In Re the Arbitration Between Capital Siding & Construction, LLC , 31 N.Y.S.3d 230 ( 2016 )


Menu:
  •                            State of New York
    Supreme Court, Appellate Division
    Third Judicial Department
    Decided and Entered: April 14, 2016                     520787
    ________________________________
    In the Matter of the
    Arbitration between CAPITAL
    SIDING & CONSTRUCTION, LLC,
    Doing Business as ABAR
    CONSTRUCTION,
    Appellant,               MEMORANDUM AND ORDER
    and
    ALLTEK ENERGY SYSTEM, INC.,
    Respondent.
    ________________________________
    Calendar Date:    February 19, 2016
    Before:    Peters, P.J., Garry, Rose, Lynch and Clark, JJ.
    __________
    Fox & Kowalewski, LLP, Clifton Park (Brendan R. Wolf of
    counsel), for appellant.
    McNamee, Lochner, Titus & Williams, PC, Albany (Kevin
    Laurilliard of counsel), for respondent.
    __________
    Rose, J.
    Appeal from an order of the Supreme Court (Platkin, J.),
    entered March 17, 2015 in Albany County, which denied
    petitioner's application pursuant to CPLR 7503 to permanently
    stay arbitration between the parties.
    Petitioner, a contractor, entered into a construction
    contract (hereinafter the subcontract) with respondent
    subcontractor. When a dispute arose and petitioner withheld
    certain payments from respondent, respondent sought expedited
    arbitration pursuant to General Business Law article 35-E, also
    -2-                520787
    known as the Prompt Payment Act (hereinafter PPA). Petitioner
    then commenced this proceeding, seeking to permanently stay the
    arbitration on the ground that section 6.2 of the subcontract
    expressly states that litigation, not arbitration, is the
    parties' chosen method of dispute resolution. Supreme Court
    denied petitioner's application, interpreting the PPA to render
    the subcontract's dispute resolution provision void and
    unenforceable because it denies respondent the option to
    arbitrate the payment dispute. Petitioner appeals.
    "The governing rule of statutory construction is that
    courts are obliged to interpret a statute to effectuate the
    intent of the Legislature, and when the statutory language is
    clear and unambiguous, it should be construed so as to give
    effect to the plain meaning of the words used" (People v Brown,
    25 NY3d 247, 250 [2015] [internal quotation marks, brackets and
    citations omitted]; accord Matter of Arita v Goodman, 132 AD3d
    1108, 1109 [2015]). The PPA's stated purpose is "to expedite
    payment of all monies owed to those who perform contracting
    services pursuant to [private] construction contracts" exceeding
    a certain monetary threshold (General Business Law § 756-a; see
    General Business Law § 756 [1]). As relevant here, that purpose
    is effectuated by General Business Law § 756-b (3) (c), which
    states that, if a contractor is accused of violating any of the
    PPA's provisions, an aggrieved subcontractor "may refer the
    matter . . . to the American Arbitration Association for an
    expedited arbitration." The PPA also states that, "[e]xcept as
    otherwise provided in this article," the terms and conditions of
    the parties' written agreement will supersede the PPA's
    provisions (General Business Law § 756-a). However, General
    Business Law § 757 (3) specifically directs that "[a] provision,
    covenant, clause or understanding in, collateral to or affecting
    a construction contract stating that expedited arbitration as
    expressly provided for and in the manner established by [General
    Business Law § 756-b] is unavailable to one or both parties" is
    "void and unenforceable."
    Here, petitioner contends that the PPA expressly provides
    that the subcontract's dispute resolution provision supersedes
    the PPA's requirement that expedited arbitration be available to
    an aggrieved party, and that it is unaffected by the "[e]xcept as
    -3-                520787
    otherwise provided" language of General Business Law § 756-a.
    Petitioner argues that the only exception to the PPA's general
    policy of giving primacy to the terms of a construction contract
    is found in General Business Law § 756-b (1), which provides for
    the accrual of interest on overdue payments "[n]otwithstanding
    any contrary agreement." Petitioner's reading of the PPA,
    however, ignores the existence of General Business Law § 757 (3),
    which, as we have stated, unambiguously voids and renders
    unenforceable any contractual provision that makes expedited
    arbitration unavailable to one or both parties. Contrary to
    petitioner's argument, the obvious function of section 6.2 of the
    subcontract is to establish litigation as the sole legal option
    for the resolution of disputes under the subcontract, which, in
    turn, denies both parties the opportunity to arbitrate such
    claims. Inasmuch as General Business Law § 757 (3) clearly
    operates to void and render unenforceable the subcontract's
    dispute resolution provision, we find that Supreme Court properly
    denied petitioner's application to stay arbitration.
    Although petitioner also argues that Supreme Court's
    reading of the PPA violates its own constitutional right to a
    jury trial, petitioner admittedly raised this issue for the first
    time on appeal and, thus, it is unpreserved for our review (see
    People v Haskell, 68 AD3d 1358, 1361 [2009]; Matter of County of
    Sullivan [ABC Pac. Realty LLC], 55 AD3d 1029, 1031 [2008], lv
    denied 12 NY3d 713 [2009]). Moreover, even if we were to
    consider this issue (see State of New York v Butti, 304 AD2d 917,
    918 [2003]; Matter of Woodin v Lane, 119 AD2d 969, 970 [1986]),
    petitioner's argument – though styled as a challenge to the
    application of the PPA to the facts of this case – is, in
    reality, a facial challenge to the constitutionality of its
    provisions requiring expedited arbitration. Accordingly,
    petitioner was required to serve notice upon the Attorney
    General, who must be permitted to intervene in support of the
    constitutionality of the statute (see Executive Law § 71; CPLR
    1012 [b]). As there is no evidence that petitioner did so at any
    stage of this proceeding, we decline to pass upon the
    constitutional issue at this time (see People v Parker, 290 AD2d
    650, 652 [2002], lv denied 97 NY2d 759 [2002]).
    -4-                  520787
    Peters, P.J., Garry, Lynch and Clark, JJ., concur.
    ORDERED that the order is affirmed, with costs.
    ENTER:
    Robert D. Mayberger
    Clerk of the Court
    

Document Info

Docket Number: 520787

Citation Numbers: 138 A.D.3d 1265, 31 N.Y.S.3d 230

Judges: Rose, Peters, Garry, Lynch, Clark

Filed Date: 4/14/2016

Precedential Status: Precedential

Modified Date: 11/1/2024