TRAX Constr. Co. v. Reminderville , 2021 Ohio 3481 ( 2021 )


Menu:
  • [Cite as TRAX Constr. Co. v. Reminderville, 
    2021-Ohio-3481
    .]
    IN THE COURT OF APPEALS OF OHIO
    ELEVENTH APPELLATE DISTRICT
    LAKE COUNTY
    TRAX CONSTRUCTION CO.,                                   CASE NOS. 2020-L-113
    2020-L-127
    Plaintiff-Appellee,                                2021-L-008
    -v-
    Civil Appeals from the
    VILLAGE OF REMINDERVILLE,                                Court of Common Pleas
    Defendant-Appellee,
    Trial Court No. 2018 CV 000184
    OHM ADVISORS, et al.,
    Defendants-Appellants.
    OPINION
    Decided: September 30, 2021
    Judgment: Affirmed
    O. Judson Scheaf, III, Jeffrey A. Yeager, and Elise K. Yarnell, Hahn Loeser & Parks
    LLP, 65 East State Street, Suite 1400, Columbus, OH 43215, and Andrew J. Natale
    and Aaron S. Evenchik, Hahn Loeser & Parks LLP, 200 Public Square, Suite 2800,
    Cleveland, OH 44114 (For Plaintiff-Appellee).
    Angela F. Lohan, Village of Reminderville Law Director, 3382 Glenwood Boulevard,
    Reminderville, OH 44202 (For Defendant-Appellee).
    Michelle A. Thomas, Dickie, McCamey & Chilcote, P.C., 89 Kercheval Avenue, Grosse
    Pointe Farms, MI 48236, Paul J. Schumacher and Kristin L. Wedell, Dickie, McCamey
    & Chilcote, P.C., 600 Superior Avenue East, Fifth Third Center, Suite 2330, Cleveland,
    OH 44115, and George S. Coakley and Richard T. Lobas, Coakley Lammert Co., LPA,
    20600 Chagrin Boulevard, Suite 1100, Cleveland, OH 44122 (For Defendants-
    Appellants).
    CYNTHIA WESTCOTT RICE, J.
    {¶1}   Appellants, OHM Advisors (“OHM”), et al., appeal from the judgment of the
    Lake County Court of Common Pleas, after a trial by jury, in favor of appellee, TRAX
    Construction Co., which awarded appellee $1,061,551.84 in compensatory damages,
    $325,000 in punitive damages, and $483,870.53 in attorney fees. We affirm.
    {¶2}   TRAX is a construction company specializing in excavating, repairing, and
    replacing underground utilities. By way of its owner and president, Christopher Valletto,
    TRAX contracted with appellee, the Village of Reminderville (“Village”), to perform
    underground utility construction work, including a new sanitary-force main, a new water
    main, and new storm sewers (“the Project”). The contract bid was for $2,078,000 and
    was based upon a specified work schedule which was originally set to commence on June
    12, 2017 and finish on October 31, 2017. At a preconstruction meeting, the parties
    confirmed that the city of Cleveland and Summit County would be involved in inspecting
    and paying for a portion of the work, and that all contractor pay requests and change
    orders (work added to or deleted from the original contract) had to be submitted to OHM,
    the engineering firm used by the Village, for processing before submission to the Village
    for final approval.
    {¶3}   OHM engineer Chad Lewis assisted OHM in drafting the design. According
    to Mr. Lewis, TRAX was entitled to rely upon the plans set forth in the design, in particular
    the location of the utilities to be replaced or repaired as depicted in the design. Appellant-
    Eugene Esser, an engineer for OHM, acted as the Project Manager and as well as the
    contractual liaison between TRAX and the Village (Mr. Esser was designated as the
    Village’s engineer outside of his work on the project).       Mr. Scott Hines was OHM’s
    construction manager and was the main point of contact between TRAX and OHM.
    2
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    According to Mr. Valetto, all communications went through Mr. Hines who was in direct
    contact with Mr. Esser.
    {¶4}   Mr. Esser, along with the Village, were responsible for establishing funding
    for the Project. According to the Village’s Mayor, Sam Alonso, the Village relied upon
    OHM to properly administer the contract; and, if something noteworthy or important
    occurred or failed to occur during the course of the Project, the Mayor maintained the
    Village expected OHM to contact him and/or the Village council to discuss such matters.
    {¶5}   When TRAX began excavation for the Project, it discovered the project
    design was flawed; initially, the utilities depicted in the design were not in the location
    identified. Mr. Hines subsequently advised TRAX to move further down the line as
    depicted on the plan to address what was shown to be an abandoned water line. When
    TRAX located this line, it discovered it was not abandoned and, due to certain regulations
    relating to excavating live lines, the plan needed to be revised. According to Mr. Valletto,
    the postponement required TRAX to remain on the job and incur additional time and
    resource costs. OHM, via Mr. Lewis, admitted that TRAX was entitled to rely upon the
    design plans, including utility locations. And Mr. Lewis conceded the actual utility locations
    were different than those depicted on the design plan.
    {¶6}   In light of the construction delay, TRAX, via Mr. Jeffrey Busch (TRAX’s
    Project Manager), Mr. Valletto, or other representatives, provided OHM, Mr. Hines, Mr.
    Esser, and the Village with numerous written correspondences requesting, inter alia,
    progress meetings to discuss factors impacting the project due to the postponement(s)
    and what was eventually characterized as an “indefinite standby.”          Overall, some 16
    letters were sent between August 3, 2017 and February 23, 2018 – Ultimately, only two
    3
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    progress meetings were held (the first on October 30, 2017 and the second occurring on
    November 28, 2017); and, although on-site verbal communications took place, OHM sent
    a written response to only two of TRAX’s letters.
    {¶7}   After the first issue causing the re-design, Mr. Valleto stated that Mr. Hines
    directed TRAX to continue to remain on site to complete the workable aspects of the
    Project. And, with respect to TRAX’s concerns about significant additional expenses
    accumulating due to the delays and “standbys,” Mr. Valleto asserted Mr. Hines assured
    him TRAX would be paid for its additional incurred costs. Although nothing in writing was
    offered to confirm this conversation, Mr. Hines assured Mr. Valletto “his word has value.”
    TRAX accordingly submitted change orders for the additional work to confirm the changes
    and ensure payment. According to Mr. Valletto, however, as of November 28, 2017,
    nearly a month beyond the initial, contractual completion date, TRAX had not received
    any payment from the Village. Had TRAX been told it was not going to be paid for the
    additional time and work, Mr. Valletto stated it would have stopped work immediately.
    {¶8}   As of late November 2017, Mr. Valletto stated TRAX had explained to the
    Village, via letter and verbal exchanges, the problems it was experiencing due to the
    inability to move forward. Specifically, TRAX, through Mr. Valletto, advised the Village
    and OHM: “we are continually being damaged by our equipment and manpower out there
    on the project well beyond the completion time and that we are also financing the project
    and financing additional work that we’ve been assured payments on and that’s basically
    what we are telling them and that we are tracking these costs.” According to Mr. Valletto,
    no representative of the Village or OHM disputed these points. Indeed, during this
    timeframe, a point at which construction would be slowed due to potential weather
    4
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    interference, no agent of the Village or OHM advised TRAX to leave the site to avoid
    further time-and-resource costs.
    {¶9}   Considering the lack of payment and additional expenditures, TRAX made
    a public-records request asking the Village to produce all files, including emails and text
    messages, relating to the changes to the project design, additional-cost claims submitted
    by TRAX, and the “positions that exist between the Village and its design engineer.”
    TRAX stated it required this information in the event it “must escalate the matter to recover
    the compensation due.” TRAX received no response to the request.
    {¶10} On December 12, 2017, nearly six weeks after the original, scheduled
    completion date, TRAX sent a letter to Mr. Hines, OHM, and the Village regarding a
    change order and pay application which did not account for its completed work. The letter
    noted the Village would be in material breach of the contract by failing to timely process
    payment requests for work performed. On the same date, Mr. Hines sent TRAX a letter
    indicating the Village and OHM would be addressing only an extension of time for the
    Project’s completion and nothing else. The letter also stated that, due to, among other
    things, the winter weather, the Village was putting a work hold on certain aspects of the
    Project.
    {¶11} In Mr. Valletto’s view, the representations in Mr. Hine’s letter implied that
    unless TRAX cooperated with OHM on its terms, it would not be paid.                   TRAX
    subsequently responded requesting further clarification of the Village’s and OHM’s
    intentions and advised the Village if it desired to terminate TRAX for convenience from
    the Project (pursuant to the contract), it would need the proper paperwork to minimize the
    5
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    cost. According to Mr. Valletto, TRAX received no written response from either the Village
    or OHM and no meeting was arranged or held.
    {¶12} On December 27, 2017, TRAX sent the Village and OHM a letter advising
    that it had not been paid for base contract work and had been unable to confirm the
    processing of pending payment applications. The letter noted that OHM and the Village
    represented to TRAX “many weeks ago” that the applications had been submitted but,
    given the uncertainty and delay, TRAX was concerned the applications were never sent.
    TRAX requested copies of the submission and any related paperwork regarding the
    payment applications. The letter also advised that TRAX had sent various letters to the
    Village and OHM regarding the absence of required design documents, certain
    interferences with work, and additional-cost claims associated with compensable delays.
    TRAX noted that despite repeated efforts to mitigate costs, the Village and OHM have
    failed and refused to follow the provisions of the original contract and timely process
    accurate payment applications. TRAX received no written response to this letter and no
    meeting was arranged or held.
    {¶13} On January 22, 2018, TRAX, via Mr. Valletto, again wrote the Village and
    OHM. That letter advised that the Village’s finance officer’s certificate in the original
    contract was $897,000 and TRAX has, or will, surpass that level of costs.          TRAX
    expressed serious concern regarding the uncertainties surrounding the certified financing
    and noted it had endeavored to meet with the Village and OHM but received no response.
    TRAX stated it was entitled to a revised certificate showing the entire amount of the
    contract bid.   Meanwhile, the letter advised TRAX will not work, and is not required to
    work beyond the amount certified. TRAX also reminded the Village that it was in breach
    6
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    of the contract relating to its failure to respond to its pending change orders for payment,
    as well as the Village’s and OHM’s failure to act which prevented performance under the
    contract. If the Village or OHM disputed any change orders, TRAX requested a meeting.
    TRAX requested the Village and OHM to respond by the close of business on Friday,
    January 26, 2018. Mr. Valletto stated he did not receive a response to this letter and no
    meeting was arranged.
    {¶14} Mr. Valletto pointed out that the Village finance officer’s certification
    essentially ensures that funds are available to pay a contractor for work completed.
    Because the project had went in an unexpectedly bad direction for TRAX, Mr. Valletto
    and his associates revisited the contract and found the funds certified, $897,000, were
    far lower than the $2,078,000 accepted by the Village on TRAX’s bid. He noted this
    discovery was “a big alarm button for us.” As such, if TRAX performed more than
    $897,000 of actual work, it was at risk of not being paid beyond that amount. Thus, TRAX
    requested the Village to recertify the funds to an amount that would be sufficient to cover
    expenses to date. Mr. Valletto ultimately admitted he did not fully review the fund-
    certification aspect of the contract when he signed it on behalf of TRAX. He also admitted
    he would not have signed it had he known the certification was much lower than the bid.
    {¶15} On January 29, 2018, OHM sent TRAX a letter, via Mr. Hines, which
    reiterated its December 12, 2017 statements. It also requested a written schedule for
    when TRAX intended to return to work on the project. TRAX subsequently responded to
    this request, stating it could not provide a schedule for returning to work because its
    billings have reached the limit of the finance officer’s certificate in the contract. Moreover,
    TRAX pointed out that OHM had previously directed it to stop work and, without a
    7
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    recertification, re-commencing work was not possible. In effect, TRAX stated “OHM is
    preventing TRAX’s performance and delaying TRAX.” TRAX demanded the Village and
    OHM to process its pending pay applications. Mr. Valletto stated he received no response
    to this missive.
    {¶16} In light of the foregoing, on February 1, 2018, TRAX sent the Village and
    OHM a letter advising them that it had filed the underlying complaint and submitted a copy
    of the same. TRAX pointed out that, even though it had tried to work with both the Village
    and OHM, they essentially ignored all requests for meetings and failed to certify funds for
    further payments. TRAX stated it remained ready and willing to discuss the issues, but
    no further work would occur on the project. Also, TRAX emphasized that, because the
    project had not been recertified and its equipment and materials were sitting idle, the
    Village had commenced taking its materials. Mr. Valletto stated TRAX had a surplus of
    stone; the Village, however, without TRAX’s permission, began using the materials to
    backfill potholes and trenches.
    {¶17} In their complaint, TRAX alleged fraud/willful concealment, breach of
    contract, and theft/conversion against the Village; and, against OHM and Mr. Esser, it
    alleged fraud/willful concealment, negligence, and theft/conversion. The Village filed a
    counterclaim against TRAX and a cross-claim against OHM and Mr. Esser, seeking, in
    relevant part, indemnity and contribution from OHM and Mr. Esser.
    {¶18} Subsequently, on April 11, 2018, the Village issued a funding certificate in
    the amount of $2,078,789.55. Later, on May 24, 2018, the Village terminated TRAX for
    convenience; at that point, TRAX had been paid $979,509.83 for the work it had
    performed.
    8
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    {¶19} Meanwhile, the Village filed cross-claims against the OHM defendants
    seeking indemnity and contribution, with a supplemental cross-claim alleging negligence.
    The OHM defendants filed a motion to dismiss the complaint, alleging the economic-loss
    rule barred TRAX’s tort claims.       The trial court denied the motion and the matter
    proceeded to jury trial. TRAX subsequently moved for an order of spoliation and an
    adverse evidentiary presumption, asserting Mr. Esser had lost or destroyed a flash drive
    containing documents relating to the Project. The trial court denied TRAX’s motion and
    issued an order in limine preventing reference to the alleged spoliation as well as the
    potential for an adverse inference.
    {¶20} Beyond the facts set forth above, Mr. Esser testified that, while acting as
    OHM’s project manager, OHM owed TRAX the duties to take ownership of mistakes, to
    deal fairly and honestly with it, and to act as a faithful agent, including keeping it fully
    informed.   Mr. Esser stated that such duties also involve being fully informed and
    communicating with a client in various forms such as writing, email, and verbal contact.
    He testified that a project manager and engineer has an obligation to be truthful and
    neither conceal nor fail to disclose important information. Mr. Esser agreed that the
    foregoing standards applied to OHM’s relationship with TRAX, and TRAX was entitled to
    rely upon him and OHM to adhere to these standards.
    {¶21} Mayor Alonso testified that having the necessary money to fund a project is
    important, and TRAX was entitled to be concerned if sufficient funds had not been
    secured. He also agreed that if TRAX was on the project longer than expected, through
    no fault of its own, it is entitled to the requisite compensation. Moreover, Mayor Alonso
    agreed that TRAX kept OHM, at the very least, apprised of the entire time and costs it
    9
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    had incurred on the project. And the mayor testified that the Village would remit payment
    to TRAX to the extent “everything looks good” (with respect to payment applications) to
    OHM. Mr. Valletto testified that, after the initial hold up due to problematic designs, Mr.
    Hines directed TRAX to go outside the project limits and proceed with additional work
    necessitated by the changes. And, even though, according to Mr. Valletto, OHM had
    repeatedly assured TRAX, via both Mr. Esser and Mr. Hines, it would be paid for the
    additional time and work, no such payment was promptly or obviously processed.
    {¶22} Contrary to Mr. Valletto’s testimony, Mr. Hines testified he did not assure
    TRAX it would be paid; instead, Mr. Hines observed that the applications relating to the
    change orders would be reviewed and decisions would be made accordingly. During its
    case in chief, TRAX submitted an email received in discovery which was written on
    December 12, 2017, by Mr. Hines to Terry Bowlin, a technician for OHM. The email
    related to TRAX submission of a change order as well as a “winter shutdown.” The email
    additionally sought confirmation that certain materials related to the project can be stored
    on a baseball field because “[i]t is likely that the rebid will push the project past the start
    of the field being used.”      When questioned about “the rebid,” Mr. Hines testified
    discussions had occurred that suggested TRAX might be pulling off the job. When
    pressed on this point, however, Mr. Hines stated that neither he nor OHM had discussed
    the possibility of a rebid with either TRAX or the Village. Although Mr. Hines testified no
    rebid would occur unless TRAX left the project, he also acknowledged that the winter
    months slowed, if not halted work. Further, even though OHM was discussing rebidding
    the job, Mr. Hines conceded there was no discussion at that point of terminating the
    10
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    contract for convenience, a contractual tool that would allow either party to sever ties to
    the contract without issue or incurring further expense.
    {¶23} In December 2017, Mr. Esser was transitioning into retirement and Thomas
    Tucker, a senior project manager and engineer for OHM, was assuming his role as Project
    Manager on the Project. In a December 22, 2017 email from Mr. Hines to Mr. Tucker (on
    which Mr. Esser, Mr. Lewis, and Mr. Bowlin were copied), Mr. Hines recommended they
    discuss “Reminderville verbally” because “[i]t is a different animal for which we do not sit
    in the zoo keepers chair.” (sic.) Mr. Hines denied writing the email.1 In light of this, OHM
    objected to the email’s admission. The trial court, however, overruled the objection, ruling
    the jury should be permitted to consider and weigh the import of the email because it was
    in OHM’s system, a point counsel for appellants later conceded.
    {¶24} Mr. Esser additionally testified that he had removed certain project-related
    information on his company-issued computer after he retired. Although Mr. Esser saved
    the information to a flash drive, and agreed to save the information during his deposition,
    he later deleted it from the flash drive and, according to his testimony, saved it to a
    different computer. The information, therefore, whatever it may have been, was ultimately
    unavailable.2
    {¶25} After each party rested, the trial court entered a directed verdict for OHM on
    TRAX’s and the Village’s negligence claims but denied a directed verdict on TRAX’s fraud
    claims. The jury ultimately returned a verdict in favor of the Village on TRAX’s fraud
    1. Notwithstanding Mr. Hines’ denial at trial, appellants appear to concede he wrote and sent the
    message at page 4 of their brief (“On 12/20/17, and in light of TRAX’s escalating complaints and
    demands, Hines directed an email to Tucker indicating that they should discuss the [project] ‘verbally’
    * * *.”)
    2. It was this information that prompted TRAX’s motion regarding spoliation and an adverse inference.
    11
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    claims and in favor of TRAX on the breach of contract claims but awarded zero damages
    for the Village’s breach of contract. The jury found in favor of TRAX on the fraud claims
    against OHM and Mr. Esser. The jury also found in favor of the Village against OHM and
    Mr. Esser on its indemnity cross-claim. The jury found that TRAX’s damages were
    caused exclusively by OHM/Esser due to their concealments and fraudulent actions on
    which TRAX justifiably relied. OHM and Mr. Esser moved for a judgment notwithstanding
    the verdict and a new trial, each of which were denied. As outlined above, the jury and
    judge eventually ordered damages and fees in an amount just under $1.9 million. This
    appeal follows.
    {¶26} Appellants’ first assignment of error provides:
    {¶27} “The trial court committed reversible error by denying the motion to dismiss
    the complaint (9/13/18 judgment entry), the motion for directed verdict (TTr pp 648-649),
    and the motion for JNOV (10/21/20 journal entry) because the economic loss rule barred
    all tort claims by plaintiff TRAX against the OHM defendants.”
    {¶28} Appellants assert that the trial court erred, as a matter of law, in denying its
    various motions because the economic-loss rule barred all TRAX’s tort claims, including
    the intentional tort of fraud, because their status as design professionals on the Project
    was not a sufficient nexus to substitute for privity under the contract between TRAX and
    the Village. Moreover, they argue they owed no general duty under tort law to protect
    TRAX from purely economic harm arising out of contractual obligations regarding the
    Project’s design because this duty arose and was binding between OHM (and its agents)
    and the Village exclusively.    In this respect, appellants maintain whatever allegedly
    reasonable reliance TRAX had on OHM’s representations cannot serve as a substitute
    12
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    for privity between TRAX and appellants. Finally, appellants contend that, even if the
    economic-loss rule does did not bar the fraud claim, Ohio law does not permit a contractor
    to evade contractual limitations by pleading fraud grounded upon an alleged breach of an
    ethical duty to disclose – the foundation, in appellants’ view, for the jury’s verdict in
    TRAX’s favor.
    {¶29} Initially, TRAX asserts appellants failed to preserve their arguments vis-à-
    vis the economic-loss rule because they (1) did not raise it as to fraud as part of their
    motion to dismiss; (2) did not raise it as part of their directed verdict motion; (3) failed to
    revisit its directed verdict motion at the conclusion of evidence; and (4) failed to raise the
    rule until its final reply in support of its motion for judgment notwithstanding the verdict.
    {¶30} With respect to TRAX’s first contention, a review of appellants’ pretrial
    motion to dismiss the complaint demonstrates they raised the issue as to all tort claims.
    Although they did not specifically use the economic-loss-rule nomenclature, they did
    argue the complaint should be dismissed because TRAX was seeking purely economic
    damages in tort against OHM and Mr. Esser, parties with whom it had no privity of
    contract. In this respect, we conclude the motion to dismiss was sufficient to preserve
    the legal issue for appeal.
    {¶31} Further, because the issue was preserved, the judgment denying the
    dismissal was appealed, and the issue of the application of the economic-loss rule is a
    question of law, we additionally conclude, even assuming appellants failed to raise the
    issue anew at the points identified by TRAX, the matter was not waived.
    {¶32} “The economic-loss rule generally prevents recovery in tort of damages for
    purely economic loss.” Corporex Dev. & Const. Mgmt Inc. v. Shook, Inv., 
    106 Ohio St.3d 13
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    412, 
    2005-Ohio-5409
    , ¶6. “‘[T]he well-established general rule is that a plaintiff who has
    suffered only economic loss due to another’s negligence has not been injured in a manner
    which is legally cognizable or compensable.’” Chemtrol Adhesives, Inc. v. Am. Mfrs. Mut.
    Ins. Co., 
    42 Ohio St.3d 40
    , 45 (1989), quoting Nebraska Innkeepers, Inc. v. Pittsburgh–
    Des Moines Corp., 
    345 N.W.2d 124
    , 126 (Iowa 1984). This rule stems from the
    recognition of a balance between tort law, designed to redress losses suffered by breach
    of a duty imposed by law to protect societal interests, and contract law, which holds that
    “parties to a commercial transaction should remain free to govern their own
    affairs.” Chemtrol, supra, at 42; see, also, Floor Craft Floor Covering, Inc. v. Parma
    Community Gen. Hosp. Assn., 
    54 Ohio St.3d 1
    , 7 (1990), quoting Sensenbrenner v. Rust,
    Orling & Neale Architects, Inc., 
    236 Va. 419
    , 425 (1988). “‘Tort law is not designed * * *
    to compensate parties for losses suffered as a result of a breach of duties assumed only
    by agreement. That type of compensation necessitates an analysis of the damages which
    were within the contemplation of the parties when framing their agreement. It remains the
    particular province of the law of contracts.’” Floor Craft, supra, at 3, quoting
    Sensenbrenner, supra.
    {¶33} In effect, the economic-loss rule separates contract and tort claims by
    preventing a plaintiff from bringing a tort claim when the matter is properly resolved in
    contract. See Corporex, supra, at ¶6. The crucial difference between the law of tort and
    contracts is the source of the duty imposed. Contractual duties emanate from bargained-
    for agreements between specific parties who allocate risks and benefits. See Floor Craft,
    supra, at 7. Alternatively, tort duties arise from public policy considerations. That is,
    “[t]ort law offers redress for losses suffered by reason of a breach of some duty imposed
    14
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    by law to protect the broad interests of social policy.”               Morgan v. Mikhail, 10th Dist.
    Franklin Nos. 08AP-87 and 08AP-88, 
    2008-Ohio-4598
    , ¶62, citing Floor Craft, supra. Put
    simply, the law of tort protects people and property from injury, while the law of contract
    protects parties’ bargained-for expectations. Morgan, 
    supra.
    {¶34} If a plaintiff suffers only economic losses, a court must consequently
    determine the source of the duty that forms the basis of the action. See Corporex, supra,
    at ¶10. A plaintiff may pursue such a tort claim if it is “based exclusively upon [a] discrete,
    preexisting duty in tort and not upon any terms of a contract or rights accompanying
    privity.” Corporex, supra at ¶9.        Consequently, the economic-loss rule would not bar a
    plaintiff from bringing a tort where the tort duty is independent of the contract. The issue,
    therefore, is whether, irrespective of the substantive evidence presented at trial,
    appellants had a duty not to defraud TRAX which was independent of the contract giving
    rise to TRAX’s involvement in the Project. We hold such a duty exists.3
    {¶35} The societal interest in protecting people from fraud is fundamental and
    reflected by the civil and criminal liability imposed for such acts or omissions. Hanamura-
    Valashinas v. Transitions by Firenza, LLC, 11th Dist. Lake No. 2019-L-089, 2020-Ohio-
    4888, ¶37. No societal interest is served by promoting either the concealment of material
    facts with the intent to mislead or the affirmative flow of information not genuinely believed
    by its source to be true. Hence, we hold public policy is best served by acknowledging
    an independent duty not to commit fraud and leaving open the potential of an intentional
    3. It is important to note that the seminal economic loss rule cases cited by appellants concern
    negligence claims, not intentional torts, such as fraud. See Corporex, supra; Floor Craft, supra; Chemtrol
    Adhesives, Inc., supra. In this respect, those cases are factually different than this matter, which alleged
    an intentional tort – a matter outside the economic loss rule to the extent it is premised upon a duty
    independent of the contract at issue.
    15
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    tort suit to loom over a party considering actual fraud. This conclusion is consistent with
    other cases with similar fact patterns. See Eysoldt v. ProScan Imaging, 
    194 Ohio App.3d 630
    , 
    2011-Ohio-2359
    , ¶21 (1st Dist.) (“the economic-loss doctrine does not apply to
    intentional torts.”); Hanamura-Valashinas, supra (wherein this court concluded the
    falsification of billing statements violated a duty independent of the construction
    agreement and so provided grounds for a claim of fraud not barred by the economic-loss
    rule); see also Windsor Med. Ctr., Inc. v. Time Warner Cable, Inc., 5th Dist. Stark No.
    2020CA00085, 
    2021-Ohio-158
    , ¶27 (fraud claims are “exempt” from the economic-loss
    doctrine). We therefore conclude the trial court did not err, as a matter of law, in denying
    the pretrial motion to dismiss; the motion for directed verdict; and its motion for judgment
    notwithstanding the judgment as the economic loss rule did not bar TRAX’s fraud claim.
    {¶36} With the foregoing in mind, appellants suggest the fraud claim was
    improperly premised upon the breach of ethical obligations, which, in their view, cannot
    serve as the basis for imposing an actionable duty of care under the law. Regardless of
    the accuracy of this legal premise, any alleged breach of ethical standards (which were
    addressed at length during Mr. Esser’s and Mr. Lewis’ cross-examination) was not the
    basis of the intentional tort. Rather, as discussed above, the obligation not to commit
    fraud, which the jury determined appellants violated, was the independent source out of
    which liability was premised.
    {¶37} We recognize that TRAX went to great lengths to illustrate how the OHM
    defendants’ acts or omissions violated professional duties; still, this testimony was elicited
    prior to the trial court’s granting appellants’ motion for directed verdict on TRAX’s
    negligence claim. In other words, the testimony may have been initially offered to help
    16
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    establish the OHM defendants were negligent in their management of the Project.
    Because, however, that claim was subsequently dismissed, it was no longer material to
    that theory. Still, the testimony was probative to the extent it served to establish that the
    OHM defendants were not operating above professional reproach throughout their
    administration of the Project. In this respect, the fraud claim was not premised upon an
    ethical duty of disclosure, but evidence of the alleged breach of that duty (or other
    professional obligations) provides evidence of potential fraud. Because the basis of
    liability was the breach of the independent duty not to commit fraud, not the breach of
    professional ethical duties, appellants’ suggestion is without merit.
    {¶38} Finally, appellants further argue that if this court determines the economic-
    loss rule does not bar TRAX’s fraud claims, the professional-design community will suffer
    the peril of significantly increased business-related costs and be exposed to heightened
    litigation risks which, in many cases, could be frivolous. The specter of the slippery slope
    does not dissuade this court’s position.      Fraud is an intentional tort which requires
    heightened pleading requirements and, as with any intentional tort, proof. Furthermore,
    a plaintiff can bring a fraud claim without subverting contract law because the viability of
    such a claim depends only upon a defendant’s conduct, not the type of damage or the
    existence of an underlying contract. In this respect, professional designers need only
    meet the standard of care they owe all clients and adhere to the general duty not to
    defraud in order to avoid exposure to liability. In short, the best way to minimize the costs
    and burdens identified by appellants is to require the party with the best access to
    information to disclose the information.     An otherwise innocent, nonbreaching party
    17
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    should not bear the burden of trying to police potentially deceitful conduct that society, as
    a whole, detests.
    {¶39} Appellants’ first assignment of error lacks merit.
    {¶40} For their second assignment of error, appellants allege:
    {¶41} “The trial court committed reversible error by denying the motion for directed
    verdict (TTr pp 648-649) and the motion for JNOV (10/21/20 journal entry) with respect
    to plaintiff TRAX’s fraud claims because TRAX failed to present competent and credible
    evidence on every essential element.”
    {¶42} Initially, when the court denies a motion for a directed verdict at the close of
    a plaintiff's case-in-chief, the disappointed party must renew the motion at the close of all
    the evidence in order to preserve it for appeal. See Chem. Bank of New York v. Neman,
    
    52 Ohio St.3d 204
    , 207 (1990) (finding that a plaintiff “waived any claim of error in the
    denial of the directed verdict by failing to renew his motion at the close of all evidence”).
    At the close of evidence, the OHM defendants moved for a directed verdict only on the
    Village’s claims against them. They did not renew their motion against TRAX and, in this
    respect, the arguments, as they relate to the trial court’s initial denial of the motion for
    directed verdict are forfeited. Nevertheless, because the arguments asserted in the
    motion for judgment notwithstanding the verdict challenge the same points, namely,
    TRAX’s proof, we shall address them accordingly.
    {¶43} The elements of a claim of fraudulent concealment requires sufficient,
    credible evidence of the following elements:
    {¶44} “(a) a representation or, where there is a duty to disclose, concealment of
    a fact, (b) which is material to the transaction at hand, (c) made falsely, with knowledge
    18
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    of its falsity, or with such utter disregard and recklessness as to whether it is true or false
    that knowledge may be inferred, (d) with the intent of misleading another into relying upon
    it, (e) justifiable reliance upon the representation or concealment, and (f) a resulting injury
    proximately caused by the reliance.” (citation omitted). Groob v. KeyBank, 
    108 Ohio St.3d 348
    , 
    2006-Ohio-1189
    , ¶47.
    {¶45} Appellants first contend there was no fiduciary relationship between the
    OHM defendants and TRAX.               At most, they concede an arm’s-length business
    relationship existed between the parties; this, however, does not rise to a fiduciary
    relationship. While appellants are correct that the parties’ business relationship was not
    a special relationship rising to a fiduciary association, this does not undermine TRAX’s
    proof on the first element of fraud.
    {¶46} Generally, in business transactions, each party is presumed to have the
    opportunity to ascertain relevant facts, and therefore, neither party has an obligation to
    disclose material information to the other. Blon v. Bank One, 
    35 Ohio St.3d 98
    , 101
    (1988). A duty to disclose arises in business dealings, however, when the parties are in
    a fiduciary relationship, both parties to the transaction understand that a special trust or
    confidence has been reposed, or full disclosure is necessary to dispel misleading
    impressions that are or might have been created by partial revelation of the facts. Id.; see,
    also, Word of God Church v. Stanley, 2d Dist. Montgomery No. 07-CV-4467, 2011-Ohio-
    2073, ¶26-27; Gator Dev. Corp. v. VHH, Ltd., 1st Dist. Hamilton No. C-080193, 2009-
    Ohio-1802, ¶28; Levy v. Seiber, 12th Dist. Butler Nos. CA2015-02-019, CA2015-02-021,
    and CA2015-02-030, 
    2016-Ohio-68
    , ¶31. For instance, a party must speak upon failing
    “‘to exercise reasonable care to disclose a material fact which may justifiably induce
    19
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    another party to act or refrain from acting, and the nondisclosing party knows that the
    failure to disclose such information to the other party will render a prior statement or
    representation untrue or misleading.’” State v. Warner, 
    55 Ohio St.3d 31
    , 54, (1990),
    quoting Miles v. McSwegin, 
    58 Ohio St.2d 97
    , 100 (1979)
    {¶47} Furthermore, we recognize that “the mere failure to disclose a fact is not
    equivalent to concealment, which implies a purpose or design.” Jenkins v. Clark, 
    7 Ohio App.3d 93
    , 101 (2d Dist.1982). “Silence[, however,] will constitute a misrepresentation *
    * * if the circumstances are such that the law recognizes a duty to speak.” Schulman v.
    Wolske & Blue Co., L.P.A., 
    125 Ohio App.3d 365
    , 372 (10th Dist.1990); see also Miles,
    supra, at 99 (an action for fraud may be based upon “the failure of a party to a transaction
    to fully disclose facts of a material nature where there exists a duty to speak.”)          Put
    differently, “within the context of the law of fraud, where there is a duty to disclose, silence
    alone may constitute concealment.” PYA/Monarch, Inc. v. Horner, 
    72 Ohio App.3d 791
    ,
    793 (3d Dist.1991). Under the circumstances, the jury could conclude that full disclosure
    was necessary to dispel misleading or false impressions created by partial revelation of
    facts on OHM’s behalf such that a duty to disclose was created. See Stanley, supra.
    {¶48} At trial, although Mr. Hines testified he never assured Mr. Valletto the
    change orders, which occurred as a result of design problems, would be paid, Mr. Valletto
    testified to the contrary. Mayor Alonso testified that if OHM approved payments, the
    Village would pay. As of November 28, 2017, almost a month after the originally
    scheduled completion date, Mr. Valletto stated TRAX had not received any payment.
    And, on December 12, 2017, TRAX again inquired into the processing of payment
    applications; Mr. Hines responded that OHM would only discuss extensions of the
    20
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    completion date and nothing else. Mr. Valletto stated that had he known TRAX would not
    be paid (or, by circumstantial implication, payment would be such a strenuous process),
    it would have stopped work instead of incurring greater expense.
    {¶49} Mr. Esser recognized that, acting as the Project’s manager, OHM owed
    TRAX various duties: “integrity, honor, and the dignity of the engineering profession”; the
    obligation to issue truthful statements; and to deal fairly and honestly and to keep TRAX
    fully informed regarding the Project. Moreover, TRAX continued to work in reliance on
    Mr. Hines’ assurances of payment. It regularly communicated its concern with the lack
    of transparency regarding payment and/or the payment application process. If there were
    issues internal to OHM’s ability to approve the applications, it was obligated to notify
    TRAX or, at least, respond to TRAX’s repeated inquiries regarding payment as well as
    the Project’s overall status.
    {¶50} Also, an email, sent by Mr. Hines (or some agent of OHM) to the
    transitioning project manager in December 2017, stated that the former must speak to the
    latter “verbally” to discuss the Project. This suggests that OHM desired to avoid a “paper
    trail” regarding the Project’s progress and ultimate completion – matters to which TRAX
    never had access (despite numerous inquiries directed at both OHM and the Village) and
    never would have access due to its eventual termination for convenience in favor of a
    third-party contractor, Trimor.    Trimor is a company owned by a friend and former
    business associate of Mr. Esser.
    {¶51} The evidence was sufficient to establish that OHM did not fully and
    accurately disclose the inner-workings of the change order/payment application process,
    yet full disclosure would have dispelled any misleading impressions on behalf of TRAX.
    21
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    There was also sufficient evidence that TRAX could have been terminated for
    convenience much earlier, saving it significant time and resources; instead, due to OHM’s
    failure to disclose material points regarding the Project’s direction and progress as well
    as TRAX’s reliance on Mr. Hines’ representations vis-à-vis payment, it remained on site,
    expecting to complete the work at OHM’s direction. TRAX presented adequate, credible
    evidence to establish OHM misrepresented or concealed facts, material to the Project
    and its work, that were made either falsely or with reckless disregard to the truth or falsity
    and the reasonable inferences that could be drawn from the misrepresentation(s) or
    concealment(s).
    {¶52} Next, appellants contend TRAX failed to establish direct evidence of
    fraudulent intent.
    {¶53} Initially, TRAX was not required to provide direct evidence of intent to
    defraud. Courts have noted that establishing fraudulent intent by direct evidence is
    difficult; as a result, circumstantial evidence may be used to establish intent to defraud.
    Doyle v. Fairfield Mach. Co., 
    120 Ohio App.3d 192
    , 208 (11th Dist.1997); Davis v. Sun
    Refining & Mktg. Co., 
    109 Ohio App.3d 42
    , 56 (2d Dist.1996).
    {¶54} With this in mind, TRAX presented evidence that it sent numerous written
    communications to OHM and the Village; neither OHM nor the Village directly or
    materially responded to TRAX’s concerns regarding payment applications, processing of
    change orders, deadline extensions, or the status of the Project. Although OHM offered
    testimony that on-site, verbal conversations occurred regularly, the substance of these
    conversations is relatively unknown. Furthermore, the letters routinely sought meetings
    with OHM and the Village – only two progress meetings, however, occurred throughout
    22
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    TRAX’s time on the Project. Moreover, Mr. Esser testified he was OHM’s designated
    contractual contact with TRAX as well as the Project Manager; he additionally testified he
    did not agree with TRAX’s representations (in its letters) regarding its concerns that there
    were significant design errors in OHM’s plans.       Still, he did not contact any TRAX
    representative to discuss the matter.
    {¶55} Additionally, TRAX contacted OHM (including Mr. Esser) and stated it was
    concerned with expenses relating to unforeseen delays on the Project and costs
    associated with its idle equipment. And, although Mr. Esser stated he was unsure why
    TRAX could not continue with “other work” during the idle time, he agreed that TRAX was
    entitled to notice that either OHM or the Village did not believe it was entitled to
    compensation for the idle time. No such communication occurred.
    {¶56} Further, eventually, in late December, TRAX notified OHM and the Village
    it considered itself on “indefinite standby” by being forced to finance costs of extra work
    due to delays and other interferences; notwithstanding these remarkable concerns, TRAX
    received no response.     From these points, the jury could infer appellants intended to
    keep information regarding the Project from TRAX and keep it on the Project as long as
    it could without processing its paperwork or financing the additional work or idle time.
    This is a particularly strong inference given that OHM admittedly disagreed with some of
    TRAX’s concerns, but did not reach out, let alone meet with its representatives despite
    multiple requests.
    {¶57} Moreover, during his deposition, Mr. Esser stated he had information on his
    company lap-top and he would provide the same to TRAX. This information, whatever it
    was, was never produced and was ostensibly lost. Even though the content of the
    23
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    information was unknown, TRAX and Mr. Esser were aware of its existence, TRAX was
    told Mr. Esser would produce it, and it was never produced and potentially lost. The jury
    could draw the circumstantial inference that, in light of these and other points, the
    information was intentionally lost.
    {¶58} Additionally, a December 17, 2017 email sent by Mr. Hines to Mr. Tucker,
    after Mr. Tucker was installed as Project Manager, stated the former wished to speak with
    the latter regarding the Project. It also stated, however, that communication should be
    verbal rather than written. The jury could infer that this email was an effort to avoid the
    creation of a paper trail regarding OHM’s strategy regarding further administration of the
    Project. Mr. Hines denied writing the email, but OHM ultimately admitted the message
    came from OHM’s server. In light of OHM’s reluctance to respond to TRAX’s numerous
    letters regarding change orders, payment, delay, and concerns on idle equipment and
    time, this email could be reasonably viewed to show an intent to deceive or conceal
    material information from TRAX regarding its status on the Project.
    {¶59} Regarding TRAX’s justifiable reliance, Mr. Esser, Mr. Lewis, and Mr. Hines
    agreed that TRAX was entitled to rely upon OHM’s designs and representations as well
    as its professional duty to be honest and respond appropriately to TRAX’s written
    concerns. And Mr. Valletto testified Mr. Hines stated TRAX had the right to rely upon
    payment in relation to payment applications and change orders. Although Mr. Hines
    disputed he made any such assurance, the jury was entitled to weigh the testimony and
    elected to believe TRAX’s evidence. There was thus sufficient, credible evidence on the
    element of reasonable and justifiable reliance.
    24
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    {¶60} Finally, appellants claim TRAX failed to establish damages proximately
    resulting from the foregoing elements.          Appellants essentially claim TRAX only
    established “contract damages,” not “fraud damages.” We find this distinction of little
    import.
    {¶61} Initially, TRAX, via its Exhibit 33, provided the following evidence of
    damages:
    {¶62} Outstanding Line Items and Pay:          $65,459.47; Request Discrepancies
    Retainage Owed: $82,852.25; Change Order Amounts Owed: $308,021.27; Claims
    Submitted Including Home Office, Stand-By: $590,218.85; Estimated Interest Owed:
    $15,000.00. These damages totaled $1,061,551.84.
    {¶63} This court has held that even if a plaintiff seeks damages against one party
    for a breach of contract, that plaintiff may still recover against another party in tort, even
    if the damages overlap. Kent State Univ. v. Bradley Univ., 11th Dist. Portage No. 2017-
    P-0056, 
    2019-Ohio-2088
    , ¶78. Specifically, this court, adopting the reasoning of the First
    and Twelfth Appellate Districts, observed “‘“the mere existence of a plaintiff’s inchoate
    cause of action against one party for breach of contract does not foreclose an action in
    tort against another party for all damages suffered by reason of the latter’s inducement of
    such a breach.”’” 
    Id.,
     quoting Ginn v. Stonecreek Dental Care, 12th Dist. Fayette No.
    CA2016-10-014, 
    2017-Ohio-4370
    , ¶16, quoting Davison Fuel & Dock Co. v. Pickands
    Mather & Co., 
    54 Ohio App.2d 177
     (1st Dist.1977). Accordingly, even if the calculated
    damages were initially a function of a breach of contract, they were still recoverable in tort
    to the extent TRAX met its burden that they were also a proximate result of appellants’
    actions.
    25
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    {¶64} Moreover, the trial court instructed the jury that: “There may be more than
    one proximate cause of the damages. The fact that some other cause combined with the
    acts or omissions of a defendant in producing damage does not relieve a defendant from
    liability so long as the plaintiff proves that the conduct of a defendant was a substantial
    factor in producing the harm.” Appellants did not object to this instruction and, because
    it reasonably reflects the law set forth above, we hold TRAX established, by a
    preponderance of the evidence, that the damages were a proximate result of appellants’
    acts or omissions.
    {¶65} Finally, and notwithstanding the foregoing points, appellants cite cases
    which suggest that fraud claims require definitive proof of damages separate from and in
    addition to economic damages attributable to a breach of contract.       See Textron Fin.
    Corp. v. Nationwide Mut. Ins. Co., 
    115 Ohio App.3d 137
    , 150-153 (9th Dist.1996);
    Strategy Group for Media, Inc. v. Lowden, 5th Dist. Delaware No. 12 CAE 03 0016, 2013-
    Ohio-1330, ¶30-31; Dayton Children’s Hosp. v. Garrett Day, LLC., 2d Dist. Montgomery
    No. 28047, 
    2019-Ohio-4875
    , ¶106-107. The first two of these cases involve fraud and
    contract claims against same defendant; and in the third, although various defendants
    were named, the court indicated the plaintiffs were unable to establish an independent
    duty beyond the contract. These cases are therefore not analogous to the instant matter.
    Here, the overlap between TRAX’s breach of contract claim against the Village and fraud
    damages sought against appellants relate to distinct actors and, therefore, the breach of
    contract claim does not bar the damages claimed resulting from appellants’ alleged fraud.
    {¶66} Appellants’ second assignment of error is without merit.
    {¶67} Appellants’ third assignment of error provides:
    26
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    {¶68} “The trial court clearly erred by denying a JNOV (10/21/20 Journal Entry)
    with respect to punitive damages and attorney fees awarded to TRAX because the
    awards were legally untenable and TRAX failed to satisfy the onerous burden of proof.”
    {¶69} When reviewing a ruling on a motion for judgment notwithstanding the
    verdict, we must construe the evidence most strongly in favor of the nonmoving party,
    and where there is substantial evidence to support that side of the case, upon which
    reasonable minds could reach different conclusions, the motion must be overruled.
    Pelletier v. Rumpke Container Serv., 
    142 Ohio App.3d 54
    , 60 (1st Dist.2001). “Neither
    the weight of the evidence nor the credibility of the witnesses is for the court’s
    determination in ruling upon either motion.” 
    Id.
    {¶70} Punitive damages are designed to punish tortfeasors for losses caused by
    actual malice and to deter similar conduct in the future. Whetsone v. Binner, 
    146 Ohio St.3d 395
    , 
    2016-Ohio-1006
    , ¶15. Ohio law is well settled that punitive damages are
    available for personal injury or property loss caused by malice or “‘“intentional, reckless,
    wanton, willful and gross acts.”’” Rubeck v. Huffman, 
    54 Ohio St.2d 20
    , 23 (1978),
    quoting Columbus Fin., Inc. v. Howard, 
    42 Ohio St.2d 178
    , 184 (1975), quoting the
    appellants’ brief. Further, “[a]ttorney fees are proper when the court has awarded punitive
    damages.” Boaeuf v. Memphis Station, L.L.C., 8th Dist. Cuyahoga No. 105799, 2018-
    Ohio-745, ¶15.
    {¶71} The trial court charged the jury accordingly:
    {¶72} “Punitive damages may be awarded against the defendants as a
    punishment to discourage others from committing similar wrongful acts.         You are not
    required to award punitive damages to TRAX Construction Company, and you may not
    27
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    do so unless you find that TRAX Construction Company has met its burden to prove by
    clear and convincing evidence that: (A) Defendants’ actions demonstrated actual malice;
    or (B) Defendants’ actions demonstrated aggravated or egregious fraud.” The instruction
    defined actual malice (a state of mind characterized by hatred, ill will, or a conscious
    disregard for the rights and safety of others which creates the great possibility of
    substantial harm), aggravated fraud (where fraud is accompanied by malice or ill will or if
    it is particularly gross or malicious), and clear and convincing evidence (evidence
    producing in the minds of the jurors a firm belief or conviction about the facts to be
    proved).
    {¶73} Appellants initially claim the punitive damages award fails because TRAX
    failed to establish the requisite proof of fraud. As we previously concluded TRAX met its
    burden on the predicate claim of fraud, appellants’ argument in this respect fails.
    {¶74} The evidence adduced at trial could allow the jury to find, by clear and
    convincing evidence, that appellants willfully, intentionally, or maliciously misrepresented
    or concealed material facts that proximately cause the damages sought. The jury could
    reasonably conclude that OHM kept TRAX on the Project, without transparently
    communicating with it and/or ignoring its entreaties to discuss payment, change orders,
    as well as the Project’s general direction. Appellants draw our attention to allegedly
    misleading arguments made during closing that they claim improperly invited the jury to
    engage in conspiratorial, inferential leaps. As just noted, there was sufficient testimonial
    evidence to support TRAX’s fraud claim and, from this evidence, the jury could have
    reasonably premised its determination that it was entitled to punitive damages, either
    through a finding of actual malice or aggravated fraud. As we may not consider the weight
    28
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    of the evidence or witness credibility when reviewing the denial of a JNOV, we conclude
    TRAX advanced sufficient evidence to support the jury’s award of punitive damages and
    the trial court’s order of attorney fees.
    {¶75} Appellants’ third assignment of error lacks merit.
    {¶76} Appellants’ fourth assignment of error provides:
    {¶77} “The trial court committed reversible error by denying a motion for directed
    verdict (TTr pp 785-786; 1/27/20 Judgment Entry) and a subsequent motion for JNOV
    (10/21/20 Journal Entry) on VOR’s [The Village’s] legally defective cross-claim for
    indemnification.”
    {¶78} Appellants assert the trial court erred in denying its motion for directed
    verdict and its motion for judgment notwithstanding the verdict on the Village’s indemnity
    claim because the jury did not find it liable as a common tortfeasor and, even though it
    was found liable for breach of contract, the jury awarded zero damages. As a result,
    appellants assert their derivative claim for indemnification must fail as a matter of law.
    {¶79} “Indemnity arises from contract, either express or implied, and it is the right
    of a person, who has been compelled to pay what another should have paid, to require
    complete reimbursement.” Worth v. Aetna Cas. & Sur. Co., 
    32 Ohio St.3d 238
    , 240
    (1987). Implied indemnification “‘arises in favor of a person who without any fault on his
    part is exposed to liability and compelled to pay damages on account of the negligence
    or tortious act of another, the former having a right of action against the latter for
    indemnity, provided they are not joint tort-feasors * * *.’” Maryland Cas. Co. v. Frederick
    Co., 
    142 Ohio St. 605
    , 607 (1944), quoting 31 Corpus Juris., 447, Sec. 47.
    29
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    {¶80} First of all, the evidence demonstrated that although the Village and TRAX
    entered into the contract for TRAX to be the underground utility contractor on the Project,
    Mayor Alonso testified the OHM defendants oversaw the Project and dealt directly with
    TRAX. There was no dispute that Mr. Esser was the Project Manager up through
    December 2017 and Mr. Hines was the on-site contact between TRAX and OHM.
    Moreover, the Mayor indicated that all payments the Village owed TRAX were considered
    and approved by OHM prior to the Village releasing payment. Given the factual nature
    of the relationship the Village had with TRAX, the jury’s determination that if the Village
    was found liable for damages relating to the contract, it should be entitled to
    indemnification from OHM is reasonable.
    {¶81} In this matter, the Village is not a joint or common tortfeasor. And, while the
    Village was found liable for breach of contract, the jury concluded that, given the context
    of the case, TRAX suffered no damages that were the natural and probable result of the
    Village’s breach. As such, the Village was responsible for no compensatory or punitive
    damages. Because the Village was deemed to owe TRAX nothing, TRAX cannot pursue
    the Village for damages and, as a result, the Village would never need to exercise its right
    to indemnification. The indemnification verdict, therefore, has no effect. This, however,
    does not imply the trial court erred in denying OHM’s motion for JNOV on the
    indemnification verdict. Simply because the verdict has no practical effect does not mean
    the jury erred in rendering it; it simply means the issue of indemnification, in light of the
    zero damages award, is moot.
    {¶82} As a general matter, courts will not resolve issues that are moot. In re
    Brown, 10th Dist. Franklin No. 03AP-1205, 
    2005-Ohio-2425
    , ¶15. Actions are moot “when
    30
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    they are or have become fictitious, * * * hypothetical, academic or dead. The distinguishing
    characteristic of such issues is that they involve no actual genuine, live controversy, the
    decision of which can definitely affect existing legal relations. * * * ‘A moot case is one
    which seeks to get a judgment on a pretended controversy, when in reality there is none,
    or a decision in advance about a right before it has been actually asserted and contested,
    or a judgment upon some matter which, when rendered, for any reason cannot have any
    practical legal effect upon a then-existing controversy.’” Grove City v. Clark, 10th Dist.
    Franklin No. 01AP-1369, 
    2002-Ohio-4549
    , ¶11, quoting Culver v. Warren, 
    84 Ohio App. 373
    , 393 (7th Dist.1948). The issue identified by OHM is merely academic and presents
    a point which we can offer no meaningful remedy. We therefore conclude the issue raised
    under this assignment of error is moot, and the trial court did not err in denying OHM’s
    motion for JNOV on the Village’s indemnification claim.
    {¶83} Appellants’ fourth assignment of error lacks merit.
    {¶84} Appellants’ final assignment of error provides:
    {¶85} “The trial court committed reversible error by refusing to order a new trial
    (10/21/20 Journal Entry) on TRAX’s fraud claims and VOR’s [the Village’s] indemnity
    cross-claim because the jury verdict was against the great weight of the evidence and
    was the product of instructional error and attorney misconduct.”
    {¶86} Appellants first argue the trial court improperly instructed the jury on TRAX’s
    burden of proof; in their view, the proper standard for civil fraud is “clear and convincing
    evidence,” not the lower, general civil proof of a “preponderance of the evidence.” We do
    not agree.
    31
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    {¶87} “A party seeking an equitable remedy, such as declaratory judgment,
    reformation or rescission of a contract, must prove a fraud claim with clear and convincing
    evidence,   while   a   party   seeking   a    monetary   remedy     must   prove fraud by
    the preponderance of the evidence.” Andrew v. Power Marketing Direct, Inc., 10th Dist.
    Franklin No. 11AP-603, 
    2012-Ohio-4371
    , ¶47, citing Household Finance Corp. v.
    Altenberg, 
    5 Ohio St.2d 190
     (1966), syllabus; see, also, Rider v. Rider, 11th Dist. Trumbull
    No. 98-T-0202, 
    2000 WL 522349
    , *2 (Mar. 31, 2000) (“Since the present case does not
    involve equitable relief but, instead, is an ordinary action at law for money damages based
    upon fraud, the proper standard of proof is ‘preponderance of the evidence.’”). In this
    case, because TRAX sought monetary damages, i.e., a legal remedy, the trial court
    correctly instructed the jury the standard of proof is a “preponderance of the evidence.”
    {¶88} Next, appellants assert the jury’s verdict on TRAX’s fraud claim is against
    the manifest weight of the evidence.
    {¶89} “[A]n appellate court will not reverse a judgment as being contrary to the
    weight of the evidence as long as there is some competent, credible evidence supporting
    the judgment.” In re Kangas, 11th Dist. Ashtabula No. 2006-A-0084, 
    2007-Ohio-1921
    ,
    ¶81. The manifest-weight standard of review is the same in a civil case as in a criminal
    case. Eastley v. Volkman, 
    132 Ohio St.3d 328
    , 
    2012-Ohio-2179
    , ¶17.
    {¶90} When applying the manifest-weight standard of review, the reviewing court
    reviews the entire record, “‘weighs the evidence and all reasonable inferences, considers
    the credibility of witnesses and determines whether in resolving conflicts in the evidence,
    the [finder of fact] clearly lost its way and created such a manifest miscarriage of justice
    that the [judgment] must be reversed and a new trial ordered.’” Id. at ¶20,
    32
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    quoting Tewarson v. Simon, 
    141 Ohio App.3d 103
    , 115, (9th Dist.2001). “The finder of
    fact is entitled to believe all, part, or none of the testimony of any witness.” River Oaks
    Homes, Inc. v. Twin Vinyl, Inc., 11th Dist. Lake No. 2007-L-117, 
    2008-Ohio-4301
    , ¶27.
    {¶91} “Under the manifest weight standard of review, we are ‘guided by a
    presumption’ that the fact-finder’s findings are correct.” Terry v. Kellstone, Inc., 6th Dist.
    Erie No. E-12-061, 
    2013-Ohio-4419
    , ¶13, citing Seasons Coal Co. v. Cleveland, 
    10 Ohio St.3d 77
    , 79-80 (1984). See also Eastley, 
    supra, at ¶21
    . We must make “‘every
    reasonable presumption * * * in favor of the judgment and the finding of facts.’
    ” 
    Id.,
     quoting Seasons Coal Co. at 80, fn. 3. “‘If the evidence is susceptible of more than
    one construction,’” we are “‘bound to give it that interpretation which is consistent with the
    * * * judgment [and] most favorable to sustaining the * * * judgment.’” Eastley,
    
    supra,
     quoting Seasons Coal Co., 
    supra.
    {¶92} As discussed under appellants’ second and fourth assignments of error, the
    jury’s verdicts on TRAX’s fraud count and the Village’s indemnification count are
    supported by sufficient, credible evidence.        OHM, via its representatives, presented
    competing testimony and attempted to explain the reasons why the Project went in a
    direction which led to the underlying suit. The jury was able to evaluate OHM’s, Mr.
    Esser’s, the Village’s and TRAX’s acts and omissions. In doing so, if found OHM and Mr.
    Esser liable for fraud and determined that the Village was entitled to indemnification, to
    the extent such was required. We cannot conclude the jury lost its way or the result of the
    trial resulted in a manifest miscarriage of justice.
    {¶93} Finally, appellants claim TRAX’s counsel and the Village’s counsel
    embraced a “scorched earth” strategy during closing by launching personal attacks on
    33
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    witnesses, creating false flags, asserting baseless conspiracy theories, and requesting
    the jury to draw negative inferences against them. Appellants assert this strategy was
    designed to mislead, influence, and inflame the jury in way that would compel a verdict
    against them. In this respect, appellants contend the jury did not render a verdict based
    upon the evidence, but accepted counsels’ invitation to make its decision on passion and
    bias. We do not agree.
    {¶94} Appellants point to various phrases used by TRAX’s counsel they deem
    troublesome, e.g., “cone of silence,” “missing” flash drive, “snowed fraud in the
    courtroom,” “liar,” and “took advantage of the small guy.” Although counsel may not
    comment on his or her personal belief regarding the evidence, these comments, when
    viewed in relationship to the closing as a whole, do not rise to the level of misconduct.
    Indeed, a review of counsels’ respective closings reveal little in the way of any
    grandstanding or commentary that might be considered unfair or prejudicial. In effect,
    appellants overstate the purported problematic content counsels’ rhetoric and argument
    in closing.
    {¶95} Moreover, appellants assert that TRAX’s counsel improperly asserted Mr.
    Esser engaged in the spoliation of evidence, in violation of a pre-trial motion in limine. In
    closing, counsel does mention that Mr. Esser failed to provide certain evidence that was
    previously on an OHM thumb drive and connects this point to other evidence which
    supported TRAX’s theory that the OHM defendants were fraudulently concealing material
    information from it. Still, no objection was leveled at this line of argument and appellants
    did not renew their motion in limine at trial. It is axiomatic in Ohio that “[a] motion in limine
    is tentative and precautionary in nature, reflecting the court’s anticipatory treatment of an
    34
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008
    evidentiary issue at trial. * * * Finality does not attach when the motion is granted. * * *
    (Citations omitted.)” Defiance v. Kretz, 
    60 Ohio St.3d 1
    , 4 (1991). Thus, “a motion in
    limine is a prospective order and makes no determination as to the ultimate admissibility
    of   the   evidence.” Krosky    v.   Ohio   Edison    Co.,   
    20 Ohio App.3d 10
       (9th
    Dist.1984), paragraph five of the syllabus. As there was no renewed objection, we
    decline to find error in counsels’ angle of argumentation.
    {¶96} “‘“A [party] may freely comment in closing argument on what the evidence
    has shown and what reasonable inferences the [party] believes may be drawn
    therefrom.”’” Torres v. Concrete Designs, 8th Dist. Cuyahoga Nos. 105833 and 106493
    
    2019-Ohio-1342
    , ¶19, quoting Peffer v. Cleveland Clinic Found., 8th Dist. Cuyahoga No.
    94356, 
    2011-Ohio-450
    , ¶27, quoting State v. Clay, 
    181 Ohio App.3d 563
    , 2009-Ohio-
    1235, ¶47 (8th Dist.).    In our view, counsels’ comments during closing were not so
    suspect or inflammatory to justify a finding of misconduct. We therefore conclude that the
    verdict, which was explained via post-trial jury interrogatories, was based not upon
    counsels’ closing, but upon the evidence submitted during the trial.
    {¶97} Appellants’ fifth assignment of error lacks merit.
    {¶98} For the reasons discussed in this opinion, the judgment of the Lake County
    Court of Common Pleas is affirmed.
    MARY JANE TRAPP, P.J.,
    MATT LYNCH, J.,
    concur.
    35
    Case Nos. 2020-L-113, 2020-L-127, 2021-L-008