Conwell v. Degnon Contracting Co. , 154 N.Y.S. 182 ( 1915 )


Menu:
  • LEHMAN, J.

    On May 27, 1914, the defendant was engaged in laying a high-pressure water main along Twenty-Eighth street under a contract with the-city. Running parallel to the projected main was a 12-inch low-pressure main. This main was at least 3% feet from the edge of the trench which the defendant was excavating for the new main, and was about 4 feet below the surface of the street. The defendant blasted out some rock, and almost immediately after the blast was set off water gushed from the earth surrounding the existing water main and flowed into the plaintiff’s premises. For the resulting damage to his property the plaintiff has brought this action and recovered the sum of $75. The complaint sufficiently sets forth a cause of action in either negligence or trespass, but in my opinion the evidence is insufficient to sustain a recovery on either theory.

    [1,2] The plaintiff has failed to establish any action in trespass unless the water from the low-pressure main was precipitated into the plaintiff’s premises by the direci action of the defendant; that is, unless the main was broken by impact with a rock or debris precipitated upon it by the blast. Derrick v. Kelly, 136 App. Div. 433, 120 N. Y. Supp. 996. If it was broken only as a result of the concussion, then the plaintiff must show that the blast was negligently set off. The evidence shows that there was a solid space -of 3% feet between the trench and the broken pipe, and it is difficult to see how a blast could have driven a rock through this space. It does appear, however, that when the flow of water was stopped, and the earth surrounding the broken main was taken away, it was found that a piece of pipe 46 inches long and in width nearly one-half the diameter of the pipe was broken, and at one point a large rock was found resting hard up against the broken main. It appears, however, that the main was an old one, and had been in that place for many years, and it does not appear whether this pipe had not been placed against this rock when it was originally laid. The plaintiff’s own witness testifies that: .

    “I can’t say whether the rock that was np against the pipe was a large piece of broken rock, or whether it was solid rock.”

    On cross-examination this witness, who was the assistant engineer of the water department in charge of this work, testified as follows:

    “Q. This corner of the’ rock which you saw up against the low-pressure main after the earth was removed—as far as you know that comer of rock could have been up against that pipe before the explosion, couldn’t it? A. That’s right. Q. In other words, after that low-pressure trench had been excavated, you found the situation in which the low-pressure main had lain in *184a bed of rock which had been excavated before that main was laid there, didn’t you? A. Yes; the rock had been excavated before the main had been laid".”

    From this testimony it seems to me perfectly obvious that it is absolutely impossible to infer from the presence of the rock against the pipe that it had been cast against the pipe by the blast. All the testimony is quite consistent with the view that the rock was there at the time of the original excavation 30 years ago, and that the break in this old pipe was due to concussion.

    [3] There remains, therefore, only the question of whether there is any evidence of negligence. The plaintiff has presented no evidence that there was any excessive force used in blasting, claiming mainly that the defendant had no right to send off any blast in proximity to the low-pressure main without shutting off the water. There is, however, no evidence to show that the defendant had any reason to foresee that the blast would be sufficiently strong to break a properly laid pipe by concussion. There is not even any evidence that the defendant knew, or had reason to know, tnat such a mam was in the street. On the contrary, it affirmatively appears that the working plans furnished by the city fail to show such a main.

    Judgment should be reversed, and new trial ordered, with costs to appellant to abide the event. All concur.

Document Info

Citation Numbers: 154 N.Y.S. 182

Judges: Lehman

Filed Date: 6/29/1915

Precedential Status: Precedential

Modified Date: 11/12/2024