Riley v. Hawley , 2011 Ohio 4422 ( 2011 )


Menu:
  • [Cite as Riley v. Hawley, 2011-Ohio-4422.]
    COURT OF APPEALS
    ASHLAND COUNTY, OHIO
    FIFTH APPELLATE DISTRICT
    TIM RILEY                                    :
    :
    Plaintiff-Appellant                  :
    :
    -vs-                                         :
    :
    JOEL HAWLEY                                  :
    :
    Defendant-Appellee                   :
    JUDGES:
    Hon. W. Scott Gwin, P.J.
    Hon. Sheila G. Farmer, J.
    Hon. Julie A. Edwards, J.
    Case No. 11-COA-010
    OPINION
    CHARACTER OF PROCEEDING:                         Appeal from the Municipal Court, Case No.
    10-CVI-01443
    JUDGMENT:                                        Judgment Vacated; New Judgment Entered
    DATE OF JUDGMENT ENTRY:                          August 30, 2011
    APPEARANCES:
    For Plaintiff-Appellant                     For Defendant-Appellee
    TIM RILEY, PRO SE                           JOEL HAWLEY, PRO SE
    4525 Gibbs Road                             309 Country Road 40
    Norwalk, OH 44857                           Sullivan, OH 44880
    Farmer, J.
    {¶1}   On October 13, 2010, appellant, Tim Riley, filed a complaint against
    appellee, Joel Hawley, alleging breach of contract. The parties had entered into an oral
    contract wherein appellant was to provide architectural work and obtain a building
    permit for a property appellee was contracted to work on.        Appellant alleged that
    appellee owed him $2,640.90 for services rendered.
    {¶2}   On November 9, 2010, appellee filed a counterclaim, alleging that he had
    to spend $2,995.00 to remedy appellant's errors.
    {¶3}   A hearing before a magistrate was held on November 17, 2010.           By
    decision filed January 20, 2011, the magistrate found against appellant on his complaint
    and for appellee on his counterclaim. Appellant filed objections. By judgment order
    filed March 9, 2011, the trial court approved and adopted the magistrate's decision and
    awarded appellee $2,995.00.
    {¶4}   Appellant filed an appeal and this matter is now before this court for
    consideration. Assignment of error is as follows:
    I
    {¶5}   "THE TRIAL COURT ERRED BY AWARDING THE INCORRECT
    AMOUNT OF DAMAGES IN FAVOR OF APPELLEE HAWLEY."
    I
    {¶6}   Appellant claims the trial court erred in its determination of damages as it
    did not apply the correct legal standard in awarding damages. We agree in part.
    {¶7}   A judgment supported by some competent, credible evidence will not be
    reversed by a reviewing court as against the manifest weight of the evidence. C.E.
    Morris Co. v. Foley Construction Co. (1978), 
    54 Ohio St. 2d 279
    . A reviewing court must
    not substitute its judgment for that of the trial court where there exists some competent
    and credible evidence supporting the judgment rendered by the trial court. Myers v.
    Garson, 
    66 Ohio St. 3d 610
    , 1993-Ohio-9.
    {¶8}   As explained by our brethren from the Ninth District in McKinley v. Brandt
    Construction, Inc., 
    168 Ohio App. 3d 214
    , 2006-Ohio-3290, ¶10:
    {¶9}   "Any contract to perform work imposes on the contractor the duty to
    perform the work in a workmanlike manner. Lin v. Gatehouse Constr. Co. (1992), 
    84 Ohio App. 3d 96
    , 101, 
    616 N.E.2d 519
    . ' "Workmanlike manner" has been defined as
    the way work is customarily done by other contractors in the community.' Jones v.
    Davenport (Jan. 26, 2001), 2nd Dist. No. 18162, at 8, 
    2001 WL 62513
    , citing Salewsky
    v. Williams (Sept. 17, 1990), 5th Dist. No. CA-8131, at 4, 
    1990 WL 139731
    . When a
    contractor fails to perform in a workmanlike manner, the proper measure of damages is
    the cost to repair the damage to the condition contemplated by the parties at the time of
    the contract. McCray v. Clinton Cty. Home Improvement (1998), 
    125 Ohio App. 3d 521
    ,
    523-524, 
    708 N.E.2d 1075
    ."
    {¶10} Appellant stated he drew and submitted plans and obtained the required
    building permit in partial performance of the contract. T. at 3. Appellant argues the
    work performed enabled appellee to secure the permit and therefore he should be paid
    in full. In support of his position, appellant presented Plaintiff's Exhibit C, a copy of the
    check he wrote to pay for the permit ($100.00).            T. at 5.    In the magistrate's
    determination of damages, as approved and adopted by the trial court, there was no
    acknowledgment of this cost:
    {¶11} "Based upon all of the evidence, the Magistrate finds that the Plaintiff is
    not entitled to recover any monies from the Defendant. The work he was contracted to
    do was done in an unworkmanlike manner and was not fit for the purpose for which it
    was intended. It ended up requiring Defendant to hire another architect to complete the
    work and fix the errors, and also cost him money. Defendant is not required to pay for
    these services.
    {¶12} "The Magistrate finds that Defendant is entitled to recover the amount of
    $2995.00 from Plaintiff for the damages he incurred as a result of relying upon the faulty
    work done by Plaintiff. The evidence establishes that the work was done with errors
    and deficiencies and that as a direct result, Defendant incurred costs of $2995.00.
    Therefore, the Magistrate finds that the Defendant is entitled to judgment in the amount
    of $2995.00 against the Plaintiff, with interest thereon at the statutory rate of 4 percent
    per annum until paid, plus costs.
    {¶13} "The Plaintiff's claim should be dismissed with costs taxed to Plaintiff."
    {¶14} It was appellee's position that appellant did not have that much to do to
    obtain the building permit. T. at 7. Once the permit was procured, mistakes were
    discovered in the plans. T. at 8. Appellant was contacted to make the necessary
    corrections, but he never did them. T. at 8-9, 21. As a result of following the plans, a
    required retention pond was oversized and had to be corrected.                T at 10, 17;
    Defendant's Exhibit A. Appellee had to provide new plans, and paid $425.00 to an
    architectural group for the work. T. at 9; Defendant's Exhibits B. The total cost for the
    architectural work and to fix the pond amounted to $2,995.00. T. at 13; Defendant's
    Exhibit D. It was appellee's opinion that sixty percent of what appellant drew had to be
    redone. T. at 22.
    {¶15} The trial court awarded appellee damages on his counterclaim pursuant to
    Defendant's Exhibit D which included the amounts for the redesign and reconstruction
    of the pond.
    {¶16} We find the evidence is sufficient to support the trial court's determination
    on the costs for repairs as a result of appellant's unsatisfactory plans. However, we
    also find the trial court erred in not crediting appellant for the $100.00 permit he
    obtained which was used to perform the work. Pursuant to App.R. 12(C), we hereby
    adjust the judgment to appellee to $2,895.00 to reflect the $100.00 permit fee.
    {¶17} The sole assignment of error is granted in part.
    {¶18} The judgment of the Municipal Court of Ashland County, Ohio is hereby
    vacated, and judgment is entered for appellee as against appellant in the amount of
    $2,895.00.
    By Farmer, J.
    Gwin, P.J. and
    Edwards, J. concur.
    _s/ Sheila G. Farmer______________
    __s/ W. Scott Gwin___________________
    _Julie A. Edwards___________________
    JUDGES
    SGF/sg 816
    IN THE COURT OF APPEALS FOR ASHLAND COUNTY, OHIO
    FIFTH APPELLATE DISTRICT
    TIM RILEY                                   :
    :
    Plaintiff-Appellant                  :
    :
    -vs-                                        :         JUDGMENT ENTRY
    :
    JOEL HAWLEY                                 :
    :
    Defendant-Appellee                   :         CASE NO. 11-COA-010
    For the reasons stated in our accompanying Memorandum-Opinion, the
    judgment of the Municipal Court of Ashland County, Ohio is vacated, and judgment is
    entered for appellee as against appellant in the amount of $2,895.00.
    s/ Sheila G. Farmer______________
    __s/ W. Scott Gwin___________________
    _Julie A. Edwards___________________
    JUDGES
    

Document Info

Docket Number: 11-COA-010

Citation Numbers: 2011 Ohio 4422

Judges: Farmer

Filed Date: 8/30/2011

Precedential Status: Precedential

Modified Date: 10/30/2014