In the Matter of Kenneth Nicosia Flood Hazard General Permit, Etc. ( 2024 )


Menu:
  •                 NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-2921-22
    IN THE MATTER OF
    KENNETH NICOSIA                            APPROVED FOR PUBLICATION
    FLOOD HAZARD                                       July 30, 2024
    GENERAL PERMIT                                 APPELLATE DIVISION
    BY CERTIFICATION 5
    NO. 1519-23-002.1 FHC230001.1
    _____________________________
    Argued July 16, 2024 – Decided July 30, 2024
    Before Judges Sabatino, Susswein, and Perez Friscia.
    On appeal from the New Jersey Department of
    Environmental Protection.
    Stuart J. Lieberman argued the cause for appellants
    Henry Dewing and Sarah Dewing (Lieberman Blecher
    & Sinkevich, PC, attorneys; Stuart J. Lieberman, of
    counsel; Ching Wei Michael Gan and Erica L. Peralta,
    on the briefs).
    Jordan Viana, Deputy Attorney General, argued the
    cause for respondent Department of Environmental
    Protection (Matthew J. Platkin, Attorney General,
    attorney; Janet Greenberg Cohen, Assistant Attorney
    General, of counsel; Jordan Viana, on the brief).
    John J. Jackson, III, argued the cause for respondent
    Kenneth Nicosia (John J. Jackson III & Associates,
    1
    Although the briefs denote the permit number as "1419," the record shows the
    issued permit bears the number "1519."
    LLC, attorneys; John J. Jackson, III, of counsel and on
    the brief; Jilian McLeer, on the brief).
    The opinion of the court was delivered by
    SABATINO, P.J.A.D.
    This appeal arises from a denial by respondent New Jersey Department of
    Environmental Protection ("DEP") of a request by appellants Henry and Sarah
    Dewing to rescind what is known as a flood hazard area general permit-by-
    certification 5 ("GPC 5") granted to a neighboring residential property owner,
    Kenneth Nicosia. The Dewings own residential property in Mantoloking that
    abuts Nicosia's parcel, both located within a block of the Atlantic Ocean
    shoreline. Nicosia, a developer, sought the permit to replace a single-family
    house on the site with a new house.
    After receiving notice of Nicosia's application for a GPC 5, appellants and
    several other Mantoloking residents submitted comments to the DEP contesting
    the application. The comments objected to the issuance of the GPC 5, and
    further alleged that Nicosia's ongoing construction of the new house was not
    adhering to the permit's conditions. A DEP Section Chief responded to the
    Dewings by email, rejecting their objections and declining to modify or rescind
    the permit. This appeal by the Dewings ensued.
    Appellants principally argue that (1) the written notice they received of
    A-2921-22
    2
    Nicosia's permit application was deficient because it failed to state the permit
    was effective during the comment period; and (2) the applicable DEP regulations
    should be construed to require a GPC 5 applicant to show that an existing
    structure is not in "usable condition" due to "decay" or "damage." See N.J.A.C.
    7:13-1.2 (defining the terms "reconstruct" and "repair" under the regulations).
    For the reasons that follow, we affirm. The GPC 5 notice did not violate
    any statutory or regulatory provisions, nor was it constitutionally deficient. In
    addition, although the pertinent regulations are poorly worded and punctuated,
    the DEP has reasonably construed them to not require an applicant who, as here,
    seeks to replace a lawfully existing structure to demonstrate the structure is
    decayed, damaged, or otherwise not in usable condition. That said, nothing in
    this opinion precludes the pursuit of available enforcement remedies if the
    construction, as built, does not comply with the conditions of the GPC 5 or
    applicable statutes or regulations.
    I.
    A.
    We begin with an overview of the statutory and regulatory scheme.
    "Under the Flood Hazard Area Control Act (FHAC Act), N.J.S.A. 58:16A-50 to
    -103, and its regulations, [the FHAC Act Rules,] N.J.A.C. 7:13-1.1 to -24.11,
    A-2921-22
    3
    certain types of developments are regulated and require permits if the
    development is in the flood hazard area or the riparian zone of a regulated
    water." Musconetcong Watershed Ass'n v. N.J. Dep't of Env't Prot., 
    476 N.J. Super. 465
    , 472-73 (App. Div. 2023). "The FHAC Act 'confers broad authority'
    on the DEP 'to protect the "safety, health, and general welfare" of the public by
    "deliniat[ing] and mark[ing] flood hazard areas" and subjecting them to "land
    use regulations."'" 
    Id. at 476-77
     (quoting Am. Cyanamid Co. v. State, Dep't of
    Env't Prot., 
    231 N.J. Super. 292
    , 297 (App. Div. 1989) (alterations in original)
    (quoting N.J.S.A. 58:16A-50(b))).
    The FHAC Act Rules "shall be liberally construed to effectuate the
    purpose of the Acts under which it was adopted."             N.J.A.C. 7:13-1.6.
    Specifically, the Rules are intended "to minimize damage to life and property
    from flooding caused by development within flood hazard areas, to preserve the
    quality of surface waters, and to protect the wildlife and vegetation that exist
    within and depend upon such areas for sustenance and habitat." N.J.A.C. 7:13-
    1.1(c). Likewise, the FHAC Act itself "shall be liberally construed to effectuate
    the purpose and intent thereof." N.J.S.A. 58:16A-64.
    The general permit-by-certification ("GPC") program at issue here was
    adopted by the DEP in 2016. 48 N.J.R. 1067(a) (Jun. 20, 2016). The program
    A-2921-22
    4
    is codified in regulations set forth in N.J.A.C. 7:13-8.1 to -8.16 and is also
    subject to other FHAC Act regulations.          Applicable to those regulations,
    N.J.A.C. 7:13-6.7 imposes five enumerated requirements designed to secure
    structures during floods and avoid interference with waterways, animal habitats,
    and vegetation. N.J.A.C. 7:13-6.7(b)(1) to (5). Additionally, "[e]xcept for
    normal property maintenance . . . and forest management activities . . . regulated
    activities authorized under a . . . general permit-by-certification . . . in
    combination with all proposed activities, shall not constitute a major
    development, as defined in the Stormwater Management rules at N.J.A.C. 7:8-
    1.2." N.J.A.C. 7:13-6.7(c).2
    As a permit-by-certification, the GPC 5 in this case was issued
    automatically by the DEP after "completion of the application submission
    through the [DEP's] electronic system in accordance with N.J.A.C. 7:13-18.3
    [specifying payment of fees and information to be supplied in the application]. "
    N.J.A.C. 7:13-6.3.     As highlighted by the DEP in its brief, permits-by-
    certification are available "for a tightly circumscribed subset of activities" where
    "tight limitations on the activity or activities that can be authorized enable the
    2
    "Major developments" generally include construction for which approval is
    necessary under the Municipal Land Use Law. N.J.A.C. 7:8-1.2. No party
    alleges that Nicosia's proposed construction constitutes a "major development."
    A-2921-22
    5
    automated issuance . . . because there is no need for a case-by-case evaluation"
    of the application. 46 N.J.R. 1051(a) (Jun. 2, 2014). The DEP "will not entertain
    a request to review engineering calculations, in the context of an applicability
    determination or otherwise, for the purposes of determining that a proposed
    activity will meet any condition of a permit-by-rule or general permit-by-
    certification." N.J.A.C. 7:13-6.7(d).
    The expedited process facilitated by the automatic approval of a GPC 5 is
    conditioned upon a regulation that expressly imposes liability on the person who
    is "seeking authorization under a general permit-by-certification . . . for
    ensuring that each condition . . . is met." N.J.A.C. 7:13-6.7(d). Moreover, "an
    authorization under a general permit-by-certification or general permit does not
    relieve the person conducting the authorized regulated activities from the
    obligation to obtain any other applicable permits or approvals required by law. "
    N.J.A.C. 7:13-6.3(d).
    These requirements apply to the sixteen categories of GPCs obtainable
    under N.J.A.C. 7:13-8.1 to -8.16. In addition to the GPC 5 for reconstruction of
    buildings at issue in this case under N.J.A.C. 7:13-8.5, applicants may seek
    GPCs for such activities as removal of debris from waterways, restoring
    agricultural banks, enhancing riparian zones, maintenance of stormwater
    A-2921-22
    6
    management structures, placement of solar panels or water monitoring devices,
    and other activities. N.J.A.C. 7:13-8.1 to -8.16.
    A GPC 5 "authorizes the reconstruction, relocation, expansion, and/or
    elevation of a lawfully existing building located outside a floodway, provided
    [the GPC] conditions at N.J.A.C. 7:13-6.7 are met," and also:
    1. The flood hazard area elevation for the site has been
    determined by [the DEP's] delineation or FEMA flood
    mapping . . . ;
    2. The building is not located in a floodway;
    3. The applicant obtains an engineering certification
    confirming that the building is not being expanded
    within or relocated into a floodway;
    4. The footprint of the building has not increased by
    more than 750 square feet, cumulatively, since
    November 5, 2007;
    5. The applicant obtains an engineering certification
    confirming that the lowest floor of the building is being
    reconstructed or elevated to at least one foot above the
    flood hazard area design flood elevation and no lower
    than the elevation required under the Uniform
    Construction Code, N.J.A.C. 5:23;
    6. Any new enclosure below the lowest floor of the
    building is not used for habitation, remains open to
    floodwaters, and is constructed in accordance with
    N.J.A.C. 7:13-12.5(p);
    7. Any existing enclosure below the lowest floor of the
    building, which does not conform to the requirements
    A-2921-22
    7
    of N.J.A.C. 7:13-12.5(p), such as a basement having a
    floor that is below grade along all adjoining exterior
    walls, is abandoned, filled-in, and/or otherwise
    modified to conform with the requirements of N.J.A.C.
    7:13-12.5;
    8. No disturbance is located within 25 feet of any top of
    bank, unless the project lies adjacent to a lawfully
    existing bulkhead, retaining wall, or revetment along a
    tidal water or impounded fluvial water;
    9. Any building to be relocated is either moved outside
    a riparian zone or located within an actively disturbed
    area; and
    10. No riparian zone vegetation is cleared, cut, and/or
    removed, except for vegetation within 20 feet of the
    building, where such disturbance is necessary to access
    the building and facilitate its reconstruction, relocation,
    expansion, and/or elevation.
    [N.J.A.C. 7:13-8.5 (emphasis added).]
    Critical to this appeal, the term "reconstruct" is defined by the FHAC Act
    Rules within N.J.A.C. 7:13-1.2 as:
    "Reconstruct" means to patch, mend, replace, rebuild
    and/or restore a lawfully existing structure to a usable
    condition after decay or damage has occurred, in which
    50 percent or greater of the structure is replaced and/or
    the size, shape or location of the structure is altered.
    For habitable buildings, the percentage of replacement
    shall be determined by comparing the cost of the
    reconstruction to the market value of the building as
    determined before the start of construction; where the
    percentage of replacement is 50 percent or greater, such
    reconstruction shall also constitute a substantial
    A-2921-22
    8
    improvement as defined in this section. For all other
    structures, the percentage of replacement shall be
    determined by comparing the area of the structure being
    reconstructed to the total area of the structure.
    [N.J.A.C. 7:13-1.2 (emphasis added).]
    This definition of "reconstruct" set forth in N.J.A.C. 7:13-1.2
    complements the definition of a "repair" within the same set of regulatory
    definitions:
    "Repair" means to patch, mend, replace, rebuild and/or
    restore a lawfully existing structure to a usable
    condition after decay or damage has occurred, in which
    less than 50 percent of the structure is replaced and the
    size, shape or location of the structure is not altered.
    For habitable buildings, the percentage of replacement
    shall be determined by comparing the cost of the repair
    to the market value of the building as determined before
    the start of construction; where the percentage of
    replacement is less than 50 percent, such repair shall
    not constitute a substantial improvement as defined in
    this section. For all other structures, the percentage of
    replacement shall be determined by comparing the area
    of the structure being repaired to the total area of the
    structure.
    [N.J.A.C. 7:13-1.2 (emphasis added).]
    Simply stated, under these definitions, a "repair" occurs when less than 50
    percent of a lawfully existing structure is replaced, whereas a "reconstruction"
    occurs when 50 percent or more of the structure is replaced. Here, Nicosia's
    construction fully replaces the pre-existing house, and thus must be evaluated
    A-2921-22
    9
    under the definition of a "reconstruction."
    B.
    With this regulatory backdrop in mind, we summarize the pertinent facts
    and procedural history concerning Nicosia's GPC 5.
    As noted above, Nicosia is a real estate developer. He is the owner of
    residential property on Ocean Avenue in Mantoloking. On April 13, 2023,
    Nicosia mailed notice to all owners of property within 200 feet of his property
    of his intention to replace the existing single-family dwelling pursuant to a GPC
    5 to be obtained from the DEP. Among other things, the notice stated that the
    new house would "compl[y] with the elevation and flood requirements [of] the
    New Jersey Flood Area Control Act Rules at N.J.A.C. 7:13 et seq."
    The notice stated the permit application could "be reviewed at the
    municipal clerk's office."    It further advised that persons "may provide
    comments concerning the proposed development and site" through "written
    comments within 30 calendar days." The notice supplied an address at the DEP
    for this purpose, attention to the "Borough of Mantoloking Supervisor."
    The following day, Nicosia filed an application with the DEP for a GPC
    5. The DEP automatically issued the permit the same day.
    A-2921-22
    10
    In early May 2023, several neighbors submitted comments to the DEP.
    Apart from appellants, the commenters included approximately seven other
    households. The commenters raised concerns about the quality and quantity of
    fill dumped at the construction site, the clearance of all vegetation, the
    construction of a concrete retaining wall that might alter water flow throughout
    the neighborhood, the demolition of the preexisting house, the planned four-
    foot increase in lot elevation, and other aspects of Nicosia's plan.        One
    commenter claimed to have conducted "a visual inspection" and observed the
    "fill appears to be strewn with construction debris including degradable organic
    and metallic articles" and was not "clean fill" compliant with Borough
    ordinances and State regulations.
    Appellants Henry and Sarah Dewing submitted a comment to the DEP on
    May 11, 2023, objecting to the permit as ineligible for a GPC 5 and against DEP
    flood regulations. Their comment was submitted by an attorney, who alleged
    Nicosia, without a permit, had demolished the preexisting house and constructed
    a wall around three sides of the lot. The Dewings' counsel asserted the house
    had been in good condition before its demolition, arguing a GPC 5 was therefore
    inappropriate because N.J.A.C. 7:13-8.5 allegedly is only available to restore or
    replace damaged homes. Further, the Dewings asserted the construction of a
    A-2921-22
    11
    wall "surrounding almost three sides of the lot" redirected flood flows onto
    Route 35, a State highway and "evacuation route" "not designed to collect and
    drain flood or storm waters." The Dewings further alleged the construction of
    the wall involved excavating not only Nicosia's property, but also involved
    excavating part of their own property.
    To support their objections, the Dewings commissioned a report by Becht
    Engineering BT, Inc. ("Becht Engineering"). Becht Engineering determined the
    new construction covers 2,811 square feet, in contrast to the 1,600 square feet
    occupied by the previous dwelling.
    Becht Engineering's report incorporated a report prepared by Coastal
    Environmental    Consulting,   LLC       ("Coastal   Environmental").   Coastal
    Environmental's report opined that a GPC 5 is inappropriate for Nicosia's
    construction because the site plans contemplate increasing the footprint of the
    original home by more than 750 square feet and because the DEP never verified
    the flood hazard area elevation of the site, a requisite of a GPC 5. Coastal
    Environmental contended that a "GPC 6" permit under N.J.A.C. 7:13-8.6 was
    more appropriate.
    The Dewings further commissioned a report by Princeton Hydro, LLC
    ("Princeton Hydro").    The report alleged Nicosia demolished the home in
    A-2921-22
    12
    December 2022, began filling the site with soil and constructing a retaining wall
    in January 2023, and continued construction until issuance of a cease-and-desist
    order by an Ocean County agency in January 2023 and a stop work order by the
    Borough of Mantoloking later that month. Like Becht Engineering and Coastal
    Environmental, Princeton Hydro asserted that a GPC 5 was inappropriate
    because the preexisting structure was not damaged.
    On June 8, 2023, DEP Section Chief Keith P. Stampfel, P.E., emailed the
    Dewings' attorney with a response to their objections. In that email, Stampfel
    stated:
    I did a review of this permit and I don't see any problem
    with [it]. There was a house existing at least until
    September 2022 (that is the most recent nearmap
    imagery that we have, but the house could have been
    there even later than that), so we would allow that to be
    considered a reconstruction of an existing house.
    There is also a reference to an objection regarding a
    retaining wall, but that is not regulated under the FHA
    regulations since it is not in a floodway nor is it in a
    regulated water itself or within 25' top of bank.
    Also, if the permittee wants to install a pool in the
    future, they would be able to qualify for a FHA permit
    by rule #21, so that wouldn't require additional FHA
    permits other than the PBR.
    There is also a reference to stormwater management
    and grading objections, however that would be
    reviewed under the local level since it is not a 'major
    A-2921-22
    13
    development,' so a stormwater management review isn't
    required at the State level.
    It should also be noted that a FHA Verification is not
    required for a [GPC 5].
    [(Emphasis added.)]
    After receiving Stampfel's email, the Dewings filed this appeal of the
    DEP's final agency decision. R. 2:2-3(a)(2). The record does not inform of us
    what, if any, responses the DEP may have provided to the comments of the other
    objectors.3
    II.
    We apply well-settled principles in reviewing the issues raised in this
    administrative appeal. Appellate courts "will not reverse an agency's decision
    unless: (1) it was arbitrary, capricious, or unreasonable; (2) it violated express
    or implied legislative policies; (3) it offended the State or Federal Constitution;
    or (4) the findings on which it was based were not supported by substantial,
    credible evidence in the record." Univ. Cottage Club of Princeton N.J. Corp. v.
    3
    We learned at the appellate oral argument that separate litigation is pending
    in the Law Division challenging the approvals Nicosia obtained under the
    MLUL from the Mantoloking Joint Planning and Zoning Board. Counsel for
    Nicosia represented to us that the construction of the new house is nearly
    completed. Appellants' counsel noted that a letter had been previously served
    on Nicosia, warning that such continued construction would be at his own risk
    while this litigation has been pending.
    A-2921-22
    14
    N.J. Dep't of Env't Prot., 
    191 N.J. 38
    , 48 (2007). "Generally, courts afford
    substantial deference to an agency's interpretation of a statute that it is charged
    with enforcing . . . [but] [a]n appellate court, however, is 'in no way bound by
    the agency's interpretation of a statute or its determination of a strictly legal
    issue.'"   
    Ibid.
     (quoting In re Taylor, 
    158 N.J. 644
    , 658 (1999) (quoting
    Mayflower Sec. Co. v. Bureau of Sec., 
    64 N.J. 85
    , 93 (1973))).
    Guided by these standards, we address the two main issues presented by
    appellants: (1) the alleged deficiency of the notice, and (2) whether the
    definition of a "reconstruction" requires GPC 5 applicants to prove that a
    lawfully existing structure is not in usable condition due to either "damage" or
    "decay."
    A.
    The notice issue is the easier of the two main issues on appeal. At oral
    argument, counsel represented to us that the notice form used by Nicosia was
    patterned after sample forms on the DEP website.
    A key facet of our notice analysis, which the Attorney General has
    highlighted in a supplemental brief, is the distinction within the state
    Administrative Procedure Act ("APA"), N.J.S.A. 52:14B-1 to -31, between a
    "public notice" process utilized for rulemaking and a "public notice" process
    A-2921-22
    15
    used in a permit context such as the one before us. This distinction is reflected
    by the difference within the APA between N.J.S.A. 52:14B-4(a)(4) (providing
    for public distribution of "the agency's response" to objections to proposed new
    rules) and N.J.S.A. 52:14B-3.1(a) (allowing any "interested persons" to submit
    objections to DEP permitting decisions, but not imposing requirements for an
    agency response).
    Because this case involves a permitting dispute rather than a challenge to
    the adoption of DEP administrative rules, there are no provisions within the
    statutes or regulations that required the DEP to respond to the comments
    received from appellants or the other objectors to the Nicosia permit . As the
    DEP acknowledges, its obligation is simply to consider the comments, if any,
    that are submitted from the public. Such consideration is duly reflected in
    Section Chief Stampfel's June 8, 2023 email. To be sure, the email does not
    explicitly respond to each comment submitted on appellants' behalf4 and their
    retained experts. However, nothing in applicable statutes, regulations, or case
    law mandates that degree of specificity. The email reflects that, at the very least,
    the DEP gave substantial consideration to appellants' comments.
    4
    We need not address whether the DEP duly considered the objections from the
    other commenters who, unlike the Dewings, have not appealed.
    A-2921-22
    16
    The Dewings argue the public comment process is "flawed" as applied to
    permits-by-certification because the automatic issuance of such permits and
    their immediate publication in the DEP Bulletin starts: (1) the 30-day period to
    request an adjudicatory hearing under N.J.A.C. 7:13-23.1(b), and (2) the 45-day
    period to appeal to this court under Rule 2:4-1(b). The Dewings maintain neither
    of those avenues of review are informed by the public comment process, which
    requires no response of the agency and calls for submissions within 30 days of
    the permit's issuance.
    The Dewings' contentions of procedural shortcomings are undermined by
    their limited status as third-party objectors to a permit issued by the DEP. The
    APA "prohibit[s] State agencies from promulgating rules and regulations which
    would allow third party appeals of permit decisions unless specifically
    authorized to do so by federal law or State statute." N.J.S.A. 52:14B-3.1(d).
    That provision of the APA still recognizes the "constitutional and statutory
    rights and remedies" of people "who have particularized property interests or
    who are directly affected by a permitting decision," which the Dewings could
    vindicate through an adjudicatory hearing. N.J.S.A. 52:14B-3.1(b). But they
    requested no such adjudicatory hearing in this case.
    A-2921-22
    17
    Appellants contend the notice form used for GPC 5 permits should
    explicitly advise would-be objectors that the permit recipient can immediately
    proceed with demolition and construction and does not have to wait before the
    30-day comment period expires. That proposed enhancement to the notice form,
    however, raises policy concerns beyond the scope of this appeal.
    The policies underlying the GPC 5 program strive to minimize delay. A
    key facet of the permit-by-certification program is to enable property owners
    who abide by the rules to move ahead with their construction activities
    expeditiously, and not get bogged down with bureaucratic delays and
    unwarranted litigation burdens. Indeed, we can take judicial notice that such
    expediency became especially important in recent years as New Jersey shore
    communities were rebuilt in the aftermath of Superstorm Sandy. If, as here, an
    affected third party has a valid objection to the permit, it does not have to wait
    a full 30 days to voice its concerns and take action.
    Third-party objectors have limited constitutional interests in participating
    in the procedures used for DEP permitting. See In re Riverview Development,
    LLC, 
    411 N.J. Super. 409
    , 425-29 (App. Div. 2010). Here, the basic elements
    of notice and an opportunity to be heard are met by the existing GPC 5 process.
    Mathews v. Eldridge, 
    424 U.S. 319
    , 332-35 (1976).                Any suggested
    A-2921-22
    18
    enhancements of that process can be pursued generally outside of this appeal
    through a petition for rulemaking under N.J.S.A. 52:14B-4(f).
    B.
    Appellants' second point—which their counsel declared at oral argument
    to be their primary ground for reversal—stems from the wording and
    punctuation of the definition of "reconstruct" within N.J.A.C. 7:13-1.2, which
    applies to GPC 5 permits. We repeat the full definition here for the reader's
    convenience.
    "Reconstruct" means to patch, mend, replace, rebuild
    and/or restore a lawfully existing structure to a usable
    condition after decay or damage has occurred, in which
    50 percent or greater of the structure is replaced and/or
    the size, shape or location of the structure is altered.
    For habitable buildings, the percentage of replacement
    shall be determined by comparing the cost of the
    reconstruction to the market value of the building as
    determined before the start of construction; where the
    percentage of replacement is 50 percent or greater, such
    reconstruction shall also constitute a substantial
    improvement as defined in this section. For all other
    structures, the percentage of replacement shall be
    determined by comparing the area of the structure being
    reconstructed to the total area of the structure.
    [N.J.A.C. 7:13-1.2 (emphasis added).]
    As we noted above, appellants want us to construe the first sentence of the
    definition to require GPC 5 applicants to show that a lawfully existing structure
    A-2921-22
    19
    is decayed or damaged, and therefore not in usable condition.             In their
    opposition, the DEP and Nicosia interpret the text to not require such a showing
    in a context where, as here, a property owner seeks to "replace" an existing
    structure.
    Our interpretative task is guided by well-established principles. "The
    Legislature's intent is the paramount goal when interpreting a statute and,
    generally, the best indicator of that intent is the statutory language." DiProspero
    v. Penn, 
    183 N.J. 477
    , 492 (2005). A court should "ascribe to the statutory words
    their ordinary meaning and significance, and read them in context with related
    provisions so as to give sense to the legislation as a whole." 
    Ibid.
     (internal
    citations omitted); see also State v. Gomes, 
    253 N.J. 6
    , 15-16 (2023). Those
    same core principles for construing statutes apply to the judicial interpretation
    of administrative regulations. Patel v. N.J. Dep't of Treasury, A-2370-22, __
    N.J. Super. __, __ (App. Div. 2024).
    "In the absence of explicit indication of a special meaning, words will be
    given their ordinary and well understood meaning." In re Schedule of Rates for
    Barnert Mem'l Hosp., 
    92 N.J. 31
    , 40 (1983). In addition, courts should attempt
    to accord meaning to all words of a codified provision. Smith v. Dir., Div. of
    Tax'n, 
    108 N.J. 19
    , 27 (1987) ("it is well-established that a [code] should not be
    A-2921-22
    20
    construed in a manner that renders any portion of it a nullity"); see also Med.
    Soc. of N.J. v. N.J. Dep't of L. & Pub. Safety, 
    120 N.J. 18
    , 26-7 (1990) ("[W]e
    should try to give effect to every word of the [code], and should not assume that
    the [drafter] used meaningless language . . . [n]or should we construe the statute
    to render part of it superfluous").
    The interpretation of N.J.A.C. 7:13-1.2's definition of "reconstruct" is
    complicated by the use of the term "and/or" within the first sentence: "to patch,
    mend, replace, rebuild and/or restore a lawfully existing structure to a usable
    condition after decay or damage has occurred . . . ." (emphasis added). As Judge
    Fisher rightly pointed out in State v. Gonzalez, 
    444 N.J. Super. 62
    , 71-76 (App.
    Div. 2016), the term "and/or" can breed confusion. Grammatically, "and/or"
    literally conveys that any one of the items within a list can be true, or some of
    them, or all of them. 
    Ibid.
    Applying that "and/or" concept here, the term "reconstruct" encompasses
    "patch" or "mend" or "replace" or "rebuild" or "restore" a lawfully existing
    structure, or to perform all or some of those activities. Any one of those terms
    suffices.
    Common dictionary definitions treat the terms "patch" and "mend" as
    A-2921-22
    21
    synonymous or overlapping. 5 Likewise, the terms "rebuild" and "restore" have
    substantially cognate meanings. 6 All of these words, to some extent, connote
    actions undertaken to address a deficiency.
    The term "replace," however, is unlike the others on the list. Something
    need not be in damaged condition in order to be replaced. Merriam-Webster
    defines "replace" as "to put something new in the place of." Replace, Merriam-
    Webster, https://www.merriam-webster.com/dictionary (last visited Jul. 24,
    2024). With respect to a home, a property owner may want to replace it, not
    because it is in disrepair or dilapidated, but because the owner wishes to have,
    say, a more modern, attractive, or energy efficient one. To be sure, at times an
    owner will want to replace a structure, rather than try to restore it, because it is
    in disrepair.   The cost of home restoration can often be far greater than
    replacement of the structure with new materials. But that logically is not the
    only reason that can motivate such a desire.
    5
    To "patch" is "to mend, cover, or fill up a hole or weak spot," whereas to
    "mend" is "to free from faults or defects" or "put into good shape or working
    order again."      Patch, Mend, Merriam-Webster, https://www.merriam-
    webster.com/dictionary (last visited Jul. 24, 2024) (emphasis added).
    6
    To "rebuild" is "to restore to a previous state," whereas to "restore" is "to bring
    back to or put back into a former or original state." Rebuild, Restore, Merriam-
    Webster, https://www.merriam-webster.com/dictionary (last visited Jul. 24,
    2024) (emphasis added).
    A-2921-22
    22
    This leads us to consider the phrase that follows the list of verbs: "a
    lawfully existing structure to a usable condition after decay or damage has
    occurred." We concur with the DEP and Nicosia that this phrase does not have
    to modify each of the verbs that precedes it. If that were the case, it would
    eliminate the wide range of circumstances in which an owner would want to
    "replace" a structure for reasons other than disrepair.       The definition of
    reconstruct was crafted broadly to include replacements, not just synonyms for
    fixing things that need repair.
    Such an interpretation also harmonizes the GPC 5 with the GPC 6, which
    is a permit used for construction of new single-family dwellings on lots with no
    preexisting structures.   N.J.A.C. 7:13-8.6.   No additional requirements are
    imposed on GPC 6 applicants beyond those applicable to GPC 5s, suggesting
    the distinction between the two permits is the existence of a prior structure. If
    GPC 5 construction required decay or damage of the preexisting structure,
    replacement of dwellings for energy efficiency, aesthetic, or other non-
    rehabilitative purpose would not be suitable for any GPC. Thus, it would be
    inexplicably harder to obtain approval for demolition and replacement of an
    energy inefficient home than the automatically-authorized demolition and
    replacement of a decayed home through a GPC 5 or the construction of a new
    A-2921-22
    23
    home on a vacant lot through a GPC 6. Appellants' interpretation of the GPC 5
    regulation conceivably could incentivize property owners to encourage damage
    or decay to qualify for a GPC 5.
    Although the question is not free from doubt, we construe the agency's
    regulation in the manner it has interpreted it. We do so mindful of the agency's
    expertise within the zone of its statutory responsibilities. Although deference is
    not warranted on pure questions of law, courts generally "afford substantial
    weight to an administrative agency's own interpretation of its delegated
    functions." State v. Coviello, 
    252 N.J. 539
    , 557 (2023); see also Patel v. N.J.
    Motor Vehicle Comm'n, 
    200 N.J. 413
    , 420 (2009).
    In reaching this conclusion, we by no means diminish the importance of
    compliance with our state's environmental laws. The permit-by-certification
    process authorized by the flood control statutes and regulations is a special
    program designed to enable compliant property owners to obtain permits
    expeditiously.   That process ought not to be regarded as acquiescence to
    environmental harm. Recipients of GPC 5 permits must still adhere to the
    pertinent FHAC Act requirements as they proceed with construction. We trust
    the DEP in its important role as an environmental enforcement agency will be
    attentive to such compliance.
    A-2921-22
    24
    Consequently, the DEP did not act in a manner that was arbitrary or
    capricious, or contrary to law, in rejecting appellants' claim that Nicosia needed
    to prove the existing house was damaged or decayed or in non-usable condition
    in order to obtain a GPC 5. We therefore sustain its decision.
    C.
    To the extent we have not discussed any remaining arguments of
    appellants, they lack sufficient merit to warrant discussion. R. 2:11-3(e)(1)(E).
    However, nothing in this opinion precludes enforcement action if Nicosia fails
    to comply with the conditions of the GPC 5 or applicable statutes or regulations.
    Affirmed.
    A-2921-22
    25
    

Document Info

Docket Number: A-2921-22

Filed Date: 7/30/2024

Precedential Status: Precedential

Modified Date: 7/30/2024