WEST RAC CONTRACTING CORP. v. SAPTHAGIRI, LLC (L-7918-20, BERGEN COUNTY AND STATEWIDE) ( 2022 )


Menu:
  •                                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2355-20
    WEST RAC CONTRACTING
    CORP.,
    Plaintiff-Respondent,
    v.
    SAPTHAGIRI, LLC,
    Defendant-Appellant.
    ___________________________
    Argued February 28, 2022 – Decided March 28, 2022
    Before Judges Vernoia and Firko.
    On appeal from the Superior Court of New Jersey, Law
    Division, Bergen County, Docket No. L-7918-20.
    Scott H. Bernstein argued the cause for appellant
    (Skolnick Legal Group, PC, attorneys; Martin P.
    Skolnick and Scott H. Bernstein, on the briefs).
    Parshhueram T. Misir argued the cause for respondent
    (Forchelli  Deegan     Terrana,      LLP,  attorneys;
    Parshhueram T. Misir, on the brief).
    PER CURIAM
    Defendant Sapthagiri, LLC appeals from orders dismissing its
    counterclaim seeking vacatur of an arbitration award entered in favor of plaintiff
    West Rac Contracting Corp. and affirming the award. The arbitration award
    resolved plaintiff's claims for compensation for certain costs incurred during
    periods of delay in the construction of a hotel. On appeal, defendant argues the
    trial court erred by failing to vacate the arbitration award because the arbitrator
    manifestly disregarded the law, exceeded his powers, refused to hear relevant
    and pertinent evidence, and was evidently partial towards plaintiff.
    Unpersuaded, we affirm.
    I.
    The parties contracted for plaintiff to serve as the construction manager
    for the construction of a hotel on defendant's property. The parties executed
    four separate agreements (collectively the "Contract Agreements") related to the
    construction. Three of the agreements were executed on May 27, 2015, and, on
    December 21, 2017, the parties entered into a Rider to the Contract (the GMP
    Rider). The Contract Agreements provide that any disputes shall resolved by
    the American Arbitration Association (AAA) in accordance with its
    "Construction Industry Arbitration Rules."
    A-2355-20
    2
    The Contract Agreements limit plaintiff's compensation to the "Contract
    Sum," which is comprised of the "Cost of Work . . . plus the Construction
    Manager's Fee." The three May 27, 2015 agreements provide that the "Contract
    Sum" would not exceed the Guaranteed Maximum Price (the GMP), and that the
    GMP would be agreed upon in a subsequently executed GMP amendment. The
    May 27, 2015 agreements further provided that to the extent the "Cost of Work"
    exceeded the GMP, plaintiff would "bear such costs in excess of the [GMP]
    without reimbursement or additional compensation."
    On December 21, 2017, the parties executed the GMP Rider setting a GMP
    of $25,900,925.55 and establishing a construction completion date of May 8,
    2019. The GMP Rider further included the following provision addressing
    plaintiff's entitlement to compensation in the event of construction delays: "[i]n
    the event that the [c]onstruction phase is delayed through no fault of [plaintiff],
    [plaintiff] shall be entitled to the additional or extended general conditions, if
    any, it incurs as a result."
    The Contract Agreements provide the GMP is subject to adjustment
    through the execution of change orders. A change order is defined as a "written
    instrument" in which the parties may agree to a "change in Work," changes to
    the "Contract Sum," and changes to the "Contract Time," without invalidating
    A-2355-20
    3
    the Contract Agreements. The agreements provided that a change order may
    only be issued in the event of a delay "beyond [plaintiff's] control" or for other
    reasons authorized by defendant.
    Construction of the hotel was not completed by the GMP Rider's May 8,
    2019 completion date. A temporary certificate of occupancy was not issued
    until April 16, 2020, and construction was not substantially completed until
    April 30, 2020.    However, prior to completion of construction, the parties
    executed numerous change orders extending the completion date and increasing
    the GMP.
    In July 2019, plaintiff filed a demand for arbitration asserting it a claim
    of "its extended costs due to [seven] months of delay" in the completion of the
    hotel "caused by [defendant] and its design professionals." Defendant filed an
    answer and counterclaim alleging plaintiff breached the parties' contract and
    violated the covenant of good-faith and fair-dealing. There is no verbatim
    record or transcription of the ensuing five-day arbitration.
    In his December 9, 2020 award, the arbitrator determined plaintiff was
    entitled to compensation for some, but not all, of its claimed expenses related to
    the construction delays. He concluded that under the GMP Rider plaintiff was
    "entitled to recover its proven general conditions and general requirements for
    A-2355-20
    4
    the period of actual delay for which it was granted time extensions in the
    executed change orders." 1     More particularly, he found the GMP Rider
    "expressly allowed recovery to [plaintiff] for periods of delay for which it bore
    no responsibility." The arbitrator also rejected some of plaintiff's claims for
    increased costs allegedly caused by the delays, finding one of plaintiff's
    requested claims was barred by the Contract Agreements' waiver of
    consequential damages.
    The arbitrator determined plaintiff was entitled to $1,101,488.71 in
    increased costs due to the delays and found defendant had paid plaintiff
    $549,970 of the sum under protest prior to the arbitration.        The arbitrator
    concluded plaintiff was due a total "net award of $551,518.71."
    During the arbitration, defendant requested the arbitration award include
    a reservation of defendant's right to litigate in separate proceedings any claims
    1
    The Contract Agreements do not clearly define "general conditions" or
    "general requirements." However, the GMP Rider distinguishes between the
    two, stating "[t]he GMP includes the [plaintiff's] general conditions which are
    intended to compensate [plaintiff] only for its management and associated
    burdens." The GMP Rider provides general requirements are not part of
    plaintiff's general conditions, but instead are "included in the GMP as a Cost of
    Work." It also includes examples of "general requirements such as site trailer,
    phones, blueprinting, laborers, temp toilets, temp fencing, etc." Before the trial
    court, defendant's counsel offered plaintiff's payment of employees as an
    example of a general condition. General requirement costs were broadly
    characterized by defendant's counsel as "on-site expenses."
    A-2355-20
    5
    defendant had or might have in the future against plaintiff for indemnification
    for subcontractor liens on the construction project and any claims defendant
    might have against plaintiff for a claim defendant asserted arose during the
    testimony of the final witness, plaintiff's president, concerning a "related party
    transaction" that is prohibited under the Contract Agreements. In the award, the
    arbitrator expressly declined defendant's request for the reservation of rights
    related to those claims.
    Following issuance of the arbitration award, plaintiff filed a complaint
    pursuant to Rule 4:67-1 to confirm the arbitration award. Defendant filed an
    answer and counterclaim to vacate the arbitration award. Defendant argued the
    award should be vacated because: the arbitrator manifestly disregarded the law
    in his interpretation of the Contract Agreements; the arbitrator exceeded his
    authority by ignoring the plain language of the agreements; the arbitrator refused
    to consider material evidence related to who was at fault for construction delays;
    the arbitrator exceeded his power by refusing to reserve defendant's rights to
    pursue certain claims, potentially precluding defendant from asserting them in
    the future; and the arbitrator was evidently partial to plaintiff.
    After hearing argument, the court rendered a bench opinion first noting
    neither party had addressed whether the New Jersey Arbitration Act (NJAA),
    A-2355-20
    6
    N.J.S.A. 2A:23B-1 to -36, or the Federal Arbitration Act (FAA), 
    9 U.S.C.S. §§1
    to -16, should be applied in consideration of the parties' arbitration award.
    However, under either statute's standard for vacatur, compare N.J.S.A. 2A:23B-
    23 with 
    9 U.S.C.S. § 10
    , the court found the same conclusion would result.
    The court applied the United States Supreme Court's holding in Oxford
    Health Plans LLC v. Sutter, 
    569 U.S. 564
     (2013), as the standard for determining
    whether the award should be vacated based on defendant's claims the arbitrator
    exceeded his authority and the arbitrator's decision was founded on manifest
    disregard of the law. The court explained that under the Oxford Health standard,
    an award must be confirmed so "long as the arbitrator considered the parties'
    contract and issued a ruling based upon his interpretation of the
    contract . . . [e]ven if the arbitrator committed a grave error."     The court
    concluded the arbitrator had done "what he was supposed to do" and the court
    declined to vacate the award on those grounds.
    The court also rejected defendant's claim the arbitrator was guilty of
    misconduct by refusing to hear evidence from defendant's expert and other
    witnesses concerning the causes of the construction delays. The court found the
    arbitrator had been provided the proffered expert witness' report as a pre-
    arbitration submission, and the arbitrator admitted the report as evidence during
    A-2355-20
    7
    the arbitration.     The court also found the arbitrator properly exercised his
    discretion "not to listen" to the proffered testimony because the arbitrator
    determined plaintiff bore no responsibility for the delays as a matter of law under
    the Contract Agreements. The court also found the mere fact the arbitrator made
    rulings adverse to defendant did not establish he was evidently partial to
    plaintiff.   Further, the court found the language in the award declining
    defendant's requested reservation of rights was merely dicta and not binding on
    either party.      The court rejected defendant's request it find the arbitrator
    exceeded his powers by making a "gratuitous comment" on the reservation of
    rights that defendant asked him to address.
    The court issued orders confirming the arbitration award and denying
    defendant's claim for vacatur of the award. The order confirming the arbitration
    award stated the language in the award declining defendant's reservation of
    rights was "dicta and . . . premature" and the issues "were not the subject of
    submission" to arbitration.
    Defendant appeals from the court's orders. On appeal, defendant asserts,
    and plaintiff does not dispute, that we should apply the FAA's standard for
    A-2355-20
    8
    vacatur, 
    9 U.S.C.S. § 10
    , in our review of the court's orders. The record also
    demonstrates the motion court analyzed the issues under the FAA.2
    II.
    "[T]he decision to vacate an arbitration award is a decision of law [and]
    this court reviews the denial of a motion to vacate an arbitration award de novo."
    Minkowitz v. Israeli, 
    433 N.J. Super. 111
    , 136 (App. Div. 2013) (quoting
    Manger v. Manger, 
    417 N.J. Super. 370
    , 376 (App. Div. 2010)); see also
    Metromedia Energy, Inc. v. Enserch Energy Servs., 
    409 F.3d 574
    , 579 (3d Cir.
    2005) (applying the de novo standard of review in reviewing an order vacating
    an arbitration award under the FAA). In considering whether to reverse or
    affirm an order confirming an arbitration award, we must determine whether the
    trial court and the arbitrator adhered to the requirements of the controlling
    statute. 
    Ibid.
    "Review of arbitration awards under the FAA is 'extremely deferential.'
    Vacatur is appropriate only in 'exceedingly narrow' circumstances[.]"
    2
    We need not address application of the NJAA since the parties' arguments on
    appeal rest solely on the standard under the FAA. Additionally, the parties do
    not argue the result would be different under the NJAA. See Sklodowsky v.
    Lushis, 
    417 N.J. Super. 648
    , 657 (App. Div. 2011) (holding an issue not briefed on
    appeal is deemed waived); Jefferson Loan Co. v. Session, 
    397 N.J. Super. 520
    , 525
    n.4 (App. Div. 2008) (same).
    A-2355-20
    9
    Metromedia Energy, Inc., 
    409 F.3d at 578
     (quoting Dluhos v. Strasberg, 
    321 F.3d 365
    , 370 (3d Cir. 2003)). The United States Supreme Court has held that
    under the FAA, the "exclusive" grounds for vacating an arbitration award are
    provided in 
    9 U.S.C.S. § 10
    . Hall St. Assocs., L.L.C. v. Mattel, Inc., 
    552 U.S. 576
    , 584 (2008). Thus, an award may be vacated only:
    (1) where the award was procured by corruption, fraud,
    or undue means;
    (2) where there was evident partiality or corruption in
    the arbitrators, or either of them;
    (3) where the arbitrators were guilty of misconduct in
    refusing to postpone the hearing, upon sufficient cause
    shown, or in refusing to hear evidence pertinent and
    material to the controversy; or of any other misbehavior
    by which the rights of any party have been prejudiced;
    or
    (4) where the arbitrators exceeded their powers, or so
    imperfectly executed them that a mutual, final, and
    definite award upon the subject matter submitted was
    not made.
    [
    9 U.S.C.S. § 10
    (a).]
    "Under the FAA, courts may vacate an arbitrator's decision 'only in very
    unusual circumstances.'" Oxford Health Plans LLC, 569 U.S. at 568 (quoting
    First Options of Chicago, Inc. v. Kaplan, 
    514 U.S. 938
    , 942 (1995)). "When an
    arbitrator resolves disputes regarding the application of a contract, and no
    A-2355-20
    10
    dishonesty is alleged, the arbitrator's 'improvident, even silly, factfinding' does
    not provide a basis for a reviewing court to refuse to enforce the award ." Major
    League Baseball Players Ass'n v. Garvey, 
    532 U.S. 504
    , 509 (2001) (quoting
    United Paperworkers Int'l Union v. Misco, Inc., 
    484 U.S. 29
    , 39 (1987)).
    In reviewing an application to vacate an arbitration award under the FAA,
    "courts . . . have no business weighing the merits of the grievance [or]
    considering whether there is equity in a particular claim." 
    Ibid.
     (alterations in
    original) (quoting Misco, Inc., 
    484 U.S. at 37
    ). "Our role in reviewing the
    outcome of the arbitration proceedings is not to correct factual or legal errors
    made by an arbitrator." Major League Umpires Ass'n v. Am. League of Pro.
    Baseball Clubs, 
    357 F.3d 272
    , 279 (3d Cir. 2004). "It is only when the arbitrator
    strays from interpretation and application of the agreement and effectively
    'dispenses his own brand of industrial justice' that his [or her] decision may be
    unenforceable." Garvey, 
    532 U.S. at 509
     (quoting United Steelworkers of Am.
    v. Enter. Wheel & Car Corp., 
    363 U.S. 593
    , 597 (1960)); see, e.g., Stolt-Nielsen
    S.A. v. AnimalFeeds Int'l Corp., 
    559 U.S. 662
    , 668-69 (2010) (finding
    arbitrators exceeded their authority in determining they could decide a class
    arbitration where the parties stipulated they did not have an agreement to
    arbitrate a class arbitration).
    A-2355-20
    11
    On appeal, defendant argues the trial court erred by affirming the
    arbitration award and declining to vacate the award because the arbitrator's
    construction of the Contract Agreements manifestly disregarded the law and the
    award exceeded the arbitrator's authority under 
    9 U.S.C.S. § 10
    (a)(4). It is
    unclear whether manifest disregard of the law constitutes a viable ground for
    vacatur under the FAA. That ground for vacatur was suggested in Wilko v.
    Swan, where the Supreme Court found an arbitrator's erroneous interpretation
    of the law did not support vacatur and suggested an arbitrator's manifest
    disregard of the law might support vacatur. 
    346 U.S. 427
    , 436-37 (1953).
    In Hall Street Associates, LLC, the Court seemingly rejected the plaintiff's
    claim that Wilko added "'manifest disregard of the law' as a further ground for
    vacatur on top of those listed in" 
    9 U.S.C. § 10
    , finding "no reason to accord"
    Wilko "the significance that [the plaintiff] urge[d]." Hall St. Assocs. LLC, 
    552 U.S. at 584-85
    . The Court, however, also noted the "vagueness" in the language
    used in Wilko to address manifest disregard of the law as a ground for vacatur
    under the FAA, and observed that some courts interpreted Wilko's reference to
    "manifest disregard of the law" as a "shorthand for [9 U.S.C.] § 10(a)(3) or §
    10(a)(4), the paragraphs authorizing vacatur when the arbitrators were 'guilty of
    misconduct' or 'exceeded their powers.'" Id. at 585. In Stolt-Nielsen S.A, the
    A-2355-20
    12
    Court explained it had not decided whether "manifest disregard" as a ground for
    vacatur survived Hall Street Associates "as an independent ground for review or
    as a judicial gloss on the enumerated grounds for vacatur set forth at 
    9 U.S.C. § 10
    ." Stolt-Nielsen S.A, 
    559 U.S. at
    672 n.3.
    It remains unclear whether manifest disregard of the law constitutes a
    viable ground for vacatur under the FAA. For example, the Third Circuit has
    observed Hall Street Associates "called into question the viability of manifest
    disregard as an independent ground for vacating an arbitration award[,]" Ross
    Dress for Less, Inc. v. VIWP, L.P., 
    750 F. App'x 141
    , 145 n.1 (3d Cir. 2018),
    but the court also explained that "[d]espite an emerging Circuit split[,]" it had
    not resolved the issue, ibid.; see also Schwartz v. Merrill Lynch & Co., 
    665 F. 3d 444
    , 452 (2d Cir. 2011) (finding "manifest disregard [of the law] remains a
    valid ground for vacating arbitration awards" (quoting T.Co Metals, LLC v.
    Dempsey Pipe & Supply, Inc., 
    592 F.3d 329
    , 340 (2d Cir. 2010))).
    We need not decide whether the manifest disregard of the law standard
    survived the Court's decision in Hall Street Associates because even if the
    standard applied here, the record does not support a finding the arbitrator
    manifestly disregarded the law. It has been held the standard of review of the
    judicially created manifest disregard of the law standard "is severely limited."
    A-2355-20
    13
    Westerbeke Corp. v. Daihatsu Motor Co., Ltd., 
    304 F.3d 200
    , 208 (2d Cir. 2002).
    Relief under the standard requires "something beyond and different from a mere
    error in the law or failure on the part of the arbitrator[] to understand and apply
    the law." 
    Ibid.
     (quoting Saxis S.S. Co. v. Multifacs Int'l Traders, Inc., 
    375 F.2d 577
    , 582 (2d Cir. 1967)); see also Zayas v. Bacardi Corp., 
    524 F.3d 65
    , 68 (1st
    Cir. 2008) (explaining there is an "exceedingly small window of opportunity for
    vacation of arbitral awards that are 'in manifest disregard of the law'").
    To establish an arbitrator manifestly disregarded the law in the Second
    Circuit, a party challenging an arbitration award must first find the law allegedly
    disregarded is "well defined, explicit, and clearly applicable." Merrill Lynch,
    Pierce, Fenner & Smith, Inc. v. Bobker, 
    808 F.2d 930
    , 934 (2d Cir. 1986). It
    must also be demonstrated that the arbitrator "appreciate[d] the existence of
    [this] clearly governing legal principle but decide[d] to ignore or pay no
    attention to it." Westerbeke, 
    304 F.3d at 209
     (quoting Merrill Lynch, Pierce,
    Fenner & Smith, Inc., 
    808 F.2d at 934
    ). In the First Circuit, a manifest disregard
    of the law is established where the arbitration award is "(1) unfounded in reason
    and fact; (2) based on reasoning so palpably faulty that no judge, or grou p of
    judges, ever could conceivably have made such a ruling; or (3) mistakenly based
    on a crucial assumption that is concededly a non-fact." Zayas, 
    524 F.3d at
    68
    A-2355-20
    14
    (quoting Teamsters Local Union No. 42 v. Supervalu, Inc., 
    212 F.3d 59
    , 66 (1st
    Cir. 2000)).
    Here, defendant does not make a showing the arbitrator manifestly
    disregarded the law under any recognized formulation of the standard.
    Defendant claims the GMP acted as a cap on general requirements costs—
    "onsite expenses"—incurred by plaintiff beyond the GMP as adjusted by the
    change orders, and although the GMP Rider permitted compensation for
    additional general conditions costs —"plaintiff's management and associated
    burdens"—there is no similar provision in the Contract Agreements providing
    compensation for general requirements costs in the event of delays. It also
    asserts the change orders unambiguously barred any further compensation
    because plaintiff agreed to an extension of time in exchange for no further
    compensation. Defendant claims the Contract Agreements' exclusion from the
    "Cost of Work" of off-site personnel and costs, as well as the waiver of
    consequential damages provision, were ignored by the arbitrator when he
    awarded plaintiff certain costs associated with plaintiff's "home office
    personnel."
    In asserting the arbitrator manifestly disregarded the law, defendant
    actually claims only that the arbitrator misinterpreted and misapplied various
    A-2355-20
    15
    contractual provisions. However, as the Court explained in Oxford Health,
    "[b]ecause the parties 'bargained for the arbitrator's construction of their
    agreement,' an arbitral decision 'even arguably construing or applying the
    contract' must stand, regardless of a court's view of its (de)merits." 569 U.S. at
    569 (quoting E. Associated Coal Corp. v. Mine Workers, 
    531 U.S. 57
    , 62
    (2000)). In determining whether an arbitrator exceeded their power in issuing
    an award under the FAA, a court does not entertain "full-bore legal and
    evidentiary appeals." Id. at 568-69 (quoting Hall St. Assocs., LLC., 
    552 U.S. at 588
    ). Rather, "the sole question . . . is whether the arbitrator (even arguably)
    interpreted the parties' contract, not whether he got its meaning right or wrong."
    Id. at 569.
    Here, the arbitration award is grounded in the arbitrator's interpretation of
    the Contract Agreements. For example, the arbitrator rejected one of plaintiff's
    claims for reimbursement of costs based on the waiver of consequential damages
    provision in the Contract Agreements. The arbitrator also rejected defendant's
    argument the change orders barred plaintiff's entitlement to recovery of
    additional costs based on a determination defendant's interpretation of the
    contract terms "render[ed] meaningless" language in the GMP Rider entitling
    plaintiff to "additional or extended general conditions" in the event of delays not
    A-2355-20
    16
    caused by plaintiff. The arbitrator premised his award of general conditions and
    general requirements on the same contractual provision, interpreting the GMP
    Rider to "expressly allow[] recovery to [plaintiff] for periods of delay for which
    it bore no responsibility." The arbitrator's analysis of the many other issues
    presented is similarly grounded in his interpretation of the Contract Agreements.
    Defendant makes no showing the arbitrator recognized a clearly governing
    legal principle but then decided to ignore it, Westerbeke, 
    304 F.3d at 209
    , that
    the arbitrator's decision is unfounded in reason and logic, is based on reas oning
    so faulty no judge could conceivably have made the same decision, or is based
    on a critical assumption of a non-fact, Zayas, 
    524 F.3d at 68
    . Thus, defendant
    makes no showing the arbitration award is founded on a manifest disregard of
    the law, even assuming that standard remains viable following the Court's
    decision in Hall Street Associates, LLC.
    In tethering his reasoning to his interpretation of the parties' agreements,
    the arbitrator's award "draw[s] its essence from the contract." E. Associated
    Coal Corp., 
    531 U.S. at 62
     (quoting Misco, Inc., 
    484 U.S. at 38
    ). A court will
    not   vacate   an    arbitration   award    where    the    arbitrator   "arguably
    constru[ed] . . . the contract and act[ed] within the scope of his authority," and,
    even where the "court is convinced he committed serious error[, this] does not
    A-2355-20
    17
    suffice to overturn his decision." 
    Ibid.
     (quoting Misco, Inc., 
    484 U.S. at 38
    ).
    "The potential for . . . mistakes is the price of agreeing to arbitration" as an
    "arbitrator's construction [of the contract]" is what is "bargained for; and so far
    as the arbitrator's decision concerns construction of the contract, the courts have
    no business overruling him [or her] because their interpretation of the contract
    is different from his." Oxford Health Plans LLC, 569 U.S. at 572-73 (second
    alteration in original) (quoting Enter. Wheel & Car Corp., 
    363 U.S. at 599
    ). "So
    long as the arbitrator was 'arguably construing' the contract . . . a court may not
    correct his [or her] mistakes under §10(a)(4)." Id. at 572 (quoting E. Associated
    Coal Corp., 
    531 U.S. at 62
    ).
    Defendant next argues the trial court erred in declining to vacate the award
    under 
    9 U.S.C. § 10
    (a)(3), because the arbitrator did not the testimony of three
    witnesses, two of defendant's architects and a "delay expert," who defendant
    avers would have testified plaintiff was responsible for the delays and therefore
    not entitled to any compensation under the GMP Rider. Defendant concedes the
    arbitrator accepted its "delay expert['s]" report as a pre-arbitration submission.
    An arbitration award may be vacated under 
    9 U.S.C. § 10
    (a)(3) "where
    the arbitrators were guilty of misconduct . . . in refusing to hear evidence
    pertinent and material to the controversy." However, "Section 10(a)(3) 'cannot
    A-2355-20
    18
    be read, . . . to intend that every failure to receive relevant evidence constitutes
    misconduct which will require the vacation of an arbitrator's award.'" Century
    Indem. Co. v. Certain Underwriters at Lloyd's, 
    584 F.3d 513
    , 557 (3d Cir. 2009)
    (quoting Newark Stereotypers' Union No. 18 v. Newark Morning Ledger Co.,
    
    397 F.2d 594
    , 599 (3d Cir. 1968)). Rather, "misconduct under § 10(a)(3) will
    not be found 'unless the aggrieved party was denied a fundamentally fair
    hearing.'" Vitarroz Corp. v. G. Willi Food Int'l Ltd., 
    637 F. Supp. 2d 238
    , 248
    (D.N.J. 2009) (quoting Sherrock Bros. v. DaimlerChrysler Motors Co., LLC,
    
    260 F. App'x 497
    , 501 (3d Cir. 2008)).
    "[I]t is clear that 'in making evidentiary determinations, an arbitrator need
    not follow all the niceties observed by the federal courts.'" Century Indem. Co.,
    
    584 F.3d at 557
     (quoting Lessin v. Merrill Lynch, Pierce, Fenner & Smith, Inc.,
    
    481 F.3d 813
    , 816 (D.C. Cir. 2007)). "It is well within an arbitrator's authority
    to refuse to hear evidence that is cumulative or of little relevance." Lessin, 
    481 F.3d at 817
     (citations omitted).
    Our determination of whether defendant was afforded a fundamentally fair
    hearing is complicated by the absence of any record of the arbitration
    proceedings. It is further complicated by defendant's assertion, made in his
    counterclaim to vacate the award, that the arbitrator found plaintiff was not at
    A-2355-20
    19
    fault for delays without hearing testimony from its witnesses, and defendant's
    simultaneous      but   incongruous   assertion   its   "witnesses    testified     that
    [construction] delays were primarily caused by" plaintiff.
    In any event, based on the record presented, we are not convinced
    defendant was denied a fair hearing by the arbitrator's decision to exclude the
    testimony of the witnesses. Defendant proffers that the witnesses would have
    testified plaintiff was at fault for the delays resulting from the change orders.
    The arbitrator, however, concluded the testimony was unnecessary because fault
    for the delays could be determined as a matter of law under the Contract
    Agreements. More particularly, the arbitrator determined that, as a matter of
    law, defendant was at fault for the delays because under the parties' plain
    agreement, as reflected in the Contract Agreements, change orders could only
    be granted for delays for which plaintiff was not responsible.             Thus, the
    arbitrator determined that by the express agreement of the parties, any delays
    resulting from change orders were delays for which plaintiff bore no
    responsibility.
    It is for the arbitrator "to decide issues of relevance [or] . . . admissibility
    of evidence," Ass'n of Flight Attendants, AFL-CIO v. USAir, Inc., 
    960 F.2d 345
    ,
    350 (3d Cir. 1992), and it was within the arbitrator's discretion to exclude
    A-2355-20
    20
    testimony that was irrelevant to what he determined to be a legal issue governed
    by the parties' agreement concerning delays resulting from change orders ,
    Lessin, 
    481 F.3d at 817
    . We discern no error in the arbitrator's decision the
    proffered testimony was unnecessary; it was based on his reasoned interpretation
    of the Contract Agreements.
    Moreover, even if the arbitrator erred in not hearing testimony from three
    witnesses concerning the fault for the delays, defendant makes no showing
    exclusion of the testimony deprived defendant of "a fundamentally fair hearing."
    Vitarroz Corp., 
    637 F. Supp. 2d at 248
     (quoting Sherrock Bros., 260 F. App'x at
    501). To provide a fair hearing, an arbitrator "must give each of the parties to
    the dispute an adequate opportunity to present its evidence and argument."
    Tempo Shain Corp. v. Bertek, Inc., 
    120 F.3d 16
    , 20 (2d Cir. 1997) (quoting
    Hoteles Condado Beach v. Union de Tronquistas Local 901, 
    763 F.2d 34
    , 39 (1st
    Cir. 1985)).
    Here, although there is no transcript of the proceedings, it is clear the
    arbitrator was provided with defendant's expert report detailing its position
    concerning responsibility for the delays. The report comprehensively addresses
    various delays and includes an unequivocal opinion that plaintiff, and not
    defendant, caused the delays. In its post-hearing brief, defendant also argued at
    A-2355-20
    21
    length that the parties' agreement to change orders alone did not preclude a
    finding plaintiff was responsible for the delays.
    Although the arbitrator limited evidence on the delay-fault issue, in
    accepting the expert's report and permitting argument as to whether the change
    orders amounted to an agreement plaintiff bore no responsibility for the delays,
    the arbitrator gave defendant "an adequate opportunity to present its evidence
    and arguments" on this issue. Vitarroz Corp., 
    637 F. Supp. 2d at 250-51
     (quoting
    Sunshine Mining Co. v. United Steelworkers of Am., AFL-CIO, 
    823 F.2d 1289
    ,
    1295 (9th Cir. 1987)). In the end, however, the arbitrator's decision to limit the
    evidence on the issue was within his discretion and was consistent with his legal
    conclusion the parties had agreed that change orders would be issued only where
    plaintiff was not at fault and, as such, as a matter of law there was no need for
    additional evidence on the fault issue. We do not find the decision barring the
    testimony constituted misconduct warranting vacatur under 
    9 U.S.C. § 10
    (a)(3)
    or "deprive[d] defendant[] of a fundamentally fair hearing." 
    Id. at 251
    . The
    trial court did not err in declining to vacate the award on those grounds.
    We also find no merit to defendant's argument the trial court erred by
    declining to vacate the arbitration award because the arbitrator allegedly
    demonstrated evident partiality in plaintiff's favor. Vacatur under 9 U.S.C. §
    A-2355-20
    22
    10(a)(2) is permitted "where there was evident partiality or corruption in the
    arbitrator[]." "[T]o show evident partiality, . . . the challenging party must show
    a reasonable person would have to conclude that the arbitrator was partial to the
    other party to the arbitration." Freeman v. Pittsburgh Glass Works, LLC, 
    709 F.3d 240
    , 252 (3d Cir. 2013) (first alteration in original) (quoting Kaplan v. First
    Options of Chicago, Inc., 
    19 F.3d 1503
    , 1523 n.30 (3d Cir. 1994)). "[E]vident
    partiality is strong language and requires proof of circumstances powerfully
    suggestive of bias." 
    Ibid.
     (quoting Kaplan, 
    19 F.3d at
    1523 n.30). The bias must
    be "sufficiently obvious that a reasonable person would easily recognize it." Id.
    at 253.
    Here, defendant's argument is premised on the various determinations
    made by the arbitrator in plaintiff's favor that it challenges on appeal. Defendant
    simply asserts there is "no colorable" justification for the decisions made by the
    arbitrator.   As the District of Columbia District Court aptly explained in
    considering a similar assertion of an arbitrator's partiality, "[a]lthough a series
    of unfavorable rulings by the arbitrator may produce an appearance of bias in
    the eyes of the unsuccessful party, it does not justify vacating the arbitration
    award." Thian Lok Tio v. Wash. Hosp. Ctr., 
    753 F. Supp. 2d 9
    , 18 (D.D.C.
    2010). Beyond the arbitrator's unfavorable determinations related to the issues
    A-2355-20
    23
    submitted to arbitration, defendant does not offer any proof of circumstances
    that suggest improper bias, let alone any that "powerfully" suggest bias.
    Freeman, 709 F.3d at 252. The trial court did not err in concluding there was
    no evidence of partiality to support vacating the award under 
    9 U.S.C. § 10
    (a)(2).
    We also reject defendant's argument the trial court erred in declining to
    vacate the award because the arbitrator exceeded his power by failing to include
    a reservation of rights in the award and "potentially [and] improperly barred
    [d]efendant's [f]uture [i]ndemenification [c]laims" as well as defendant's
    potential future claims against plaintiff and its president for claims related to the
    alleged interested party transaction under New Jersey's entire controversy
    doctrine. At oral argument, plaintiff agreed that no claims by defendant for
    indemnification from plaintiff for subcontractor liens on the project, and no
    claims by defendant against plaintiff for violation of the related-party-
    transaction provision of the Contract Agreements, were presented to the
    arbitrator for decision or were decided by the arbitrator in the award. Plaintiff
    also agreed that nothing in the arbitration award, in the litigation concerning the
    vacatur or affirmance of the award, or in this appeal precludes defendant from
    A-2355-20
    24
    pursuing the subcontractor indemnification or related-party claims in other
    proceedings.
    Our review of the arbitration record and the arbitration award is consistent
    with the parties' representations at oral argument. Although we affirm the
    court's orders confirming the arbitration award and denying defendant's request
    to vacate the award, neither the arbitration award, the Law Division's orders, nor
    this opinion shall be interpreted as barring defendant's right to pursue claims
    against plaintiff for indemnification for subcontractor's liens on the project or
    defendant's claims for violation of the related-party transaction provision of the
    Contract Agreements.
    Defendant may therefore prosecute "claims against [p]laintiff for
    contractual indemnification and reimbursement of [d]efendant's attorney's fees
    and costs that [may be] be incurred in . . . enforcement proceedings involving
    [p]laintiff's subcontractor liens against" defendant and its property. Defendant
    is similarly free to prosecute claims arising from "[p]laintiff's and [plainti ff's
    president] Mr. Gary Krupnick's" alleged "failures to disclose their conflict of
    interest when recommending and pushing for [d]efendant's use of the Eco Span
    structural support system in which" defendant claims "they had a financial
    interest." We do not express an opinion on the merits of any of these claims,
    A-2355-20
    25
    but simply note they are not barred by the arbitration award or any of the ensuing
    proceedings through this appeal.
    Any arguments asserted on defendant's behalf we have not directly
    addressed are without sufficient merit to warrant discussion in a written opinion.
    R. 2:11-3(e)(1)(E).
    Affirmed.
    A-2355-20
    26
    

Document Info

Docket Number: A-2355-20

Filed Date: 3/28/2022

Precedential Status: Non-Precedential

Modified Date: 3/28/2022

Authorities (27)

Vitarroz Corp. v. G. Willi Food International Ltd. , 637 F. Supp. 2d 238 ( 2009 )

Manger v. Manger , 417 N.J. Super. 370 ( 2010 )

United Steelworkers v. Enterprise Wheel & Car Corp. , 80 S. Ct. 1358 ( 1960 )

Thian Lok Tio v. Washington Hospital Center , 753 F. Supp. 2d 9 ( 2010 )

Wilko v. Swan , 74 S. Ct. 182 ( 1953 )

Newark Stereotypers' Union No. 18 v. Newark Morning Ledger ... , 397 F.2d 594 ( 1968 )

In the Matter of the Arbitration Between Tempo Shain ... , 120 F.3d 16 ( 1997 )

Hoteles Condado Beach, La Concha and Convention Center v. ... , 763 F.2d 34 ( 1985 )

Jefferson Loan Co. v. Session , 397 N.J. Super. 520 ( 2008 )

T. CO METALS, LLC v. Dempsey Pipe & Supply, Inc. , 592 F.3d 329 ( 2010 )

Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Jack Bobker , 808 F.2d 930 ( 1986 )

Sunshine Mining Company v. United Steelworkers of America, ... , 823 F.2d 1289 ( 1987 )

Association of Flight Attendants, Afl-Cio v. Usair, Inc , 960 F.2d 345 ( 1992 )

Teamsters Local Union No. 42 v. Supervalu, Inc. , 212 F.3d 59 ( 2000 )

Zayas v. Bacardi Corp. , 524 F.3d 65 ( 2008 )

Lessin, Michael v. Merrill Lynch Pierce , 481 F.3d 813 ( 2007 )

saxis-steamship-co-owners-of-the-ss-warm-springs-v-multifacs , 375 F.2d 577 ( 1967 )

Hall Street Associates, L. L. C. v. Mattel, Inc. , 128 S. Ct. 1396 ( 2008 )

metromedia-energy-inc-v-enserch-energy-services-inc-txu-energy-company , 409 F.3d 574 ( 2005 )

Westerbeke Corporation v. Daihatsu Motor Co., Ltd. , 304 F.3d 200 ( 2002 )

View All Authorities »