Colosseo USA, Inc. v. Univ. of Cincinnati , 2019 Ohio 2026 ( 2019 )


Menu:
  • [Cite as Colosseo USA, Inc. v. Univ. of Cincinnati, 2019-Ohio-2026.]
    IN THE COURT OF APPEALS
    FIRST APPELLATE DISTRICT OF OHIO
    HAMILTON COUNTY, OHIO
    COLOSSEO USA, INC.,                               :          APPEAL NO. C-180223
    TRIAL NO. A-1703142
    Plaintiff-Appellant,                      :
    vs.                                             :              O P I N I O N.
    UNIVERSITY OF CINCINNATI,                         :
    Defendant-Appellee.
    :
    Civil Appeal From: Hamilton County Court of Common Pleas
    Judgment Appealed From Is: Affirmed
    Date of Judgment Entry on Appeal: May 24, 2019
    Stites & Harbison PLLC, William G. Geisen and Andrew J. Poltorak, for Plaintiff-
    Appellant,
    Brickler & Eckler LLP, Jeffrey P. McSherry and Mark E. Evans, for Defendant-
    Appellee.
    OHIO FIRST DISTRICT COURT OF APPEALS
    MYERS, Presiding Judge.
    {¶1}    Colosseo, USA, Inc., (“Colosseo”) appeals the trial court’s judgment
    granting the motion of the University of Cincinnati (“UC”) to dismiss for lack of
    subject-matter jurisdiction Colosseo’s claims for a declaratory judgment stemming
    from UC’s award of a contract for the replacement of a video scoreboard at UC’s
    Nippert Stadium to another bidder, and for other future projects.
    Background
    {¶2}    In February 2017, UC issued a Request for Proposal (“RFP”) that
    sought proposals from vendors for an integrated videoboard and digital signage
    system for six of UC’s athletic facilities, including Nippert Stadium, Fifth Third
    Arena, Schott Stadium, Gettler Stadium, Keating Natatorium, and Sheakley Athletic
    Center. The RFP made clear that awards for each of the facilities would be made
    separately as funding became available.
    {¶3}    Four vendors submitted responses to the RFP. On April 11, 2017, UC
    notified two of them, Colosseo and Daktronics, Inc., that they were the vendors
    under primary consideration and that UC would contact each of them to schedule a
    final interview.
    {¶4}    Before the final interview, UC notified Colosseo and Daktronics that
    the interview would be focused solely on the replacement of the scoreboard for
    Nippert Stadium. Then UC asked them to submit supplemental proposals limited to
    that scoreboard.
    {¶5}    Colosseo and Daktronics submitted supplemental proposals for only
    the replacement of the Nippert Stadium scoreboard. After reviewing both proposals,
    UC’s outside consultant and UC’s review committee recommended that the contract
    for the Nippert Stadium scoreboard project be awarded to Daktronics.
    2
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶6}   On May 11, 2017, UC advised Colosseo and Daktronics that the
    contract for the replacement of the Nippert Stadium scoreboard was awarded to
    Daktronics.   UC informed Colosseo that, even though it did not win the award for
    Nippert Stadium, Colosseo was selected as one of two firms qualified to bid on the
    remaining projects.
    {¶7}   Accordingly, UC issued a term contract that identified Colosseo and
    Daktronics as approved vendors who were qualified to participate in the replacement
    of scoreboards for the facilities identified in the RFP. The term contract specified
    that each of the athletic-facility projects would “be individually bid, scored, and
    awarded.” The contract stated that it was not an “exclusive” commitment, and
    contemplated the possibility of “multiple awards.” In addition, the contract specified
    that “[c]ontractors may be added and assignments may be changed.”
    {¶8}   On May 12, 2017, UC issued a purchase order to Daktronics for the
    Nippert Stadium scoreboard replacement, requiring installation to be completed by
    the end of August 2017, the date of the first home game for UC’s football team.
    {¶9}   On June 12, 2017, Colosseo filed a complaint for a temporary
    restraining order, preliminary injunction, and permanent injunction to enjoin UC
    from proceeding on the Nippert Stadium scoreboard replacement project and on any
    other work related to the RFP. In addition, Colosseo sought a declaratory judgment
    that the Nippert Stadium contract with Daktronics was void because in awarding the
    contract to Daktronics, UC had violated Ohio’s competitive-bidding laws, UC’s
    competitive-bidding rules established by its board of trustees, and the standards set
    forth in the RFP. It argued that it was the lowest and best bidder for both the
    Nippert Stadium contract and for the contract awarded under the RFP, and that the
    contract for the RFP should be awarded solely to Colosseo.
    {¶10} Simultaneously, Colosseo moved for a temporary restraining order and
    a preliminary injunction to enjoin UC from continuing work related to the Nippert
    3
    OHIO FIRST DISTRICT COURT OF APPEALS
    Stadium scoreboard project. UC responded that the contract for the procurement of
    the scoreboard involved the purchase of goods and services and was not a public-
    improvement contract subject to competitive-bidding laws and rules.
    {¶11} Following a hearing on June 16, 2017, the trial court denied Colosseo’s
    motion for a temporary restraining order and a preliminary injunction. The court
    reasoned that Colosseo was unlikely to succeed on the merits because the contract
    for the Nippert Stadium project was a goods and services contract not subject to
    competitive-bidding laws and rules. In addition, the court found that Colosseo had
    not demonstrated that it would suffer irreparable harm if the requested relief was
    denied because it was still an approved vendor for the other five projects. The court
    also found that any injury suffered by Colosseo would not outweigh the potential
    harm to UC, and that the public interest would not be served by an award of
    injunctive relief. Colosseo did not appeal the denial of its motion for a temporary
    restraining order and a preliminary injunction.
    {¶12} In mid-July 2017, UC filed an answer, a motion to stay discovery, and
    a motion for judgment on the pleadings. After an August hearing, the trial court
    issued a written decision in September denying both motions.
    {¶13} The case progressed and the parties proceeded with written discovery.
    In January 2018, UC filed a motion to dismiss for lack of subject-matter jurisdiction,
    or, in the alternative, for reconsideration of its earlier motion for judgment on the
    pleadings, arguing that the Nippert Stadium scoreboard replacement was now
    complete and contracts for the remaining projects had not yet been awarded.
    {¶14} The trial court granted UC’s motion and dismissed the action. The
    court determined that, with respect to the Nippert Stadium scoreboard replacement
    project, no further controversy existed for the court to decide, and no meaningful
    relief could be granted to Colosseo. The court dismissed Colosseo’s claims relating to
    the remaining athletic facilities for lack of subject-matter jurisdiction, concluding
    4
    OHIO FIRST DISTRICT COURT OF APPEALS
    that they were not ripe for review and that no justiciable controversy existed.
    Colosseo appeals the trial court’s judgment.
    1. Dismissal of the Action
    {¶15} In its first assignment of error, Colosseo argues that the trial court
    erred by granting UC’s motion to dismiss for lack of subject-matter jurisdiction.
    {¶16} Where a trial court has resolved a declaratory-judgment action by
    determining that no justiciable controversy exists, we review the determination for
    an abuse of discretion. Arnott v. Arnott, 
    132 Ohio St. 3d 401
    , 2012-Ohio-3208, 
    972 N.E.2d 586
    , ¶ 13; Waldman v. Pitcher, 2016-Ohio-5909, 
    70 N.E.3d 1025
    , ¶ 17 (1st
    Dist.). Reversal is therefore warranted only if the trial court’s decision regarding
    justiciability was unreasonable, arbitrary, or unconscionable. Waldman at ¶ 17. A
    decision is unreasonable where it is not supported by a sound reasoning process. 
    Id. {¶17} A
    common pleas court’s subject-matter jurisdiction is constitutionally
    limited to “justiciable matters.”   Ohio Constitution, Article IV, Section 4(B).    A
    justiciable matter exists for purposes of a declaratory-judgment action where a real
    controversy exists between adverse parties and speedy relief is necessary to preserve
    the parties’ rights. Moore v. Middletown, 
    133 Ohio St. 3d 55
    , 2012-Ohio-3897, 
    975 N.E.2d 977
    , ¶ 49. A declaratory-judgment action does not authorize a court to
    render an advisory opinion. See Arnott at ¶ 10, quoting Mid-American Fire & Cas.
    Co. v. Healey, 
    113 Ohio St. 3d 133
    , 2007-Ohio-1248, 
    863 N.E.2d 142
    , ¶ 9.
    {¶18} To be justiciable, the danger or dilemma to a party’s position must be
    present, and not merely possible or remote. Arnott at ¶ 10. The controversy must be
    ripe for judicial review, so it “cannot be dependent on the occurrence or
    nonoccurrence of future events.” William Powell Co. v. Onebeacon Ins. Co., 2016-
    Ohio-8124, 
    75 N.E.3d 909
    , ¶ 47 (1st Dist.); Keller v. Columbus, 
    100 Ohio St. 3d 192
    ,
    5
    OHIO FIRST DISTRICT COURT OF APPEALS
    2003-Ohio-5599, 
    797 N.E.2d 964
    , ¶ 26.           A case is not yet ripe if “it rests on
    contingent future events that may not occur as anticipated or may never occur at all.”
    Ohio Renal Assn. v. Kidney Dialysis Patient Protection Amendment Comm., 
    154 Ohio St. 3d 86
    , 2018-Ohio-3220, 
    111 N.E.3d 1139
    , ¶ 12, citing State v. Loving, 
    180 Ohio App. 3d 424
    , 2009-Ohio-15, 
    905 N.E.2d 1234
    (10th Dist.).
    {¶19} It is well settled that a court’s role is to “decide actual controversies by
    a judgment which can be carried into effect.” Cyran v. Cyran, 
    152 Ohio St. 3d 484
    ,
    2018-Ohio-24, 
    97 N.E.3d 487
    , ¶ 12, quoting Miner v. Witt, 
    82 Ohio St. 237
    , 238, 
    92 N.E. 21
    (1910).     A case becomes moot when an event occurs that renders it
    impossible for the court to grant the requested relief; “under such circumstances,
    there is no longer a ‘live’ issue that demands resolution.” Ohio Renal Assn. at ¶ 12,
    citing State ex rel. Gaylor, Inc. v. Goodenow, 
    125 Ohio St. 3d 407
    , 2010-Ohio-1844,
    
    928 N.E.2d 728
    , ¶ 11. “In a construction-related case, if an unsuccessful bidder
    seeking to enjoin the construction of a public-works project fails to obtain a stay of
    the construction pending judicial resolution of its claims challenging the decision,
    and construction commences, the unsuccessful bidder’s action will be dismissed as
    moot.” Gaylor at ¶ 11.
    A. Nippert Stadium
    {¶20} After the trial court denied Colosseo’s request for a temporary
    restraining order and a preliminary injunction, Colosseo did not appeal the denial of
    its motion for injunctive relief.1 And UC moved forward on the Nippert Stadium
    project. When UC filed its January 2018 motion to dismiss for lack of subject-matter
    jurisdiction or, in the alternative, for reconsideration of its motion for judgment on
    the pleadings, UC had completed the Nippert Stadium project.
    1We make no determination as to whether the trial court’s order was immediately appealable.
    Rather, we point out that as a factual matter, no appeal was taken.
    6
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶21} Ohio law is clear that the only remedy generally available to a rejected
    bidder under a public contract situation is injunctive relief. Cementech, Inc. v.
    Fairlawn, 
    109 Ohio St. 3d 475
    , 2006-Ohio-2991, 
    849 N.E.2d 24
    , ¶ 10.             This is
    because the rejected bidder cannot recover lost profits as damages. 
    Id. at ¶
    14.
    {¶22} In some circumstances, the rejected bidder may, however, be able to
    recover reasonable bid-preparation costs in the Court of Claims, which has exclusive,
    original jurisdiction over civil suits seeking money damages against the state even
    where injunctive or declaratory relief is also sought. See Meccon, Inc. v. Univ. of
    Akron, 
    126 Ohio St. 3d 231
    , 2010-Ohio-3297, 
    933 N.E.2d 231
    , ¶ 18-19. To recover its
    bid-preparation costs, the rejected bidder must establish that a public authority
    violated state competitive-bidding laws in awarding a public-improvement contract,
    and that the bidder promptly sought, but was denied, injunctive relief and it is later
    determined that the bidder was wrongfully rejected and injunctive relief is no longer
    available. 
    Id. at ¶
    13.
    {¶23} But, once a rejected bidder’s request for preliminary injunctive relief
    has been denied and work begins on a public-improvement project, “the rejected
    bidder will not be able to perform the public contract even if the bidder demonstrates
    that its bid was wrongfully rejected.” 
    Id. at ¶
    12, citing Cementech at ¶ 13. In those
    circumstances, “the wrongfully rejected bidder is left with no remedy for the public
    authority's unlawful conduct, and injunctive relief will no longer serve to deter the
    public authority’s unlawful conduct.” 
    Id. at ¶
    13.
    {¶24} In this case, therefore, even if UC violated state competitive-bidding
    laws in awarding the Nippert Stadium scoreboard contract, once Colosseo’s request
    for injunctive relief was denied and the work on the project commenced or was
    completed, there was no longer any remedy or injunctive relief that the trial court
    could have awarded to Colosseo. Accordingly, we hold that the trial court did not
    abuse its discretion in determining that there was no further controversy to decide
    7
    OHIO FIRST DISTRICT COURT OF APPEALS
    and no meaningful relief that the court could have granted to Colosseo with respect
    to the Nippert Stadium project.
    B. The Remaining Athletic Facilities
    {¶25} The RFP made clear that awards for each of the athletic facilities would
    be made separately as funding became available. Because a declaratory judgment as
    to the remaining facilities was contingent upon the occurrence of future events, i.e.,
    the securing of funding for each award for each facility, the actual award of the work,
    and the possibility of future agreements, the action was not ripe for judicial review.
    {¶26} Accordingly, we hold that the trial court did not abuse its discretion in
    determining that no justiciable controversy yet existed as to the remaining projects.
    Therefore, the trial court did not err by dismissing the action. We overrule the first
    assignment of error.
    2. Reconsideration of Trial Court’s Earlier Ruling
    {¶27} In its second assignment of error, Colosseo argues that the trial court
    erred to the extent that it reconsidered or modified its earlier decision denying UC’s
    motion for judgment on the pleadings.               The denial of the original motion for
    judgment on the pleadings was a not a final order,2 so the trial court retained
    jurisdiction to reconsider its earlier ruling. See Othman v. Bd. of Edn., 1st Dist.
    Hamilton Nos. C-160878 and C-170187, 2017-Ohio-9115, ¶ 12. We overrule the
    second assignment of error.
    2Generally, the denial of a motion for judgment on the pleadings is not a final, appealable order.
    See Buchanan v. Ohio Dept. of Rehab. and Corr., 10th Dist. Franklin No. 18AP-970, 2019-Ohio-
    1423, ¶ 8; Steinbrink v. Greenon Local School Dist., 2d Dist. Clark No. 11CA0050, 2012-Ohio-
    1438, ¶ 16. An exception exists if the denial is based on political-subdivision immunity. See
    Supportive Solutions, L.L.C. v. Electronic Classroom of Tomorrow, 
    137 Ohio St. 3d 23
    , 2013-
    Ohio-2410, 
    997 N.E.2d 490
    , ¶ 14.
    8
    OHIO FIRST DISTRICT COURT OF APPEALS
    Conclusion
    {¶28} Having overruled both assignments of error, we affirm the judgment of
    the trial court.
    Judgment affirmed.
    CROUSE and WINKLER, JJ., concur.
    Please note:
    The court has recorded its own entry on the date of the release of this opinion.
    9
    

Document Info

Docket Number: C-180223

Citation Numbers: 2019 Ohio 2026

Judges: Myers

Filed Date: 5/24/2019

Precedential Status: Precedential

Modified Date: 5/24/2019