Cleveland Constr., Inc. v. Ruscilli Constr. Co., Inc. , 2023 Ohio 363 ( 2023 )


Menu:
  • [Cite as Cleveland Constr., Inc. v. Ruscilli Constr. Co., Inc., 
    2023-Ohio-363
    .]
    IN THE COURT OF APPEALS OF OHIO
    TENTH APPELLATE DISTRICT
    Cleveland Construction, Inc.,                          :
    Plaintiff-Appellant,                  :
    No. 18AP-480
    v.                                                     :                          and
    No. 21AP-375
    Ruscilli Construction Co., Inc. et al.,                :                   (C.P.C. No. 16CV-798)
    Defendant-Appellee.                   :              (REGULAR CALENDAR)
    :
    D E C I S I O N
    Rendered on February 8, 2023
    On brief: Daniel R. Wireman, Dinsmore & Shohl LLP, Peter
    J. Georgiton, and Joshua M. Cartee, for appellant. Argued:
    Peter J. Georgiton.
    On brief: Ruscilli Construction Co., Inc., Andrew Fredelake,
    Porter Wright, Morris & Arthur LLP, J. Thomas Nocar, and
    Ryan Sherman, for appellee. Argued: J. Thomas Nocar.
    APPEAL from the Franklin County Court of Common Pleas
    MENTEL, J.
    {¶ 1} Plaintiff-appellant, Cleveland Construction, Inc. ("Cleveland"), appeals from
    the decisions of the Franklin County Court of Common Pleas denying Cleveland's motion
    to partially vacate an arbitration award and granting post-judgment attorneys' fees, costs
    and interests favor of defendant-appellee, Ruscilli Construction Co., Inc. ("Ruscilli"). For
    the reasons that follow, we affirm.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    Nos. 18AP-480 & 21AP-375                                                                      2
    {¶ 2} This appeal arises out of a subcontract for a construction project at the
    Goodale Landing Building in Columbus, Ohio. The structure is owned by Ohio Presbyterian
    Retirement Services Communities ("OPRS"). Ruscilli and Cleveland were hired as the
    project's general contractor and metal stud and drywall subcontractor, respectively. On
    February 17, 2014, Ruscilli and Cleveland entered into a subcontract for Cleveland's work.
    During the course of the project, disputes about performance under the agreement arose
    between Ruscilli and Cleveland.
    {¶ 3} Eventually, Cleveland brought claims of breach of contract, violation of the
    Ohio Prompt Payment Act, foreclosure, and unjust enrichment against Ruscilli. (Jan. 25,
    2016 Compl.) Cleveland alleged that Ruscilli required Cleveland to perform "additional
    work outside the scope" of the parties' agreement, "failed to properly manage the
    construction schedule," and caused delays and inefficiencies on the project. Id. at ¶ 9-13.
    Additionally, Cleveland alleged that Ruscilli did not pay Cleveland for all of its completed
    work. Id. at ¶ 15. Consequently, Cleveland filed a mechanic's lien on the construction
    project to protect its interests. Id. at ¶ 17.
    {¶ 4} Pursuant to Article 6 of the parties' Subcontractor Agreement, which requires
    arbitration of "[a]ny claim arising out of or related to" it, the parties submitted their claims
    to binding arbitration before a three-arbitrator panel ("Panel"). Id., Ex. A at 8. After a nine-
    day arbitration hearing from April 24 to May 5, 2017, the Panel issued an interim
    arbitration award, disposing of all of Cleveland's claims and Ruscilli's counterclaims.
    (Nov. 21, 2017 Mot. to Partially Vacate, Ex. 3 hereinafter "Interim Arbitration Award"). The
    Panel concluded that Cleveland was entitled to an award of $102,271.59, inclusive of pre-
    judgment interest as of June 12, 2017, with interest accruing at $10.82 per day thereafter
    Nos. 18AP-480 & 21AP-375                                                                     3
    until payment.    Id. at 18.   Additionally, the Panel directed Cleveland to release its
    mechanic's lien and bond claim upon Ruscilli's payment of the interim award. Id.
    {¶ 5} In addition to damages related to the contract balance, both Cleveland and
    Ruscilli made claims for attorneys' fees and costs.         For several reasons, the Panel
    determined that Cleveland was not entitled to an award. The Panel noted that, based on its
    findings, Ruscilli "had a good-faith basis to withhold funds from" Cleveland. Id. at 16. The
    Panel also referenced its findings when rejecting Cleveland's assertion that Ruscilli had
    been "vexatious and unreasonable in prosecuting its claims," while nevertheless stating
    that:
    the Panel acknowledges and agrees that some of the tactics
    employed by [Ruscilli] and its counsel, specifically the late
    detailing of its damages, caused problems for [Cleveland's]
    legal team. The Panel has determined [that Cleveland] had the
    ability and opportunity to ameliorate any problem created by
    this late identification through a request for a continuance but
    chose not to do so.
    Id. at 16.
    {¶ 6} Thus, the Panel concluded that Cleveland was "not entitled" to an attorney
    fee award. Id.
    {¶ 7} Regarding Ruscilli's claim for attorneys' fees and costs, the Panel found that
    Section 4.6.3.2 of the parties' agreement supported an award. Id. at 17. The Panel stated
    that "[t]he Parties are two sophisticated commercial entities that entered into a negotiated,
    lengthy Subcontract agreement that included several specific provisions that shifted the
    risk of [Ruscilli's] attorneys' fees and costs onto [Cleveland] in any dispute between the
    Parties." Id. at 16. Accordingly, the Panel directed Ruscilli to file a petition for attorneys'
    fees and costs and allowed Cleveland the opportunity to respond. Id. at 17.
    Nos. 18AP-480 & 21AP-375                                                                     4
    {¶ 8} After reviewing the parties' briefing on the issue, the Panel found that Ruscilli
    was entitled to recover from Cleveland $624,087.45 in attorneys' fees, costs, and expenses.
    (Nov. 21, 2017 Mot. to Partially Vacate, Ex. 5.) The combined effect of the interim
    arbitration award and the final arbitration award was a net award to Ruscilli of
    $521,885.34.
    {¶ 9} On the same day the Panel issued the final arbitration award, Cleveland filed
    suit against OPRS, asserting a claim of tortious interference with a contractual relationship.
    Based on its finding that the "cases stem from the same construction project and involve
    substantially similar parties and related issues," the trial court ordered the cases to be
    consolidated. (Apr. 20, 2018 Decision & Entry.) The trial court also ordered "all future
    filings" to "be filed in both cases," based on its Local Rule 31.02(E)(2). Id.
    {¶ 10} Cleveland also filed a motion under R.C. 2711.10 in the trial court to partially
    vacate the arbitration award, arguing that the Panel exceeded its authority by ignoring a
    notice provision under Article 3.3.2.2 of the parties' subcontract. (Nov. 21, 2017 Mot. to
    Partially Vacate Arbitration Award.) The trial court rejected Cleveland's argument and
    denied the motion, noting that the language Cleveland had cited to support its argument
    actually applied to the Panel's ruling on attorneys' fees. (May 15, 2018 Decision & Entry at
    7.)
    {¶ 11} As the litigation continued, Ruscilli filed several motions to increase its award
    of post-judgment attorney fees, costs and interest. (June 1, 2018 Petition for Post-Jgmt.
    Attorneys' Fees, Costs, and Interest; Oct. 14, 2019 Second Supp.; Mar. 18, 2020 Third
    Supp.) Because Cleveland had not released its mechanic's lien as the arbitrators ordered,
    Ruscilli claimed that it had incurred an additional $12,223 in bond premium payments per
    Nos. 18AP-480 & 21AP-375                                                                      5
    year. Id. at 3. Ruscilli also claimed additional attorneys' fees arising from Cleveland's filing
    of the case against OPRS. Id. at 5.
    {¶ 12} After a hearing, a magistrate concluded that Ruscilli was entitled to recover
    the following from Cleveland: (1) post-judgment interest on the unpaid arbitration award
    in the amount of $59,006.45 as of March 18, 2020; (2) post-judgment attorney fees in the
    amount of $86,805.96 as of March 18, 2020; and (3) bond premium costs in the amount
    of $36,669 for 2018, 2019, and 2020 on the unreleased mechanic's lien. (June 8, 2020
    Mag.'s Decision at 27.) Cleveland filed objections to the decision, but the trial court
    overruled them and adopted the magistrate's decision. (June 30, 2021 Jgmt. Entry.)
    {¶ 13} Cleveland has appealed and asserts the following assignments of error:
    [I.] THE TRIAL COURT ERRED IN FAILING TO VACATE
    THE PORTION OF THE ARBITRATION AWARD IN FAVOR
    OF RUSCILLI CONSTRUCTION, INC.
    [II.] THE TRIAL COURT ERRED IN CONCLUDING THAT
    RUSCILLI CONSTRUCTION IS ENTITLED TO ITS POST-
    ARBITRATION ATTORNEYS' FEES.
    [III.] THE TRIAL COURT ERRED IN CONCLUDING THAT
    RUSCILLII     CONSTRUCTION    IS  ENTITLED   TO
    ATTORNEYS' FEES FOR MONITORING ACTIVITY IN A
    CASE TO WHICH IT WAS NOT A PARTY.
    [IV.] THE TRIAL COURT ERRED IN CONCLUDING THAT
    RUSCILLI CONSTRUCTION IS ENTITLED TO ITS BOND
    PREMIUM PAYMENTS.
    II. STANDARD OF REVIEW
    {¶ 14} A mixed standard of review applies to appellate review of a trial court's
    decision review of an arbitration award under R.C. 2711.10: "when reviewing a decision of
    a common pleas court confirming, modifying, vacating, or correcting an arbitration award,
    an appellate court should accept findings of fact that are not clearly erroneous but decide
    Nos. 18AP-480 & 21AP-375                                                                   6
    questions of law de novo." Portage Cty. Bd. of Dev. Disabilities v. Portage Cty. Educators'
    Assn. for Dev. Disabilities, 
    153 Ohio St.3d 219
    , 
    2018-Ohio-1590
    , ¶ 26. Furthermore, "[t]he
    question whether an arbitrator has exceeded his authority is a question of law." Id. at ¶ 25,
    quoting Green v. Ameritech Corp., 
    200 F.3d 967
    , 974 (6th Cir.2000).
    {¶ 15} The trial court's decision to award post-arbitration attorney fees will be
    reviewed under an abuse of discretion standard. Bittner v. Tri-County Toyota, Inc., 
    58 Ohio St.3d 143
    , 146 (1991). However, its interpretation of the parties' contract as the basis
    for awarding fees and bond payments is reviewed de novo. EAC Properties, L.L.C. v.
    Brightwell, 10th Dist. No. 13AP-773, 
    2014-Ohio-2078
    , ¶ 9, citing Long Beach Assn. v.
    Jones, 
    82 Ohio St.3d 574
    , 576 (1998).
    III. ANALYSIS
    {¶ 16} "Because Ohio law favors and encourages arbitration, courts only have
    limited authority to vacate an arbitrator's award." Fraternal Order of Police Capital City
    Lodge No. 9 v. Reynoldsburg, 10th Dist. No. 12AP-451, 
    2013-Ohio-1057
    , ¶ 22, citing Assn.
    of Cleveland Fire Fighters, Local 93 v. Cleveland, 
    99 Ohio St.3d 476
    , 
    2003-Ohio-4278
     ¶ 13.
    See also Bd. of Trustees v. FOP, Ohio Labor Council, 
    81 Ohio St.3d 269
    , 273 (1998) ("Once
    the arbitrator has made an award, that award will not be easily overturned or modified.").
    R.C. 2711.10 defines the limited authority courts have for vacating an arbitration award.
    Goodyear Tire & Rubber Co. v. Local Union No. 220, United Rubber, Cork, Linoleum &
    Plastic Workers of Am., 
    42 Ohio St.2d 516
     (1975), paragraph two of the syllabus (stating
    that the statute "limits judicial review of arbitration to claims of fraud, corruption,
    misconduct, an imperfect award, or that the arbitrator exceeded his authority").
    {¶ 17} Relevant here is the ground set forth in R.C. 2711.10(D), under which a court
    must vacate an arbitration award if "[t]he arbitrators exceeded their powers, or so
    Nos. 18AP-480 & 21AP-375                                                                    7
    imperfectly executed them that a mutual, final, and definite award upon the subject matter
    submitted was not made." "An arbitrator derives his power from the parties' contract."
    Professionals Guild of Ohio v. Franklin Cty. Children Servs., 
    180 Ohio App.3d 91
    , 2008-
    Ohio-6682, ¶ 13 (10th Dist.). Thus, "an arbitrator exceeds his powers when the award
    conflicts with the express terms of the agreement or cannot be derived rationally from the
    terms of the agreement." Summit Cty. Children Servs. Bd. v. Community Workers, Local
    4546, 
    113 Ohio St.3d 291
    , 
    2007-Ohio-1949
    , ¶ 13, citing Ohio Office of Collective Bargaining
    v. Ohio Civ. Serv. Emp. Assn., Local 11, 
    59 Ohio St.3d 177
     (1991), syllabus. On the other
    hand, where "there is a rational nexus between the agreement and the award, and where
    the award is not arbitrary, capricious or unlawful," the arbitrator's award draws its essence
    from the parties' agreement and will not be vacated under R.C. 2711.10(D). Mahoning Cty.
    Bd. of Mental Retardation & Dev. Disabilities v. Mahoning Cty. TMR Edn. Assn., 
    22 Ohio St.3d 80
     (1986), paragraph one of the syllabus.
    A. First Assignment of Error
    {¶ 18} In the first assignment of error, Cleveland contends that the arbitrators
    exceeded their authority by not recognizing the materiality of Article 3.3.2.2 of the parties'
    agreement, which required Ruscilli to provide "a written compilation -- in other words,
    backup documentation" to support any claim for costs arising from Cleveland's alleged
    failure to perform. (Brief of Plaintiff-Appellant at 28.) Article 3.3.2 states:
    [Ruscilli's] claims for the costs of services or materials provided
    due to [Cleveland's] failure to execute the Work shall require:
    1. seven days' written notice prior t0 [Ruscilli] providing
    services or materials, except in an emergency; and
    2. written compilations to [Cleveland] of services and
    materials provided by [Ruscilli] and charges for such
    services and materials no later than the fifteenth day of the
    Nos. 18AP-480 & 21AP-375                                                                     8
    month following [Ruscilli] providing such services or
    materials.
    (Jan. 25, 2016 Compl., Ex. A at 5.)
    {¶ 19} According to Cleveland, it is "undisputed" that Ruscilli did not comply with
    this provision, which Cleveland claims was "a material term" of the parties' agreement
    under IPS Elec. Servs., LLC v. Univ. of Toledo, 10th Dist. No. 15AP-207, 
    2016-Ohio-361
    .
    (Brief of Plaintiff-Appellant at 28.) Citing page 16 of the Panel's decision, Cleveland states:
    "The arbitration panel acknowledged that documentation detailing Ruscilli's alleged
    damages was not provided until just before the hearing – long after the time required under
    the subcontract." Id. at 28-29.
    {¶ 20} The Panel's award provides no support for Cleveland's assertion that Ruscilli
    ignored any material notice provision of the parties' agreement. The Panel stated that
    Ruscilli "submitted documentation, including numerous notices of default, many of which
    detailed specific defective conditions." (Interim Arbitration Award at 4.) The Panel stated
    that Cleveland "provided little, if any, evidence addressing its responses to the various
    [Ruscilli] notices of default which would demonstrate why those contemporaneous notices
    were somehow incorrect." Id. With regard to Ruscilli's claim for nonconforming drywall,
    the Panel specifically found that Ruscilli "gave proper notice entitling it to repair defective
    work, complete incomplete work, and pay other trades for repairing their work caused by
    [Cleveland's] actions." Id. at 6. The Panel's findings flatly contradict Cleveland's assertion
    that it was "undisputed" that Ruscilli had ignored its obligation to provide notice. The
    findings also demonstrate that the Panel considered such notice requirements integral to
    Ruscilli's claims, thereby undermining Cleveland's argument that the Panel ignored a
    Nos. 18AP-480 & 21AP-375                                                                    9
    material provision of the parties' agreement, which is the entire premise of its position that
    the Panel exceeded its authority under R.C. 2711.10.
    {¶ 21} Moreover, the portion of the Panel's award cited by Cleveland to support its
    claim that the Panel had "acknowledged" that Ruscilli had failed to comply with the notice
    provision appears to refer to the activity of Ruscilli's counsel during discovery or in
    preparation for the hearing, well after the period of time when Ruscilli's claims and
    obligations of notice under the agreement had passed. The Panel recognized that "some of
    the tactics employed by [Ruscilli] and its counsel, specifically the late detailing of its
    damages, caused problems for [Cleveland's] legal team," but concluded that Cleveland
    nevertheless "had the ability and opportunity to ameliorate any problem created by this late
    identification through a request for a continuance but chose not to do so." (Interim
    Arbitration Award at 16.) The Panel also stated that it relied on the foregoing findings to
    reject Cleveland's argument that Ruscilli "was vexatious and unreasonable in prosecuting
    its claims." Id. The only plausible interpretation of these events is that they occurred
    during litigation, not during the construction project.
    {¶ 22} Finally, as the trial court noted, this discussion appears in the context of the
    Panel's analysis of whether Ruscilli was entitled to attorneys' fees, not the substance of the
    parties' claims. (May 15, 2018 Decision & Entry at 7.) After its "review of the arbitrators'
    award," the trial court concluded that "it did not depart from the essence of the
    subcontract." Id. at 5. In this appeal, Cleveland has presented no compelling challenge to
    the trial court's conclusion that the award draws its essence from the parties' agreement.
    Furthermore, Cleveland has failed to identify the absence of a rational nexus between the
    agreement and the award or any basis to indicate that the award was arbitrary, capricious,
    Nos. 18AP-480 & 21AP-375                                                                     10
    or unlawful. Accordingly, the trial court did not err by refusing to vacate the award under
    R.C. 2711.10(D). The first assignment of error is overruled.
    B. Second & Third Assignments of Error
    {¶ 23} In its second assignment of error, Cleveland contends that the trial court
    erred in concluding that Ruscilli is entitled to its post-arbitration attorneys' fees. When
    awarding post-arbitration attorneys' fees to Ruscilli, the trial court relied on Article 4.6.3.2
    of the Supplementary Conditions to the parties' subcontract. Article 4.6.3.2 provides:
    4.6.3 To the fullest extent permitted by law, [Cleveland] shall
    indemnify and hold harmless [Ruscilli] from and against
    claims, damages, losses and expenses, including but not
    limited to its actual attorneys' fees incurred, arising out of or
    resulting from performance of Subcontract. This indemnity
    shall include, but not be limited to the following:
    ***
    4.6.3.2. The prosecution of any claim by [Ruscilli] against
    [Cleveland] or an[y] of its subcontractors or suppliers for
    breach of contract, negligence or defective work.
    4.6.3.3. Any action, whether in prosecution or defense, relating
    to or arising from the filing or removal of any mechanic's lien
    filed by [Cleveland] or any of its subcontractors, suppliers, or
    laborers.
    4.6.3.4. The defense of any claim asserted by [Cleveland]
    against [Ruscilli] whether for additional compensation, breach
    of contract, negligence, or any other cause.
    (June 30, 2021 Jgmt. Entry at 5.)
    {¶ 24} Cleveland argues that "post-arbitration proceedings do not 'arise out of or
    result from performance of the Subcontract' " as stated in Section 4.6.3, and that the
    provision does not specifically "provide for the recovery of fees in post-judgment
    proceedings."     (Brief of Plaintiff-Appellant at 35.)     Cleveland also argues that the
    description of "any claim * * * for breach of contract, negligence, or defective work" limits
    Nos. 18AP-480 & 21AP-375                                                                      11
    the indemnification the fee-shifting clause otherwise provides. Id. at 37. Cleveland does
    not challenge the reasonableness of the fee amount as calculated, but whether the
    agreement itself authorizes them.
    {¶ 25} The default "American Rule" requires each party to pay its own attorney fees
    in litigation, but three exceptions to the rule exist: a statute authorizing attorney fees, a
    finding of bad faith conduct by one party, or a fee-shifting provision in the parties'
    agreement. Orth v. State, 10th Dist. No. 14AP-937, 
    2015-Ohio-3977
    , ¶ 12. In this case, the
    parties' agreement contains a fee-shifting provision in favor of Ruscilli.
    {¶ 26} When applying this provision, the trial court did not abuse its discretion by
    awarding Ruscilli attorney fees in post-arbitration proceedings challenging the arbitrator's
    award. The agreement broadly required Cleveland to indemnify Ruscilli "from and against
    claims, damages, losses and expenses, including but not limited to its actual attorneys' fees
    incurred, arising out of or resulting from performance of Subcontract." This language does
    not limit the indemnification to arbitration proceedings. Parties may expressly contract to
    limit attorney fees to arbitration, but that is not the case here. For example, in Handel's
    Ent. v. Wood, 7th Dist. No. 04 MA 238, 
    2005-Ohio-6922
    , ¶ 106, a party unsuccessfully
    moved the trial court for attorney fees incurred during the post-arbitration confirmation
    proceeding, citing a fee-shifting provision stating that the "costs and expenses of
    arbitration, including the fees of the arbitrators, shall be borne by the losing party or in such
    proportions as the arbitrators shall determine." The Seventh District affirmed the decision
    refusing to award attorney fees, noting that "the words 'costs and expenses of arbitration'
    only address the arbitration and not the confirming of that arbitration award." Id. at ¶ 107.
    Here, the parties' agreement placed no similar limitation on Cleveland's obligation to
    indemnify Ruscilli.
    Nos. 18AP-480 & 21AP-375                                                                   12
    {¶ 27} Nor do the subsections following the main indemnification clause limit its
    scope, as Cleveland suggests. They are introduced by stating that Cleveland's "indemnity
    shall include, but not be limited to," the examples provided, which do not limit the scope of
    indemnity. Cleveland believes they should be limited, citing the "principle of construction
    known as ejusdem generis [that] requires that a general phrase following an enumeration
    of specific items includes only things of the same nature as those items which were
    specified." Direct Carpet Mills Outlet, Inc. v. Amalgamated Realty Co., 10th Dist. No.
    87AP-101, 
    1988 Ohio App. LEXIS 3349
    , *8 (Aug. 11, 1988). However, "while firmly
    established as an interpretive rule, the ejusdem generis rule 'is only an instrumentality for
    ascertaining the correct meaning of words when there is uncertainty.' " Gabbard v.
    Madison Local School Dist. Bd. of Edn., 
    165 Ohio St.3d 390
    , 
    2021-Ohio-2067
    , ¶ 27, quoting
    United States v. Powell, 
    423 U.S. 87
    , 91 (1975). Cleveland does not argue that the language
    is ambiguous. Like the trial court, we consider it clear.
    {¶ 28} In addition, the language of the indemnification does not contain a general
    phrase following an enumeration of specific items such as the language discussed in Direct
    Carpet Mills Outlet, Inc., which concerned an insurance exclusion defined as "damages for
    water, fire, explosion, wind or accident of any kind" and limited the exclusion to " things
    similar in nature to fire, explosion, and wind," excluding negligence. Direct Carpet Mills
    Outlet, Inc. at *8. In contrast, the first paragraph of the parties' indemnification provision
    expressly states that "indemnity shall include, but not be limited to" the examples that
    follow. Brown v. Creative Restaurants, Inc., W.D.Tenn. No. 11-2710-STA-cgc, 
    2013 U.S. Dist. LEXIS 189927
    , *15 (Feb. 19, 2013) (holding that esjudem generis did not apply where
    unambiguous statute prefaced examples with the phrase "including without limitation").
    Nos. 18AP-480 & 21AP-375                                                                      13
    Thus, even if the agreement were ambiguous, we are not convinced that the canon of
    construction Cleveland points to would apply.
    {¶ 29} As the trial court noted, once Cleveland filed the motion to vacate the
    arbitration award, "Ruscilli necessarily needed to defend the[] claims by Cleveland" to
    defend the award. (June 30, 2021 Jgmt. Entry at 6.) The trial court did not err when
    concluding that the provision required it to indemnify Ruscilli for attorneys' fees incurred
    in the post-arbitration proceeding.
    {¶ 30} Finally, the trial court did not abuse its discretion when awarding attorney
    fees to Ruscilli's attorneys when performing work on the consolidated case. When arguing
    for consolidation of the cases, ORPS argued that both actions arose out of the parties'
    subcontract and Cleveland's "filing of a second action, even under a different legal theory,
    [was] improper claim splitting." (Sept. 20, 2017 Mot. to Consolidate Cases at 2.) Cleveland
    did not oppose the motion. When ordering consolidation, the trial court ruled that the cases
    "stem from the same construction project and involve substantially similar parties and
    related issues." (Apr. 20, 2018 Decision & Entry at 2.) Because of breadth of the
    indemnification provision, once the consolidation was in effect, Cleveland should have been
    aware that it was potentially liable for any of Ruscilli's attorney fees in the consolidated
    case. Even before initiating the ancillary litigation with OPRS, this potential liability was
    clear. The second and third assignments of error are overruled.
    C. Fourth Assignment of Error
    {¶ 31} In the final assignment of error, Cleveland contends the trial court erred in
    concluding that Ruscilli is entitled to its bond premium payments. Cleveland asserts that
    it has a right to file a lien to protect its interests, pursuant to R.C. 1311.01, et seq., Ohio's
    mechanic's lien law. (Brief of Plaintiff-Appellant at 42. ) According to Cleveland, because
    Nos. 18AP-480 & 21AP-375                                                                   14
    there is no "statutory authority for assessing bond premium payment as costs," the trial
    court erred by awarding them to Ruscilli.
    {¶ 32} The trial court did not rely on any statutory authority when ordering the
    payment of Ruscilli's bond premium payments. Rather, it relied upon Section 4.6.3 of the
    parties' agreement, which required Cleveland to indemnify Ruscilli for any "claims,
    damages, losses and expenses" that included "[a]ny action, whether in prosecution or
    defense, relating to or arising from the filing or removal of any mechanic's lien filed by
    [Cleveland] or any of its subcontractors, suppliers, or laborers." (June 30, 2021 Jgmt. Entry
    at 5.)
    {¶ 33} Cleveland's sole argument against the trial court's decision to enforce this
    language is that the Panel chose not to order it to reimburse Ruscilli for bond premium
    payments in the original arbitration award. (Brief of Plaintiff-Appellant at 41.) This
    argument does not address the language of the indemnification provision itself, which
    expressly recognizes Ruscilli's entitlement to compensation. Furthermore, it is doubtful
    that the Panel could have foreseen Cleveland's refusal to not comply with its order to release
    the lien for years after issuing its award. As the trial court noted, timely compliance with
    the Panel's order "would have prevented Ruscilli from continuing to incur the bond
    premium payments," but it made "the conscious choice not to release the mechanic's lien."
    (June 30, 2021 Jgmt. Entry at 7.) By choosing not to release the mechanic's lien, Cleveland
    caused Ruscilli to continue incurring bond claim premiums beyond September 6, 2017. The
    trial court's award limits Ruscilli's recovery to the bond premiums incurred after Cleveland
    consciously chose to ignore the arbitration panel's orders. These additional costs are a
    direct result of Cleveland's decision to ignore the Panel's orders. The fourth assignment of
    error is overruled.
    Nos. 18AP-480 & 21AP-375                                                        15
    IV. CONCLUSION
    {¶ 34} Having overruled Cleveland's four assignments of error, we affirm the
    judgment of the Franklin County Court of Common Pleas.
    Judgment affirmed.
    BEATTY BLUNT, P.J. and KLATT, J., concur.
    _________________