VIDEAN, DAVID v. NRG ENERGY, INC. , 53 N.Y.S.3d 436 ( 2017 )


Menu:
  •         SUPREME COURT OF THE STATE OF NEW YORK
    Appellate Division, Fourth Judicial Department
    416
    CA 16-01604
    PRESENT: CENTRA, J.P., CARNI, LINDLEY, CURRAN, AND TROUTMAN, JJ.
    DAVID VIDEAN, PLAINTIFF-APPELLANT,
    V                             MEMORANDUM AND ORDER
    NRG ENERGY, INC., NRG HUNTLEY OPERATIONS, INC.,
    AND HUNTLEY POWER, LLC, DEFENDANTS-RESPONDENTS.
    KAMMHOLZ MESSINA, LLP, VICTOR (BRADLEY P. KAMMHOLZ OF COUNSEL), FOR
    PLAINTIFF-APPELLANT.
    GOLDBERG SEGALLA, LLP, SYRACUSE (KENNETH M. ALWEIS OF COUNSEL), FOR
    DEFENDANTS-RESPONDENTS.
    Appeal from an order of the Supreme Court, Livingston County
    (Dennis S. Cohen, A.J.), entered January 28, 2016. The order granted
    defendants’ motion for summary judgment dismissing plaintiff’s
    complaint and denied plaintiff’s cross motion for partial summary
    judgment.
    It is hereby ORDERED that the order so appealed from is
    unanimously modified on the law by denying the motion in part and
    reinstating the complaint with respect to the Labor Law § 240 (1)
    claim, and as modified the order is affirmed without costs.
    Memorandum: Plaintiff commenced this Labor Law and common-law
    negligence action seeking damages for injuries that he sustained when
    he stepped on the midrail of a scaffold, began to fall, and grabbed
    onto a pipe to stop his fall. At the time of the incident, he was
    working for API Construction Services (API), which had been
    subcontracted to perform insulation work on property allegedly owned
    by defendants. The scaffold was supplied by another subcontractor,
    Patton Construction (Patton), and only employees of Patton were
    authorized to assemble, modify or adjust the scaffolds.
    Defendants moved for summary judgment dismissing the complaint in
    its entirety. Plaintiff opposed the motion only insofar as it sought
    dismissal of the Labor Law §§ 240 (1) and 241 (6) claims, and cross-
    moved for partial summary judgment on liability on the section 240 (1)
    claim. Supreme Court granted defendants’ motion in its entirety and
    denied plaintiff’s cross motion. We agree with plaintiff that the
    court erred in granting that part of defendants’ motion with respect
    to the section 240 (1) claim, and we therefore modify the order
    accordingly.
    -2-                           416
    CA 16-01604
    Contrary to defendants’ contention, they failed to establish as a
    matter of law that plaintiff’s actions were the sole proximate cause
    of the accident, i.e., that “plaintiff had adequate safety devices
    available; that he knew both that they were available and that he was
    expected to use them; that he chose for no good reason not to do so;
    and that had he not made that choice he would not have been injured”
    (Cahill v Triborough Bridge & Tunnel Auth., 4 NY3d 35, 40; see Fazekas
    v Time Warner Cable, Inc., 132 AD3d 1401, 1403).
    Defendants’ submissions establish that, on the day of the
    accident, there were planks missing from the scaffold that plaintiff
    needed to use for his work, and the scaffold itself was too low for
    plaintiff to reach the area where he needed to work. Inasmuch as only
    Patton employees could modify the scaffolds, a request was made for
    the scaffold to be adjusted or modified for plaintiff’s use. Several
    hours later, during plaintiff’s afternoon break, he was informed that
    the scaffold was being modified. Upon returning to his work area
    following his break, plaintiff observed that a green tag had been
    placed on the scaffold, which meant that the scaffold was ready for
    use. When plaintiff climbed the scaffold, he realized that it was
    still too short to reach the area of his work, i.e., the scaffold was
    inadequate for the work plaintiff needed to perform. Although two of
    plaintiff’s supervisors had directed him to wait until the required
    modifications could be performed, plaintiff testified during his
    deposition that a third supervisor subsequently told him, “ ‘It’s got
    to be done. Get up there and get it done. Do what you have to do to
    get it done. . . Do whatever to get it done.’ ”
    Inasmuch as a modification to the scaffold was required and could
    have taken hours to be performed, we conclude that there are triable
    issues of fact whether an adequate safety device was “readily
    available” for plaintiff’s use (Montgomery v Federal Express Corp., 4
    NY3d 805, 806; see Miro v Plaza Constr. Corp., 9 NY3d 948, 949; cf.
    Robinson v East Med. Ctr., LP, 6 NY3d 550, 554-555). Moreover, based
    on plaintiff’s testimony describing the third supervisor’s
    instructions, we conclude that there are triable issues of fact
    whether plaintiff chose “for no good reason” not to wait for the
    scaffold to be modified (Cahill, 4 NY3d at 40; see DeRose v
    Bloomingdale’s Inc., 120 AD3d 41, 45-47). Although the third
    supervisor denied making such a comment, that denial merely
    establishes that neither party is entitled to summary judgment on the
    Labor Law § 240 (1) claim.
    With respect to the dismissal of plaintiff’s Labor Law § 241 (6)
    claim, we note that, in his bills of particulars, plaintiff asserted
    numerous violations of the Industrial Code (12 NYCRR 23-1.1 et seq.)
    in support of that claim. In opposition to defendants’ motion,
    however, plaintiff relied on only sections 23-5.1 (e) (1), 23-5.1 (e)
    (5) and 23-5.1 (f). On this appeal, plaintiff contends that the court
    erred in dismissing the Labor Law § 241 (6) claim only insofar as it
    was based on the violation of sections 23-5.1 (e) (1) and (5). We
    thus conclude that plaintiff has abandoned any reliance on the
    sections cited in his bills of particulars, except for sections 23-5.1
    (e) (1) and (5) “by failing to address them either in the motion court
    -3-                           416
    CA 16-01604
    or on appeal” (Cardenas v One State St., LLC, 68 AD3d 436, 438; see
    Roosa v Cornell Real Prop. Servicing, Inc., 38 AD3d 1352, 1354; see
    generally Ciesinski v Town of Aurora, 202 AD2d 984, 984).
    Contrary to plaintiff’s contention, the court properly dismissed
    his Labor Law § 241 (6) claim insofar as it was based on the alleged
    violations of 12 NYCRR 23-5.1 (e) (1) and (5) because defendants
    established as a matter of law that any alleged violation of those
    sections was not a proximate cause of plaintiff’s accident (see
    generally Schroeder v Kalenak Painting & Paperhanging, Inc., 27 AD3d
    1097, 1099, affd 7 NY3d 797; Carroll v County of Erie, 48 AD3d 1076,
    1077). Those Industrial Code sections concern the size and placement
    of planks on a scaffold, and plaintiff admitted at his deposition that
    his accident did not occur because of any problems with the planks on
    the scaffold. Rather, his accident occurred because the scaffold was
    not high enough to enable him to reach his work area. We thus
    conclude that, even if there are triable issues of fact whether planks
    were missing at the time the accident occurred, which would render
    those sections applicable to the facts of this case (see Klimowicz v
    Powell Cove Assoc., LLC, 111 AD3d 605, 607), defendants established as
    a matter of law that plaintiff’s accident did not result from any
    violation of those sections. Plaintiff, in opposition to the motion,
    failed to raise a triable issue of fact (see generally Zuckerman v
    City of New York, 49 NY2d 557, 562).
    Entered:   April 28, 2017                       Frances E. Cafarell
    Clerk of the Court
    

Document Info

Docket Number: CA 16-01604

Citation Numbers: 149 A.D.3d 1533, 53 N.Y.S.3d 436

Judges: Centra, Carni, Lindley, Curran, Troutman

Filed Date: 4/28/2017

Precedential Status: Precedential

Modified Date: 11/1/2024