ACCADIA SITE CONTRACTING, INC. v. CARUANA, ANTHONY F. ( 2012 )


Menu:
  •                SUPREME COURT OF THE STATE OF NEW YORK
    Appellate Division, Fourth Judicial Department
    791.1
    CA 12-00843
    PRESENT: SCUDDER, P.J., SMITH, FAHEY, LINDLEY, AND MARTOCHE, JJ.
    IN THE MATTER OF ACCADIA SITE CONTRACTING, INC.,
    PETITIONER-APPELLANT,
    V                                     MEMORANDUM AND ORDER
    ANTHONY F. CARUANA, SUPERVISOR, TOWN OF TONAWANDA,
    MEMBERS OF TOWN OF TONAWANDA BOARD, IN THEIR
    OFFICIAL CAPACITIES, YARUSSI CONSTRUCTION, INC.,
    AND CONCRETE APPLIED TECHNOLOGIES, INC.,
    RESPONDENTS-RESPONDENTS.
    LIPSITZ GREEN SCIME CAMBRIA LLP, BUFFALO (JEFFREY F. REINA OF
    COUNSEL), FOR PETITIONER-APPELLANT.
    DUKE, HOLZMAN, PHOTIADIS & GRESENS LLP, BUFFALO (PATRICIA GILLEN OF
    COUNSEL), FOR RESPONDENT-RESPONDENT CONCRETE APPLIED TECHNOLOGIES,
    INC.
    COLUCCI & GALLAHER, P.C., BUFFALO (PAUL G. JOYCE OF COUNSEL), FOR
    RESPONDENTS-RESPONDENTS ANTHONY F. CARUANA, SUPERVISOR, TOWN OF
    TONAWANDA, AND MEMBERS OF TOWN OF TONAWANDA BOARD, IN THEIR OFFICIAL
    CAPACITIES.
    Appeal from a judgment (denominated order) of the Supreme Court,
    Erie County (John F. O’Donnell, J.), entered April 23, 2012 in a
    proceeding pursuant to CPLR article 78. The judgment dismissed the
    proceeding and vacated a temporary restraining order.
    It is hereby ORDERED that the judgment so appealed from is
    unanimously affirmed without costs.
    Memorandum: Petitioner commenced this CPLR article 78 proceeding
    seeking, inter alia, to restrain the Town of Tonawanda respondents
    (collectively, Town) from proceeding on a contract with respondent
    Concrete Applied Technologies, Inc. (CATCO), the second lowest bidder
    for a public works project aimed at repairing and improving the Town’s
    sanitary sewer system (project), and requiring the Town to re-bid the
    contract for the project. After granting petitioner a temporary
    restraining order (TRO) pending a hearing and later holding such a
    hearing, Supreme Court dismissed the proceeding and vacated the TRO.
    We granted a stay pending this expedited appeal by petitioner, and now
    affirm.
    Pursuant to the terms of the “bid book” provided to prospective
    bidders, they were required to agree to all of the contractual
    -2-                           791.1
    CA 12-00843
    provisions, including a provision that requires the winning bidder to
    indemnify the Town for any claims “arising out of or incidental to”
    work on the project. Additionally, the bid book informed prospective
    bidders that the Town would not accept “[c]onditional bids.”
    Upon reviewing the specifications for the project, petitioner, a
    prospective bidder, became concerned about the property damage that
    could result from performing the “sheet piling” component of the
    project. In a letter dated January 11, 2012, a representative of
    petitioner informed a representative of the entity hired by the Town
    to oversee the project that, “should [petitioner] be the low bidder on
    the project, [petitioner] will not be held responsible for any damage”
    stemming from the sheet piling work. The letter also stated that
    petitioner “wishe[d] to go on record prior to the bid regarding this
    situation and will be held harmless should any damage claims [arise]
    from the piles being driven through the clay strata.”
    Petitioner thereafter submitted a compliant bid proposal in which
    it affirmed its understanding of the terms of the contract governing
    the project and neither referenced nor attached its pre-bid letter.
    When the Town publicly opened the seven bids it received for the
    project, petitioner’s bid was the lowest and CATCO’s bid was the
    second lowest. By a subsequent resolution, the Town determined that
    petitioner’s bid was made conditional by its pre-bid letter and was
    therefore nonresponsive. The Town thus awarded the project to CATCO,
    the second lowest bidder.
    A municipality that solicits bids for a public works project
    generally must award the contract for that project to the “lowest
    responsible bidder” (Town Law § 122; see General Municipal Law § 103
    [1]; Matter of AAA Carting & Rubbish Removal, Inc. v Town of
    Southeast, 17 NY3d 136, 142). If a bid fails to comply with bid
    specifications, the municipality may waive such noncompliance “if the
    defect is a mere irregularity and it is in the best interests of the
    municipality to do so” (Le Cesse Bros. Contr. v Town Bd. of Town of
    Williamson, 62 AD2d 28, 32, affd 46 NY2d 960). If, however, “the
    variance between the bid and the specification is material or
    substantial, . . . the defect may not be waived and the municipality
    must reject the bid so that all bidders may be treated alike and so
    that the possibility of fraud, corruption or favoritism is avoided”
    (id.). The municipality “has the right to determine whether a
    variance from bid specifications is material” (Matter of AT&T
    Communications v County of Nassau, 214 AD2d 666, 667), and such a
    determination “ ‘must be upheld by the courts if supported by any
    rational basis’ ” (Diamond D Constr. Corp. v County of Erie, 209 AD2d
    922, 923). A variance from bid specifications is material, and thus
    cannot be waived by a municipality, if the variance “affect[ed] the
    competitive character of the bidding” and gave the bidder “a
    substantial advantage or benefit not enjoyed by the other bidders” (Le
    Cesse Bros. Contr., 62 AD2d at 32; see Diamond D Constr. Corp., 209
    AD2d at 922-923). In a CPLR article 78 proceeding challenging a
    municipality’s handling of bids for a public works project, the
    municipality’s “discretionary decision [to reject any bids] ought not
    to be disturbed by the courts unless [that decision is] irrational,
    -3-                           791.1
    CA 12-00843
    dishonest or otherwise unlawful” (Matter of Conduit & Found. Corp. v
    Metropolitan Transp. Auth., 66 NY2d 144, 149).
    Here, we conclude that the determination of the Town that
    petitioner’s bid was conditional and nonresponsive, and thus
    constituted a material variance from the project’s bid specifications,
    was rational, honest, and lawful (see generally id.). The unequivocal
    language of petitioner’s pre-bid letter was such that it was
    reasonable for the Town to conclude that the term stated therein
    concerning the refusal to be held liable for any damage arising from
    the sheet piling work was intended to impose a condition on
    petitioner’s subsequent bid proposal regardless of whether the pre-bid
    letter was attached to or otherwise incorporated into that proposal.
    Because petitioner indicated prior to submitting its bid that it did
    not intend to comply with the indemnification clause in the contract
    governing the project with respect to an apparently risky component of
    the project to which other bidders would be subject, we conclude that
    the Town had a “ ‘rational basis’ ” for determining that petitioner’s
    bid materially deviated from the bid specifications (Diamond D Constr.
    Corp., 209 AD2d at 923; see generally Le Cesse Bros. Contr., 62 AD2d
    at 31-32). Thus, it was reasonable for the Town to determine that
    petitioner had “a substantial advantage or benefit not enjoyed by the
    other bidders” (Le Cesse Bros. Contr., 62 AD2d at 32), because the
    Town reasonably could have believed that, if other bidders had known
    that they could shift liability to the Town for claims arising out of
    the sheet piling work, their bids would have been lower. Inasmuch as
    it was reasonable for the Town to deem petitioner’s bid variance
    “material,” it necessarily follows that it was reasonable for the Town
    to reject petitioner’s bid and to accept the next lowest bid (id.).
    Petitioner’s contention that the parol evidence rule barred the
    Town from considering its pre-bid letter is without merit because
    petitioner’s bid was a mere offer to contract (see S.S.I. Invs. v
    Korea Tungsten Min. Co., 80 AD2d 155, 157-159, affd 55 NY2d 934; Le
    Cesse Bros. Contr., 62 AD2d at 33), and because there was no written
    contract between the Town and petitioner (see generally W.W.W. Assoc.
    v Giancontieri, 77 NY2d 157, 161-162). Moreover, contrary to
    petitioner’s contention, it was not required to send its pre-bid
    letter pursuant to the terms of the “Information to Bidders” portion
    of the bid book. The section to which petitioner refers states that
    prospective bidders should notify the Town of “discrepancies[] in, or
    omissions from the Drawings or Contract Documents” and should inquire
    if they are “in doubt as to their meaning,” but petitioner’s letter
    did neither. Finally, although petitioner is correct that CATCO and
    several other bidders, like petitioner, estimated a cost of $0.01 per
    square foot for the sheet piling work, which may have been an
    indication that those bidders did not intend to carry out that part of
    the project, the fact remains that only petitioner expressly stated
    its intention to demand that the contract be altered to hold it
    harmless for that activity.
    Entered:   June 15, 2012                        Frances E. Cafarell
    Clerk of the Court
    

Document Info

Docket Number: CA 12-00843

Filed Date: 6/15/2012

Precedential Status: Precedential

Modified Date: 10/8/2016