Sherman v. Cimarex Energy Co. ( 2013 )


Menu:
  •        IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO
    Opinion Number: _______________
    Filing Date: November 25, 2013
    Docket No. 32,164
    LARRY SHERMAN,
    Plaintiff-Appellant,
    v.
    CIMAREX ENERGY CO., CIMAREX
    ENERGY CO. OF COLORADO and
    MAGNUM HUNTER PRODUCTION INC.,
    Defendants-Appellees,
    APPEAL FROM THE DISTRICT COURT OF LEA COUNTY
    Gary L. Clingman, District Judge
    Sutin, Thayer & Browne, P.C.
    Timothy J. Atler
    Kerry Kiernan
    Albuquerque, NM
    Kelly, Morgan, Dennis, Corzine & Hansen, P.C.
    Denis Dennis
    Odessa, TX
    Law Office of Allen Moore
    Allen Moore
    Odessa, TX
    for Appellant
    Madison & Mroz, P.A.
    Robert J. Mroz
    Jennifer L. Collins
    Albuquerque, NM
    for Appellees
    1
    OPINION
    FRY, Judge.
    {1}     Plaintiff Larry Sherman appeals the district court’s order granting summary judgment
    in favor of Defendants, which we refer to collectively as Cimarex. Plaintiff was injured
    when he fell over the handrail of a flight of stairs while working on an oil drilling rig.
    Plaintiff, an employee of an independent contractor hired by Cimarex, sued Cimarex, the
    owner and operator of the well site. The district court determined that Cimarex owed no
    duty to Plaintiff to protect against the injury that occurred in this case. We conclude that
    there are issues of fact as to whether Cimarex had supervisory control over the independent
    contractor’s operations so as to give rise to a duty to act reasonably in exercising that
    control. We further determine that there are issues of fact surrounding the questions of
    whether Cimarex’s actions breached any duty it owed Plaintiff and whether those actions
    caused Plaintiff’s injuries. Accordingly, we reverse the district court.
    BACKGROUND
    {2}     Plaintiff worked as a toolpusher for Patterson-UTI Drilling Company. Cimarex
    contracted with Patterson to drill a well and furnish labor, equipment, and services “under
    the direction, supervision and control of [Cimarex].” As a toolpusher, Plaintiff was the head
    Patterson employee on the well site, while Thomas Glen Smith was Cimarex’s drilling
    consultant—the person assigned by Cimarex to supervise the overall operation of the
    project.
    {3}     Patterson required the toolpusher to be able to remain on location twenty-four hours
    a day for eight days. However, Plaintiff and another Patterson toolpusher, Tye Lem, had
    worked out an arrangement whereby the two men alternated a four-days-on-four-days-off
    work schedule. At the time of the accident, Plaintiff had worked twelve consecutive days
    because he covered for one of Lem’s shifts in the midst of working his own, although only
    five of these twelve days were spent working on the current well site and under Smith’s
    supervision1.
    {4}     In the early hours of August 8, 2006, Plaintiff was injured when he fell over a
    handrail while walking down the stairs from the rig’s doghouse. In the district court, the
    parties disputed what event triggered Plaintiff’s movement from the doghouse to the stairs.
    On appeal, they seem to agree that Plaintiff was asleep in the doghouse and that Smith woke
    him up so that he could perform a task at the bottom of the rig. Plaintiff got up and left the
    doghouse, whereupon the accident occurred.
    1
    While Cimarex disputes that Plaintiff worked for twelve consecutive days, that
    dispute is immaterial to our resolution of this case.
    2
    {5}     Plaintiff filed suit against Cimarex, alleging that it was negligent in failing to provide
    him a safe place to work, failing to keep a proper lookout for his safety, failing to allow him
    proper time for rest and recuperation and interrupting his sleep for unnecessary supervision,
    and creating a system that caused him to work while Cimarex, through the actions of Smith,
    knew he was fatigued. Cimarex filed a motion for summary judgment on the basis that it
    owed no duty to Plaintiff because it was not aware that Plaintiff was fatigued. The district
    court agreed and granted summary judgment in Cimarex’s favor. Plaintiff now appeals.
    DISCUSSION
    Standard of Review
    {6}    “We review de novo the granting of summary judgment, construing reasonable
    inferences from the record in favor of the party that opposed the motion. Summary judgment
    is proper when there are no genuine issues of material fact and the movant is entitled to
    judgment as a matter of law.” Blea v. Fields, 2005-NMSC-029, ¶ 10, 
    138 N.M. 348
    , 
    120 P.3d 430
    (citation omitted).
    Outline of this Opinion
    {7}        The district court granted summary judgment on the ground that Cimarex owed no
    duty to Plaintiff, and the parties address their arguments to the question of duty. While “duty
    . . . is a question of law for the courts to decide,” Herrera v. Quality Pontiac, 2003-NMSC-
    018, ¶ 6, 
    134 N.M. 43
    , 
    73 P.3d 181
    (internal quotation marks and citation omitted), in the
    context of the relationship between an independent contractor and an employer,2 there are
    fact questions that inform the court’s determination about duty. In this Opinion, we first
    discuss the general principles governing the employer/independent contractor relationship,
    and we distill the principles set out in our case law and Section 414 of the Restatement
    (Second) of Torts (1965). We then analyze the parties’ arguments in this case.
    General Principles Governing an Employer’s Liability to the Employees of an
    Independent Contractor
    {8}     Generally speaking, “the employer of an independent contractor is not liable for
    injuries to an employee of the independent contractor.” Valdez v. Cillessen & Son, Inc.,
    1987-NMSC-015, ¶ 21, 
    105 N.M. 575
    , 
    734 P.2d 1258
    . “The rationale underlying the rule
    2
    Our Supreme Court has noted that in the context of landowner-contractor-
    subcontractor liability cases, the terms “general contractor,” “owner,” “lessor,” “lessee,” and
    “employer” are often used interchangeably to denote the possessor of the premises. See
    Tipton v. Texaco, Inc., 1985-NMSC-108, ¶ 20, 
    103 N.M. 689
    , 
    712 P.2d 1351
    (internal
    quotation marks omitted). For clarity, we use the term “employer” to identify the person or
    entity that hired the independent contractor.
    3
    is that the independent contractor, free to achieve a legal result (set by the [employer]) by
    any means it chooses, bears the risk should that operation, negligently performed, cause
    physical harm to others.” Marc M. Schneier, The Independent Contractor Rule: The Shifting
    Bedrock of Construction Accident Law, Construction Briefings No. 2002-8, at 2 (2002). As
    with any general rule, however, there are exceptions, including two scenarios: where the
    employer controls the premises on which the work is being performed or where the employer
    retains control over the independent contractor’s performance of its work. Pollard v.
    Westinghouse Elec. Corp., 1995-NMCA-038, ¶ 6, 
    119 N.M. 783
    , 
    895 P.2d 683
    . These two
    grounds for an employer’s liability correspond to different sections of the Restatement
    (Second) of Torts (1965), Section 343 and Section 414, respectively. See Hinger v. Parker
    & Parsley Petroleum Co., 1995-NMCA-069, ¶ 22, 
    120 N.M. 430
    , 
    902 P.2d 1033
    . In this
    case, we are concerned with the second basis of liability, which relates to whether Cimarex
    had control over Patterson’s work so as to give rise to a duty owed by Cimarex to Plaintiff.
    {9}    Section 414 of the Restatement addresses the notion of retained control and provides:
    One who entrusts work to an independent contractor, but who retains the
    control of any part of the work, is subject to liability for physical harm to
    others for whose safety the employer owes a duty to exercise reasonable care,
    which is caused by his failure to exercise his control with reasonable care.
    The Restatement’s comments clarify that the extent of the employer’s control informs both
    (1) the question of whether the employer owes a duty to an independent contractor’s
    employee and (2) the question of whether the employer can be deemed liable to that
    employee, i.e., whether the employer breached its duty and caused the employee’s injuries.
    See Herrera, 2003-NMSC-018, ¶ 6 (explaining that “a negligence claim requires the
    existence of a duty from a defendant to a plaintiff, breach of that duty, which is typically
    based upon a standard of reasonable care, and the breach being a proximate cause and cause
    in fact of the plaintiff's damages”). Comment a to Section 414 explains that, even where the
    employer “may retain only the power to direct the order in which the work shall be done, or
    to forbid its being done in a manner likely to be dangerous to himself or others,” this
    “supervisory control” may subject the employer to liability “unless [the employer] exercises
    [the employer’s] supervisory control with reasonable care so as to prevent the work which
    [the employer] has ordered to be done from causing injury to others.” Restatement (Second)
    of Torts § 414 cmt. a. Thus, (1) the employer owes a duty to an employee of an independent
    contractor if the employer has some kind of supervisory control over the independent
    contractor and, if the employer owes this duty, (2) it may be liable if it exercises its control
    in a negligent manner that causes injury to the independent contractor’s employee.
    {10} It is clear that both inquiries are fact driven. With respect to the employer’s duty, the
    parties must introduce evidence of the extent of the employer’s control over the independent
    contractor’s operations. Once the duty is established, the parties must introduce evidence
    on the question of liability, which involves the way in which the contractor exercised its
    control.
    4
    {11} Our case law in New Mexico has primarily addressed the duty aspect of Section 414.
    For example, in Tipton, our Supreme Court noted that the extent of an employer’s duty to
    the employees of an independent contractor “has been held to vary according to the . . .
    degree of control the [employer] exercises over . . . the details of the work.”
    1985-NMSC-108, ¶ 20. Similarly, in Valdez, decided by our Supreme Court, and in two
    cases decided in 1995 by this Court, the focus was on the extent of the control retained or
    exercised by the employer. See 1987-NMSC-015, ¶ 20 (stating that “the critical issue is the
    degree of control alleged to have been maintained by [the employer]”); Pollard,
    1995-NMCA-038, ¶ 6 (stating that “the extent of the duty owed by [the employer] is to some
    degree a function of the kind of control either retained or exercised by [the employer] over
    the work performed by [the independent contractor]”); Hinger, 1995-NMCA-069, ¶ 22
    (stating that “[t]he extent and nature of the duty is often a function of the degree of control
    or power retained by the employer over the job”).
    {12} In each of these cases, the Court determined, directly or indirectly, that the extent of
    the employer’s control was a fact question. In Valdez, the Court reversed summary judgment
    in favor of the employer because there were issues of fact as to the extent of control
    exercised by the employer, 1987-NMSC-015, ¶ 27, as did the Court in Pollard,
    1995-NMCA-038, ¶¶ 8, 10. And in Hinger, the Court concluded that the jury had been
    properly instructed on the theory of the employer’s retained control, thereby implying that
    the matter was a fact question for the jury. 1995-NMCA-069, ¶¶ 22, 26, 31, 33; see also
    Pollard, 1995-NMCA-038, ¶ 6 (explaining that an analysis of “the kind of control either
    retained or exercised by [the employer] is primarily a fact-based question which does not
    lend itself easily to resolution by summary judgment”).
    {13} The question not expressly answered by our case law is how much control the
    employer must have before it has a duty to an independent contractor’s employee. Instead,
    our cases have simply left the matter up to the fact finder if the evidence created issues about
    how much control the employer had. For example, in Valdez, the employer “agreed to be
    ultimately responsible for any infractions by [the independent contractor] of labor standards
    provisions,” and it issued detailed instructions to the independent contractor about how to
    do certain aspects of its work. 1987-NMSC-015, ¶ 24. The Court held that this evidence
    created issues of fact precluding summary judgment. 
    Id. ¶ 26.
    In Pollard, the contract
    between the employer and independent contractor “arguably reserve[d] to [the employer] the
    right to direct [the independent contractor] to take such additional measures for the
    protection of [the independent contractor’s] employees, as [the employer] determine[d] to
    be reasonably necessary.” 1995-NMCA-038, ¶ 7 (internal quotation marks omitted). The
    employer also required the independent contractor to comply with the employer’s safety
    manual and retained the right to approve any safety changes made by the independent
    contractor. 
    Id. {14} While
    this case law does not provide much definitive guidance about how much
    control is necessary to give rise to a duty, the Restatement gives us some assistance.
    Comment c to Section 414 states that “[i]t is not enough that [the employer] has merely a
    5
    general right to order the work stopped or resumed, to inspect its progress or to receive
    reports, to make suggestions or recommendations which need not necessarily be followed,
    or to prescribe alterations and deviations.” Restatement (Second) of Torts § 414 cmt. c.
    Rather, “[t]here must be such a retention of a right of supervision that the contractor is not
    entirely free to do the work in his own way.” 
    Id. {15} With
    these principles in mind, we turn to the circumstances and arguments in the
    present case.
    Issues of Fact Preclude Summary Judgment
    {16} We understand Cimarex’s primary argument to be that, as a matter of law, it owed
    no duty to Plaintiff because it was not required to recognize that Plaintiff was exhibiting
    signs of fatigue or that he was possibly incapacitated by fatigue, especially given the facts
    that Cimarex had no control over or awareness of Plaintiff’s work schedule and Cimarex did
    not create the work environment that caused Plaintiff’s fatigue. Cimarex’s argument is too
    narrow. The question related to duty is not whether Cimarex had control over Plaintiff’s
    fatigue or his schedule. The question is whether Cimarex had any right of supervision over
    Patterson’s operations such that Patterson was not free do its work in its own way. See
    Restatement (Second) of Torts § 414 cmt. c.
    {17} Plaintiff introduced evidence supporting the view that Cimarex indeed had such
    supervisory control. Plaintiff submitted the contract between Patterson and Cimarex, which
    stated that Patterson would “furnish equipment, labor, and perform services . . . under the
    direction, supervision, and control of [Cimarex].” It further provided, “Except for such
    obligations and liabilities specifically assumed by [Patterson], [Cimarex] shall be solely
    responsible and assumes liability for all consequences of operations by both parties . . . ,
    including results and all other risks or liabilities incurred in or incident to such operations.”
    The contract also stated that “[Cimarex] agrees to adhere to [Patterson]’s [s]afety [p]rogram,
    [p]rocedures and [p]olicies[,]” and Patterson’s safety manual included a provision that every
    employee had the authority to prevent any co-worker from performing unsafe acts. In
    addition, Smith, Cimarex’s drilling consultant, testified that Plaintiff answered to him while
    they were on the rig. While Cimarex points to evidence suggesting that Patterson retained
    responsibility over the blowout preventer, which was what Plaintiff was en route to service
    at the time of the accident, this evidence simply creates an issue of fact about whether
    Cimarex had supervisory control over Patterson’s operations. In any event, whether
    Cimarex did or did not have this control is not a determination that could be made by the
    district court as a matter of law, given the dispute in the evidence.
    {18} Cimarex’s arguments about whether it should have recognized that Plaintiff was
    fatigued or that his fatigue incapacitated him are not relevant to the question of duty but
    instead relate to whether Cimarex reasonably exercised the control it had, if any. For
    example, if on remand the court determines—following the fact finder’s conclusions
    regarding Cimarex’s retention of control—that Cimarex owed a duty to Plaintiff, the
    6
    question becomes whether Cimarex knew or should have known that Plaintiff was
    incapacitated by fatigue and, if so, whether it should have done something affirmative to
    address the problem. The extent of control Cimarex had informs the extent to which it
    should have known anything about Plaintiff’s condition or done anything about it. These
    are questions related to breach of duty and causation.
    {19} We recognize that this Court in Fresquez v. Southwestern Industrial Contractors and
    Riggers, Inc. stated that “[t]he right in a[n employer] to stop the [independent contractor]
    from proceeding with the work if dangerous practices are observed, does not carry with it
    liability to the employees of the very same [independent contractor] causing the dangerous
    condition.” 1976-NMCA-090, ¶ 39, 
    89 N.M. 525
    , 
    554 P.2d 986
    . However, this statement
    relates to the question of causation, not the concept of duty. If the evidence showed that it
    was Patterson alone whose conduct resulted in Plaintiff’s incapacitating fatigue, then a jury
    could assess one hundred percent fault against Patterson.
    {20} To the extent Cimarex is arguing that, as a matter of law, its failure to recognize the
    impact of Plaintiff’s fatigue did not constitute a breach of duty or did not proximately cause
    Plaintiff’s injuries, we are not persuaded. Plaintiff’s evidence created issues of fact on
    breach and causation. Plaintiff testified at his deposition that Smith knew that he had not had
    any sleep in twenty-four hours at the time the accident happened. Miguel Aguirre,
    Patterson’s lead tongs floorman, testified that he had worked with Plaintiff in the days
    preceding the accident and that Plaintiff looked tired and told him he had been up working
    for two days. Other workers on the rig reported that Plaintiff had looked tired or said he was
    tired prior to the accident. We “view the facts in a light most favorable to the party opposing
    summary judgment and draw all reasonable inferences in support of a trial on the merits.”
    Romero v. Philip Morris Inc., 2010-NMSC-035, ¶ 7, 
    148 N.M. 713
    , 
    242 P.3d 280
    (internal
    quotation marks and citation omitted). Under this standard, Plaintiff has presented evidence
    giving rise to a reasonable inference that workers on the rig, including Cimarex’s consultant,
    knew or should have known that Plaintiff was fatigued prior to the accident. It is for the jury
    to decide whether this was in fact the case and, if it was, whether Cimarex’s knowledge of
    Plaintiff’s fatigue had anything to do with his accident and injuries.
    {21} The cases relied on by Cimarex are not helpful to its argument. See Nabors Drilling,
    U.S.A., Inc. v. Escoto, 
    288 S.W.3d 401
    (Tex. 2009); Nat’l Convenience Stores Inc. v.
    Matherne, 
    987 S.W.2d 145
    (Tex. Ct. App. 1999). The courts in both cases analyzed the facts
    before them according to the duty announced in Otis Engineering Corp. v. Clark, which
    holds that only an employer who takes affirmative action over an incapacitated employee
    because of the employee’s incapacitation must exercise reasonable care to prevent the
    employee from causing an unreasonable risk of harm to others. 
    668 S.W.2d 307
    , 311 (Tex.
    1983); see 
    Nabors, 288 S.W.3d at 403-404
    ; Nat’l Convenience Stores 
    Inc., 987 S.W.2d at 150
    . Unlike the showing required to invoke the duty found in those cases—evidence of
    actual knowledge of employee impairment and affirmative exercise of employer control over
    such impairment—our interpretation of the duty under the circumstances in the present case
    requires no such showing. Instead, if Cimarex had supervisory control over Patterson, which
    7
    is a fact question, then Cimarex had a duty to Patterson’s employees to exercise that control
    with reasonable care.
    CONCLUSION
    {22} For the foregoing reasons, we reverse summary judgment and remand for
    proceedings consistent with this opinion.
    {23}   IT IS SO ORDERED.
    ______________________________________
    CYNTHIA A. FRY, Judge
    WE CONCUR:
    ____________________________________
    JAMES J. WECHSLER, Judge
    ____________________________________
    M. MONICA ZAMORA, Judge
    8