Reno Technology Center 1, LLC v. New Cingular Wireless PCS, LLC ( 2019 )


Menu:
  • 1 2 3 4 5 6 UNITED STATES DISTRICT COURT 7 DISTRICT OF NEVADA 8 * * * 9 RENO TECHNOLOGY Case No. 3:17-cv-00410-LRH-WGC CENTER 1, LLC., 10 ORDER Plaintiff, 11 v. 12 NEW CINGULAR WIRELESS 13 PCS LLC, 14 Defendant. 15 16 Plaintiff Reno Technology Center 1, LLC (“RTC”) has filed a motion for reconsideration 17 of the Court’s summary judgment order (ECF No. 37). (ECF No. 39). In the Court’s previous 18 order, the Court denied RTC’s motion for summary judgment and denied the defendant New 19 Cingular Wireless PCS LLC’s (“AT&T”) motion for summary judgment in part and granted it in 20 part. RTC now requests partial reconsideration of the Court’s denial of its motion for summary 21 judgment. RTC argues that the Court “mistakenly held” that the site lease agreement, whereby 22 RTC agreed to lease space on the rooftop of a building it owned to AT&T, no longer existed at the 23 time of this litigation. (ECF No. 39 at 4). It also argues that the Court erred when it found that 24 AT&T’s failure to install a separate power meter and “pay all costs associated therewith” was not 25 a “contractual debt.” (Id.) 26 Although the Federal Rules of Civil Procedure do not explicitly allow for an aggrieved 27 party to seek reconsideration of a court’s judgment, federal courts have typically construed such 1 court is presented with newly discovered evidence, an intervening change of controlling law, the 2 original decision was manifestly unjust, or where the prior order was clearly erroneous. United 3 States v. Cuddy, 147 F.3d 1111, 1114 (9th Cir. 1998); School Dist. No. 1J, Multnomah County v. 4 AcandS, Inc., 5 F.3d 1255, 1263 (9th Cir. 1993). Motions for reconsideration are “extraordinary 5 remed[ies],” and they should only be used “sparingly in the interests of finality and conservation 6 of judicial resources.” Kona Enters., Inc. v. Estate of Bishop, 229 F.3d 887, 890 (9th Cir. 2000). 7 Whether or not to grant reconsideration is within the sound discretion of the district court. Navajo 8 Nation v. Confederated Tribes and Bands of the Yakama Indian Nation, 331 F.3d 1041, 1046 (9th 9 Cir. 2003). 10 RTC is mistaken when it states that the Court believed that the site lease agreement was 11 terminated at some point prior to this litigation. In the factual background section of the Court’s 12 summary judgment order, the Court stated that since AT&T installed a separate power meter to 13 power its telecommunications equipment, it has been paying the utility company directly for its 14 power usage. (ECF No. 37 at 4). Based on the record before the Court, it was readily apparent that 15 the site lease agreement was and is still in effect, and there is no language in the Court’s order to 16 the contrary. 17 RTC also misunderstands the nature of a “contractual debt” and the holding from the 18 Nevada Supreme Court case Riff v. Kowal, 352 P.2d 819 (Nev. 1960). In the Court’s summary 19 judgment order, the Court explained that NRS §11.200, which tolls the statute of limitations for 20 enforcing a debt when payment is made on an existing contract, is inapplicable in this case for two 21 separate reasons. First, §11.200 only applies when a partial payment is made on a contractual 22 “debt.” Pursuant to the terms of the site lease agreement, AT&T agreed to make monthly rent 23 payments to RTC in exchange for space on its rooftop to operate telecommunications equipment. 24 The relationship between RTC and AT&T is clearly not debtor-creditor but rather that of a 25 landlord-lessee. RTC argues that §7(b) of the site lease agreement requires AT&T to “pay all costs 26 associated” with the installation of the power meter, and therefore, AT&T was indebted to RTC 27 once it failed to install a separate power meter and RTC paid for its power usage. (ECF No. 39 at 1 indebted to RTC in any way. The only way RTC is entitled to these “costs” is by way of monetary 2 damages if it can demonstrate to the trier of fact that the statute of limitations on its breach of 3 contract claim has not lapsed. 4 This leads into the second reason why §11.200 does not apply in this case. As the Nevada 5 Supreme Court clarified in Riff, a partial payment on a debt only tolls the statute of limitations if 6 that debt comes from an “existing contract.” Riff v. Kowal, 352 P.2d 819, 820 (Nev. 1960). 7 “Existing contract” means “an existing [enforceable] contract and not a contract the enforcement 8 of which has already been [barred] by the statute of limitations.” Id. Thus, if the trier of fact finds 9 that the statute of limitations bars enforcement of a breach of the site lease agreement, the fact that 10 AT&T later paid RTC for electricity usage does not make the breach of contract claim enforceable. 11 For example, if a breach of contract claim premised on a failure to make debt repayments is 12 discovered in 2010, the creditor has six years to file a lawsuit, with the statute of limitations 13 running in 2016. But if the debtor makes a partial payment in 2013, then the statute of limitations 14 is extended from the time of the partial payment, and the creditor would have until 2019 to file 15 suit. But if the debtor makes a partial payment in 2017, the creditor cannot use that payment as a 16 way to toll the statute of limitations because any suit filed past 2016 would be time barred. 17 This is precisely the situation here. There is an issue of material fact as to whether RTC 18 discovered AT&T’s breach in 2001 or 2015. (ECF No. 37 at 3). If the trier of fact determines that 19 RTC discovered the breach in 2001, then the fact that AT&T paid RTC for its utilities usage in 20 2017 (which, as discussed above, is not a “debt”) does not take RTC’s claim for breach of contract 21 outside the statute of limitations. 22 RTC has not provided any evidence of new or controlling law, new factual evidence that 23 was not available at the time of the Court’s original decision, and it has not demonstrated that the 24 Court’s order was manifestly unjust. It merely attempts to relitigate the same arguments presented 25 in its motion for summary judgment, arguments that the Court previously considered and rejected. 26 There is no basis for which the Court to reconsider its previous order, and the Court will 27 accordingly deny RTC’s motion for reconsideration. 1 IT IS THEREFORE ORDERED that RTC’s motion for reconsideration (ECF No. 39) is 2 || DENIED. 3 DATED this 16th day of August, 2019. 4 5 LAR . HIC 6 UNITED STATES DISTRICT JUDGE 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Document Info

Docket Number: 3:17-cv-00410

Filed Date: 8/16/2019

Precedential Status: Precedential

Modified Date: 6/25/2024