Brainard v. . Jones ( 1858 )


Menu:
  • The rule has often been laid down in general term, that sureties are not liable beyond the penalty of the bond in which their obligation is contained. But on a careful examination of the reason and justice of the rule, it will be found inapplicable to a question of interest accruing after they are in default, for not paying according to the condition of the bond. There is a plain distinction which has sometimes been lost sight of, and consequently some confusion and contradiction will be found in the cases on this subject. Whether a surety, at the time of his default, can be held beyond the penalty of his bond, is a question on the interpretation and effect of his contract. Whether interest can be computed after his default, where the effect will be thus to increase his liability, is a question of compensation for the breach of his contract.

    In this case the defendants' bond was conditioned that Ramsdell should pay whatever sum might be recovered against him in a certain action of replevin. If the sum recovered against Ramsdell had been greater than the penalty of the bond, such penalty would, nevertheless, have been the measure of their liability at that time. But on the recovery of the judgment, their obligation was mature. Its utmost extent then, was the penalty under which they had bound themselves for the payment by Ramsdell. But, after that, they were in default, and during the continuance of that default, interest is due from them as in any other case where money is not paid when the creditor becomes entitled to it. It may be a reasonable doctrine, that a surety who has bound himself under a fixed penalty for the payment of money or some other act to be done by a third person, has marked the utmost limit of his own liability. But when the time has come for him to discharge that liability, and he neglects or refuses to do so, it is equally reasonable, and altogether just, that he should compensate the creditor for the delay which he has interposed. The legal measure of this compensation is, interest on the sum which *Page 37 he ought to have paid from the time when the payment was due from him.

    In Clark v. Bush (3 Cow., 151), one McCracken, with Barney as his surety, had given to Bush a bond of indemnity against certain debts and demands. It appeared that the surety had paid upon the bond a sum equal to the penalty, and the question was, whether he was liable beyond the penalty, it appearing that the debts indemnified against amounted to a greater sum. It was held that his liability was discharged by the payments made. This was in accordance with the general rule which has been so frequently laid down. But there was no question of computing interest against the surety as a compensation for his own default. If the debts indemnified against had just equaled the penalty of the bond, and the surety had for a long time refused or neglected to indemnify as he had agreed, a very different question would have been presented. In that case he performed his contract in full, and he was held discharged. In this case there has been a non-performance for a long course of time, persisted in by defending a suit brought to compel performance, and the law is not so unreasonable as to withhold compensation for this delay.

    Returning to the distinction already mentioned, interest may be due, first, by contract express or implied from a course of dealing and the relations of parties; second, the law may exact it from a party who is in the wrong, by withholding money or value due from him to another. In the latter case, it is allowed as the just measure of damage for the violation of duty or contract; and sureties can claim no exemption from the rule. So far as interest is provided for in the contract, a limit to their liability may be found in the penalty which is a part of the same contract. But when the sum claimed becomes a debt actually due from them, and they continue in default, the question, properly considered, is one of damages for the delay. As the law in imposing these damages finds its warrant, not in the terms *Page 38 of the contract, but in the rules of reason and justice, so it must follow that the same rules furnish the only restraint upon its power in such cases. The question, in short, is, not what is the measure of a surety's liability under a penal bond, but what does the law exact of him for an unjust delay in payment after his liability is ascertained and the debt is actually due from him.

    We have not overlooked other cases in this state, one or two of which may seem opposed to the conclusion at which we arrive. They were, however, but very slightly considered, and were determined without any examination of the principles which the subject involves.

    The judgment of the Supreme Court must be reversed, and a reassessment of damages ordered.

    SELDEN, HARRIS and STRONG, Js., expressed no opinion; all the other judges concurring,

    Judgment reversed, and reassessment ordered.

Document Info

Judges: Comstock

Filed Date: 9/5/1858

Precedential Status: Precedential

Modified Date: 10/19/2024