Finkelstein v. Balkin , 103 N.Y.S. 99 ( 1907 )


Menu:
  • HENDRICK, J.

    The plaintiff brought this action and recovered a judgment for injuries sustained by him in falling from a scaffold on which he and his partners were at work in whitewashing a building owned by the defendant. The plaintiff applied to the defendant, and asked to be let a contract for whitewashing certain premises in 136th street. He was asked to look at a house on the corner of Market and Cherry streets, and estimate on the cost of the work to be done there. Thereafter he and his partner called upon the defendant, and an agreement was entered into between them, by which the plaintiff and his partner was to do the work of whitewashing the rear of the building for the sum of $25. Up to this point there is no substantial dispute in the testimony. The breaking of the handrail upon a scaffold used in the work was the cause of the accident, and as to who was to furnish the material to do the work and the scaffold to work upon is in question.

    The plaintiff claims that the defendant was to furnish all the material and a scaffold, and the defendant and his witnesses testifjr that the plaintiff "was to furnish all the means to do the work with, but that he asked the defendant to loan him the scaffold used, which request was granted. When the plaintiff began work the scaffold was at the front of the building, and was moved by him to the rear, and then suspended by ropes attached to the roof in the manner usually employed in such work. It was hanging against the wall of the building, and the plaintiff and his partner had worked thereon for nearly three days, when the accident happened. The manner in which it occurred is substantially as follows: The plaintiff went upon the scaffold, and, it giving a sudden move, he caught the railing attached to the scaffold to save himself from falling, whereupon the railing broke’ and he fell to the ground, receiving the injuries complained of. He says that at the very instant he caught the rail, and while he was attempting to save himself from falling, he noticed a crack in it, and that before he could remove his hand it broke. He made no particular examination of the scaffold or rail before he began using it, and nobody but himself and his partner had used it during the progress of this work. On the part of the defendant it was shown, without substantial contradiction, that on Saturday, prior to the time plaintiff began to use the scaffold, his use .thereof beginning on the following Monday, it was in first-class condition, the handrail being of pine 2y2 by.2 inches, that size being the usual size employed in handrails on scaffolds on this kind of work, and that the rail was apparently solid. It was not contradicted that an examination of the rail immediately after the accident, revealed that it was a new, clean break of apparently solid wood, with no evidence of rot or crack therein.

    Under this.state of fact it is difficult to see upon what theory- the plaintiff is entitled to recover. It is quite evident that the plaintiff was an independent contractor. The appellant says in his brief, that:

    *101“Independence of control in employing workmen and in selecting the moans of doing work is tlie test usually employed by courts to determine whether the contractor is independent or not.”

    This is broadly stated, but, adopting that as the test, it is quite clear that in the case at bar the plaintiff and his partner had an absolute right in doing this work to select the time and means and to employ any workmen they might choose to assist them. The plaintiff testified:

    “Q. What did he [defendant] tell you at the time he employed you to work? A. He did not say anything, except to take the scaffold and go ahead and do the work. ‘It is my scaffold and my rope. Go ahead and do the work.’ ”

    In this same connection, evidently endeavoring to be considered as a mere employé, the plaintiff testified that he was promised $25 a week for doing the work, but subsequently he admitted that he and his partner were to have $25 for doing the job, whether it took “one day or ten.” There certainly was no suggestion in the foregoing remark of the defendant, as testified to by plaintiff, that the plaintiff was not to engage other workmen, nor to furnish any material, or to supply, if he chose to do so, a different or other scaffold from the one owned by the defendant upon which to stand while doing the work.' It is very evident that the plaintiff and his partner had the complete and absolute control over the work and the means to be employed to perform it. The record will be searched in vain for any testimony tending to show that the defendant exercised or assumed to exercise any control over the work, or that he gave a single direction in reference thereto, or claimed a right to direct the manner in which it was to be done or the appliances to be employed in its prosecution. The plaintiff represented the will of the employer only as to the result of the work, and not as to the means by which it was to be accomplished, which is the true test. Thompson on Negligence, p. 570.

    It is true that the plaintiff, in answer to the question, “You did not have a boss over you while you were doing the work?” said, “The contractor, Balkin.” But, in the absence of any direct testimony showing direction or control by the defendant, the answer must be deém'ed a mere conclusion of the witness, not based upon any shown or admitted fact, and is not sufficient to establish the relation of master and servant between the parties; and, unless that relation is shown,' the provisions of the labor law have no application. As the record stands, if the defendant owed the plaintiff any duty, it was shown to have been discharged by the undisputed testimony that the scaffold was properly constructed, of proper material, and was in perfect condition when it went into the plaintiff’s possession, having no known or discoverable defects so far as could be ascertained by careful inspection. If any presumption of negligence is raised by the happening of the accident, it was overcome by the proof given by the defendant, as before stated.

    Judgment reversed, and new trial ordered, with costs to appellant ty abide the event. All concur.

Document Info

Citation Numbers: 103 N.Y.S. 99

Judges: Hendrick

Filed Date: 3/14/1907

Precedential Status: Precedential

Modified Date: 11/12/2024