LHR, INC. v. T-MOBILE USA, INC. , 977 N.Y.S.2d 816 ( 2013 )


Menu:
  •         SUPREME COURT OF THE STATE OF NEW YORK
    Appellate Division, Fourth Judicial Department
    1085
    CA 13-00751
    PRESENT: SMITH, J.P., PERADOTTO, CARNI, VALENTINO, AND WHALEN, JJ.
    LHR, INC., PLAINTIFF-APPELLANT-RESPONDENT,
    V                             MEMORANDUM AND ORDER
    T-MOBILE USA, INC. AND SUNCOM WIRELESS
    OPERATING COMPANY, LLC,
    DEFENDANTS-RESPONDENTS-APPELLANTS.
    SCHRÖDER, JOSEPH & ASSOCIATES, LLP, BUFFALO (LINDA H. JOSEPH OF
    COUNSEL), FOR PLAINTIFF-APPELLANT-RESPONDENT.
    JAECKLE FLEISCHMANN & MUGEL, LLP, BUFFALO (B. KEVIN BURKE, JR., OF
    COUNSEL), AND KLEINBARD BELL & BRECKER LLP, PHILADELPHIA,
    PENNSYLVANIA, FOR DEFENDANTS-RESPONDENTS-APPELLANTS.
    Appeal and cross appeal from an order of the Supreme Court, Erie
    County (John A. Michalek, J.), entered March 25, 2013. The order,
    among other things, granted those parts of the motion of defendants
    for partial summary judgment seeking to limit plaintiff’s damages and
    to dismiss the cause of action for intentional interference with
    contract, but denied that part of the motion seeking to dismiss the
    cause of action for conversion.
    It is hereby ORDERED that the order so appealed from is
    unanimously modified on the law by vacating the second, fourth, and
    fifth ordering paragraphs, denying that part of the motion seeking to
    limit plaintiff’s damages to $1.2 million, and granting that part of
    the motion seeking to dismiss the 29th cause of action, and as
    modified the order is affirmed without costs.
    Memorandum: Plaintiff, a debt collection agency, commenced this
    action seeking damages resulting from defendants’ alleged breach of
    contract and negligence with respect to the sale by defendant SunCom
    Wireless Operating Company, LLC (SunCom) of delinquent customer
    accounts to plaintiff. From November 2005 until March 2008, plaintiff
    and SunCom executed six “Purchase and Sale Agreements” (purchase
    agreements). Four of the purchase agreements involved the transfer of
    a single debt portfolio; the other two agreements, which the parties
    refer to as “forward flow agreements,” provided for the transfer of
    debt portfolios on a monthly basis. The purchase agreements are
    largely identical, although the forward flow agreements contain
    modifications to reflect the ongoing nature of the arrangement. As
    particularly relevant here, article 5 of each of the purchase
    agreements includes certain indemnification obligations on the part of
    -2-                          1085
    CA 13-00751
    plaintiff and SunCom, and provides that the “Seller,” i.e., SunCom,
    “will not be required to indemnify, and will not otherwise be liable
    to, [plaintiff] for Seller’s indemnification obligations under this
    Article 5 for any amounts in excess of a maximum aggregate amount of
    Two Hundred Thousand Dollars ($200,000).”
    In or about February 2008, SunCom became a wholly-owned
    subsidiary of defendant T-Mobile USA, Inc. (T-Mobile). According to
    plaintiff, SunCom and/or T-Mobile, as successor in interest to the
    purchase agreements, breached those agreements by failing to provide
    plaintiff with documents necessary to verify the amount of the debt
    transferred under the agreements. Plaintiff also initially alleged
    that defendants acted negligently in failing to preserve the necessary
    documents. Supreme Court granted in part defendants’ motion to
    dismiss the complaint by dismissing the negligence cause of action
    against SunCom, granted in part plaintiff’s cross motion for leave to
    amend the complaint by permitting plaintiff to add a cause of action
    against T-Mobile for intentional interference with contract, and
    denied that part of plaintiff’s cross motion seeking to add a cause of
    action against T-Mobile for conversion. On a prior appeal, this Court
    modified that order by dismissing the negligence cause of action
    against T-Mobile, and granting plaintiff leave to amend the complaint
    to include a cause of action for conversion against T-Mobile (LHR,
    Inc. v T-Mobile USA, Inc., 88 AD3d 1301). Defendants thereafter moved
    for partial summary judgment seeking to limit plaintiff’s damages to
    $1.2 million, i.e., $200,000 on each of the six purchase agreements,
    and to dismiss plaintiff’s causes of action against T-Mobile for
    conversion and intentional interference with contract. The court
    granted those parts of defendants’ motion seeking to limit plaintiff’s
    damages and to dismiss the cause of action for intentional
    interference with contract, but denied that part of the motion seeking
    to dismiss the cause of action for conversion. Plaintiff appeals and
    defendants cross-appeal.
    Contrary to plaintiff’s contention on its appeal, we conclude
    that the court properly determined that the clear and unambiguous
    language of the indemnification provisions of the purchase agreements
    apply to this action. The purchase agreements provide that they are
    to be “governed by, and construed and enforced in accordance with[,]
    the laws of the Commonwealth of Pennsylvania,” and all parties agree
    that Pennsylvania law applies here. “In undertaking the
    interpretation of a contract under Pennsylvania law, the court must
    begin with the language of the contract itself” (United States Steel
    Corp. v Lumbermens Mut. Cas. Co., 
    2005 WL 2106580
    , *7 [US Dist Ct, WD
    Pa, Aug. 31, 2005, No. Civ. A. 02-2108]). “The ultimate goal of
    interpreting a contract is to ascertain and give effect to the intent
    of the parties as reasonably manifested by the language of their
    written agreement” (County of Delaware v J.P. Mascaro & Sons, Inc.,
    830 A2d 587, 591, affd 582 Pa 590, 873 A2d 1285). Where contractual
    language is “clear and unambiguous, the focus of interpretation is
    upon the terms of the agreement as manifestly expressed, rather than
    as, perhaps, silently intended” (Steuart v McChesney, 498 Pa 45, 49,
    444 A2d 659, 661; see Halpin v LaSalle Univ., 432 Pa Super 476, 481,
    -3-                          1085
    CA 13-00751
    639 A2d 37, 39, appeal denied 542 Pa 670, 668 A2d 1133). “A contract
    is not rendered ambiguous by the mere fact that the parties do not
    agree upon its proper construction” (J.P. Mascaro & Sons, Inc., 830
    A2d at 591; see Halpin, 432 Pa Super at 482, 639 A2d at 39; see also
    12th St. Gym, Inc. v General Star Indem. Co., 93 F3d 1158, 1165).
    Rather, “[a] contract is ambiguous if it is reasonably susceptible of
    different constructions and capable of being understood in more than
    one sense” (Trizechahn Gateway LLC v Titus, 601 Pa 637, 653, 976 A2d
    474, 483 [internal quotation marks omitted and emphasis added]; see
    Madison Constr. Co. v Harleysville Mut. Ins. Co., 557 Pa 595, 606, 735
    A2d 100, 106).
    Here, we agree with defendants that the indemnification
    provisions at issue herein are broadly worded and encompass first-
    party claims, i.e., claims between the contracting parties (see SBA
    Network Servs., Inc. v Telecom Procurement Servs., Inc., 250 Fed Appx
    487, 492 [3rd Cir 2007]; Waynesborough Country Club of Chester County
    v Diedrich Niles Bolton Architects, Inc., 
    2008 WL 4916029
    , *4-5 [ED
    Pa, Nov. 12, 2008, No. Civ. A. 07-155]; STS Holdings, Inc. v CDI
    Corp., 
    2004 WL 739869
    , *2-3 [US Dist Ct, ED Pa, Mar. 19, 2004, No.
    Civ. A. 99-3480]; Circuit City Stores, Inc. v Citgo Petroleum Corp.,
    
    1995 WL 393721
    , *5 [US Dist Ct, ED Pa, June 29, 1995, No. Civ. A. 92-
    7394]; see also Benchmark Group, Inc. v Penn Tank Lines, Inc., 612 F
    Supp 2d 562, 594 n16 [ED Pa 2009]). We note that nothing in article 5
    of the purchase agreements limits that article’s provisions to claims
    commenced by third parties (see STS Holdings, Inc., 
    2004 WL 739869
    , at
    *3; Circuit City Stores, Inc., 
    1995 WL 393721
    , at *5). To the
    contrary, section 5.5 of the purchase agreements, entitled “Procedure
    for Indemnification,” specifically contemplates first-party
    indemnification claims. Because the relevant provisions of the
    purchase agreements are unambiguous, we must enforce the language as
    written (see Waynesborough Country Club of Chester County, 
    2008 WL 4916029
    , at *3; see generally Madison Constr. Co., 557 Pa at 606, 735
    A2d at 106). Although plaintiff contends that such result is unfair
    and economically unreasonable, it is well established that “[a] court
    may not rewrite [a] contract for the purpose of accomplishing that
    which, in its opinion, may appear proper, or, on general principles of
    abstract justice . . . make for [the parties] a better contract than
    they chose, or saw fit, to make for themselves, or remake a contract,
    under the guise of construction, because it later appears that a
    different agreement should have been consummated in the first
    instance” (Steuart, 498 Pa at 51, 444 A2d at 662). Thus, the court
    properly concluded that plaintiff is bound by the indemnification
    provisions and, thus, the limitations on liability set forth in
    article 5 of the purchase agreements (see STS Holdings, Inc., 
    2004 WL 739869
    , at *3).
    We agree with plaintiff, however, that there is an issue of fact
    whether the $200,000 limitation on liability applies to each of the
    six purchase agreements executed by the parties or to each of the 28
    debt portfolio transfers collectively consummated thereunder. In
    order to affirm an order granting “ ‘summary judgment on an issue of
    contract interpretation, we must conclude that the contractual
    -4-                          1085
    CA 13-00751
    language is subject to only one reasonable interpretation’ ” (Sanford
    Inv. Co., Inc. v Ahlstrom Mach. Holdings, Inc., 198 F3d 415, 420-421).
    Here, we conclude that the language of the purchase agreements is
    ambiguous, i.e., it is “subject to more than one reasonable
    interpretation when applied to a particular set of facts” (Shepard v
    Temple Univ., 948 A2d 852, 857), and thus that the court erred in
    granting partial summary judgment to defendants limiting plaintiff’s
    damages to $200,000 per purchase agreement. We therefore modify the
    order accordingly.
    As noted above, the parties executed a total of six purchase
    agreements containing the indemnification clauses at issue—the four
    agreements transferring individual debt portfolios and the two forward
    flow agreements. The forward flow agreements provide that each of the
    monthly debt portfolio transfers are “[s]ubject to the terms of this
    Agreement,” and that the accounts are to be “transferred and assigned
    pursuant to a Bill of Sale in the form attached [t]hereto.” The
    language of the forward flow agreements and the form bill of sale
    support defendants’ interpretation, accepted by the court, that
    article 5’s limitation of liability applies to the six agreements, not
    to each separate debt portfolio transfer. According to the court,
    “[c]onstruing the writings themselves, the Bills of Sale and
    Assignments of Accounts were not intended to be separate agreements
    from the [purchase agreements] under which they were issued.” We
    note, however, that the parties did not use the form bill of sale
    attached to the forward flow agreements for their subsequent
    transactions, and that the bills of sale that they actually executed
    appear to function as stand-alone agreements. Specifically, the bills
    of sale accompanying each forward flow agreement do not refer back to
    the forward flow agreement, but rather refer to a separate “Purchase
    Agreement” dated as of the date of the transfer. The bills of sale
    were accompanied by an “Inventory of Receivables included under this
    Agreement”; a document listing the number and face value of the
    accounts transferred, the total purchase price, the total due at
    closing, and the closing date; and a cover page entitled “General
    Terms and Conditions,” which is followed by a copy of the forward flow
    agreement. The parties followed the same pattern with respect to the
    first five bills of sale executed under the second forward flow
    agreement. After plaintiff terminated the second forward flow
    agreement and amended the agreement to provide for a lower purchase
    price, the parties amended the bill of sale to refer back to the
    second forward flow agreement.
    We conclude that the imprecise language contained in the earlier
    bills of sale is ambiguous, i.e., “it is reasonably susceptible of
    different constructions and capable of being understood in more than
    one sense” (Madison Constr. Co., 557 Pa at 606, 735 A2d at 206
    [internal quotation marks omitted]). Specifically, it is unclear
    whether the terms and conditions of the forward flow agreements—most
    notably, the indemnification provisions—apply to all of the debt
    portfolio transfers under a given purchase agreement or to each debt
    portfolio transfer, individually. In our view, that ambiguity
    presents an issue “of fact for the trier of fact to resolve in light
    -5-                          1085
    CA 13-00751
    of the extrinsic evidence offered by the parties in support of their
    respective interpretations” (Sanford Inv. Co., Inc., 198 F3d at 421;
    see School Dist. of City of Monessen v Farnham & Pfile Co., Inc., 878
    A2d 142, 149; Juniata Val. Bank v Martin Oil Co., 736 A2d 650, 663;
    see generally Community Coll. of Beaver County v Community Coll. of
    Beaver County, Socy. of the Faculty [PSEA/NEA], 473 Pa 576, 592, 375
    A2d 1267, 1275). Here, plaintiff’s president and vice president
    averred that each debt portfolio purchased under the forward flow
    agreements constituted a separate and distinct contract. Plaintiff’s
    expert likewise opined that “[i]t is generally understood and accepted
    in the [debt collection] industry that a forward flow agreement sets
    forth the general terms and conditions for each successive monthly
    purchase, and that each sale of a portfolio is a separate and distinct
    contract or agreement.” Thus, in his opinion, there were “28 separate
    contracts entered into between the parties” and “any limitation on the
    indemnification obligation would apply to each separate portfolio
    purchase.” In light of plaintiff’s extrinsic evidence and the well-
    settled principle that “indemnity clauses are construed most strictly
    against the party who drafts them especially when that party is the
    indemnitee” (Ratti v Wheeling Pittsburgh Steel Corp., 758 A2d 695,
    702, appeal denied 567 Pa 715, 785 A2d 90), we conclude that the court
    erred in accepting defendants’ interpretation of the contract and in
    limiting plaintiff’s damages to $1.2 million upon defendants’ motion
    for partial summary judgment (see School Dist. of City of Monessen,
    878 A2d at 149; Juniata Val. Bank, 736 A2d at 663-664).
    Contrary to plaintiff’s final contention, we conclude that the
    court properly dismissed the cause of action for tortious interference
    with contract against T-Mobile. As SunCom’s successor in interest to
    the purchase agreements, T-Mobile cannot be liable for interfering
    with its own contract (see Ahead Realty LLC v India House, Inc., 92
    AD3d 424, 425; Tri-Delta Aggregates v Goodell, 188 AD2d 1051, 1051, lv
    denied 82 NY2d 653).
    With respect to the cross appeal, we agree with defendants that
    the court erred in denying that part of their motion for partial
    summary judgment dismissing the 29th cause of action, for conversion.
    “[I]t is well established that a cause of action to recover damages
    for conversion cannot be predicated on a mere breach of contract”
    (Schmidt v Lorenzo, 70 AD3d 1362, 1362 [internal quotation marks
    omitted]). Because plaintiff “failed to show . . . that [T-Mobile]
    engaged in tortious conduct separate and apart from [its alleged]
    failure to fulfill its contractual obligations,” the cause of action
    for conversion must be dismissed (LHR, Inc., 88 AD3d at 1304 [internal
    quotation marks omitted]; see Matzan v Eastman Kodak Co., 134 AD2d
    863, 863-864). We therefore further modify the order accordingly.
    Entered:   December 27, 2013                   Frances E. Cafarell
    Clerk of the Court
    

Document Info

Docket Number: CA 13-00751

Citation Numbers: 112 A.D.3d 1293, 977 N.Y.S.2d 816

Filed Date: 12/27/2013

Precedential Status: Precedential

Modified Date: 10/19/2024