LLC, 
    216 N.J. 115
    , 144
    (2013)). "Evidential support for an expert opinion is not limited to treatises or
    any type of documentary support, but may include what the witness has learned
    from personal experience." Rosenberg v. Tavorath, 
    352 N.J. Super. 385
    , 403
    (App. Div. 2002).
    The record supports the judge's finding that Peña possessed ample
    knowledge, experience, training and education to testify as an expert in the field
    of demolition cost analysis.     Peña has worked exclusively for demolition
    companies as an estimator/project manager for almost twenty-five years. He has
    a bachelor's degree in civil engineering technology, and his undergraduate
    coursework included estimation classes. He testified at length about his work
    on numerous large demolition projects and his experience estimating percentage
    completion while the jobs are underway.
    A-1852-18T4
    13
    Contrary to defendants' contention, the fact that Peña had never been
    asked to determine "the percentage completion of a contractor's work after a
    contractor abandoned a Project prior to completing its work," where no schedule
    of values existed in the contract, does not mean he was unqualified to do so here.
    His extensive experience in the demolition industry is just as relevant to the
    unique facts at issue here.    Moreover, defendants' reliance on Goldman v.
    Shapiro, 
    16 N.J. Super. 324
    (App. Div. 1951), and Zulla Steel, Inc. v. A & M
    Gregos, Inc., 
    174 N.J. Super. 124
    (App. Div. 1980), both decided before the
    CLL was enacted, is misplaced. Neither case involved a construction lien claim
    and neither case addressed the admissibility of expert testimony.
    And Peña's opinion on the percentage completion of SEI's work did not
    amount to a net opinion. As the judge found, Peña explained the basis for his
    opinion and expressed that it was firmly grounded in his experience as an
    estimator in the area of demolition and his familiarity with the job site. He
    reviewed, among other documents, the contract between SEI and BTU in
    evidence, and deposition testimony from DiNatale about the work SEI had
    completed. He explained the methodology he used to arrive at his conclusion
    that SEI had completed 15 percent of the work. Specifically, he reviewed the
    A-1852-18T4
    14
    total scope of work as defined by the contract and compared it to the actual work
    that SEI completed between April 2013 and December 2013.
    Defendants further claim that Peña "failed to offer any objective basis
    justifying his decision to assign 5 [percent] of the SEI/BTU contract value to
    mobilization." However, Peña testified that, in his experience, mobilization
    costs for demolition contracts are typically billed at the beginning of the project,
    with the exact number negotiated between contractor and owner, and that they
    could be valued as low as 3 percent or as high as 10 percent. He explained that
    mobilization includes moving equipment to the site, submitting plans, paying
    permit fees, buying materials, addressing soil erosion, and hiring electricians,
    among other tasks. His experience in the field provided a sound basis for his
    opinion. 
    Rosenberg, 352 N.J. Super. at 403
    . See State v. Townsend, 
    186 N.J. 473
    , 495 (2006) (holding that an expert's "education, training, and most
    importantly, her experience, provided a sound foundation for her opinion" which
    was "not a net opinion").
    In addition, we reject defendants' assertion that Peña's opinion is
    inadmissible because he did not consider SEI's actual costs.          "An expert's
    proposed testimony should not be excluded merely 'because it fails to account
    for some particular condition or fact which the adversary considers relevant.'"
    A-1852-18T4
    15
    
    Townsend, 221 N.J. at 54
    (quoting Creanga v. Jardal, 
    185 N.J. 345
    , 360 (2005)).
    Peña testified repeatedly that he did not find SEI's actual costs to be relevant to
    a percentage completion analysis for a lump sum contract, and the court
    ultimately agreed. "The expert's failure 'to give weight to a factor thought
    important by an adverse party does not reduce his testimony to an inadmissible
    net opinion if he otherwise offers sufficient reasons which logically support his
    opinion.'" Ibid. (quoting 
    Rosenberg, 352 N.J. Super. at 402
    ).
    Because Peña was qualified to testify as an expert in demolition cost
    analysis and offered sufficient reasons to support his findings and conclusions,
    his opinion was not a net opinion and the court did not abuse its discretio n by
    allowing him to testify.   Moreover, the court's finding that SEI completed at
    least 15 percent of the work is further supported by the credible testimony of
    DiNatale, Rock, and Guzman about their firsthand observations of the work that
    SEI completed, as well as Guzman's daily project status reports which state that
    SEI completed 16 percent of the work under the contract as of December 2013.
    The court's credibility determinations are entitled to deference on appeal.
    
    Cesare, 154 N.J. at 412
    .
    A-1852-18T4
    16
    B. Whether the lien amount was overstated
    There exists support in the record for the judge's finding that the value of
    the work performed by SEI was $450,000. Defendants criticize Guzman's daily
    reports, upon which the court relied, as "inaccurate," of "little probative worth,"
    and "not conclusive with respect to any claim by SEI against BTU" even though
    Guzman     was     BTU's     project   manager     for   the    Werner     project.
    There are multiple problems with these assertions.
    First, defendants claim that Guzman failed to testify about the
    methodology he used to determine percentage completion when he authored the
    daily reports.   However, this contention is belied by the record.        Guzman
    credibly testified that, as project manager, he personally monitored and observed
    SEI on site each day and often discussed the day's tasks with SEI representatives.
    He explained that he discussed the percentage completion figures with Carroll,
    the project manager for CAMS, and that they looked at each task completed to
    arrive at the percentages. We defer to the judge's finding that Guzman testified
    credibly. See 
    Cesare, 154 N.J. at 412
    .
    Second, defendants claim that Guzman's percentage completion figures
    were inaccurate because, as of May 15, 2013, he determined that SEI had
    completed 16 percent of the work, valued at $592,000, but "SEI issued an
    A-1852-18T4
    17
    invoice in the amount of $150,000 for work performed through May 24, 2013 ."
    The judge found, however, that the invoices were not particularly relevant to the
    lien claim or the percentage completion of work by SEI because the parties' lump
    sum contract did not require SEI to maintain cost records.
    As the factfinder in this case, the judge was permitted to assign greater
    evidentiary weight to Guzman's daily project status reports and related
    testimony and less weight to the invoices. See Brill v. Guardian Life Ins. Co.
    of Am., 
    142 N.J. 520
    , 536 (1995) (discussing the "weighing that a factfinder
    (judge or jury) engages in when assessing the preponderance or credibility of
    evidence"). Moreover, DiNatale credibly testified that the invoices were only
    issued pursuant to Carroll's request, and the fact that SEI sought $150,000 from
    BTU in May 2013 is consistent with DiNatale's credible testimony that he had
    negotiated a $150,000 payment with BTU for mobilization costs in May 2013.
    Furthermore, Guzman testified that he did not make monetary valuations of each
    task.     In short, Guzman's percentage completion calculations need not be
    reconciled with the invoices as his calculations have nothing to do with SEI's
    costs.
    Third, defendants claim that Guzman's assessment of percentage
    completion cannot be reconciled with BTU's records pertaining to scrap material
    A-1852-18T4
    18
    removed from the site between April 2013 and December 2013.            But Peña
    credibly testified that the amount of scrap material removed from the site while
    SEI was working is a poor indicator of the work completed because many of
    SEI's contractual tasks, including asbestos abatement, site maintenance,
    demolition of smaller structures, and attendance at meetings, did not generate
    any salvageable scrap material. Because there is little to no correlation between
    the amount of scrap material removed and the tasks that SEI completed,
    defendants' data pertaining to the amount of scrap removed from the site does
    not contradict or undermine Guzman's assessment of percentage completion.
    Contrary to defendants' assertions, Guzman's daily project status reports
    and his testimony thereto constituted adequate, substantial, credible evidence
    that supported the court's finding that the value of the work SEI performed was
    $450,000. Other credible evidence also supported the court's finding, including
    testimony from DiNatale and Rock about the tasks SEI performed through
    December 2013 and Peña's expert opinion that SEI completed 15 percent of the
    work under the contract as of December 2013. Notably, 15 percent of $3.7
    million is $555,000, and SEI sought only $450,000 in its lien claim.
    We reject defendants' argument that SEI's lien was "willfully overstated"
    pursuant to N.J.S.A. 2A:44A-15(a). "[A] willful overstatement connotes an
    A-1852-18T4
    19
    intent to recover that to which the claimant knows he is not entitled; in other
    words, a claim made in bad faith." Legge Indus. v. Joseph Kushner Hebrew
    Acad./JKHA, 
    333 N.J. Super. 537
    , 561 (App. Div. 2000). Defendants failed to
    present any evidence of bad faith and SEI's lien claim is supported by both the
    trial testimony and the documents in evidence. Cf. Patock Constr. Co. v. GVK
    Enters., LLC, 
    372 N.J. Super. 380
    , 388 (App. Div. 2004) (holding that lien was
    willfully overstated where the amount of the lien was neither supported by
    witness testimony nor trial exhibits). Defendants' discussion of Zulla Steel and
    Goldman is once again inapt because both were decided before the CLL and do
    not involve construction lien claims.
    Lastly, defendants contend that the only competent evidence of the value
    of the work performed by SEI is Brower's expert opinion that the reasonable
    value of the work was $169,000—despite the fact that the court rejected
    Brower's opinion in its entirety. As the trier of fact in a non-jury trial, the trial
    judge is empowered "to accept or reject, in whole or in part, the testimony of
    one expert over that of another." Maudsley v. State, 
    357 N.J. Super. 560
    , 586
    (App. Div. 2003). See also LaBracio Family P'Ship v. 1239 Roosevelt Ave.,
    Inc., 
    340 N.J. Super. 155
    , 165 (App. Div. 2001) (indicating that "the weight to
    be given to the evidence of experts is within the competence of the fact-finder").
    A-1852-18T4
    20
    Here, the judge acted well within his authority when he considered and
    soundly rejected Brower's opinion because he used a cost analysis that was "not
    relevant to the contract at hand" and had not "performed an analysis of the
    responsibilities of SEI pursuant to the contract." Moreover, its determination
    that SEI's costs are not relevant to the amount of the lien is supported by the
    CLL's plain language which states that the claimant "shall be entitled to a lien
    for the value of the work or services performed, or materials or equipment
    furnished in accordance with the contract and based upon the contract price[.]"
    N.J.S.A. 2A:44A-3.
    V.
    Defendants contend incorrectly that SEI's lien was untimely filed and
    therefore invalid under N.J.S.A. 2A:44A-15(a). The judge concluded that SEI's
    lien, filed on December 26, 2013, was timely. Specifically, the court found that
    it was "undisputed" that SEI's work "began in April, 2013 and continued until
    demobilization occurred in December, thus making the lien filing timely ." But
    defendants argue there is no evidential support in the record for these
    conclusions.
    The CLL requires claimants to file lien claims "within 90 days from the
    last date of work, services, material or equipment provided for which payment
    A-1852-18T4
    21
    is claimed." Thomas 
    Grp., 163 N.J. at 513
    (citing N.J.S.A. 2A:44A-6(a)).
    "Work" is broadly defined under the CLL as "any activity, including, but not
    limited to, labor, performed in connection with the improvement of real
    property." N.J.S.A. 2A:44A-2.
    Defendants once again rely on the invoices that SEI prepared for Carroll
    and assert that because SEI did not issue any invoices for labor after July 24,
    2013, it neither completed nor sought payment for any work beyond that date
    and thus the lien was untimely filed. This contention is belied by the credible
    testimony of DiNatale, Rock, Guzman, and Peña, who each testified that SEI's
    work on the project continued through December 2013. That work included
    canal plating, as shown in a photograph dated September 30, 2013; 4 cable tray
    work; ongoing daily asbestos-related maintenance activities; maintenance of the
    silt fence to address soil erosion; participating in project meetings and phone
    calls concerning, among other topics, Guzman's daily project status reports and
    4
    Contrary to defendants' assertion, the fact that SEI removed the canal plates
    when it demobilized does not negate the fact their installation, which was
    required under the contract to prevent ACM from entering the water, constituted
    work under the CLL. Their reliance on a 1939 Missouri case, Tallman Co. v.
    Villmer, 
    133 S.W.2d 1085
    , 1086 (Mo. Ct. App. 1939) is misplaced as Tallman,
    involved a mechanic's lien claim for a hot water heater that was brought to a
    premises and never installed. Tallman is factually distinguishable and not
    controlling.
    A-1852-18T4
    22
    EPA approval for the open demolition permit; and submission of safety-related
    documentation to BTU. Additionally, DiNatale received project-related emails
    in October and December 2013 that corroborate the testimony.
    The Statement of Work appended to the contract required SEI to complete
    the activities as part of the project for demolition and abatement of the Werner
    generating station, and they each qualify as work under the statute. The broad
    definition of work codified at N.J.S.A. 2A:44A-2 is not limited to labor.
    Moreover, the lack of invoices for August, September, October, and November
    2013 does not undermine the credible witness testimony upon which the court
    relied. DiNatale testified that Carroll had not requested invoices for August
    through November 2013 and, as the court found, SEI was not required to send
    BTU any invoices under the terms of the lump sum contract.
    Despite the lack of invoices, the record shows that SEI sought payment
    for its work from BTU. DiNatale credibly testified that he asked Rossi for
    $450,000 to begin demolition of the main power plant building in early
    December 2013, before the lien was filed. DiNatale's testimony in this regard
    was corroborated by Rossi's testimony and by text messages between the two.
    Although SEI generated several invoices dated December 2013 that sought
    $450,000, it is not known from the record whether any of those invoices were
    A-1852-18T4
    23
    received by BTU prior to the filing of the lien. Nonetheless, neither the CLL
    nor the parties' contract require invoices to be issued when seeking payment and
    the testimony and text messages constituted adequate, substantial, credible
    evidence to support the court's ruling.
    Defendants further claim that even assuming SEI maintained a presence
    on site and performed asbestos-related housekeeping tasks in the Fall of 2013
    "while the project was delayed," those tasks do not qualify as work under the
    CLL—entitling SEI to a lien—and therefore the lien was untimely filed. This
    somewhat     confusing   claim   appears       to   be   grounded   in   defendants'
    characterization of SEI's lien claim as a delay damages claim. They assert that
    because demolition of the main building was delayed, and because both the
    prime contract between NRG and Werner and the subcontract between Werner
    and BTU contained "no-damage-for-delay" clauses,5 SEI was not entitled to any
    recovery for its asbestos-related housekeeping tasks done during the "delay and
    disruption" of the project.
    5
    Those clauses, which did not appear in SEI's contract with BTU, state that
    "neither party shall be liable for any loss or damage for delay or for
    nonperformance due to causes not reasonably within its control, including . . .
    unusual or extraordinary delays in issuance of permits by Governmental
    Authorities."
    A-1852-18T4
    24
    But this is an action for enforcement of a construction lien. Nothing in
    the record supports defendants' characterization of SEI's lien claim as a claim
    for delay damages, and SEI asserted no such claim in its complaint. As the judge
    found, SEI never sought delay damages and the delayed portion of the job —
    demolition of the main power plant building—was not part of SEI's lien claim.
    Under the CLL, SEI sought to be paid for the work it completed between April
    2013 and December 2013, which was a small percentage of the total work
    contemplated under the contract. Even though demolition of the main power
    plant building was delayed, the credible testimony and documents in evidence
    support the court's conclusion that SEI continuously worked on other ancillary
    aspects of the project through December 2013. The CLL entitles SEI to payment
    for that work.
    VI.
    There is no basis to overturn the judge's award of counsel fees. "A trial
    court's award of attorneys' fees generally is not disturbed unless there is a clear
    abuse of discretion." 
    Patock, 372 N.J. Super. at 390
    (citing Packard-Bamberger
    & Co. v. Collier, 
    167 N.J. 427
    , 444 (2001)). 6 Defendants erroneously contend
    6
    SEI's construction lien was timely filed and not willfully overstated, therefore
    we reject defendants' contention that they are entitled to attorney's fees and costs
    under N.J.S.A. 2A:44A-15(a).
    A-1852-18T4
    25
    that the judge erred by awarding attorney's fees and costs to SEI under N.J.S.A.
    2A:44A-15(b).
    The judge found that "from the time [defendants] received notice that
    Helio Guzman would appear as a witness at trial" to authenticate the daily
    reports he authored, their defenses "were 'without basis' pursuant to N.J.S.A.
    2A:44A-15(b)." Thus, the judge awarded reasonable fees and costs from the
    time defendants were noticed that Guzman had been located and would testify
    (February 22, 2017) in the amount of $80,188.26 which was 100 percent of what
    SEI had requested in its detailed and itemized certification of services. The
    judge rejected defendants' objections to SEI's certification of services and found
    "both the amount of time spent and the rates reasonable per the applicable
    RPCs."
    "[W]ithout basis" is defined as "frivolous, false, unsupported by a
    contract, or made with malice or bad faith or for any improper purpose."
    N.J.S.A. 2A:44A-15(d). Guzman worked for defendant BTU and his daily
    reports coupled with his credible testimony established that: (1) SEI's work on
    the project continued through December 2013 and (2) SEI had completed 16%
    of the work contemplated under the contract, valued at $592,000 of the total
    contract price of $3.7 million.       That said, SEI sought only $450,000.
    A-1852-18T4
    26
    Nonetheless, defendants took the untenable position that the court should ignore
    the testimony of and records kept by Guzman, who was physically present at the
    project observing the work, in favor of the opinion of Brower and find that the
    lien was both willfully overstated and untimely filed.
    Brower's insistence that SEI's costs were relevant to the amount of the lien
    is inconsistent with the CLL's plain language which states that the claimant
    "shall be entitled to a lien for the value of the work or services performed, or
    materials or equipment furnished in accordance with the contract and based upon
    the contract price[.]"   N.J.S.A. 2A:44A-3.     Consequently, SEI expended a
    significant amount of money to litigate the matter due to defendants' frivolous
    defenses that were unsupported by the contract.              Given the unique
    circumstances, it was reasonable for the court to conclude that defendants'
    defenses were without basis and to award SEI attorney's fees and costs.
    Affirmed.
    A-1852-18T4
    27