New Riegel Local School Dist. Bd. of Edn. v. Bueherer Group Architecture & Eng., Inc. , 2019 Ohio 5040 ( 2019 )


Menu:
  • [Cite as New Riegel Local School Dist. Bd. of Edn. v. Bueherer Group Architecture & Eng., Inc., 2019-
    Ohio-5040.]
    IN THE COURT OF APPEALS OF OHIO
    THIRD APPELLATE DISTRICT
    SENECA COUNTY
    NEW RIEGEL LOCAL SCHOOL
    DISTRICT, BOARD OF EDUCATION,
    CASE NO. 13-17-03
    PLAINTIFF-APPELLANT,
    -and-
    STATE OF OHIO,
    PLAINTIFF-APPELLEE,
    v.
    OPINION
    THE BUEHRER GROUP
    ARCHITECTURE & ENGINEERING,
    INC., ET AL.,
    DEFENDANTS-APPELLEES.
    NEW RIEGEL LOCAL SCHOOL
    DISTRICT, BOARD OF EDUCATION,
    CASE NO. 13-17-04
    PLAINTIFF-APPELLANT,
    -and-
    STATE OF OHIO,
    PLAINTIFF-APPELLEE,
    v.
    OPINION
    THE BUEHRER GROUP
    ARCHITECTURE & ENGINEERING,
    INC., ET AL.,
    DEFENDANTS-APPELLEES.
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    NEW RIEGEL LOCAL SCHOOL
    DISTRICT, BOARD OF EDUCATION,
    CASE NO. 13-17-06
    PLAINTIFF-APPELLANT,
    -and-
    STATE OF OHIO,
    PLAINTIFF-APPELLEE,
    v.
    OPINION
    THE BUEHRER GROUP
    ARCHITECTURE & ENGINEERING,
    INC., ET AL.,
    DEFENDANTS-APPELLEES.
    Appeal from Seneca County Common Pleas Court
    Trial Court Nos. 15 CV 0115
    Judgment Affirmed
    Date of Decision: December 9, 2019
    APPEARANCES:
    Christopher L. McCloskey and Tarik Kershah for Appellant
    Gregory D. Brunton and Allison R. Thomas for The Buehrer Group
    Architecture & Engineering, Inc.
    Marc A. Sanchez for Ohio Farmers Insurance Company
    Shannon J. George and Matthew T. Davis for Studer-Obringer, Inc.
    P. Kohl Schneider, Colleen A. Mountcastle and Melanie R. Irvine for
    Charles Construction Services, Inc.
    -2-
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    WILLAMOWSKI, J.
    {¶1} These appeals are before this court upon remand from the Ohio
    Supreme Court. New Riegel Local School Dist. Bd. of Education v. Buehrer Group
    Architecture & Engineering, Inc., et al., 
    157 Ohio St. 3d 164
    , 2019-Ohio-2851, 
    133 N.E.3d 482
    . Plaintiff-appellant New Riegel Local School District Board of
    Education (“the School”) brought this appeal from the judgment of the Court of
    Common Pleas of Seneca County granting the judgment on the pleadings filed by
    defendants-appellants the Buehrer Group Architecture & Engineering, Inc. (“the
    Group”), Studer-Obringer, Inc. (“SOI”), Charles Construction Services, Inc.
    (“CCS”), and Ohio Farmers Insurance Company (“OFIC”). For the reasons set forth
    below, the judgments are affirmed.
    {¶2} This case arises from the construction of a new Kindergarten through
    12th Grade School Facility Project (“the Project”) built as part of the Ohio Classroom
    Facilities Assistance Program. Doc. 2. As a result of the Project, the School entered
    into contracts with multiple contractors starting in February of 2000. 
    Id. The Group
    contracted with the School to provide professional design services for the Project.
    SOI contracted with the school to serve as the general trades contractor for the
    Project. 
    Id. CCS contracted
    with the school to serve as the roofing contractor for
    the Project. The School began occupying the school building on December 19,
    -3-
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    2002, Doc. 88, Ex. K. The State issued a Certificate of Completion transferring all
    of the interest of the State in the Project to the School on March 3, 2004. Doc. 24.
    {¶3} Over time, the School had issues with the facilities, including but not
    limited to condensation and moisture intrusion allegedly caused by design and
    construction errors. Doc. 2. A complaint was filed by the School on April 30, 2015.
    
    Id. The complaint
    was brought in the name of the School with the State of Ohio
    and OSFC as involuntary plaintiffs. 
    Id. The complaint
    named the Group, SOI,
    CCS, and American Buildings Company, among others, as defendants. 
    Id. The complaint
    alleged in Count One that the Group breached its contract by failing to
    perform in accord with professional standards by failing “to properly design the
    roofing system and through-wall flashing system for the Project in a manner which
    prevented moisture intrusion, heat loss, and condensation related issues, [failing] to
    properly observe and report its findings related to defective work, [failing] to make
    appropriate recommendations for repair and improvement, and [failing] to comply
    with all state and local statutory requirements.” 
    Id. at 7.
    The complaint also alleged
    that both SOI and CCS had breached its contract by failing to conform to the
    requisite standard of care to perform in a workmanlike manner. Doc. 2. The Group,
    SOI, and CCS filed answers denying the allegations in the complaint and listing
    several affirmative defenses, including the statute of repose. Doc. 21, 34, and 35.
    On February 10, 2016, the School filed an amended complaint raising the same
    alleged breach of contract claims against the Group, SOI, and CCS as the first
    complaint did. Doc. 62. The Group, SOI and CCS all filed answers to the amended
    -4-
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    complaint raising the same affirmative defenses. Doc. 65, 67, and 68. The Group
    and SOI filed motions for judgment on the pleadings pursuant to Civil Rule 12(C).
    Doc. 70 and 71. Both claimed that the claims raised by the School were time-barred
    by the statute of repose as set forth in R.C. 2305.131(A)(1). 
    Id. The School
    filed
    memoranda in opposition to these motions. Doc. 73 and 79.
    {¶4} The School then filed a second amended complaint on June 10, 2016.
    Doc. 88. This complaint added OFIC as a defendant as the surety for SOI, but did
    not make any changes to the claims against SOI, the Group, or CCS. 
    Id. The Group
    ,
    SOI, CCS, and OFIC all filed answers to the second amended complaint Doc. 93,
    99, 102, 113. The Group and SOI then renewed their respective motions for
    judgment on the pleadings pursuant to Civil Rule 12(C). Doc. 95 and 108. On
    August 24, 2016, the trial court granted the Group’s and SOI’s motions for judgment
    on the pleadings. Doc. 116 and 117. These judgments were based upon the statute
    of repose as set forth in R.C. 2305.131. 
    Id. {¶5} After
    the trial court had granted both SOI’s and the Group’s motions
    for judgment on the pleadings based upon the statute of repose, CCS filed its own
    motion for judgment on the pleadings also based upon the statute of repose. Doc.
    124. On October 31, 2017, the trial court granted CCS’s motion for judgment on
    the pleadings. Doc. 129. Likewise, OFIC filed a motion for judgment on the
    pleadings on September 6, 2016. Doc. 119. OFIC argued that since SOI was
    dismissed, OFIC was no longer liable as the surety for SOI and must also be
    dismissed. 
    Id. The School
    filed its response to OFIC’s motion on September 9,
    -5-
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    2016. Doc. 120. In the same entry that granted CCS’ motion for judgment on the
    pleadings, the trial court also granted OFIC’s motion for judgment on the pleadings
    and both parties were dismissed. Doc. 129.
    {¶6} On January 25, 2017, the School filed notices of appeal from these
    judgments of dismissal. Doc. 134, 137, and 143. The judgment dismissing SOI was
    assigned appellate case number 13-17-03. The judgment dismissing OFIC and CCS
    was assigned appellate case number 13-17-06. The dismissal of the Buehrer Group
    was assigned appellate case number 13-17-04. On appeal, these cases were all
    reversed on the grounds that pursuant to the holding of the Ohio Supreme Court in
    Kocisko v. Charles Shutrump & Sons Co., et al., 
    21 Ohio St. 3d 98
    , 
    488 N.E.2d 171
    (1986), the statute of repose did not apply to a breach of contract case, only those
    based in tort. 
    Id. at 99.
    Since the causes of action in the cases before us, when read
    in a light most favorable to the School, were based upon breaches of contract claims,
    this Court determined it had no choice but to follow Supreme Court precedent and
    find the statute of repose to be inapplicable. See New Riegel Local School Dist. Bd.
    of Education, et al. v. The Buehrer Group Architecture & Engineering, Inc., et al.,
    3d Dist. Seneca Nos. 13-17-03, 13-17-04, and 13-17-06, 2017-Ohio-8522 and 2017-
    Ohio-8521. SOI, CCS, the Group, and OFIC appealed these holdings to the Ohio
    Supreme Court. On July 17, 2019, the Ohio Supreme Court reversed this Court and
    remanded the matter to us on the grounds that stare decisis no longer compelled this
    Court to apply the holding in Kocisko to these claims. Thus, the matter is remanded
    for us to review.
    -6-
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    {¶7} On remand, this Court will address the following relevant assignments
    of error from the School.1
    First Assignment of Error
    The trial court erred in dismissing [the School’s] breach of
    contract claims against [SOI], [CCS], and [The Group], by
    finding that the Ohio Statute of Repose, R.C. 2305.131, barred
    [the School’s] claims for breach of contract.
    Second Assignment of Error
    The trial court erred in dismissing the claims against [SOI] and
    [CCS] as those contracts were entered with [the State] and
    general limitations periods do not apply to the State of Ohio.
    ***
    Fourth Assignment of Error
    The trial court erred in dismissing [the School’s] claims against
    [OFIC], as surety for [SOI], on the basis that [the School’s] surety
    bond claim against [OFIC] was barred by the virtue of the
    dismissal of the claims against [SOI].
    {¶8} In the first assignment of error, as it applies to SOI, CCS, and the
    Group, the School claims that the trial court erred in dismissing with prejudice the
    claims against those parties. The dismissal was granted by the trial court pursuant
    to the statute of repose which limits actions for damages based upon defective and
    unsafe conditions in improvements to real property.
    (A)(1) Notwithstanding an otherwise applicable period of
    limitations specified in this chapter or in section 2125.02 of the
    Revised Code and except as otherwise provided in divisions
    (A)(2), (A)(3), (C), and (D) of this section, no cause of action to
    1
    The third assignment of error was dealt with in appellate case number 13-17-05 and is not before this
    court on remand.
    -7-
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    recover damages for bodily injury, an injury to real or personal
    property, or wrongful death that arises out of a defective and
    unsafe condition of an improvement to real property and no cause
    of action for contribution or indemnity for damages sustained as
    a result of bodily injury, an injury to real or personal property,
    or wrongful death that arises out of a defective and unsafe
    condition of an improvement to real property shall accrue against
    a person who performed services for the improvement to real
    property or a person who furnished the design, planning,
    supervision of construction, or construction of the improvement
    to real property later than ten years from the date of substantial
    completion of such improvement.
    ***
    (G) As used in this section, “substantial completion” means the
    date the improvement to real property is first used by the owner
    or tenant of the real property or when the real property is first
    available for use after having the improvement completed in
    accordance with the contract or agreement covering the
    improvement, including any agreed changes to the contract or
    agreement, whichever occurs first.
    R.C. 2305.131.
    {¶9} The School argued that the statute of repose does not apply because
    they are bringing suit for breach of contract, not for a tort and the statute of repose
    does not apply to breach of contract claims. In support of this argument the School
    cites to 
    Kocisko supra
    , which held that the statute of repose did not apply in that
    case because it was a breach of contract case, not a tort case and the statute of repose
    does not apply to a breach of contract case.2 However, the Supreme Court of Ohio
    2
    This court notes that the case was based upon a prior version of R.C. 2305.131 that is no longer in effect,
    but that the relevant language is quite similar to the current version.
    -8-
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    recently held that Kocisko is not applicable in this case and that the statute did apply.
    New 
    Riegel, supra
    , 2019-Ohio-2851 at ¶ 21-23.
    {¶10} R.C. 2305.131 specifies that no cause of action for damages to real
    property, resulting from the improvement to that real property, can be brought after
    10 years from the time the improvements were substantially completed. The School
    is trying to collect damages resulting from an improvement, i.e. the Project, to real
    property. The School began occupying the building in 2002 and the Certificate of
    Completion was issued in 2004. The School did not file its complaint until 2015,
    which exceeds the ten year time limit set forth in the statute. The statute specifically
    prohibits this. Thus, it would appear that the statute specifically prohibits the filing
    of the claims in this case.
    {¶11} The Supreme Court of Ohio has held that the statute of repose “applies
    to civil actions commenced after the effective date of the statute regardless of when
    the cause of action accrued.” Oaktree Condominium Assn., Inc. v. Hallmark Bldg.
    Co., 
    139 Ohio St. 3d 264
    , 2014-Ohio-1937, ¶ 8, 
    11 N.E.3d 266
    . The plain language
    of R.C. 2305.131(A), cuts off liability for injuries arising out of defective conditions
    of an improvement to real estate that are brought more than ten years after the
    substantial completion of the improvement. Substantial completion is defined as
    the date when the owner of the property first uses the property after the
    improvements are completed. Even if we view this date in a light most favorable to
    the School and use the date of the certificate of completion, which was March 3,
    2004, the complaint was not filed until April 30, 2015. This is more than ten years
    -9-
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    after the latest possible date of substantial completion. For that reason, the first
    assignment of error is overruled.
    {¶12} The School argues in its fourth assignment of error that the trial court
    erred in dismissing OFIC as surety for SOI. A surety’s liability “is dependent upon,
    and can be no greater than, that of the principal.” State v. Herbert, 
    49 Ohio St. 2d 88
    , 
    358 N.E.2d 1090
    (1976). If the claim against the principal is barred by the
    statute of repose, then the claim against the surety is barred as well. Bd. of
    Education of Tuslaw Local School Dist. v. CT Taylor Co., Inc., 5th Dist. Stark No.
    2018CA00099, 2019-Ohio-1731, ¶ 33. Having determined that the trial court
    correctly granted judgment on the pleadings based upon the statute of repose, there
    are no longer any outstanding claims against SOI. The result of this is that the claim
    against OFIC, as the surety of SOI, must also fail. The trial court did not err in
    dismissing OFIC and the fourth assignment of error is overruled.
    {¶13} In the second assignment of error, the School argues that the trial court
    erred in dismissing the claims pursuant to the statute of repose because the contracts
    were entered with the State and the limitation does not apply to the State. This court
    has already determined that the State is not a party to this matter. New Riegel Local
    School Dist., Bd. of Education v. Buehrer Group Architecture & Engineering, Inc.,
    et al., 3d Dist. Seneca No. 13-17-05, 2017-Ohio-8523, ¶ 7. In that opinion, this
    Court stated that there was a contract between the State of Ohio and the School
    which permitted the School to act as a limited agent of the State and bind the State
    to the necessary contracts to build the new facility. 
    Id. at ¶
    6. However, this limited
    -10-
    Case Nos. 13-17-03, 13-17-04 and 13-17-06
    agency ended when the State issued the Certificate of Completion. 
    Id. The Certificate
    of Completion “specified that the School was solely responsible for the
    ownership and management of the property, specifically any enforcement of
    warranties and guarantees associated with the project.” 
    Id. Thus, this
    court held
    that the State was not a real party in interest and was properly dismissed from the
    case, leaving only the School as the plaintiff. 
    Id. {¶14} The
    State and the School are not the same entity, thus the same rules
    do not apply to the School as would apply to the State. A school district is a political
    subdivision, not a State entity. R.C. 2744.01(F). The School does not argue and
    points to no authority which would permit it to have sovereign immunity from the
    statute of repose as a political subdivision. This Court has found no such authority.
    Since the School is not entitled to claim the sovereign immunity of the State, in this
    case, the second assignment of error is overruled.
    {¶15} Having found no error prejudicial to the Appellant in the particulars
    assigned and argued, the judgments of the Court of Common Pleas of Seneca
    County are affirmed.
    Judgments Affirmed
    ZIMMERMAN, P.J. and SHAW, J., concur.
    /hls
    -11-
    

Document Info

Docket Number: 13-17-03, 13-17-04, 13-17-06

Citation Numbers: 2019 Ohio 5040

Judges: Willamowski

Filed Date: 12/9/2019

Precedential Status: Precedential

Modified Date: 12/9/2019