CITY OF PERTH AMBOY VS. INTERSTATE INDUSTRIAL CORP. VS. IMPERIAL CONSTRUCTION GROUP, INC.(L-2745-06, L-3789-07 AND L-7861-07, MIDDLESEX COUNTY AND STATEWIDE)(CONSOLIDATED) ( 2017 )


Menu:
  •                         NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court."
    Although it is posted on the internet, this opinion is binding only on the
    parties in the case and its use in other cases is limited. R.1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-0778-14T4
    A-0842-14T4
    CITY OF PERTH AMBOY,
    Plaintiff-Respondent/
    Cross-Appellant,
    v.
    INTERSTATE INDUSTRIAL CORP.,
    Defendant-Respondent/
    Cross-Appellant,
    and
    XL SPECIALTY INSURANCE COMPANY
    and S.M. ELECTRIC COMPANY, INC.,
    Defendants,
    and
    TAK CONSTRUCTION, INC.,
    SAFECO INSURANCE COMPANY
    OF AMERICA,
    Defendants-Appellants/
    Cross-Respondents,
    and
    XL SPECIALTY INSURANCE COMPANY,
    Third-Party-Plaintiff,
    v.
    IMPERIAL CONSTRUCTION GROUP,
    INC.,
    Third-Party-
    Defendant-Respondent,
    and
    MICHAEL ZEMSKY, A.I.A.,
    ARCHITECTS AND PLANNERS,
    Third-Party Defendants.
    ________________________________________
    Argued November 29, 2016 – Decided May 17, 2017
    Before Judges Messano, Espinosa and Guadagno.
    On appeal from the Superior Court of New
    Jersey, Law Division, Middlesex County, Docket
    Nos. L-2745-06, L-3789-07 and L-7861-07.
    Benjamin D. Lentz argued the cause for
    appellant/cross-respondent Safeco Insurance
    Company of America (Torre, Lentz, Gamell, Gary
    & Rittmaster, L.L.P., attorneys; Kevin M.
    Gary, on the briefs).
    Geoffrey J. Hill argued the cause for
    appellant/cross-respondent TAK Construction,
    Inc. (Law Offices of Steve M. Kalebic, P.C.,
    attorneys; Steve M. Kalebic, of counsel and
    on the briefs).
    Timothy D. Cedrone argued the cause for
    respondent/cross-appellant   City  of   Perth
    Amboy (Apruzzese, McDermott, Mastro & Murphy,
    attorneys; Mark J. Blunda, of counsel and on
    the brief; Mr. Cedrone, on the briefs).
    Robert S. Cosgrove argued the cause for
    respondent/cross-appellant         Interstate
    Industrial Corp. (Durkin & Durkin, L.L.P.,
    attorneys; Mr. Cosgrove, on the briefs).
    2                           A-0778-14T4
    James J. Ross argued the cause for respondent
    Imperial Construction Group, Inc. (Carroll,
    McNulty & Kull, L.L.C., attorneys; Joseph P.
    McNulty, of counsel and on the brief; Mr.
    Ross, of counsel and on the brief; Michael S.
    Kerr, on the brief).
    PER CURIAM
    These consolidated appeals arise from the construction of a
    municipal complex in the City of Perth Amboy (the City).                  The
    project   envisioned   a   free-standing    building   housing   the    fire
    department and emergency medical services (the first building),
    and a second building containing the public safety department,
    municipal court and community center, which included swimming
    pools and a gymnasium.      The City intended to expedite completion
    of the project within one year.      It decided not to hire a general
    contractor, but rather have its business administrator serve as
    project manager and contemporaneously award contracts to a number
    of prime contractors.         The process was delayed, and the City
    opted to begin awarding contracts seriatim, even though, in some
    instances, plans and specifications were not complete.
    The City awarded multiple contracts, including those to:
    Michael   Zemsky,   A.I.A.,    Architects    &   Planners   (Zemsky),     for
    architectural services; Imperial Construction Group (Imperial),
    for   construction     management;       Interstate    Industrial      Corp.
    (Interstate), for concrete work; and TAK Construction Co. (TAK),
    3                              A-0778-14T4
    the largest contract — $19.774 million — for general construction.
    Safeco Insurance Company of America (Safeco) was TAK's surety, and
    XL Specialty Insurance Company (XL) was Interstate's surety.
    Zemsky was to supply "normal" structural, mechanical and
    electrical "engineering services" for all project phases, from
    design through construction. He was required to prepare all design
    and construction drawings and specifications.
    Imperial     was    the    project's      construction   manager,   with
    responsibility to monitor the quality of contractor work and
    coordinate all work and other activity.            It was to review change
    orders, make recommendations to the City and Zemsky, and negotiate
    final terms with the contractors.               Imperial was charged with
    "immediately causing the remediation of any incorrect work," and
    notifying   the   City    and    Zemsky   of    such   deviations   or   other
    deficiencies, as well as "any situation" that might increase the
    project's cost or delay its completion.
    The contract with Interstate included a time of the essence
    provision that subjected the company to per diem liquidated damages
    if Interstate did not finish on time.             Interstate was subject to
    Imperial's direction about the sequencing of work, but Imperial
    had no authority over Interstate's "means, methods, techniques,
    sequences or procedures of construction."
    4                              A-0778-14T4
    The contract specified that additional time for completion
    was Interstate's only relief against the City, Zemsky, or Imperial
    for the effect of any "delay, obstruction or hindrance for any act
    or omission of" those parties or other contractors, including
    changes      in    work   schedules     or    sequencing.       Additionally,        the
    contract      allowed     the   City,    at       its   convenience,   to    terminate
    Interstate "for any reason" upon seven days' written notice. The
    City could also terminate Interstate for cause within forty-eight
    hours of its failure to begin whatever corrective measures Imperial
    might demand in order to cure or mitigate insufficient progress
    or other defaults on Interstate's contractual obligations.                       Those
    other defaults included the failure to furnish sufficient skilled
    labor or, "in the sole opinion of" Imperial, "in any respect to
    prosecute the work, to insure its completion in the manner and
    within the time determined by [Imperial] or the [City]."
    The    contract       with     TAK     included      identical       provisions
    permitting termination for convenience and for cause, as well as
    time of the essence and liquidated damages provisions.                        TAK was
    to "furnish all labor, materials, equipment, tools and services
    necessary to perform and complete the Project in strict compliance
    with   the        Contract   Documents."            That   included    the    bulk    of
    construction work following site preparation, except for work done
    by other contractors providing structural steel, concrete building
    5                               A-0778-14T4
    foundations and floor slabs, climate control, plumbing, general
    electrical work, and the alarm and building management systems,
    all of which TAK was responsible for coordinating as "project
    coordinator," subject nonetheless to Imperial's direction.
    As with Interstate, Imperial would decide questions about the
    timelines      of   TAK's    work       and    satisfaction           of    its    contractual
    obligations, and Imperial had no authority over TAK's means or
    methods of performance.             TAK also waived delay damages for any
    additional      costs      that     arose      from        Imperial's           direction     and
    acknowledged an extension of time would be its sole remedy against
    the City, Zemsky, or Imperial for delays that resulted from their
    negligence or that of another contractor.
    The project rapidly fell behind schedule.                            The City held TAK
    responsible for the delays, and the parties mediated their dispute.
    In   October    2006,      TAK    and    the       City    executed        a    memorandum     of
    understanding        (MOU),       also    designated            as    a        stipulation      of
    settlement.         The MOU was "a supplement to" TAK's contract and
    stated that, "[e]xcept as set forth herein, all other terms and
    conditions     of    [TAK's]      Contract         remain[ed]         in    full    force     and
    effect." The MOU set October 31, 2006, as the date for substantial
    completion     of    the    first    building,            and   May    15,      2007,    as   the
    completion date for the second building.                        As to each building, the
    City agreed to pay additional sums as "change orders," subject to
    6                                        A-0778-14T4
    the   right   to    impose    penalties       upon   TAK   for   failure    to    meet
    completion dates.
    Although TAK substantially completed the first building in
    December    2006,    disputes    over     TAK's      performance   regarding      the
    second building continued.         On March 26, 2007, Imperial sent TAK
    the forty-eight-hour notice required by the contract before any
    take-over of TAK's work.        It cited scheduling failures and advised
    TAK that the City was taking control of unspecified "portions" of
    TAK's obligations.           It instructed TAK "to increase [its] work
    force, work hours [and] workdays" and "to work two shifts."
    TAK responded the same day, asserting that any delays were
    beyond its control and caused by delays and errors of other prime
    contractors,       design    changes,    and    delayed     responses      to    TAK's
    requests for "decisions, approvals, and answers to" requests for
    information.       Additional disputes arose over the payment of TAK's
    invoices.     In May, TAK notified Imperial that the City was in
    "material breach" of the contract for failing to pay requisitions
    for work TAK completed earlier in the year.
    On May 16, 2007, Imperial sent TAK a notice listing ten
    specific grounds of default.            The letter stated that TAK would be
    terminated "[i]f [it] fail[ed] to correct this default within the
    next seven days." TAK responded by asserting its work was adequate
    and   any   delays    were    caused    by    other    contractors.        The   City
    7                                 A-0778-14T4
    terminated the contract with TAK on May 23, 2007.                Safeco assumed
    TAK's   contractual     responsibilities      in    June   and   completed    the
    project.
    More   problems      arose       regarding     the    second    building,
    particularly as to a trench drain for the proposed pool deck area.
    Imperial believed Interstate had clearly indicated its intention
    to   mobilize   and    address   the    issue,     but   Interstate   adamantly
    indicated that Imperial had not supplied necessary documentation
    and specifications to address an admittedly plain design error in
    Zemsky's plans.
    On   September    23,   2008,    Imperial     sent   Interstate   written
    notice of default for its alleged failure "to mobilize and schedule
    labor and material as required to proceed with the installation
    of rebar and concrete in order to complete the pool deck area."
    The letter gave Interstate seven days to cure the default to avoid
    being terminated on September 30.                Nonetheless, at a project
    meeting held on September 25, the City's representatives told
    Interstate's representatives the company had been terminated.
    Another contractor finished Interstate's remaining work and was
    paid $43,000.
    The City filed the first action in the Law Division against
    Interstate, seeking a declaration that Interstate was not entitled
    to delay damages.      Interstate answered and asserted a counterclaim
    8                              A-0778-14T4
    for wrongful termination and damages.        In the second action, TAK
    filed a complaint in lieu of prerogative writs challenging the
    City's termination of its contract.          As expected, the parties
    asserted cross-claims and counterclaims against each other, and
    other contractors and sub-contractors were added to the suits,
    which were then consolidated.1
    The   judge   dismissed   certain   claims   asserted    by   TAK   and
    Interstate against Imperial on summary judgment.        The bench trial
    began in March 2014, with the only remaining parties being the
    City, Interstate, TAK and Safeco, plus Imperial on the City's
    claim for indemnification.      The testimony did not conclude until
    June.
    In a comprehensive written opinion, which we discuss more
    fully below, the trial judge reviewed the evidence.          As summarized
    in his June 30, 2014 order for judgment, the judge concluded the
    City properly terminated the contract with TAK, but its termination
    of Interstate's contract was for the City's convenience and not
    because of Interstate's default.       The judge further determined the
    City suffered no delay damages from TAK's failure to perform
    because of Zemsky's "concurrent delay in . . . redesigning the
    1
    A third action, brought by the electrical contractor, S.M.
    Electric Company, Inc., was also consolidated with the other
    two, but, prior to trial, all claims by all parties involving
    S.M. Electric were dismissed by stipulation.
    9                               A-0778-14T4
    trench drain and the pool deck structural slab . . . ."                           He
    concluded, however, the City suffered damages from "Interstate's
    failure to provide certain work in compliance with the contract
    . . . ."
    The judge determined Safeco was entitled only to the "full
    contract balance," concluding Safeco was "barred by the . . . the
    Contract . . . from asserting damages for . . . delays . . . ."
    He also found TAK was not entitled to any damages, and Interstate
    failed to prove "it suffered measurable damages as a result of the
    City's    termination     of    its   contract      for   default   rather     than
    convenience."         Lastly, the judge concluded the City failed to
    prove that Imperial breached its contract.
    The court entered final judgment for $221,074.41 in favor of
    the City against Interstate, ordering an offset for the amount of
    the settlement the City reached with XL.              It also entered judgment
    for Safeco for $927,547.38 against the City.                  The court entered
    judgments   of   no     cause   on    Safeco's      counterclaim    for   improper
    termination of TAK and delay damages against the City, and on
    TAK's and Interstate's counterclaims and cross-claims.                    The court
    dismissed all other claims, and subsequently denied Safeco's and
    TAK's motions for reconsideration.
    In A-778-14, Safeco argues that, for various reasons, the
    court    erred   in    concluding     the    City   legally   terminated      TAK's
    10                                 A-0778-14T4
    contract.      It also contends that even if termination was proper,
    the judge should have awarded pre-judgment interest on the contract
    balance and delay damages, despite the contract's exculpatory
    clause.
    In A-842-14, TAK argues its termination was improper for a
    number of reasons.            Interstate cross-appeals, arguing the City
    terminated     its    contract     wrongfully        and   in   bad    faith,      the
    exculpatory clause is unenforceable and it is entitled to delay
    damages.       Interstate also argues the judge erred by granting
    summary    judgment      to    Imperial    on   Interstate's        indemnification
    claim.      The City filed a defensive cross-appeal, arguing its
    indemnification claims against Imperial should survive in the
    event we grant relief to Safeco, TAK or Interstate.
    We have considered these arguments in light of the record and
    applicable legal standards.          We affirm.
    I.
    We set forth the standards that guide our consideration of
    the   issues    raised    on    appeal.        "We   review   the    trial   court's
    determinations, premised on the testimony of witnesses and written
    evidence at a bench trial, in accordance with a deferential
    standard."      D'Agostino v. Maldonado, 
    216 N.J. 168
    , 182 (2013).
    "[W]e do not disturb the factual findings and legal conclusions
    of the trial judge unless we are convinced that they are so
    11                                 A-0778-14T4
    manifestly unsupported by or inconsistent with the competent,
    relevant   and   reasonably   credible   evidence   as   to   offend   the
    interests of justice . . . ."     
    Ibid. (quoting Seidman v.
    Clifton
    Sav. Bank, S.L.A., 
    205 N.J. 150
    , 169 (2011)).
    "[W]e do not weigh the evidence, assess the credibility of
    witnesses, or make conclusions about the evidence."             Mountain
    Hill, L.L.C. v. Twp. of Middletown, 
    399 N.J. Super. 486
    , 498 (App.
    Div. 2008) (quoting State v. Barone, 
    147 N.J. 599
    , 615 (1997)).
    "To the extent that the trial court's decision constitutes a legal
    determination, we review it de novo."     
    D'Agostino, supra
    , 216 N.J.
    at 182 (citing Manalapan Realty, L.P. v. Twp. Comm. of Manalapan,
    
    140 N.J. 366
    , 378 (1995)).
    With these standards in mind, we first address the substantive
    arguments raised by Safeco and TAK.
    II.
    In his written opinion, the trial judge found that Imperial
    repeatedly warned TAK that its performance was deficient.              The
    judge noted that in September 2006, Imperial recommended the City
    terminate TAK because it failed to complete tasks on schedule, and
    it "would not and could not reasonably fulfill [its] obligations
    in the near future."     Instead, the City negotiated the MOU with
    TAK, but "neglected to include any of the other prime contractors
    in the negotiating process."
    12                             A-0778-14T4
    The judge found that in November 2006, Imperial attempted to
    bring together all the prime contractors with responsibilities for
    the pool area in an attempt to reach the May 2007 target completion
    date for the second building.          The judge found, "this was not
    Imperial's responsibility; it was TAK's." The judge also concluded
    that beginning in January 2007, Imperial began notifying TAK of
    its obligations to submit shop drawings and schedules to meet the
    May deadline, and in March, Imperial directed TAK to increase its
    work force and hours. The judge detailed the numerous inadequacies
    Imperial found in TAK's performance and manpower commitment during
    April 2007.
    The judge reviewed the contract's termination provisions and
    the ten reasons listed in the May 16, 2007 notice of termination.
    The judge found "this notice is the culmination of a series of
    notices all related to [Imperial's] opinion, expressed in writing
    and in meeting minutes, that TAK [was] not manning, scheduling or
    coordinating   the   work   properly."     He   concluded,   "the    notice
    comports with the procedural requirements of the contract . . . .
    There is nothing in the evidence to support any notion that TAK
    attempted to cure the ongoing issues, or provide a detailed
    response to evidence a cure."
    The judge also found that the MOU did not "preclude the City
    from exercising its right of termination for cause."            He noted
    13                                A-0778-14T4
    that the City based the termination on more than TAK's inability
    to complete the second building by May 15, 2007.
    The judge also rejected Safeco's and TAK's claim that the
    termination was improper because delays attributable to TAK were
    not on the "critical path" to the project's completion.             The judge
    found "the parties had evidenced a clear intention that the
    completion of the disparate areas of the [second] building was to
    be sequenced."      He cited testimony from "multiple witnesses . . .
    that the City urgently wanted beneficial use of the police area
    first, the courthouse second, and the recreational area last."
    The judge found "other parties [in addition to TAK] bear
    responsibility for the project being abysmally behind schedule."
    However,     he    specifically   noted     TAK's   failure   to    challenge
    Imperial's    "litany    of   over    thirty    pieces   of   correspondence
    detailing the lack of manpower, coordination and scheduling needed
    to move the project . . . ."         In detailed fact-finding implicitly
    rejecting    the    credibility   of    TAK's    principal    and   expressly
    rejecting TAK's expert's testimony, the judge found the City
    properly terminated TAK for failure to employ sufficient skilled
    craftsmen and complete the project in a timely manner; TAK failed
    to make timely submittals for stone work, which denied the City
    "beneficial use of the police and court . . . areas"; and TAK
    failed to "schedule and coordinate all activities at the site."
    14                            A-0778-14T4
    The judge addressed Safeco's claims, finding it was entitled
    to the "full contract balance due and owing," $927,547.38.          Based
    on his earlier findings, he rejected any damages for the City's
    "improper termination" of TAK.      The judge then addressed Safeco's
    "own claim for delay damages based on the time for completion as
    the completing contractor . . . ."       The judge concluded that TAK,
    Interstate and Zemsky all played a part in causing the delays, but
    the exculpatory clause "extend[ed] the protections sought for the
    benefit    of   the   City   to   the    negligence   of   its   retained
    professionals."
    A.
    Safeco and TAK both argue that termination was improper
    because TAK's remaining work at the time was not on the "critical
    path" for completion of the project.         Safeco claims that delays
    in work not on the critical path are not sufficiently material to
    justify the severe remedy of termination.       It also argues that the
    judge constructed other "critical paths" that never existed by
    concluding, contrary to the contract and the MOU, that the second
    building was to be completed in stages.       We reject these arguments
    without extensive discussion.      R. 2:11-3(e)(1)(E).
    Safeco and TAK cite a number of federal precedents for
    support.   See Decker & Co. v. West, 
    76 F.3d 1573
    , 1580 (Fed. Cir.
    1996); Devito v. United States, 
    413 F.2d 1147
    , 1153 (Ct. Cl. 1969);
    15                            A-0778-14T4
    J.D. Hedin Constr. Co. v. United States, 
    408 F.2d 424
    , 431 (Ct.
    Cl. 1969); Sterling Millwrights, Inc. v. United States, 
    26 Cl. Ct. 49
    , 75, 92 (1992).     While these cases hold termination is akin to
    a forfeiture and should not be imposed lightly, they do not hold
    that   delay   in   work   off   a   critical   path   can   never   justify
    termination.    Rather, the decisions may be summarized as holding
    critical path analysis to be         useful in determining delay damages.
    See G.M. Shupe, Inc. v. United States, 
    5 Cl. Ct. 662
    , 728 (1984)
    ("The reason that the determination of the critical path is crucial
    to the calculation of delay damages is that only construction work
    on the critical path had an impact upon the time in which the
    project was completed." (emphasis added)).
    Only a handful of published cases from our courts even discuss
    the concept of critical path scheduling.           See, e.g., P.T. & L.
    Constr. v. State, Dep't of Transp., 
    108 N.J. 539
    , 544 (1987);
    Broadway Maint. Corp. v. Rutgers, State Univ., 
    90 N.J. 253
    , 261
    (1982); Utica Mut. Ins. Co. v. DiDonato, 
    187 N.J. Super. 30
    , 34
    (App. Div. 1982); Am. Sanitary Sales Co. v. State, Dep't of Treas.,
    
    178 N.J. Super. 429
    , 433-34 (App. Div.), certif. denied, 
    87 N.J. 420
    (1981); Edwin J. Dobson, Jr., Inc. v. Rutgers, State Univ.,
    
    157 N.J. Super. 357
    , 367-68 (Law Div. 1978), aff'd sub nom.
    Broadway Maint. Corp. v. Rutgers, State Univ., 
    180 N.J. Super. 350
    (App. Div. 1981), aff'd, 
    90 N.J. 253
    (1982); Buckley & Co. v.
    16                             A-0778-14T4
    State, 
    140 N.J. Super. 289
    , 294 (Law Div. 1975).      None of them
    support the proposition that a contract cannot be terminated unless
    there is delay to work on the critical path to completion.
    B.
    Safeco contends there was no evidence that TAK's alleged
    failure to provide sufficient manpower actually delayed completion
    of the public safety and municipal court sections of the second
    building for the City's "beneficial use," and the judge effectively
    "re-wrote" the contract by ignoring the intended unitary nature
    of the project.   It contends Zemsky and others caused the delays,
    which continued even after Safeco assumed the work.       Finally,
    Safeco claims the judge ignored the City's failure to give TAK
    forty-eight hours to cure defaults.   TAK makes similar arguments,
    stating there was no basis for the judge to conclude the parties
    intended the second building be delivered in piecemeal fashion.2
    2
    TAK also argues that, during the City's earlier motion for
    partial summary judgment, the judge concluded the contract was a
    unitary contract and rejected the City's argument that there were
    differing completion dates for the second building. We have only
    the transcript of the argument, but, in any event, an interlocutory
    "order denying summary judgment . . . decides nothing and merely
    reserves issues for future disposition." Gonzalez v. Ideal Tile
    Importing Co., Inc., 
    371 N.J. Super. 349
    , 356 (App. Div. 2004),
    aff'd, 
    184 N.J. 415
    (2005), cert. denied sub nom. Gonzalez v.
    Komatsu Forklift, U.S.A., Inc., 
    546 U.S. 1092
    , 
    126 S. Ct. 1042
    ,
    
    163 L. Ed. 2d 857
    (2006).
    17                         A-0778-14T4
    In essence, these arguments require us to reject the judge's
    factual findings, which we refuse to do. The evidence demonstrates
    TAK acknowledged the anticipated delivery of the public safety and
    court portions of the second building would precede the troubled
    pool deck area.   On June 28, 2006, TAK sent Imperial a schedule
    and sequencing update for the entire project.     TAK noted this
    comported with Imperial's request to bifurcate the work on the
    second building, with separate completion dates "to meet the
    Owner's recently desired priorities of the Police and Court areas
    followed by the Recreation [portion's] Daycare, Gymnasium, and
    Pool areas." Each of the more than 350 items in the update had its
    own schedule and completion date, with final completion projected
    for March 27, 2007, and a certificate of occupancy to be issued
    on April 10, 2007.   This alone supports the judge's conclusion
    that the parties anticipated the City's earlier beneficial use of
    the public safety and municipal court portions of the second
    building.
    As to TAK's failure to supply adequate skilled labor, the
    judge relied on Imperial's repeated and specific requests in March
    and April 2007, particularly in areas where there would be no
    disruption of ongoing work or its completion.    To the extent we
    have not specifically addressed Safeco's and TAK's other claims
    18                         A-0778-14T4
    in this regard, they lack sufficient merit to warrant discussion
    in a written opinion. R. 2:11-3(e)(1)(E).
    Safeco also contends the judge found a basis for termination
    that the City never asserted, namely, TAK's alleged failure to
    coordinate the work of other prime contractors.              However, the
    City's notice of termination cited TAK's breach of various articles
    of the contract, including Article VIII, which placed upon Imperial
    the obligation to settle "all questions concerning the acceptable
    fulfillment of the Contract by [TAK]."         In its contract, TAK was
    the   designated    "project   coordinator"    with     responsibility     to
    "[p]rovide    overall   coordination    of   the   [w]ork   of    all   other
    [c]ontractors."     The judge cited the cumulative effect of TAK's
    failure to coordinate and schedule the work of other prime and
    subcontractors.
    Safeco and TAK argue the judge erred in concluding TAK's
    delay in furnishing certain stone samples caused a significant
    delay in the public safety and municipal court portions of the
    second building.     TAK also argues that the judge's finding that
    Zemsky was negligent precluded the conclusion that TAK materially
    breached the contract, and it also contends that, under the terms
    of the MOU, the City's remedy was limited to liquidated damages.
    These   arguments   lack   sufficient    merit     to   warrant   extensive
    discussion.    R. 2:11-3(e)(1)(E).
    19                               A-0778-14T4
    The judge did not find that TAK's delay in submitting samples
    was a breach.    Rather, the judge noted Imperial's concern that TAK
    was not taking into account the long lead time for the stone
    materials to arrive once ordered.         In any event, for the reasons
    already stated, there was sufficient, credible evidence in the
    record to support the judge's conclusion that delays attributable
    to TAK's breaches justified its termination.
    We construe the legal import of the MOU de novo.            See e.g.,
    Fastenberg v. Prudential Ins. Co. of Am., 
    309 N.J. Super. 415
    , 420
    (App. Div. 1998) ("Interpretation and construction of a contract
    is [sic] a matter of law for the court subject to de novo review.").
    By its express terms, the MOU supplemented the original agreement
    and expressly continued the contract's other terms.              We reject
    TAK's argument that the MOU modified them.
    Lastly, TAK cites no authority for the proposition that other
    concurrent causes for delay barred the City's right to terminate
    the contract.         We have not recognized such an "all-or-nothing"
    approach and, instead, have held that even as between owner and
    contractor,     the    appropriate   solution   is   an   apportionment   of
    damages occasioned by concurrent delays.             Am. Sanitary 
    Sales, supra
    , 178 N.J. Super. at 434.
    20                            A-0778-14T4
    C.
    Safeco and TAK also argue the judge did not consider that the
    City's failure to pay TAK's early-2007 requisitions was a material
    breach   barring   the   City   from     declaring    TAK's   default.      TAK
    additionally argues the failure to pay evinces the City's bad
    faith.   The City contends TAK was not "entitled" to payment of the
    submitted requisitions in spring 2007, nor was it permitted by the
    contract to delay or withhold required performance over disputes
    about payment.     We agree with the City.
    "When there is a breach of a material term of an agreement,
    the non-breaching party is relieved of its obligations under the
    agreement."     Nolan v. Lee Ho, 
    120 N.J. 465
    , 472 (1990) (citing
    Stamato & Co. v. Borough of Lodi, 
    4 N.J. 14
    (1950)).              Failure to
    pay may be a material breach under the common law even if the
    contract fails to name it as a ground of default and termination.
    Ingrassia Constr. Co. v. Vernon Twp. Bd. of Educ., 
    345 N.J. Super. 130
    ,   136-37   (App.    Div.   2001).       If   the   shortcomings     in    a
    contractor's     work    are    not     significant     enough   to   justify
    withholding payment, then the owner's failure to make payments as
    required is such a breach.            Zulla Steel, Inc. v. A & M Gregos,
    Inc., 
    174 N.J. Super. 124
    , 131 (App. Div. 1980).                  However, a
    statement by the contractor of its "implied . . . willingness to
    resume service upon payment . . . waive[s] the materiality of the
    21                             A-0778-14T4
    breach."    Magnet Res., Inc. v. Summit MRI, Inc., 
    318 N.J. Super. 275
    , 287 (App. Div. 1998).
    Although the judge did not address the issue directly, he
    specifically rejected TAK's claim that the City had earlier delayed
    payments    because   of   political    reasons,   noting    the    evidence
    revealed TAK received its payments at that time without delay.
    The unpaid requisitions TAK asserted as evidence of the City's
    material breach were the subject of significant controversy at
    trial.
    For   example,   Zemsky   suggested    checks    be    drawn   but   not
    tendered, citing pages of inadequacies in TAK's submissions. TAK's
    principal testified that despite serving the May 15, 2007 letter
    alleging the City's breach for non-payment, the company continued
    to pay subcontractors so as not to slow the completion of TAK's
    work.    Imperial's representative testified at trial that, despite
    TAK's claim, the items requisitioned for payment were incomplete,
    there was still work TAK needed to do and some of it was unaffected
    by disputes with other prime contractors.            In short, there was
    substantial, credible evidence in the record to support the judge's
    implicit conclusion that the City's failure to pay previously
    requisitioned work was not a material breach of the contract and
    did not foreclose the City from legally terminating TAK's contract.
    22                               A-0778-14T4
    We also reject TAK's assertion of bad faith by the City.                    As
    Judge Skillman wrote, "To show bad faith, the claimant must
    establish   that    the    alleged   breaching      party   had     an   'improper
    motive.'" Capital Safety, Inc. v. State, Div. of Bldgs. & Constr.,
    
    369 N.J. Super. 295
    , 301 (App. Div. 2004) (quoting Wilson v.
    Amerada Hess Corp., 
    168 N.J. 236
    , 251 (2001)).               The judge clearly
    rejected any claim that the City acted in bad faith, and the record
    evidence provides no reason to conclude otherwise.
    D.
    Safeco    contends     the   judge     erred   in   denying    pre-judgment
    interest on the damage award.         The judge did not address the issue
    in the order for judgment or in his written opinion.                 The judge's
    September     19,   2014    order    that    denied      Safeco's    motion     for
    reconsideration also denied pre-judgment interest.
    The City correctly notes that Safeco did not include that
    order in its notice of appeal, and only orders included in the
    notice of appeal are subject to our review.                 30 River Court E.
    Urban Renewal Co. v. Capograsso, 
    383 N.J. Super. 470
    , 473-74 (App.
    Div. 2006).3    Safeco counters by stating in its reply brief that
    a demand for pre-judgment interest was "inherent in its claim for
    the contract balance."
    3
    TAK included the order denying reconsideration in its notice of
    appeal.
    23                                  A-0778-14T4
    "Although prejudgment interest in a tort action is expressly
    governed by R. 4:42-11(b), 'the award of prejudgment interest on
    contract and equitable claims is based on equitable principles.'"
    Litton Indus., Inc. v. IMO Indus., Inc., 
    200 N.J. 372
    , 390 (2009)
    (quoting Cty. of Essex v. First Union Nat'l Bank, 
    186 N.J. 46
    , 61
    (2006)).    "Thus the award of prejudgment interest in a contract
    case is within the sound discretion of the trial court."                
    Ibid. Here, the sparse
    record hampers our ability to review Safeco's
    contention.     Safeco did not raise the issue in its post-trial/pre-
    judgment brief, which is in the appellate record, and the issue
    was   not   raised   at   oral     argument    on   Safeco's      motion      for
    reconsideration.     In short, there is no basis for us to conclude
    Safeco ever argued the point, much less that the judge mistakenly
    exercised his discretion by denying pre-judgment interest.
    III.
    Turning to the issues raised in its cross-appeal, the judge
    found that Interstate was "one of the first contractors to begin
    its work," was given a one-hundred day timetable for completion
    and   rightly   assumed   "other    prime     contracts   would    be    issued
    contemporaneous with its contract."           By January 2005, Interstate
    had completed most of its work on the first building and signaled
    an intention to demobilize for lack of work.         Interstate completed
    most of its work on the second building before it became apparent,
    24                                  A-0778-14T4
    in fall 2005, that Zemsky's design specifications were wrong, and
    the flooring subcontractors could not make their installations
    upon the concrete slabs Interstate poured.         The judge concluded
    other design flaws were discovered when Interstate mobilized to
    work at the pool deck area.
    The judge considered the four grounds for termination in
    Imperial's September 2008 notice.        He concluded the City failed
    to demonstrate it paid Safeco or other contractors to remediate
    Interstate's unsatisfactory work after termination.         Instead, any
    additional work was "necessary to harmonize the discrepancies in
    the tolerances inherent in the contract documents."           The judge
    also concluded the City failed to permit Interstate to cure any
    alleged defaults, and therefore, the "termination . . . was not
    for cause."
    Instead, he construed the termination as one for the City's
    convenience,   and,   pursuant   to    the   contract,   Interstate   was
    entitled to "compensation 'for . . . authorized services rendered
    . . . up to that date, and for all reasonable shutdown costs as
    agreed to by both parties.'"      The judge found it was undisputed
    that the contract's unpaid balance was $43,000, and "the remaining
    work . . . exceeded this amount." The judge concluded Interstate's
    other damage claims were speculative.
    25                            A-0778-14T4
    In its cross-appeal, Interstate claims the judge erred by
    concluding      the      City    properly        terminated    the    contract     for
    convenience.     It argues the City's attempted termination for cause
    evidenced    bad      faith,     entitling       Interstate    to    delay   damages,
    despite the exculpatory clause in the contract.4
    We have followed the decisions of federal courts, which "have
    broadly   construed        termination       for    convenience      provisions     to
    authorize termination for any reason that is in the best interests
    of the government so long as the contracting agency does not act
    in bad faith."           Capital 
    Safety, supra
    , 369 N.J. Super. at 300
    (citations omitted).            "Mere error on the part of the Government,
    even if it would constitute sufficient ground for contractual
    breach were the termination clause inapplicable, is insufficient
    to   overcome      the    presumption       of    regularity    inherent      in   the
    invocation of the termination for convenience."                      
    Ibid. (quoting Kalvar Corp.
    v. United States, 
    543 F.2d 1298
    , 1303 (Ct. Cl. 1976),
    cert. denied, 
    434 U.S. 830
    , 
    98 S. Ct. 112
    , 
    54 L. Ed. 2d 89
    (1977)).
    The contractor's burden to prove bad faith is "very weighty."                      
    Id. at 301
    (quoting Krygoski Constr. Co. v. United States, 
    94 F.3d 4
      The judge's opinion did not explain in any detail the reasons
    for, or calculation of, the judgment of $221,071.41 in favor of
    the City, subject to an offset for the amount of the City's
    settlement with XL.   However, Interstate has not appealed from
    that portion of the judgment.
    26                                   A-0778-14T4
    1537, 1541 (Fed. Cir. 1996), cert. denied, 
    520 U.S. 1210
    , 117 S.
    Ct. 1691, 
    137 L. Ed. 2d 819
    (1997)).
    Interstate does not challenge the City's ability to terminate
    the contract for convenience.            Rather, it contends the City's
    attempted    termination   for    cause,    as   well    as   other     conduct,
    demonstrates the City intended to make Interstate a "scapegoat"
    for delays occasioned by others.         Interstate argues it proved the
    City acted in bad faith.
    The circumstances are unusual in that, even at trial, the
    City argued it properly terminated Interstate for cause.                      The
    judge rejected that argument and concluded the termination was
    properly for the City's convenience.             In any event, the judge
    entered judgment for the City against Interstate, and Interstate
    has   not   challenged   that    portion   of    the    judgment   on    appeal.
    Implicit in that finding was the judge's rejection of any claim
    that the City acted in bad faith.           Moreover, in addressing the
    impact of the exculpatory clauses, the judge explicitly found the
    City did not act in bad faith.        We therefore reject Interstate's
    argument the termination for convenience was improper.
    Interstate also contends the judge erred by dismissing its
    cross-claim against Imperial on summary judgment.                  Interstate
    argues it was an intended third-party beneficiary of Imperial's
    contract, and Imperial's contractual duties of proper management
    27                                  A-0778-14T4
    and coordination of the project flowed to Interstate as well as
    to the City.       Interstate contends the web of contracts for the
    project gave Imperial an enforceable duty to supervise, manage,
    and coordinate the project.         We disagree.
    In granting Imperial summary judgment, the judge reasoned the
    various contracts made clear that Imperial did not have "any
    authority or any responsibility for means, methods, sequences
    procedures.     And [it was] not . . . responsible for it."                Under
    the    circumstances,     the    judge    concluded     none    of   the   prime
    contractors had a cause of action against Imperial as implied
    third-party beneficiaries of Imperial's contract with the City.
    "The principle that determines the existence of a third party
    beneficiary status focuses on whether the parties to the contract
    intended others to benefit from the existence of the contract, or
    whether the benefit so derived arises merely as an unintended
    incident of the agreement."         Broadway 
    Maint., supra
    , 90 N.J. at
    259.    "The contractual intent to recognize a right to performance
    in the third person is the key.           If that intent does not exist,
    then the third person is only an incidental beneficiary, having no
    contractual standing."      
    Ibid. In Broadway Maintenance,
         which   involved      a    multi-prime
    contract    with   a   general   contractor,      the   owner   allocated     all
    coordination duties to the general contractor in order to insulate
    28                                 A-0778-14T4
    itself from liability for damages to any contractor arising from
    lack of coordination.            
    Id. at 256-58.
                     The Court upheld that
    arrangement and ruled that the prime contractors could assert such
    claims only against the general contractor.                         
    Id. at 266-68.
    The   Court    explained       how       the    provisions       of    the    various
    contracts "expressly" created mutual expectations that "failure
    to comply could cause damages to other prime contractors," damages
    would    "be   paid     by    other        prime       contractors      whose       improper
    performance       caused     delay,"       and    "[i]f      a    contractor        were   the
    wrongdoer, [it would] pay those damages" itself.                         
    Id. at 261-62.
    Such a "promise to pay the damages of a fellow prime contractor"
    was "strong evidence that the injured prime contractor is an
    intended beneficiary who may enforce that promise."                           
    Id. at 262.
    Imperial's     contract       in    this       case    was    devoid    of    similar
    obligations to other contractors.                     By the terms of its contract,
    Imperial was required to cooperate only with the City and Zemsky,
    it provided express indemnification only to them and the contract
    disclaimed liability for the harm that any contractor might sustain
    from    another     contractor's       failure         to    coordinate.        In    short,
    regardless     of     the     extent       of     Imperial's         responsibility          to
    coordinate, it plainly was not an enforceable duty running to the
    contractors.          The    judge        properly       granted      Imperial       summary
    judgment.
    29                                       A-0778-14T4
    IV.
    Citing    Broadway       Maintenance,      the    judge      concluded    the
    exculpatory clauses in Safeco's and Interstate's contracts were
    enforceable unless they violated public policy.                He construed the
    contracts in this case to "extend the protections sought for the
    benefit   of   the     City     to   the     negligence      of    its   retained
    professionals."      The judge concluded Zemsky was negligent and the
    City "persisted in its belief . . . [Zemsky] was properly handling
    the issues . . . ."       Although in "hindsight" the City was wrong,
    its error was not based upon bad faith or unfair dealing.                       He
    rejected any argument that Zemsky's negligence was unforeseen by
    the contractors.     The judge concluded the exculpatory clauses were
    enforceable and barred any claim for delay damages.
    Both Safeco and Interstate argue it was error to enforce the
    exculpatory clauses.      Safeco contends it was entitled to recover
    the fees it paid to FAA, a construction manager it hired to
    complete TAK's work, because Zemsky's negligence was imputed to
    the City and precludes enforcement of the exculpatory clause.                    It
    also argues the City acted in bad faith and the delays were
    unanticipated when TAK entered into the contract.
    Interstate      contends    its   contract       was   ambiguous    and   the
    exculpatory clause should not be enforced because of the City's
    bad faith in endeavoring to avoid the consequences of Zemsky's
    30                                A-0778-14T4
    negligence.   It also argues the City's decision to award contracts
    without complete plans was an independent source of negligence.
    When the Local Public Contracts Act, N.J.S.A. 40A:11-1 to -39,
    was enacted in 1971, L. 1971, c. 198, §§ 1-39, the Legislature
    allowed   publicly      bid,   local     government       contracts       to    include
    exculpatory     clauses        denying        delay    damages         and     limiting
    contractors' remedies to extensions of time.                     N.J.S.A. 40A:11-19
    (2000).   However, in 2001, the Legislature declared it was "void,
    unenforceable     and    against    public       policy      .   .   .   to    limit    a
    contractor's remedy for the contracting unit's negligence, bad
    faith, active interference, tortious conduct, or other reasons
    uncontemplated     by    the    parties        that    delay     the     contractor's
    performance, to giving the contractor an extension of time."
    Ibid.; L. 2001, c. 206, § 1.        No reported cases have construed the
    amended provision.       Cf.    Broadway 
    Maintenance, supra
    , 90 N.J. at
    269-70 (addressing only non-local government agencies or claims
    that predated the amendment).
    "The fundamental objective of statutory interpretation is to
    identify and promote the Legislature's intent."                      Parsons ex rel.
    Parsons v. Mullica Twp. Bd. of Educ., 
    226 N.J. 297
    , 307 (2016)
    (citing   State   v.    Gelman,    
    195 N.J. 475
    ,   482     (2008)     (citing
    DiProspero v. Penn, 
    183 N.J. 477
    , 492 (2005))).                      "In construing
    any statute, we must give words 'their ordinary meaning and
    31                                    A-0778-14T4
    significance,' recognizing that generally the statutory language
    is 'the best indicator of [the Legislature's] intent.'"           Tumpson
    v. Farina, 
    218 N.J. 450
    , 467 (2014) (alteration in original)
    (quoting 
    DiProspero, supra
    , 183 N.J. at 492).      "However, not every
    statute is a model of clarity.         When the statutory language is
    sufficiently ambiguous that it may be susceptible to more than one
    plausible interpretation, we may turn to such extrinsic guides as
    legislative history, including sponsor statements and committee
    reports."    Wilson ex rel. Manzano v. City of Jersey City, 
    209 N.J. 558
    , 572 (2012) (citing Burns v. Belafsky, 
    166 N.J. 466
    , 473
    (2001)).
    We conclude the Legislature did not intend to broaden a public
    entity's liability by permitting the negligence of its agents or
    independent contractors to be imputed to the public entity.             We
    reach this conclusion for a number of reasons.
    Initially, the plain language of the statute provides the
    contractor's remedy cannot be limited to an extension to complete
    the work because of the "contracting unit's negligence, bad faith,
    active     interference,   tortious     conduct,   or   other    reasons
    uncontemplated by the parties."        N.J.S.A. 40A:11-19.       N.J.S.A.
    40A:11-2(1)     defines    a   "contracting   unit"     as   a   county,
    municipality, and certain local governmental boards, commissions,
    authorities, and agencies.      The definition does not include the
    32                             A-0778-14T4
    agents or independent contractors of the "contracting unit." 
    Ibid. In other words,
    the exculpatory clauses in these contracts did not
    violate public policy, except to the extent they exculpated the
    City's     own   conduct.        There    is   nothing      to   suggest   that       the
    Legislature intended the negligent conduct of Zemsky or Imperial
    could be imputed to the City so as to transform a contract that
    did not violate public policy as to the City's agents into one
    that    violated    public    policy      as   to    the   City,   thereby        making
    cognizable a damage claim against the City that otherwise did not
    exist.
    Additionally, the history accompanying the 2001 amendment
    makes    clear   the   Legislature       never      intended     that   contractors'
    remedies could be broadened by imputing the negligence of others
    to   the     contracting     unit.       The   Assembly      sponsor's     statement
    described     the   amendment     as     "allow[ing]       contractors     to    submit
    claims of delay caused by the contracting unit to the contracting
    unit for consideration."          Sponsor's Statement to A. 2913 (Nov. 9,
    2000) (emphasis added).            The purpose of the amendment was "to
    create an incentive for the contracting unit to work cooperatively
    with the contractor to resolve project issues in a timely manner."
    
    Ibid. The amendment was
      "modeled"      after      identical    language       in
    L. 1994, c. 80, § 1, which amended N.J.S.A. 2A:58B-3.                       Assembly
    33                                    A-0778-14T4
    Local Gov't Comm., Statement to A. 2913 (Jan. 18, 2001).                  That
    1994 enactment similarly prohibited contracts with state agencies
    from having exculpatory clauses that barred delay damage claims
    arising from a state agency's "negligence, bad faith, active
    interference, or other tortious conduct."          N.J.S.A. 2A:58B-3(b).
    However, that amendment also expressly restricted delay damage
    claims against a state agency based on the imputed negligence of
    an agent:     "Nothing in this section shall be deemed to void any
    provisions in a contract, agreement or purchase order which limits
    a contractor's remedy for delayed performance caused by reasons
    contemplated by the parties nor shall the negligence of others be
    imputed to the State."     N.J.S.A. 2A:58B-3(c) (emphasis added); L.
    1994, c. 80, § 1(c).       The Senate sponsor's statement confirmed
    that the prohibition barring delay damage claims "applies solely
    to the public entity's use of these clauses to exculpate its own
    negligence or intentional tort[i]ous acts but does not allow a
    contractor to impute the sole negligence of third parties to the
    public entity."     Sponsor's Statement to S. 977 (May 5, 1994).
    In short, although we disagree with the judge's reasoning,
    we agree the exculpatory clauses in this case barred any claims
    by   Safeco   or   Interstate   against   the   City   for   delay   damages
    occasioned by the negligence of Zemsky or other contractors.               For
    the reasons that follow, we also reject any claim that Safeco or
    34                                A-0778-14T4
    Interstate may recover delay damages from the City based on the
    City's independent "negligence, bad faith, active interference,
    tortious conduct, or other reasons uncontemplated by the parties."
    N.J.S.A. 40A:11-19.
    In its brief, Interstate argues the City acted in bad faith,
    a claim the judge rejected and we affirm, and Zemsky's negligence
    should be imputed to the City, which we reject for the reasons
    already stated.   It also argues all delays were "uncontemplated"
    and therefore not subject to the exculpation clause pursuant to
    N.J.S.A. 40A:11-19.   The judge, however, concluded the parties
    could anticipate an architect's negligence.   For the reasons that
    follow, we need not address that specific conclusion by the judge.
    Interstate's contract limited damages upon termination for
    convenience to "all reasonable shutdown costs as agreed to by both
    parties."   Interstate fails to explain how, having been properly
    terminated for convenience, it can nonetheless recover any kind
    of damages beyond those permitted by the contract.       Nor does
    Interstate explain how it is entitled to delay damages, given the
    court's final judgment against the company for $221,074.41 in
    favor of the City, which Interstate has not challenged on appeal.
    Interstate also fails to explain what consequence the settlement
    reached by its surety, XL, which has not participated in these
    appeals, has upon this argument.
    35                         A-0778-14T4
    Safeco contends it was entitled to delay damages both before
    and   after    Safeco   took   over   TAK's   work    because     of   Zemsky's
    negligence, because of the City's lack of good faith and fair
    dealing and because the delay was uncontemplated.                 As noted, we
    reject the first argument and, in his findings and conclusions,
    the judge rejected the second, which we affirm.
    Safeco    arguably   asserted    a   claim     that   the    City's    own
    negligence was responsible for uncontemplated delays, and the
    judge found a project that was supposed to be completed in one
    year was not completed for nearly four years.                   In its post-
    trial/pre-judgment submission, citing certain treatises and cases
    from other jurisdictions, Safeco contended it was entitled to
    "recover its costs to complete and related damages if it can prove
    a wrongful termination."         In other words, Safeco premised its
    delay damage claim on the assertion that the City had not properly
    terminated TAK.
    Safeco fails to supply us with any authority that supports
    the position that a surety, whose insured has been properly
    terminated, may assert a claim for delay damages occasioned, at
    least in part, by the insured's failure to perform the contract.
    Safeco also fails to explain how such a damage claim, even if
    cognizable, should be apportioned to reflect the concurrent causes
    36                               A-0778-14T4
    for the delay the judge found in this case.   We therefore reject
    Safeco's claim for delay damages.
    Affirmed.
    37                         A-0778-14T4