-
Seabury, J. The complaint alleges three causes of action. The first cause of action alleged is based upon a written contract between the parties under which the plaintiff agreed to install a vacuum cleaner system. The’second and third
*482 causes of action are for labor and materials furnished. The . answers of the defendants deny performance of the contract alleged in the first cause of action. .The answers also plead as a complete defense to the causes of action set forth in the complaint that the Hedden Construction Company as agent for defendant entered into a contract with the plaintiff for the performance of certain work, etc.; that the system installed by the plaintiff did "not comply with the terms of said contract and that plaintiff failed to complete the terms of said contract, but substituted a plant or system of less value and not capable of doing* the work required to be done by the plant specified in the said contract and that the plant or system installed by the plaintiff did not exceed the sum of $5,000 in value, which said sum has been duly paid to the plaintiff.The answer does not deny any of the allegations contained in the second and third causes of action as alleged in the complaint, and the matters alleged in the answers as a “ separate and complete defense thereto ” constitute no defense in law to the second and third causes of action alleged in the complaint.
These two last mentioned causes of action stand admitted before the court. It follows that the learned court below should, under section 511 of the Code of Civil Procedure, have ordered that the action be severed, and that the plaintiff have judgment for the sums demanded in the second and third causes of action, and that the action be continued with like effect as if it had been originally brought upon the first cause of action alleged.
The learned court below denied the plaintiff’s motion upon the supposed authority of Cronin v. Tebo, 63 Hun, 190. That case is not, however, in point upon the question presented for determination. In that case the complaint set up two causes of action and the answer denied only the first cause of action but set up a counterclaim sufficient to extinguish both causes of action alleged; and it was held that, under such circumstances, a severance of the action was improper.
In the case at bar there is no counterclaim pleaded, and the alleged defense constituted no defense to the second and third causes of action alleged.
*483 The order appealed from is reversed, with ten dollars costs and disbursements, and the motion is granted with ten dollars cost's; and it is ordered that the action be severed, and that the plaintiff have judgment for the sum demanded in the second and third causes of action alleged in the complaint, and that the action be continued with like effect as if it had been originally brought upon the first cause of action alleged in the complaint.Lehman and Page, JJ., concur.
Order reversed.
Document Info
Citation Numbers: 74 Misc. 481, 132 N.Y.S. 335
Judges: Seabury
Filed Date: 12/15/1911
Precedential Status: Precedential
Modified Date: 10/19/2024