Albuquerque Lumber Co. v. Montevista Co. , 39 N.M. 6 ( 1934 )


Menu:
  • Montevista Company, the appellant, as owner of an addition to the city of Albuquerque, contracted the sale to one Townsend of a lot and fractional lot in said addition. Townsend was a builder engaged in the construction of residence properties on lots purchased under executory contracts. According to his practice, after construction of the building, he would incumber the lot and improvements with a mortgage from the proceeds of which the claims for labor and material and balance due on the lots were satisfied.

    The appellant knew of his practice and that he proposed to construct on the lots in question a building of brick for residence purposes. The contract called for $1 down and the balance in installments. The down payment represents all ever paid on the contract. Before he had purchased any materials from Albuquerque Lumber Company, the appellee, its representative visited the office of appellant and inquired if Townsend had title to the lots. The representative was informed that he did not, but was purchasing on contract. Upon being told that appellee proposed to sell him the material for the job, *Page 8 appellant's representative remained silent, making no comment the one way or the other. The appellee then began furnishing materials and continued doing so until the value thereof reached $804.37, for which amount it filed its claim of lien.

    The appellant knew the work was started, but did not post the property. No credit was extended appellant by appellee, all materials being charged to Townsend. When Townsend got the foundation in and started to lay brick on the wall, a creditor attached him and ruined his credit. The appellant intervened in the attachment suit and got an order adjudging that Townsend had no title to the land in question (which was also attached), and the writ was vacated as to that property, the appellant resuming possession and canceling Townsend's contract for failure to pay.

    The foundation and part of a wall constructed as aforesaid are of no value to the land and contribute nothing of value thereto in the way of betterments or otherwise. Within the time allowed by law, the appellee filed its claim of lien against Townsend and the land, and foreclosed in the suit out of which this appeal arises. Certain junior lien-holders against Townsend were made parties to the foreclosure suit along with Townsend, his wife, and the appellant. The junior lien-holders passed out on adverse ruling, and the contest narrowed down to the appellee as material lien claimant against the appellant. The court entered a decree foreclosing appellee's claim of lien as against appellant's estate in the land and dismissed the latter's cross-complaint against appellee, asking for cancellation of its lien claim as a cloud. This appeal followed.

    A nice question confronts us at the very threshold of this appeal. Does knowledge by appellee that Townsend, its customer, was merely an executory vendee in possession, with ownership of the legal title in appellant, deny effect to the latter's failure to post? The appellee, by invoking the provisions of Comp. St. 1929, § 82-210, furnishes a negative answer to the inquiry. The appellant affirms the contrary.

    This statute appears as section 11 of chapter 16 of the Session Laws of 1880, the original Mechanics' Lien Act. It furnishes an easy means whereby the owner of property in possession of another under tenancies, purchase contracts, or otherwise may, after knowledge that such other has commenced repairs, alterations, or improvements, relieve his (the owner's) estate in the premises from liability therefor by posting in some conspicuous place on the premises or improvements a notice of nonliability. In default of such posting, the statute declares the improvements or repairs "shall be held to have been constructed at the instance of such owner," and his interest "shall be subject to any lien filed" in accordance with the provisions of said act.

    This statute has been before the state and territorial Supreme Courts many times for consideration, although none of the decisions dealing with it involves the precise question here presented. Its effect, either to bind the owner's estate if with knowledge he fails to *Page 9 post, or to relieve him, if without knowledge, or having knowledge, where he posts, has never been questioned in any of said decisions. Post v. Miles, 7 N.M. 317,34 P. 586 (same case on subsequent appeals under other titles, see Mountain Electric Co. v. Miles, 9 N.M. 512, 56 P. 284, and Armijo v. Mountain Electric Co., 11 N.M. 235, 67 P. 726); Ford v. Springer Land Ass'n, 8 N.M. 37, 41 P. 541; Post v. Fleming,10 N.M. 476, 62 P. 1087; Pearce v. Albright, 12 N.M. 202, 76 P. 286; Stearns-Roger Mfg. Co. v. Aztec Gold Min. Mill. Co., 14 N.M. 300, 93 P. 706; Albuquerque Lumber Co. v. Tomei, 32 N.M. 5,250 P. 21; Mitchell v. McCutcheon, 33 N.M. 78, 260 P. 1086.

    But appellant reminds us that our Mechanics' Lien Act was adopted from California (Ackerson v. Albuquerque Lumber Co.,38 N.M. 191, 29 P.2d 714). It relies upon four California decisions in support of its contention that actual knowledge by appellee that appellant held the legal title to the property obviated the necessity of posting to relieve appellant's estate from liability for the improvements being made. The cases cited are Jurgenson v. Diller, 114 Cal. 491, 46 P. 610, 55 Am. St. Rep. 83; Ayers v. Green Gold Min. Co., 116 Cal. 333, 48 P. 221; Reese v. Bald Mountain Consol. Gold Min. Co., 133 Cal. 285, 65 P. 578 and Street v. Hazzard, 27 Cal. App. 263, 149 P. 770.

    There are statements in some of these cases which tend to support appellant's position. However, as held in a later decision by the Supreme Court of California, Leoni v. Quinn,189 Cal. 622, 209 P. 551, 552, where, in a controversy between a lien claimant and a lessor, the question now argued was squarely put, the point was not involved in those cases and they were not deemed decisive. The court said:

    "It is earnestly contended that actual knowledge must be held to be the equivalent of the notice prescribed by the Code. To so hold would be to hold in effect that the giving of an informal verbal notice would be a substantial compliance with the requirements of the section. This would amount to a repeal of the express provisions thereof which require the posting of a formal notice in writing and specifying what it must contain, and further require that a verified copy thereof must be filed for record. As was said in the case above cited: ``This provision is for the benefit of the owner, and he must avail himself of it, or otherwise, according to its terms, his interest will be liable for the lien.' * * * What was said in Jurgenson v. Diller,114 Cal. 491, 46 P. 610, 55 Am. St. Rep. 83, and Reese v. Bald Mountain, etc., Co., 133 Cal. 285, 65 P. 578, is not in point here. As was expressly pointed out in the latter case, section 1192, Code of Civil Procedure, was not applicable to either of those cases because they involved subtractive mining which was not ``the construction, alteration * * * or repair of any building or other improvement.' In Ayers v. Green Gold M. Co., 116 Cal. 333, 48 P. 221, it was expressly held that this section was not there applicable because the owner had no knowledge or notice of the doing of the work. Street v. Hazzard, 27 Cal. App. 263,149 P. 770, is not in point for the *Page 10 reason that it was there stipulated that the owner had posted the notice of nonliability in full compliance with all of the requirements of the section as it then read (before the amendment of 1911).

    "The case of Pasqualetti v. Hilson, 43 Cal. App. 718,185 P. 693, in which an application for rehearing was denied by this court, is squarely in point here, and goes even further than is necessary to sustain appellant's contentions in the instant case. It was there conceded that the owner had in due time posted written notice of nonliability which fully complied in all respects with the requirements of the section; that within the required time a true copy thereof had been filed for record; and that the plaintiff had actual knowledge thereof. It was held, notwithstanding these facts, that the owner's interest in the property was subject to the lien, for the sole reason that the copy of the notice which was filed for record was acknowledged before a notary public instead of being verified as the law requires."

    As pointed out in the opinion just quoted from, the case of Pasqualetti v. Hilson, 43 Cal. App. 718, 185 P. 693, presents facts even stronger for the contention made than those disclosed in Leoni v. Quinn. Nevertheless, the court in that case held a failure to observe the requirements of the nonliability statute was fatal to the owner's claim of immunity.

    Later, in Flora v. Hankins, 204 Cal. 351, 268 P. 331, the Supreme Court of that state ruled that personal oral notice by the owner of premises that she would not be responsible for any work done by contractors on building constructed under contract with lessee was insufficient under the California statute to relieve the owner's estate from liability.

    In a still later case, Hammond Lumber Co. v. Goldberg, 125 Cal. App. 120,13 P.2d 814, 818, a California Court of Appeals, dealing with the corresponding section of the California Mechanics' Lien Act, changed somewhat by amendments, said: "The courts, having adopted a rule of liberal construction relative to mechanic's liens, must follow a strict construction of any act or provision by which the owner of property upon which improvements are made may relieve himself from, or escape, liability therefor. See Pasqualetti v. Hilson, 43 Cal. App. 718, 185 P. 693, where such a notice, otherwise sufficient, was held ineffectual because acknowledged instead of verified."

    Counsel for appellant calls our attention to amendments of this section, and urges that the force of these earlier cases is not to be weakened by later decisions subsequent to the amendments. As pointed out in Ackerson v. Albuquerque Lumber Co., supra, we adopted the California act of 1872, as amended in 1873-74. As this section of the California act, section 1192, Cal. Code Civ. Proc., read then, so ours remains today. It has been several times amended, the changes involving a lengthening of the time for posting notice, a revision of its contents, and the requirement for recording a verified copy thereof. A history of the section in California follows: Enacted March 11, 1872; *Page 11 amendment approved March 30, 1874, Code Amdts. 1873-74, p. 410; March 18, 1907, Stats. and Amdts. 1907, p. 577, Kerr's Stats. and Amdts. 1906-07, p. 481; May 1, 1911, Stats. and Amdts. 1911, p. 1317; May 16, 1925, Stats. and Amdts. 1925, p. 304.

    We find nothing in the amendments, apart from the original text, controlling the basic conclusion reached in Leoni v. Quinn and Pasqualetti v. Hilson, supra, that actual knowledge by the claimant of the state of the title does not relieve the owner's estate, if he fails by posting to repel the deadly inference of consent or authorization consequent under the statute upon a default in posting. We have held in Ackerson v. Albuquerque Lumber Co., supra, that actual knowledge by the owner of the property intended does not cure in favor of the lien claimant a defective description in the notice of lien.

    The statute does no more than to furnish a rule of evidence whereby the owner's consent or acquiescence may be determined. Title Guarantee Trust Co. v. Wrenn, 35 Or. 62, 56 P. 271, 273, 76 Am. St. Rep. 454; Wheaton v. Berg, 50 Minn. 525, 52 N.W. 926 and Fauser v. McElroy, 157 Minn. 116, 195 N.W. 786. The cases of Meyer v. Berlandi, 39 Minn. 438, 40 N.W. 513, 1 L.R.A. 777, 12 Am. St. Rep. 663, and Randolph v. Builders' Painters' Supply Co., 106 Ala. 501, 17 So. 721, relied upon by appellant as pointing to unconstitutionality of the statute if held to create a conclusive presumption, dealt with a quite different statute.

    "The language in Meyer v. Berlandi, 39 Minn. 438, 40 N.W. 513, 1 L.R.A. 777, 12 Am. St. Rep. 663, was directed to entirely dissimilar provisions in the lien law of 1887 (chapter 170), which were of so drastic a nature that the court was compelled to hold the entire law unconstitutional." Fauser v. McElroy,157 Minn. 116, 195 N.W. 786, 788.

    For, as the Supreme Court of Oregon said in Title Guarantee Trust Co. v. Wrenn, supra: "It is claimed that, inasmuch as a lien can only be created upon the land of another by his consent or authority, this section is unconstitutional and void, and the cases of Randolph v. Supply Co., 106 Ala. 501, 17 So. 721, and Meyer v. Berlandi, 39 Minn. 438, 40 N.W. 513 [1 L.R.A. 777, 12 Am. St. Rep. 663], are cited in support of this contention; but neither of these cases is in point, because, by the statutes which were there held void, the fact that the person performing labor or furnishing material was not enjoined by the owner, or notified in writing not to do so, is made conclusive evidence that such labor was performed or material furnished with or by his consent, without reference to his knowledge thereof; while our statute, assuming that a lien cannot be created without the consent of the owner, express or implied, simply provides a rule of evidence by which such consent could be determined." (Italics ours).

    The basis of the presumption raised by the statute is equitable estoppel. Fauser v. McElroy, supra; Nichols v. Levy (Nev.)32 P.2d 120, 121. Our territorial Supreme Court early so recognized. Post v. Miles, supra.

    Actual knowledge often stands in law as the equivalent of a required notice. In this *Page 12 case, however, we are not put to a decision whether that principle applies to the notice required by section 82-210. All the actual knowledge appellee had was that appellant owned the property and that Townsend did not. That does not touch the subject-matter of the required notice. If appellant had posted a notice merely setting forth its ownership, it would have been worthless. The notice must state that the owner "will not be responsible." The "knowledge" here relied upon did not include the matter of responsibility. Under the California cases of Leoni v. Quinn and Pasqualetti v. Hilson, supra, it would not have availed, had it done so.

    What has been said substantially refutes appellant's next contention, that, "where materialman furnishes upon the credit of one who knows he has no title, the provisions of section 82-204 apply."

    The argument is that appellee never had any lien or right of lien except as to the vendee's interest, and that such lien or right was cut off by forfeiture of the interest.

    It is probably true, as appellant contends, that a materialman contracting with one whose title is less than the fee simple obtains a lien or right of lien only as to that lesser interest unless he can "assist himself by some proof of estoppel."

    But the statute points out what shall constitute the estoppel. It is the failure of the owner to post the property within three days after learning of the improvement. Here the facts raise the estoppel, unless appellee's knowledge as to the title is the equivalent of posting by appellant, and we have determined that it is not.

    Considering sections 82-204 and 82-210 as in pari materia, as we did in Mitchell v. McCutcheon, 33 N.M. 78, 260 P. 1086, appellee here originally risked having its lien limited to the vendee's interest, but became entitled to the benefit of the larger lien, when appellant, by failing to post, acquiesced in the subjection of the vendor's interest also.

    It seems no more necessary here than it was in Albuquerque Lumber Co. v. Tomei, 32 N.M. 5, 250 P. 21, 23, to decide "whether, by a declaration of forfeiture warranted by the terms of the contract," the vendor may cut off the lien on the vendee's interest. That question does not arise when the vendor has suffered the subjection of his own interest.

    Appellant's last point as taken from its brief is as follows: "Lien given by section 82-204, Comp. 1929, is upon the improvement itself and only incidentally upon the land, and where the improvement perishes through no fault of the landowner, the lien fails."

    If the trial court ruled adversely to appellant upon this proposition, it only did so in awarding judgment to appellee in the face of a finding that the improvement commenced, and later abandoned, was of "no value" to the appellant's land as a betterment or otherwise. In so far as the mere finding of "no value" is concerned, standing alone, we consider it no obstacle to appellee's recovery.

    While fundamentally and in a broad sense presumptive benefit to the land improved by another's labor or material from the *Page 13 beginning has afforded constitutional justification for and still supports the theory of mechanics' lien legislation, yet so to recognize does not mean that a showing of benefit in a particular case is indispensable to the right to lien. The authorities are plainly against this view. Hardwood Interior Co. v. Bull, 24 Cal. App. 129, 140 P. 702; Chamberlain v. City of Lewiston,23 Idaho, 154, 129 P. 1069; Nichols v. Levy (Nev.) 32 P.2d 120. Such a construction would greatly restrict the field of usefulness of these remedial acts as against those intended to be aided thereby.

    Nor indeed do we understand appellant to contend that a showing of value or benefit in each particular case is essential to the existence of a lien. Yet its reasoning leads logically to such a conclusion.

    It is entirely possible that the trial court attached no greater point to the finding of "no value" than we have accorded it in what has just been said. However, the appellant, arguing that such a finding puts the case as to controlling principles in the class of destruction and removal cases, invokes the rule applied in Pennsylvania and California, known as the "Pennsylvania doctrine." The theory of this doctrine is that, under statutes such as exist in the states named, the lien is primarily upon the building or structure and attaches to the land only as an incident to the lien on the building or structure.

    For Pennsylvania cases enunciating the doctrine, see Presbyterian Church v. Stettler, 26 Pa. 246; Wigton Brooks's Appeal, 28 Pa. 161; Short v. Miller, 120 Pa. 470, 14 A. 374: Short v. Ames, 121 Pa. 530, 15 A. 607; Titusville Iron-Works v. Keystone Oil Co., 130 Pa. 211, 18 A. 739; McCristal v. Cochran,147 Pa. 225, 23 A. 444; Florin v. McIntire, 14 Pa. Co. Ct. R. 127; Thompson v. Porter, 14 Pa. Co. Ct. R. 232; Wheeler v. Pierce, Kelley Co., 167 Pa. 416, 31 A. 649, 46 Am. St. Rep. 679; Alguire v. Keller, 68 Pa. Super. 279.

    See, also, the California cases and an Oregon decision based on a copy of the California statute: Humboldt Lumber Mill Co. v. Crisp, 146 Cal. 686, 81 P. 30, 106 Am. St. Rep. 75, 2 Ann. Cas. 811; Linck v. Meikeljohn, 2 Cal. App. 506, 84 P. 309; Watson v. Alta Inv. Co., 12 Cal. App. 560, 108 P. 48; Butler v. Ng Chung,160 Cal. 435, 117 P. 512, Ann. Cas. 1913A, 940; Kern v. San Francisco Co., 19 Cal. App. 157, 124 P. 862; Chenoweth v. Spencer, 64 Or. 540, 131 P. 302, Ann. Cas. 1914D, 678; Pilstrand v. Greenamyre, 34 Cal. App. 799, 168 P. 1161; Johnson v. Smith,97 Cal. App. 752, 276 P. 146; McIntosh v. Funge, 210 Cal. 592,292 P. 960, 74 A.L.R. 420; English v. Olympic Auditorium (Cal.App.) 13 P.2d 740, affirmed in part and reversed in part217 Cal. 631, 20 P.2d 946, 87 A.L.R. 1281.

    The holding of these cases is that, if there is no completed building or structure, or where after completion and before perfecting the lien the building or structure without fault of the owner is removed or destroyed, there is no lien. In other words, the lien on the land either does not come into being in the case of noncompletion, or, in so far as existent, disappears with that to which it was only an incident, in the case of removal or destruction. *Page 14

    The California cases have denied full application of the rule (a departure not noted in the Pennsylvania decisions), where the destruction is only partial. Where such is the case, in at least two decisions, the right to apportion the lien and attach it to what remains of the building and so much of the land occupied thereby seems to have been recognized. Butler v. Ng Chung and Kern v. San Francisco Co., supra.

    Our statute having been adopted from California (Ackerson v. Albuquerque Lumber Co., 38 N.M. 191, 29 P.2d 714), we must first determine the bearing, if any, which this so called "Pennsylvania doctrine" has upon the question before us. The territorial Supreme Court in a dictum appearing in Armijo v. Mountain Electric Co., 11 N.M. 235, 67 P. 726, declined to support the Pennsylvania doctrine, by praising the reasoning of cases affirming the contrary. We should prefer not to rest our decision on this dictum, even if we considered perfect, as we do not, the analogy appellant seeks to draw between the present situation and destruction cases. The dictum is contrary to California decisions based upon a condition peculiar to the California statute, present also in ours, inasmuch as we adopted it.

    We seek then the effect of the abandonment disclosed. This presents the decisive question. The abandonment was through no fault of the lien claimant, appellee. It was attributable to the vendee and resulted from his credit entanglements. Although not to be considered a voluntary abandonment, it is nevertheless to be deemed an abandonment through fault of the vendee, as owner. Cf. McIntosh v. Funge (Cal.), supra, where the destruction, although involuntary, was considered the fault of the owner, by reason whereof the court declined to apply the Pennsylvania doctrine and held the land charged with the lien.

    It seems fairly well settled both upon reason and authority that abandonment, through fault of the owner, of work already commenced, does not defeat the right to lien. 18 R.C.L. 908; 40 C.J. 192; 2 Jones on Liens (3d Ed.) § 1438; Annotation, 64 A.L.R. 276, and cases cited.

    The author of the text on mechanics' liens, at 18 R.C.L. 908, states the rule as follows: "When the work has been commenced on a contract for an improvement on land, and is abandoned by the owner without fault on the part of the contractor, the contractor and laborers and materialmen are entitled to liens on the property for the value of the work done and materials furnished.In such a case, the building or improvement is to be deemedcompleted, so far as the right of persons to assert liens isconcerned." (Italics ours.)

    This rule developed as a matter of statutory construction under statutes similar to ours, although subsequently some states added the rule by way of amendment to the statute itself.

    "In several states the general rule above referred to, that abandonment is equivalent to completion as regards the time for filing mechanics' lien claims, has been incorporated substantially into the statute itself." 64 A.L.R. 280. *Page 15

    In Hot Springs Plumbing Heating Co. v. Wallace, 38 N.M. 3,27 P.2d 984, as said in the later case of Allison v. Schuler,38 N.M. 506, 36 P.2d 519, 522, "we assumed such to be the proper rule of construction," and further stated: "We there displayed a leaning toward the Oregon rule, and cited Eastern Western Lumber Co. v. Williams, 129 Or. 1, 276 P. 257. That decision was shortly afterwards followed in Stark-Davis Co. v. Fellows et al.,129 Or. 281, 277 P. 110, 112, 64 A.L.R. 271."

    In neither of these recent pronouncements, however, were we called upon to speak decisively upon the question. We now settle it by holding that abandonment through fault of the owner and without fault of the lien claimant constitutes constructive completion under our statute, both as respects the right to lien and the time within which it must be filed.

    Then, is the vendor's interest to be charged along with that of the vendee, although the former actually may be blameless as respects the abandonment? Such is the clear import of the posting statute. Through failure to post after knowledge of the construction, the statute says the building or other improvement "shall be held to have been constructed at the instance of such owner or person having or claiming any interest therein, and the interest owned or claimed shall be subject to any lien filed inaccordance with the provisions of this article. * * *" (Italics ours.)

    Not only do we have a case where the work done is to be considered as having been ordered by appellant, but a lien filed therefor under the provisions of the act. By the very language just quoted nothing could be plainer than that the vendor's interest is subject to "any lien" so filed. Obviously, the purpose of the act was to give the vendor a way out by posting. If he fails to post, the divided interests are deemed united, under the implication arising, for the purpose of satisfying any valid lien filed consequent on improvements undertaken by the vendee.

    So viewing the matter, our action will be to affirm the judgment of the lower court.

    It is so ordered.

    WATSON, C.J., and HUDSPETH and ZINN, JJ., concur.

Document Info

Docket Number: No. 3951.

Citation Numbers: 38 P.2d 77, 39 N.M. 6

Judges: Sadler, Bickley, Watson, Hudspeth, Zinn

Filed Date: 11/23/1934

Precedential Status: Precedential

Modified Date: 11/11/2024

Authorities (23)

Kern v. San Francisco Co. , 19 Cal. App. 157 ( 1912 )

Johnson v. Smith , 97 Cal. App. 752 ( 1929 )

Watson v. Alta Investment Co. , 12 Cal. App. 560 ( 1910 )

Leoni v. Quinn , 189 Cal. 622 ( 1922 )

Humboldt Lumber Mill Co. v. Crisp , 146 Cal. 686 ( 1905 )

Flora v. Hankins , 204 Cal. 351 ( 1928 )

Linck v. Meikeljohn , 2 Cal. App. 506 ( 1905 )

Butler v. Ng Chung , 160 Cal. 435 ( 1911 )

Nichols v. Levy , 55 Nev. 310 ( 1934 )

Allison v. Schuler , 38 N.M. 506 ( 1934 )

Mitchell v. McCutcheon , 33 N.M. 78 ( 1927 )

Ackerson v. Albuquerque Lumber Co. , 38 N.M. 191 ( 1934 )

Hot Springs Plumbing & Heating Co. v. Wallace , 38 N.M. 3 ( 1933 )

Stark-Davis Co. v. Fellows , 129 Or. 281 ( 1929 )

Street v. Hazzard , 27 Cal. App. 263 ( 1915 )

Pilstrand v. Greenamyre , 34 Cal. App. 799 ( 1917 )

Hardwood Interior Co. v. Bull , 24 Cal. App. 129 ( 1914 )

English v. Olympic Auditorium, Inc. , 217 Cal. 631 ( 1933 )

McIntosh v. Funge , 210 Cal. 592 ( 1930 )

Reese v. Bald Mountain Consolidated Gold Mining Co. , 133 Cal. 285 ( 1901 )

View All Authorities »