People ex rel. Beck v. Coler , 54 N.Y.S. 639 ( 1898 )


Menu:
  • CULLEN, J.

    On December 10, 1897, at a meeting of the inhabitants of school district No. 1 of the towns of Castleton and Middle-town, Richmond county, a resolution was passed authorizing the trustees of the school district to purchase a new site, and°build a new *640school house thereon, and for that purpose to raise the sum of $80,-000 by tax upon the district. Thereafter the trustees of the school district entered into a contract with the relator for the construction of the school building for the sum of $79,500; payments to be made as the work progressed, on the certificate of the engineer and the architect in charge of the construction of the building. The relator commenced the prosecution of the work, and in February, 1898, received a certificate from the engineer and the architect that he was entitled to a payment of at least the sum of $750. This certificate was presented to' the comptroller for payment, and to the auditor of the borough for audit. The comptroller refused payment, and the auditor declined to act on the claim. Thereupon the relator applied to the special term for a writ of mandamus to the auditor and comptroller to ascertain and certify the value of the work performed and materials furnished by the relator under his contract, and to audit and allow such value as ascertained, not exceeding the amount certified by the engineer and the architect. From an order granting the writ of mandamus as prayed for, this appeal is taken.

    The first claim of the appellants is that the relator’s remedy is by action, and not by mandamus. The rule that a mandamus will not be granted where the party has a remedy by action is one addressed to the sound discretion of the court, and is not of universal application. Thus, in Re Freel, 148 N. Y. 165, 42 N. E. 586, the comptroller of the city of Brooklyn was required by a writ of peremptory mandamus to approve the relator’s claim for work and material furnished under a contract with the city for the construction of a reservoir, and to make and sign a warrant for its payment. There was no question in that case but that the relator might have sued the city for the claim in an action at law. In People v. Schieren, 89 Hun, 220, 35 N. Y. Supp. 61, a writ of mandamus was issued against the comptroller and auditor to examine the relator’s claim for gas furnished under a contract with the city, and to certify the value thereof. Undoubtedly, also, in this case an action on the claim would lie. We are of opinion that where the right of a party to payment from the city is clear, and there are funds on hand applicable to such payment, the court may and will, in the exercise of a sound discretion, compel by mandamus a ministerial officer to audit and pay the claim, though, if the city itself repudiated or denied the existence of the obligation, the rule would be different. In the present case money for the construction of the school house was raised by the issue of bonds of the school district, and the proceeds were paid to the comptroller before the time of the relator’s application; The relator therefore made out a prima facie case, and was entitled to the writ, unless the affidavits on behalf of the comptroller and auditor showed sufficient cause to the contrary.

    The affidavit of Mr. Coler states that he has examined the minutes of the meeting of the board of school trustees, and that from those minutes it appears that $5,500 was paid for the new site, a plot of about two acres, while the assessed value of the land was only $250-an acre; that a resolution was passed that the new school house should be built on the old site, and that the resolution authorizing *641the expenditure for the new school house was void, because it was passed by the votes of persons who were not qualified by law to vote on the question; that the plans of the school house are unnecessarily elaborate and ornate, and not adapted to practical purposes; and that the sum bid for the work is excessive. The rule undoubtedly is that, when a party moves for a peremptory mandamus in the first instance, all allegations of fact in the .opposing papers, sufficiently made, must be assumed as true. But in this case, by the stipulation of the parties, a certified copy of the minutes of the meetings of the school district was presented to the special term, and is before us on this appeal. The affiant, Coler, had no personal knowledge of the action of the meetings of the voters of the school district, or of the trustees, but his statements are based solely on an inspection of the records of those meetings. Therefore, where the records are in conflict with the affidavit, the former must be accepted as true, and the latter considered insufficient to raise any issue of fact. The record shows that the resolution to build the new school house on the old site was not carried, but lost. The allegation in the affidavit of the comptroller that the resolution to erect a new school house was passed by the votes of persons not qualified is a mere statement of a conclusion of law, and insufficient. The record of the meetings of the voters of the school district gives the name of every person voting for or against the resolution, and shows that the resolution was carried by a majority vote. The affidavits in opposition to the relator’s application do not name a single voter who it is claimed was not qualified to vote, nor do they state for what reasons any voter was so disqualified. For aught that appears in these affidavits, there may be no dispute whatever as to the facts , relative to the qualification of these voters, and the statement in the affidavit that voters were disqualified may be based solely on the affiant’s interpretation of the law on the subject,— an interpretation which it is impossible for the court to say was either correct or erroneous, as -it is not stated what that interpretation was. While the rule is strict that all facts averred in answer to an application for a peremptory writ, whether of an affirmative character, or merely denials, must be taken as true, the rule is equally strict that ‘‘affirmations which are only conclusions of law or fact, or are indefinite or general statements, are of no avail and worthless,” and “a deniál in gross, without stating facts, is a mere conclusion.” In re Freel (Sup.) 38 N. Y. Supp. 143; In re Guess, 16 Misc. Rep. 306, 38 N. Y. Supp. 91. Nor are the allegations of the extravagance of the proposed improvement, in its lack of utility, sufficient to defeat the relator’s claim. No allegation whatever of fraud is made. It may be that the site selected for the new school house is ill-chosen, and that the plans for the building are ill-advised; but those were matters for the voters of the school district to pass upon, and their action, taken in good faith and under authority of law, is not subject to review by the comptroller of the city. The opposing affidavits therefore stated no fact sufficient to defeat the relator’s claim, and his right was clear.

    The case is to be distinguished from that of People v. Mooney, 4 App. Div. 557, 38 N. Y. Supp. 495. There it was sought by writ of *642mandamus to compel the board of public works of the city of Buffalo to execute a contract which had been awarded the relator, as the lowest bidder, for paving a street in that city. It appeared in opposition to the application that, since the adoption of the resolution to pave the street, it had been determined to convert the street into a boulevard, and a part of the park system of the city. The application was denied, and the relator left to his remedy by action, on the ground that the board of public works was justified in refusing to prosecute an improvement which was shortly afterwards to be rendered valueless. We assume that a municipal corporation, the same as an individual, may at any stage decline to prosecute an improvement for the carrying out of which it has contracted; remaining, of course, liable to the contractor for damages for breach of the contract. But in this case the city has taken no such action. The respondents in the Buffalo case constituted that department of the city government which had, subject to the common council, control and management of the public work, the prosecution of which it was sought to compel. It may be that in the present case the board of education or the school board of the borough might suspend or terminate the construction of the new school house; but, in the absence of fraud or illegality, the comptroller has no general supervision over the conduct of other officers or departments of the city. If the further prosecution of a public work is unwise and should be abandoned, it is for the proper department, not the comptroller, to determine that question. The construction of the new school house was entered upon, and the contract with the relator for its construction made, in pursuance of law. Until the proper city authorities have determined to abandon the work, the comptroller must properly discharge the duties relating thereto imposed upon him by law.

    The order appealed from should be affirmed, with $10 costs and disbursements. All concur.

Document Info

Citation Numbers: 54 N.Y.S. 639

Judges: Cullen

Filed Date: 11/22/1898

Precedential Status: Precedential

Modified Date: 10/18/2024