In the Matter of Higbee Beach Restoration Project, Etc. ( 2024 )


Menu:
  •                             NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-1048-22
    IN THE MATTER OF HIGBEE
    BEACH RESTORATION
    PROJECT, TOWNSHIP OF
    LOWER CAPE MAY COUNTY,
    NEW JERSEY, OFFICE OF
    COASTAL ENGINEERING
    PROJECT NO. 4299-20.
    Argued October 4, 2023 – Decided January 5, 2024
    Before Judges Currier, Firko and Susswein.
    On appeal from the New Jersey Department of
    Environmental Protection.
    William J. O'Kane, Jr., argued the cause for appellant
    Mount Construction, Inc. (Archer & Greiner, PC,
    attorneys; William J. O'Kane, Jr., and Christopher M.
    Terlingo, on the briefs).
    Kathrine Motley Hunt, Deputy Attorney General,
    argued the cause for respondent New Jersey
    Department of Environmental Protection (Matthew J.
    Platkin, Attorney General, attorney; Melissa H. Raksa,
    Assistant Attorney General, of counsel; Kathrine
    Motley Hunt and Jason Brandon Kane, Deputy
    Attorney General, on the brief).
    Richard Wayne Hunt argued the cause for respondent
    A.P. Construction, Inc. (Parker McCay, PA, attorneys;
    Richard Wayne Hunt and Sean T. Fannon, on the brief).
    PER CURIAM
    Unsuccessful bidder Mount Construction, Inc. (Mount) appeals from the
    final decision of the New Jersey Department of Environmental Protection (DEP)
    denying Mount's protest of DEP's decision to award a contract for a complex
    project (Project) to A.P. Construction, Inc. (A.P.).       The Project involves
    construction of a berm with stormwater control structures, restoration of dunes ,
    and construction and installation of certain public amenities in the Higbee Beach
    area of Lower Township in Cape May County. Mount contends that DEP's
    evaluation of the bid prices was subjective and the decision to award the Project
    contract to A.P. was arbitrary, capricious, and unreasonable. After a review of
    the contentions in light of the facts and applicable principles of law, we affirm.
    In May 2022, DEP's Office of Coastal Engineering (OCE) issued an
    advertisement for bids for the Project. According to the bid specifications, the
    Project was intended to "restore[]" an "area of the Higbee Beach Wildlife
    Management Area"; the work encompassed "earthwork, grading, dynamic
    compaction, seeding and planting, trail enhancement and creation, construction
    of water control structures, pedestrian bridge construction, boardwalk
    A-1048-22
    2
    construction, wildlife viewing blinds[,] and other incidentals associated with the
    work." The bid package included 140 pages of design plans for the construction
    to which bidders were required to conform.
    All bidders required pre-qualification by the OCE and Department of
    Treasury, Division of Property Management and Construction (DPMC) . In
    addition, bidders were required to substantiate their construction experience,
    including proof they had previously accomplished "at least two (2) projects each
    entailing berm construction" and "at least two (2) projects each with a minimum
    of twenty (20) acres in size within wetlands or tidal waters entailing wetland
    restoration or construction and required plantings."          According to the
    advertisement, bidders could submit resumes of bidder and subcontractor
    representatives, "but only the most experienced as demonstrated through the
    number and type of previous similar projects overseen, will be scored, and be
    considered in the evaluation." Bidders were also required to provide an "overall
    sequencing/site management plan" including "detail of action, order of
    operations, and management" for "the major facets of the Project," such as berm
    construction, wetland restoration and planting, and "Plant Contingency."
    The advertisement informed bidders that "the winning bid" would be
    determined by an "Evaluation Committee" and the Director of the Division of
    A-1048-22
    3
    Resilience Engineering and Construction (DREC Director). The DREC Director
    "reserve[d] the right to waive minor irregularities or omissions in a bid" and to
    waive a non-material requirement. The DREC Director also "reserve[d] the
    right to reject any or all bids, or to award whole or in part if deemed to be in the
    best interest of the State to do so."
    Section 1:08 of the advertisement stated that "[b]ids shall be compared
    and awarded based on the 'price and other factors' determination of the
    Evaluation Committee, which w[ould] consider the cost proposals" and "the
    [b]idder's   construction    experience"       including   its   "berm   construction
    experience," "wetland restoration and planting experience," "dewatering
    experience," and "site remediation experience and qualification" as well as the
    bidder's "overall sequencing/site management plan" and "overall presentation
    . . . of the [b]id." With respect to the evaluation of bidders' cost proposals,
    Section 4:06.1 of the advertisement stated that:
    The pricing evaluation methodology will be date-
    stamped and entered into the record system along with
    the rest of the grading system and weighted maximum
    point totals before solicitation. If any changes or
    revisions are to be made to the evaluation process, it
    will occur during the solicitation phase and will be
    recorded in an Addendum. No changes are to be made
    upon receipt of bids on the bid opening date.
    A-1048-22
    4
    After receiving questions from bidders, OCE issued an addendum and
    clarification. In response to a request to provide the "grading system and
    weighted maximum point totals," OCE declined to provide additional
    information, and referred bidders to the language in Sections 1:08 and 4:06 of
    the bid advertisement. The bid submission deadline was also extended.
    On June 28, 2022, OCE received bid proposals for the Project from four
    contractors: Mount, A.P., Abbonizio Construction, Inc. (Abbonizio) and JPC
    Group, Inc. (JPC). The total cost proposals of each of the bidders, from highest
    to lowest, were as follows:
    A.P.        $37,503,858
    JPC         $29,962,365
    Mount       $29,352,731
    Abbonizio $28,717,058
    The "four proposals were deemed responsive" by the DEP Project Manager and
    "forwarded to the [E]valuation [C]ommittee."
    Mount was prequalified by OCE and DPMC. Its bid proposal listed three
    previous projects under "Wetlands Restoration and Planting Construction
    experience and qualifications"—one project involved eighty acres, the second
    project involved eight acres and the third project entailed six acres of wetlands
    A-1048-22
    5
    restoration. Mount also provided four pages of tables with information about its
    previous construction projects, including berm and dewatering construction, and
    site remediation.     Although Mount included the names of contractor
    representatives, it did not provide resumes for the representatives. Mount did
    not provide a sequencing or site management plan.
    A.P. was also prequalified. Its bid proposal provided descriptions of two
    previous berm construction projects and four previous wetlands projects it or its
    named subcontractors had completed, all of which were more than twenty acres.
    A.P. also listed previous dewatering projects and site remediation projects it had
    performed and provided resumes of its contractor representatives for all the
    listed projects. A.P. submitted an overall sequencing/site management plan as
    well as sequencing/site management plans for the individual aspects of the
    Project.
    The Evaluation Committee consisted of seven members, all DEP
    employees—with two members from OCE, two members from the Office of
    Dam Safety, and one member each from the Office of Natural Resources
    Restoration (ONRR), the Division of Fish and Wildlife, and the Bureau of Site
    Management.      Evaluators were instructed that communication between
    A-1048-22
    6
    committee members or with bidders about the bids or the Project was "strictly
    forbidden."
    Prior to review, the bidders' names were redacted from the proposals and
    the cost portion of each proposal was separated from the experience portion, to
    be evaluated separately. Evaluators were instructed to score each bid proposal
    based on a maximum possible 150 points, with the cost proposal scored as a
    maximum of 100 points, and the bidders' experience and other factors scored as
    a maximum of fifty points. Cost proposals were assigned a number (one through
    four) and the experience portions were assigned a letter (A through D), so that
    evaluators did not know the relationship between the cost proposal and the
    amount of experience listed in the particular bid.
    With respect to the cost proposals, evaluators were instructed that, out of
    the 100 possible points, a maximum of seventy points could be awarded for the
    total bid price; a maximum of ten points each could be awarded for the bid prices
    for berm construction and "General Work"; and a maximum of five points each
    could be awarded for the bid prices for upland and marsh plantings and
    foundational dewatering. The evaluators were given detailed instructions on
    how to evaluate the different cost categories. For example, the instructions for
    evaluation of the "General Work" category stated:
    A-1048-22
    7
    General work is included in the total bid price, but it is
    also crucial to evaluate this independently. This is
    because Contractors have been known to "front-load"
    their General Work bid since it is a lump sum item. A
    heavy General Work bid price can be unfavorable to
    OCE due to the amount of money that must be initially
    paid to the Contractor and will increase the likelihood
    for disputes on other items as the job progresses.
    With respect to the fifty possible points for bidder experience and other
    factors, evaluators were instructed to award a maximum of sixteen points for the
    bidder's berm construction experience; a maximum of ten points each for the
    bidder's wetland restoration and planting experience, and dewatering
    experience; a maximum of eight points for the bidder's overall sequencing/site
    management plan; a maximum of four points for the bidder's site remediation
    experience; and a maximum of two points for the bidder's "Overall
    Presentation."
    All four bids were evaluated under the identified scoring criteria. The
    committee awarded A.P. a total score of 758 (447 price, 311 experience);
    Abbonizio received a total score of 704.25 (547 price, 157.25 experience);
    Mount had a total score of 661 (500 price, 161 experience); and JPC received a
    total score of 632.25 (529 price, 103.25 experience). The overall scoring for the
    four bids and the detailed scoring breakdown for A.P. and Mount is attached as
    an Addendum to this opinion.
    A-1048-22
    8
    On August 22, 2022, Erick Doyle, OCE Bureau Chief, and David Bean,
    ONRR Bureau Chief, sent a memorandum to the DREC Director attaching the
    bid evaluation results for the Project. The memorandum stated that five of the
    seven Evaluation Committee members ranked A.P. as having "the highest
    overall score . . . based on the criteria set forth." It further stated that although
    A.P.'s
    proposal was the costliest of those evaluated, [A.P.]'s
    contractor representative and contractor experience
    regarding earthen berm construction, wetlands and
    planting, dewatering, and site remediation consistently
    outranked all other bid submissions. [A.P.] provided
    detailed experience documentation in a concise manner
    consistent with the requirements detailed in Section
    1:08. Furthermore, the three other bid proposals were
    not concise bid packages demonstrating sufficient
    quality of experience that was specifically outlined
    within the bid specification which was essential for the
    evaluation process. To this, proposal packages lacked
    detailed information, such as previous project
    experience for Contractors or Subcontractors, or
    sequencing plans and affidavits. These issues were
    reflected in the Committee Evaluations scoring for
    experience and qualifications.
    Thus, in accordance with N.J.A.C. 17:12-2.7, the
    evaluators recommended [A.P.]'s bid as the "most
    advantageous to the State, price and other factors
    considered."
    A-1048-22
    9
    Doyle and Bean "concur[red] with the . . . [E]valuation [C]ommittee's results"
    and recommended DREC award A.P. the contract for the Project. 1
    On September 1, 2022, the DREC Director issued a memorandum to all
    bidders, advising the OCE had concluded its evaluation of the bids received for
    the Project, and that "[f]ive of the seven evaluators granted A.P. . . . the highest
    overall score . . . ." The DREC Director stated his review of the bid packages
    and committee members' evaluations and recommendations reflected the
    "analysis and ranking of the four bids" was "appropriate" and he concurred with
    the evaluation committee's recommendation. The DREC Director informed the
    bidders of "OCE's decision . . . to award" the Project contract to A.P.
    Mount filed a formal protest of the award of the Project contract , arguing
    the award to A.P. was "arbitrary, capricious and/or unreasonable due to th[e]
    exorbitant cost of [A.P.]'s bid," which was $8.2 million more than Mount's bid.
    Mount also challenged the evaluation committee's determination that it had not
    demonstrated sufficient experience in its bid documents.              Mount later
    supplemented its bid protest, asserting that A.P.'s bid was materially defective
    1
    Abbonizio subsequently withdrew its bid from consideration because its
    "suppliers and subcontractors ma[de] several price increases [after] their
    original quotation."
    A-1048-22
    10
    because A.P. was not prequalified to perform "Special Miscellaneous Work" and
    A.P. had not submitted certain financial forms.
    On November 18, 2022, DEP issued a final agency decision denying
    Mount's bid protest and affirming the award of the contract to A.P. DEP stated
    it had the authority to award the Project contract under N.J.S.A. 12:6A -1 and
    -2, which authorizes DEP "to repair, reconstruct, or construct bulkheads,
    seawalls . . . dunes and any or all appurtenant structures" on the Atlantic Ocean
    "shore front" in New Jersey.
    DEP explained that "[t]o ensure the selected contractor met the specific
    qualifications and experience necessary to conduct the highly specialized work
    for this Project, OCE issued the solicitation under a 'most advantageous to the
    State, price and other factors' award standard instead of a 'lowest responsive
    bidder' standard," citing to N.J.S.A. 52:34-12(a)(g). DEP stated that factors such
    as "the bidder's demonstrated earthen berm construction experience, wetland
    restoration and planting experience, dewatering experience, and site remediation
    experience, and overall sequencing/site management planning"
    were selected for evaluation because successful
    implementation of this Project of this size and scope
    requires that a contractor have demonstrated experience
    successfully implementing a dewatering system in
    tidally influenced areas, constructing an earthen berm
    or dike in similar conditions, managing the overall
    A-1048-22
    11
    sequencing/site management and phasing of such a
    large project while adhering to all permit restrictions
    and requirements, have the experience and expertise
    regarding the various wetland restoration, planting, and
    seeding requirements and timing restrictions, and
    managing a large-scale project in both cost and overall
    size.
    DEP disputed Mount's claims that A.P. was not prequalified, noting that
    "both [A.P.] and Mount met the prequalification requirements" set forth in the
    bid advertisement.    DEP also rejected Mount's claims that A.P. had not
    submitted certain required forms, finding that the two forms A.P. did not submit
    were not required to be provided with its bid. Therefore, "the fact that neither
    was included did not constitute a defect—material or not—that the DEP
    waived."
    DEP found the evaluation committee gave A.P. "the highest score, price
    and other factors considered" and had given Mount "fewer points in two
    categories, largely because it did not meet two material components of the
    solicitation: wetlands experience and sequencing plans." Specifically, Mount
    only provided information about one previous wetlands project that met the
    minimum-required twenty-acre size, while A.P. "submitted two projects in this
    category, one of which included [twenty-five plus] acres of wetland construction
    while the other project contained over [twenty-one] acres of newly constructed
    A-1048-22
    12
    wetlands." In addition, DEP stated "[E]valuation [C]ommittee members also
    consistently found that Mount did not supply any sequencing/phasing plans as
    required by the specifications, and the committee members scored Mount 's bid
    accordingly." A.P. had included the required sequencing plans.
    According to DEP, "Mount's failure to submit the required sequencing
    plans, coupled with its lack of experience regarding wetland restoration and
    planting, did not demonstrate to [DEP] that it could successfully complete the
    Project."   "Thus, since Mount's proposal failed to conform to the bid
    solicitation's specifications, [DEP] awarded the contract to [A.P.], the highest-
    scoring responsible bidder, price and other factors considered."
    On November 22, 2022, Mount requested DEP stay the Project contract
    award pending appeal. DEP denied Mount's request. We permitted Mount to
    file an emergent motion seeking a stay of the Project contract award and
    thereafter granted Mount's motion for a stay pending appeal on January 6, 2023.
    On appeal, Mount asserts DEP acted arbitrarily, unreasonably, and
    capriciously in relying on the Evaluation Committee's "subjective" scoring; the
    evaluators ignored Mount's contractor representatives' experience; and its "bid
    was not materially defective." Mount does not challenge the propriety of DEP's
    A-1048-22
    13
    use of the "most advantageous to the State, price and other factors" standard
    under N.J.S.A. 52:34-12(a)(g).
    Our review of "administrative actions is severely limited." George Harms
    Constr. Co. v. N.J. Tpk. Auth., 
    137 N.J. 8
    , 27 (1994) (citing Gloucester Cnty.
    Welfare Bd. v. N.J. Civ. Serv. Comm'n, 
    93 N.J. 384
    , 390 (1983)). We "must
    defer to an agency's expertise and superior knowledge of a particular field."
    Thurber v. City of Burlington, 
    191 N.J. 487
    , 502 (2007) (quoting Greenwood v.
    State Police Training Ctr., 
    127 N.J. 500
    , 513 (1992)). We "intervene only in
    those rare circumstances in which an agency action is clearly inconsistent with
    its statutory mission or with other State policy." George Harms, 137 N.J. at 27.
    An "[a]gency action will not be overturned unless the action is arbitrary,
    capricious, or unreasonable."    In re State & Sch. Emps.' Health Benefits
    Comm'ns' Implementation of Yucht, 
    233 N.J. 267
    , 279-80 (2018) (citing Barrick
    v. State, Dep't of Treasury, 
    218 N.J. 247
    , 259 (2014)).          "The burden of
    demonstrating that the agency's action was arbitrary, capricious[,] or
    unreasonable rests upon the person challenging the administrative action."
    Seigel v. N.J. Dep't of Env't Prot., 
    395 N.J. Super. 604
    , 613 (App. Div. 2007).
    A-1048-22
    14
    "[W]e apply de novo review to an agency's interpretation of a statute or
    case law." Russo v. Bd. of Trs., Police & Firemen's Ret. Sys., 
    206 N.J. 14
    , 27
    (2011) (citing Toll Bros. Inc., v. Twp. of W. Windsor, 
    173 N.J. 502
    , 549 (2002)).
    Our Supreme Court has consistently held that contract awards under
    N.J.S.A. 52:34-12(a)(g) should be reviewed under the "gross abuse of discretion
    standard." Barrick, 
    218 N.J. at
    258 (citing Keyes Martin & Co. v. Dir., Div. of
    Purchase & Prop., Dep't of Treasury, 
    99 N.J. 244
    , 252-53 (1985); Com. Cleaning
    Corp. v. Sullivan, 
    47 N.J. 539
    , 548-49 (1966)). This includes contracts awarded
    under N.J.S.A. 52:34-12(a)(g), which permits a contract to be awarded "to that
    responsible bidder whose bid, conforming to the invitation for bids, will be most
    advantageous to the State, price and other factors considered." N.J.S.A. 52:34-
    12(a)(g); Barrick, 
    218 N.J. at 258
    ; Keyes Martin, 
    99 N.J. at 252-53
    . Under this
    higher standard, an appellate court "will not interfere in the absence of bad faith,
    corruption, fraud or gross abuse of discretion." In re Protest of the Award of the
    On-Line Games Prod. & Operation Servs. Cont., Bid No. 95-X-20175, 
    279 N.J. Super. 566
    , 592 (App. Div. 1995) (quoting Com. Cleaning, 
    47 N.J. at 549
    ).
    In turning to Mount's assertions, we are satisfied Mount has not
    demonstrated the evaluation of the cost proposals was not objective. We are
    unpersuaded by and find no precedential support for its argument that an
    A-1048-22
    15
    objective evaluation of price requires a higher bid price to receive a lower score
    in all instances, or that all bid prices must be scored according to the percentage
    differences in price between bids. To the contrary, the Evaluation Committee
    was given a structured evaluation template and criteria to score the costs
    proposals. Furthermore, the instructions advised that prices for the different line
    items could be evaluated differently. For example, a high "General Work" price
    even as part of an overall lower bid price could result in a lower score because
    "a heavy General Work bid price can be unfavorable to OCE due to the amount
    of money that must be initially paid to the Contractor and will increase the
    likelihood for disputes on other items as the job progresses." The record is
    devoid of any evidence that the evaluators did not assess the proposals
    objectively.
    Mount next contends DEP ignored its contractor representatives'
    experience, pointing to three evaluators' score of zero points (out of a possible
    two). However, two evaluators gave Mount the maximum two points, and two
    evaluators gave Mount one point for that category. See Addendum Table #3.
    Furthermore, Mount's proposal only included a spreadsheet listing its prior
    projects and the names of its contractor representatives. In contrast, A.P.'s
    proposal included "detailed resumes and descriptions of the experience of its
    A-1048-22
    16
    contractor representatives." The divergent submissions provided a reasonable
    basis for the difference in individual scores. In any event, Mount's score of six
    points (out of a maximum of fourteen) for its contractor representative site
    remediation experience was only seven points less than A.P.'s score of thirteen
    in that category, but A.P.'s total score of 758 was 97 points higher than Mount's
    total score of 661. Even if Mount had received the maximum possible fourteen
    points for contractor representative site remediation experience, it would not
    have changed the Evaluation Committee's recommendation.
    We are satisfied Mount has not demonstrated DEP grossly abused its
    discretion in awarding the contract to A.P. as it has not established the
    evaluation process was arbitrary, capricious, or unreasonable. On-Line Games,
    
    279 N.J. Super. at 592
    .
    In light of our determination to affirm the bid award, we need not address
    Mount's assertion that DEP erred in finding Mount's bid was materially
    defective. DEP's materiality determination was made in response to Mount's bid
    protest, well after the evaluation of the bids and the bid awards. Since we have
    concluded DEP was not arbitrary or capricious in its award of the contract to
    A.P., it is immaterial what statements were made following the close of the
    bidding process.
    A-1048-22
    17
    Affirmed. The order staying the award of the contract is vacated.
    A-1048-22
    18
    Addendum
    Table 1
    Total Scores for All Bidders
    Eval-   A.P. (Bidder 2/C)   JPC (Bidder 4/A)        Mount (Bidder       Abbonizio (Bidder
    uator   (Total Price:       (Total Price:           1/B)                3/D)
    $37,503,858)        $29,962,365)            (Total Price:       (Total Price:
    $29,352,731)        $28,717,058)
    Pric   Exp. Total   Pric    Exp.    Total   Price Exp Tota      Pric Exp.     Total
    e                   e                               .     l     e
    1       67     41     108   82      16      98      79      28    107   82     17     99
    2       58     49.5   107.5 79      2.25    81.25   54      16    70    58    11.75        69.75
    3       64     50     114   91      30      121     86      39    125   93    37           130
    4       64     47     111   43      8       51      64      17    81    82    23           105
    5       42     28     70    54      26      80      49      26    75    45    29           74
    6       77     49     126   83      8       91      84      17    101   92    23           115
    7       75     46.5   121.5 97      13      110     84      18    102   95    16.5         111.5
    Total   447    311    758   529     103.2   632.2   500     161   661   547   157.2        704.2
    5       5                                 5            5
    A-1048-22
    19
    Table 2
    A.P. Score Breakdown
    Eval        A.P. (Bidder 2/C) (Total Price:$37,503,858)
    -     Price                                      Experience
    uator Tota Ber Plan De-          Gen.     Ber Plant De-         Seq./   Con-     Con-        Ove
    l Bid m      t-    water Wor        m      -ing   water   Site    tracto   tracto      rall
    (70   (10    ing   -ing    k        (16    (10    -ing    Mgm     r Site   r           (2
    max max (5         (5      Exp.     max max) (10          t.      Reme     Rep.        max
    )     )      max max) (10           )             max)    Plan    d.       Site        )
    )             max                            (8      Exp.     Reme
    )                              max)    (2       d.
    max)     Exp.
    (2
    max)
    1     49     10    3      5      0        9     10      10      6       2        2           2
    2     41     4     4      5      4        16    10      10      7.5     2        2           2
    3     41     10    5      3      5        16    10      10      8       2        2           2
    4     40     10    5      2      7        14    9       10      8       2        2           2
    5     30     4     2      2      4        8     5       7       4       2        1           1
    6     52     10    5      2      8        16    10      10      7       2        2           2
    7     55     5     5      3      7        14    9.5     10      7       2        2           2
    A-1048-22
    20
    Table 3
    Mount Score Breakdown
    Eval      Mount (Bidder 1/B) (Total Price: $29,352,731)
    -      Price                                Experience
    uato   Tota Ber Plant De-          Gen.     Ber Plan       De-     Seq.   Con-     Con-        Ove
    r      l Bid m      -      water Wor        m      t-ing   water   /      tracto   tracto      rall
    (70   (10 ing       -ing    k        (16    (10     -ing    Site   r Site   r           (2
    max) max (5         (5      Exp.     max max        (10     Mg     Reme     Rep.        max
    )      max) max) (10           )      )       max)    mt.    d.       Site        )
    max                             Plan   Exp.     Reme
    )                               (8     (2       d.
    max    max)     Exp.
    )               (2
    max)
    1      68    6      5      0       0        14     4       6       0      1        2           1
    2      33    10     2      3       6        8      2.5     2.5     0      2        0           1
    3      68    7      4      1       6        16     8       10      0      2        2           1
    4      40    8      5      4       7        5      5       4       0      2        0           1
    5      35    5      2      2       5        8      3       7       4      2        1           1
    6      57    10     4      5       8        5      3       6       0      1        1           1
    7      60    10     4      5       5        6      5       5       0      1        0           1
    A-1048-22
    21
    

Document Info

Docket Number: A-1048-22

Filed Date: 1/5/2024

Precedential Status: Non-Precedential

Modified Date: 1/5/2024