Acme Co. v. Saunders TopSoil ( 2011 )


Menu:
  • [Cite as Acme Co. v. Saunders TopSoil, 2011-Ohio-6423.]
    STATE OF OHIO, MAHONING COUNTY
    IN THE COURT OF APPEALS
    SEVENTH DISTRICT
    THE ACME COMPANY,                                )
    )        CASE NO. 10 MA 93
    PLAINTIFF-APPELLEE,                      )
    )
    - VS -                                   )               OPINION
    )
    SAUNDERS & SONS TOPSOIL,                         )
    )
    DEFENDANT-THIRD-PARTY                    )
    PLAINTIFF-APPELLANT,                     )
    )
    - VS. -                                  )
    )
    R & J TRUCKING, INC., et al.,                    )
    )
    THIRD-PARTY DEFENDANTS                   )
    -APPELLEES.                              )
    CHARACTER OF PROCEEDINGS:                                 Civil Appeal from Common Pleas
    Court, Case No. 08 CV 4435.
    JUDGMENT:                                                 Affirmed.
    APPEARANCES:
    For Plaintiff-Appellee:                                   No Brief Filed.
    For Defendant-Third-Party
    Plaintiff-Appellant:                                      Attorney Robert E. Duffrin
    7330 Market Street
    Youngstown, OH 44512
    Attorney Scott C. Essad
    5815 Market Street, Suite 1
    Youngstown, OH 44512
    For Third-Party Defendants-Appellees:                     No Brief Filed.
    JUDGES:
    Hon. Mary DeGenaro
    Hon. Cheryl L. Waite
    Hon. Joseph J. Vukovich
    Dated: December 7, 2011
    [Cite as Acme Co. v. Saunders TopSoil, 2011-Ohio-6423.]
    DeGenaro, J.
    {¶1}    Defendant-Appellant, Saunders & Sons Topsoil, appeals the decision of the
    Mahoning County Court of Common Pleas, awarding judgment to Plaintiff-Appellee, the
    Acme Company, in the amount of $6,249.89 and awarding $1.00 in nominal damages to
    Saunders for conversion damages. Saunders asserts that the trial court erred when it
    only awarded nominal damages after finding that Acme had converted Saunders's topsoil.
    Saunders also alleges that the court erred when it awarded judgment to Acme for unjust
    enrichment and for the amount in R & J Trucking, Inc.'s accounts receivable. The four
    arguments are meritless.
    {¶2}    First, Saunders did not prove lost profits damages with reasonable certainty
    because it failed to provide any evidence as to its costs in processing the topsoil, and the
    sale price of the topsoil appeared to be speculative.          Second, Saunders did not
    sufficiently prove conversion damages because its evidence regarding the amount and
    value of the unprocessed topsoil was speculative. Third, Acme adequately set forth a
    claim for unjust enrichment, and fourth, R & J properly assigned its right to payment under
    the contract to Acme, thus Acme can recover those damages. Accordingly, the judgment
    of the trial court is affirmed.
    Facts and Procedural History
    {¶3}    In June of 2006, Canfield High School was removing its natural grass
    football field and installing artificial turf. David Mosure, an engineer for the project,
    contacted John Saunders of Saunders & Sons Topsoil and told Saunders that he could
    have the topsoil excavated from the football field for free if he removed the soil from the
    field. According to Saunders, Mosure suggested that Saunders use R & J to haul the soil
    because R & J was working on the project.
    {¶4}    Saunders spoke with Mark Carrocce of R & J and agreed on an hourly price
    to remove the topsoil from the field. Saunders also contacted Jeff Schrum and made
    arrangements to store the topsoil at Schrum's property. The topsoil needed to be
    removed from the football field over a two day period, and Saunders told Carrocce that he
    would supply one truck on Saturday and two trucks on Sunday and that only three
    additional trucks from R & J would be needed. Carrocce contacted Daniel Zarlenga,
    president of Acme Company, and Zarlenga agreed to supply three trucks to help R & J
    -2-
    haul the soil. According to Zarlenga, he determined that six trucks were needed to
    remove the topsoil in the two-day timeframe.
    {¶5}   On June 17, 2006, the work began to transport the topsoil from the Canfield
    football field to Schrum's property.    Acme and R & J each brought three trucks.
    According to Saunders, he informed Carrocce that only three trucks were needed, but
    Carrocce replied that they would see how things went. Saunders claims that at the end of
    the day, he told Carrocce to bring only three trucks on Sunday and Carrocce agreed. On
    June 18, 2006, Acme and R & J again each brought three trucks to complete the job.
    {¶6}   Saunders received bills from both Acme and R & J for transporting the
    topsoil, but due to the disagreement over the number of trucks, he did not pay either bill.
    In June of 2007, Acme removed the topsoil from Schrum's property and transported it to
    its own property.
    {¶7}   Acme filed a complaint in county court against Saunders alleging two
    claims; first, that it provided services to Saunders in the amount of $3,849.25 and
    attached an invoice to Saunders for its services; and second, that R & J had provided
    services to Saunders in the amount of $3,078.01, and Acme purchased the receivable of
    R & J which Saunders had refused to pay. The case was transferred to common pleas
    court on November 6, 2008 because Saunders’s counterclaim and third-party complaint
    exceeded the county court’s jurisdictional amount.
    {¶8}   On November 12, 2008, Saunders filed an amended answer and
    counterclaim in the common pleas court. Saunders admitted that Acme had demanded
    payment and Saunders refused, but it denied the rest of the allegations.             In its
    counterclaim, Saunders asserted four claims. First, that R & J breached its implied duty
    of good faith and fair dealing, rendering the contract unenforceable, and that Acme, as
    assignee, has no greater rights to enforce the contract than R & J. Second, that Acme
    removed Saunders's topsoil without its permission, and Saunders demanded the soil be
    returned but Acme refused. Third, that Acme converted its property, and finally, that
    Acme was unjustly enriched. Saunders also asserted third-party claims against Schrum
    and R & J, but those claims are not a part of this appeal. Saunders prayed that the court
    dismiss Acme's complaint with prejudice and prayed for judgment on its counterclaim and
    -3-
    third-party complaint for, inter alia, $50,000.
    {¶9}   On February 25, 2007, Saunders was granted leave to file a second
    amended complaint. In 2009, the parties filed reciprocal motions for summary judgment
    which were denied.      On January 25, 2010, Saunders filed a motion to amend its
    counterclaim to change each prayer for relief from demanding $50,000 to a demand "in
    excess of $25,000."
    {¶10} On January 26, 2010, the court issued a subpoena to Dan Zarlenga of
    Acme to give testimony at trial and bring the following documents:
    {¶11} "1) All records relating to the sale of any topsoil from The Acme Company,
    including purchase price and how many cubic yards were sold during the past two
    calendar years * * *.
    {¶12} "2) Records related to the payment of employees or contractors regarding
    the trucking and removal of soil from property owned by Jeff T. Schrum for the last two
    calendar years (2009 & 2008.)"
    {¶13} A bench trial to the magistrate commenced January 26, 2010. Daniel
    Zarlenga testified that regarding the Canfield football field project, Acme donated their
    time and handled excavation of the topsoil from the field. Zarlenga explained that he did
    not contract with Carrocce regarding removing the soil from the field, but rather, it was a
    community project. He had no contact with Saunders before he sent him a bill for the job;
    he let Carrocce coordinate the conditions of payment with Saunders.
    {¶14} Zarlenga testified that the topsoil he excavated from the field had roots,
    grass, and plastic drains in it. He did not have time to remove the debris in the soil to
    attempt to salvage it. The soil had no value to him because of all the contaminants in it
    and because there was an abundance of soil in the marketplace. On cross, Zarlenga
    clarified that the soil was worthless unless it was screened, cleaned and processed.
    Then the soil's value is whatever it can be sold for at the time. Zarlenga further testified
    that he sells unprocessed topsoil out of his yard for $1-$2 a ton, and he sells processed,
    screened, and shredded topsoil for $10-$11, but that he had sold "very, very little" cubic
    yards of topsoil in the last two years. Regarding the shelf life of topsoil, he testified that
    -4-
    unprocessed topsoil does not spoil if is piled, covered, and seeded. Although topsoil was
    a small segment of his business, Zarlenga understood the different grades of soil. The
    soil removed from the Canfield football field was unprocessed, excavation soil, which is a
    low grade that needed to be screened to remove the plastic, shredded, and sterilized,
    which costs money. He stated that the excavation soil was worth what it costs to haul it
    away.
    {¶15} Zarlenga explained that Plaintiff’s Exhibit 7 was a determination of how
    many cubic yards of soil would need to be removed from the Canfield football field. He
    had calculated that they would remove between 1,900 and 2,500 cubic yards of soil, but
    estimated that they actually removed about 2,100 cubic yards from the field.
    {¶16} Zarlenga stated that his three-axle trucks can carry between 11 and 14
    cubic yards of topsoil. He said that he did not keep track of the loads that his trucks
    made when removing the soil from the football field, and although there were tally marks
    on the trip tickets, the drivers might forget to put a mark down for each load. He said that
    there was no requirement for them to keep load counts. He further explained that the
    tally marks were not useless, but they might be plus or minus a load or two. Zarlenga
    confirmed it was a fair assessment that the tally marks on the trip tickets are between 90
    and 100 loads. Zarlenga stated that the trip tickets were used for payroll records and for
    billing the customer, and that the tickets recorded the total hours the driver worked.
    {¶17} Zarlenga identified Plaintiff's Exhibit 14 as an invoice to Saunders for hourly
    trucking at Canfield High School, which was made the following week of the job. He said
    that the invoice was sent to Saunders, but Saunders never paid nor contacted him about
    the invoice. He said that his own correspondence went through Carrocce, but he thought
    that after six or seven months, Acme may have made a couple calls to Saunders in an
    attempt to get paid.
    {¶18} Zarlenga testified that in the summer of 2007, Schrum was going to build
    pole barns on the land where the soil was sitting and had contacted Zarlenga to borrow a
    roller. Zarlenga told him that the topsoil was in the way, and Schrum said that he was
    trying to get it off the property, but it was moving very slowly. Zarlenga said that
    Saunders had not paid him for trucking the soil and that he would move it, assuming the
    -5-
    soil was Schrum's property because it was on his land. He also testified that Saunders
    had his shredder and screening plant on Schrum's property and was processing soil on
    the premises.
    {¶19} Zarlenga hauled the topsoil away to his yard at the cost to remove it and
    added it to a pile where he dumped topsoil when he did excavation and would later sell
    the soil on a commercial or industrial project. He further testified that if he considered the
    soil to have any value when he did the project, he would have taken it himself. He
    testified that he did not want the soil because it had no value to him; he said that he
    already had an abundant pile of topsoil and did not need it. However, on cross, he
    stated, "[t]he expense of loading the dirt and hauling it away, I didn't get paid for that, too.
    And the pay was I got the damn dirt. That's all I got. So, yeah, I didn't make nothing on
    that and I still had an unpaid bill."
    {¶20} Zarlenga testified that it took two afternoons to haul the soil off of Schrum's
    property in June of 2007. He did not recall how many trucks he used and stated that he
    did have trip tickets for that. He confirmed that he received a subpoena indicating to
    bring his records with him; however, he did not bring the trip tickets because the
    subpoena requested documents from 2008 and 2009, and he removed the soil from
    Schrum's property in 2007.
    {¶21} Regarding purchasing R & J's bill, Zarlenga said: "I agreed to pay Mark's bill
    so that there wasn't no argument down the road about the dirt because he claimed, you
    know, we still owned the dirt. We both owned the dirt. I didn't want to get in an argument
    with my other business associate that I work with in the community so I agreed to pay
    Mark's bill. I wrote him a check more just so I didn't have no problems down the road.
    And technically what I did was I said I'll buy your receivable for whatever the Saunders'
    bill was and he gave me the bill and I wrote him a check for it."
    {¶22} Zarlenga testified that not all of the original soil was there when he removed
    it from Schrum's property a year later, but he did not know how much was left. He said
    that Saunders had sold some of the soil. He later testified that in June 2007, there was
    "400, 500, maybe 600 yards there roughly," and the soil was spread out, rather than in
    one big pile. He agreed that at least a portion of the soil pile was not the original soil that
    -6-
    was brought in 2006 because other soil had mixed with Saunders's pile.
    {¶23} Zarlenga testified that he has sold pulverized, unprocessed, and fill soil to
    Custom Blended Soils, Inc. for $1 per cubic yard from his property on Western Reserve
    Road, although he is receiving credit towards processed topsoil from them rather than
    cash payment. He stated that CBS is selling the soil to him for $10 or $11 a ton when he
    picks it up, and then when he sells it, he has to add delivery costs to that price. He
    testified that he puts most of the markup in his transportation. Zarlenga identified
    Plaintiff's Exhibit No. 15 as the summary of the soil that CBS took off his property in 2009
    for $1 per cubic yard. Zarlenga testified that based on this he would say that the value of
    the soil taken from Schrum's property was about $3 to $4 per cubic yard because that is
    what it cost him to haul it away.
    {¶24} Zarlenga explained that Saunders's topsoil was taken to his Harvard
    Boulevard yard and it is now gone. He said he was 99 percent sure that it went to
    Cleveland into an area where Acme digs up tanks and sells unprocessed topsoil to cover
    up seed. Zarlenga stated that the bidding price for the soil on that project varies
    depending on where the job is located, and Acme sells unprocessed topsoil from $5-$14
    per ton depending on where it has to transport the soil. Zarlenga explained that if he
    hauls a load to Cleveland, it costs $180. He further explained that if he uses a semi, it
    hauls 20 tons and costs roughly $8 a ton to haul the soil to Cleveland. He then takes the
    $8 and adds it to what he wants for the material cost, and that is his delivered price.
    Counsel then asked if he was getting approximately $10 to $12 per ton at the Cleveland
    project, and Zarlenga replied, "Yes. At least I'm hoping at least. I don't know."
    {¶25} John Saunders testified next. He stated that he has been in the topsoil
    business since 1982. He explained that for his topsoil business, he usually purchases dirt
    from construction sites, paying anywhere from nothing to $4 per cubic yard. He then
    reprocesses the soil by putting it through his shredder and he also mixes compost with
    the soil. He explained that when soil is blended with compost, it becomes very enriched
    in comparison to plain topsoil, allowing plants to grow larger. He also stated that he
    charges the same amount for plain topsoil as for compost-topsoil mix.
    {¶26} Saunders also explained why the soil from the Canfield football field was
    -7-
    better than other soil: "Well, when you have soil like that there's a sand mixed with it plus
    other, probably some other chemicals, but fertilizers with it to make it grow and stay nice
    and green because they want the field looking tremendous. You're going to have to
    fertilize it. It starts off a good batch of fertilizer and some sand to keep it porous so the
    water can get down to the roots."
    {¶27} Regarding his agreement with R & J to remove the soil from the field,
    Saunders testified that he accepted their services, but that there was not a written
    contract between them. He said that he did not have a contract with Acme. Saunders
    called Carrocce who quoted a price of $73 per hour to transport the soil. Saunders
    testified that he determined only three extra trucks besides his own were needed because
    it was not profitable to have trucks waiting to be loaded. Saunders explained that when
    Carrocce had called regarding the bill, he had told him that he was willing to pay for three
    trucks, but Carrocce wanted the money for the hauling for all six trucks.
    {¶28} Saunders testified that he could have sold the soil from the Canfield football
    field in his business. When he bargained with R & J to transport the soil, he was planning
    to mix the soil with an equal amount of compost, giving him twice the amount of material
    to sell. Saunders further testified that the soil contained plastic pipes, but they did not
    affect the value for him because he has a shredder to remove them from the soil. He
    explained that he had a machine on Schrum's property to process the topsoil stored
    there, and he used the machine there.
    {¶29} By his own calculations on Defendant's Exhibit E, Acme and R & J together
    removed 3,312 cubic yards of soil from the Canfield football field. Saunders first
    calculated that five-axle dump trucks haul between 16 to 20 cubic yards of soil, based on
    information he received from several trucking companies. He then calculated that, on
    average, the trucks moved 2 loads per hour based on the trip tickets. Saunders's counsel
    clarified that although not all of the trip tickets recorded the number of loads, this figure
    was based upon the trip tickets that did record the loads. Saunders used an average
    figure of 18 cubic yards per load multiplied by 2 loads per hour, totaling 36 cubic yards of
    soil hauled per hour. Acme stipulated that Acme and R & J billed for 92 hours of work.
    Saunders then multiplied the 36 cubic yards of soil per hour by the 92 hours worked,
    -8-
    totaling 3,312 cubic yards of soil removed from the field.
    {¶30} However, during Saunders's testimony regarding Defendant's Exhibit E, the
    court referenced Carrocce's earlier testimony where he stated that the trucks R & J used
    held 14 to 16 cubic yards of soil. Saunders's counsel said that they would use 15 cubic
    yards in their calculation, but Acme later objected to this figure because Zarlenga had
    earlier testified that Acme's trucks held 11 to 14 cubic yards of soil. The court sustained
    the objection, and Saunders's counsel then used a figure of 13 cubic yards. Saunders
    agreed that using Acme and R & J's figures, they removed about 2,500 cubic yards of soil
    from the football field.
    {¶31} By his calculations, Saunders removed 704 cubic yards of soil from the
    football field with his own trucks. On Saturday, he used a single-axle truck carrying 12
    cubic yards of soil. He worked 8 hours, carrying 2 loads per hour. He calculated 24 cubic
    yards per hour multiplied by 8 hours, totaling 192 cubic yards. On Sunday, he again used
    his single-axle truck for 8 hours for a total of 192 cubic yards of soil. He also used his
    two-axle truck, which carried 20 cubic yards for 8 hours, totaling 320 cubic yards of soil.
    Saunders's counsel then added 704 cubic yards that Saunders's trucks hauled to 2,581
    cubic yards that Acme and R & J hauled, totaling 3,285 cubic yards of soil removed from
    the field in June of 2006.
    {¶32} On cross, Saunders testified that he had created Defendant's Exhibit E in
    anticipation of litigation shortly after filing his counterclaim. He further testified that no
    one knew the exact amount of soil that was taken from the Canfield football field to
    Schrum's property.
    {¶33} Saunders testified that the pile of soil decreased between June 2006 and
    June 2007. He said that he sold some plain topsoil to Foust Construction for $14 per
    cubic yard and referred to Exhibit C, the two statements he sent to Foust. He further
    testified that he donated 40 cubic yards of topsoil to Canfield Township, and this soil
    would have also been worth $14 per cubic yard. However, on cross, counsel referred to
    page 81 of Saunders's deposition, where he had testified that he believed he had
    donated 8 loads at 8 cubic yards per load to the township. He explained that he does not
    keep records when he gives soil away.
    -9-
    {¶34} Saunders also removed 10 or 11 cubic yards of soil for his own use. On
    cross, Saunders testified that he also took one load to his lot on Barth Farms. Counsel
    then referred to Saunders's deposition where he had testified that he took two loads to
    Barth Farms and one load to his house. Saunders replied that he made a mistake, but
    then stated that he knew how much soil he had removed: "I took out 10-yard loads so if I
    take two loads, 20 yards to Barth Farms and 10 yards to my place at 5138 Leffingwell."
    He further testified that he calculated the loads he took to his house based on the amount
    his bucket holds.
    {¶35} He testified that he did not sell any more of the soil in the year it was on
    Schrum's property because he had his site off Western Reserve Road with his supplies.
    He stated that it was easier to use this site by the freeway than to go out to Schrum's
    property. On cross, he also testified that there was soil taken out of the west side of the
    pile and he did not know who took it. He later stated that he allowed Schrum to take soil
    out of the pile, but he did not know how much Schrum took. Saunders also told Schrum
    that if friends of his needed topsoil, it would be fine for them to take a load or two.
    {¶36} On recross, Saunders testified that the topsoil he sold to Foust was
    processed, but that the unprocessed topsoil was not worth less than the processed
    topsoil. He stated that he does not sell unprocessed soil, explaining: "Why would I go
    through the expense of having a machine that does this and then give a person a product
    that they're going to have problems with?" He confirmed that the soil stored on the
    Schrum property was unprocessed, but the value he calculated for the soil on
    Defendant's Exhibit E was for processed soil. He also confirmed that he could not give a
    value for the unprocessed soil.      Counsel also referred to page 19 of Saunders's
    deposition testimony, where he had agreed that when calculating the value of the
    processed topsoil, there would be a deduction for the additional cost of transporting it
    from Schrum's property to Barth Farms and processing it there.
    {¶37} Saunders testified that he sold the soil to Foust for $14 per cubic yard
    because Foust was purchasing a large quantity and it was a short haul, so he lowered the
    price. He stated that his price is normally $17 per cubic yard; he also currently charged
    $17 per cubic yard for his topsoil-compost blend. Regarding the current value of the soil
    - 10 -
    he sold to Foust, he stated: "Now it is up in the 20s. From what I heard from competitors
    it goes anywhere were 17, 18 up to 25, 26." He further testified that selling topsoil in
    Mahoning County was tough because of the economy. He stated that since the job in
    June 2006 to the present, he had been selling topsoil, and he could have sold the soil
    from the Canfield football field throughout that time. Saunders testified that when Acme
    removed the topsoil from Schrum's property, he did not have any contracts for the sale of
    that topsoil.
    {¶38} Saunders did not know the exact size of the pile remaining in June of 2007
    and stated that was because "no one actually knew what the size of the pile was we
    brought in." He confirmed that he had no idea how much soil Acme took because of the
    soil removed from the west side of the pile.
    {¶39} Saunders calculated the amount of soil Acme removed from Schrum's
    property in June of 2007: 3,285 cubic yards of soil originally hauled to Schrum's property,
    subtracting 586 cubic yards sold to Foust, 40 cubic yards donated to Canfield Township,
    10 cubic yards for his personal use, and 20 cubic yards to Barth Farms, equaling 2,629
    cubic yards. Regarding the percentage of the pile missing from the west side, Saunders
    stated: "I'd say it had to be a very small – single digit, two or three percent of the pile, if
    that. I couldn't – it's hard to tell the depth from the outside of the pile that was there to the
    – to the depth that it was in, so it would be a small amount." He further explained that he
    would be able to judge the percentage missing based on his experience by seeing how
    the contour of the pile appeared. Saunders agreed to use a figure of 5 percent of the pile
    missing, and his counsel calculated 2497.55 cubic yards of soil remaining.
    {¶40} On cross, counsel referred to Saunders's deposition where he testified
    regarding the amount of soil missing from the west end of the pile. Counsel asked if
    Saunders had testified that a big portion was missing. Saunders replied: "Well, it was a
    large pile. The depth of the indentation into the pile – if you look at something, and you
    dig in three feet and it's a ten by ten area, there's a considerable amount gone. If you
    take that and take only four inches, and you take it over a 25 by 25 area, it would look a
    lot bigger." Counsel then read Saunders's deposition testimony: "Well, I know for a fact
    that on the back side, which would have been on the west side of the pile, that there was
    - 11 -
    a big chunk missing out of the back, and I assumed that being Schrum's property, he has
    to know who did it if he didn't do it." Counsel asked if a big chunk was a big percentage,
    and Saunders replied that it can be either depending on how big the surface is.
    {¶41} An additional witness, Christopher Altiere, the owner of CBS, testified during
    the trial. However, Saunders ordered the transcript that included Altiere’s testimony on
    appeal, not for his objections to the magistrate’s decision; thus, we can only consider the
    summary of Altiere’s testimony contained in the findings of fact in the magistrate’s
    decision. Civ.R. 53; App.R. 9.
    {¶42} Following a bench trial, the magistrate awarded Acme judgment in the
    amount of $6,249.89, and Saunders $1.00 in nominal damages.                Saunders filed
    objections to the magistrate's decision, which Acme opposed.
    {¶43} On May 14, 2010, the trial court issued a judgment entry adopting the
    magistrate's decision. The trial court found that R & J and Saunders entered into a valid,
    enforceable agreement for the removal of the topsoil. R & J, and hence Acme, as
    purchaser of the receivable, performed its obligations under the contract, and Saunders
    has failed to perform its obligation of payment without legal justification or excuse. The
    trial court stated that although Saunders had no contractual agreement directly with
    Acme, Acme conferred a benefit upon Saunders in the form of trucking services without
    receiving any compensation. Therefore, the trial court found that Saunders would be
    unjustly enriched if it was permitted to retain the benefit of those services without paying
    for them. The trial court further found that the reasonable value of Acme's services was
    $3,171.88 and together with the receivable of R & J in the amount of $3,078.01, Acme
    was entitled to judgment in its favor in the amount of $6,249.89.
    {¶44} The trial court found that the facts of the case failed to support Saunders's
    claim for unjust enrichment. With respect to Saunders's conversion claim, the court found
    that Mosure gave the topsoil to Saunders on the condition that it remove the soil from the
    field. Saunders had the soil removed from the field but did not pay for the removal
    services; this failure constituted a contractual breach, not a condition precedent to the
    enforceability of the contract. The topsoil belonged to Saunders once it was removed
    from the field. Furthermore, the court found that:
    - 12 -
    {¶45} "[Acme] had no legal right or basis to resort to self-help repossession or
    prejudgment execution when it removed Saunders's soil from Schrum's property. Even
    had [Acme] actually sold this soil to Saunders, in the absence of a valid security
    agreement or writing evidencing a purchase money security interest in the soil, [Acme]
    had no legal right to remove this soil from Schrum's property and when it did so, it
    converted Saunder's [sic] property."
    {¶46} With regard to damages for conversion, the trial court noted that the
    measure of damages is the value of the converted property at the time it was converted.
    Saunders had the burden of proving the fair market value of the soil by a preponderance
    of the evidence, and the court found that Saunders had failed to do so. The trial court
    explained that all aspects of Saunders's damages calculation were speculative, including
    the initial amount of soil deposited at Schrum's property, the amount of soil taken by
    Acme, and the value of the soil taken by Acme. The trial court also noted that the soil
    remaining on Schrum's property was "unprocessed" and Saunders intended to process it
    before selling it; however, Saunders did not provide any evidence regarding the cost of
    processing the soil and, therefore, its unit value at the time Acme converted it in
    "unprocessed" form. Finally, the trial court found that although Saunders testified it
    intended to sell the enriched topsoil for $17 per cubic yard, it failed to provide evidence of
    a contract or name of a customer reflecting a prospective sale. Thus, the trial court found
    that Saunders failed to sustain its burden of proof on compensatory damages for
    conversion.
    {¶47} The trial court found that once conversion is proven, the claimant is entitled
    to at least nominal damages, and in the absence of evidence of compensatory damages,
    a court should only award nominal damages. Thus, the trial court found that Saunders is
    entitled to nominal damages in the amount of $1.00 from Acme for its conversion of
    Saunders's topsoil.
    - 13 -
    Conversion Damages
    {¶48} In the first of two assignments of error, Saunders asserts:
    {¶49} "The trial court erred when it awarded only nominal damages after finding
    that The Acme Company illegally converted topsoil that did not belong to it."
    {¶50} Saunders asserts that the trial court abused its discretion in its damages
    award, specifically by only awarding nominal damages, and argues that the court should
    have awarded lost profits. An appellate court will not disturb a trial court's determination
    of damages absent an abuse of discretion. Roberts v. United States Fid. & Guar. Co.
    (1996), 
    75 Ohio St. 3d 630
    , 634, 
    665 N.E.2d 664
    . However, this court has also used a
    manifest weight of the evidence standard when reviewing a trial court's award of
    damages. See, e.g., Mt. Pleasant Volunteer Fire Dept. v. Stuart, 7th Dist. No. 01 JE 11,
    2002-Ohio-5227, at ¶30. Because Saunders requests that this court review the evidence
    to determine if an award of compensatory damages is appropriate, manifest weight is a
    more appropriate standard of review.
    {¶51} Judgments supported by some competent, credible evidence going to all
    the essential elements of the case will not be reversed by a reviewing court as being
    against the manifest weight of the evidence. C.E. Morris Co. v. Foley Construction Co.
    (1978), 
    54 Ohio St. 2d 279
    , 
    376 N.E.2d 578
    , at syllabus. When considering whether the
    judgment of the trial court is against the manifest weight of the evidence, it is important
    that the court of appeals be guided by a presumption that the findings of the trier of fact
    are correct. Seasons Coal Co. v. Cleveland (1984), 
    10 Ohio St. 3d 77
    , 80, 
    461 N.E.2d 1273
    . The weight to be given the evidence as well as the credibility of the witnesses are
    primarily for the trier of fact. State v. DeHass (1967), 
    10 Ohio St. 2d 230
    , 
    227 N.E.2d 212
    ,
    at paragraph one of the syllabus.
    {¶52} In general, "[t]he measure of damages in a conversion action is the value of
    the converted property at the time it was converted." Allied Erecting & Dismantling Co.,
    Inc. v. Youngstown, 
    151 Ohio App. 3d 16
    , 2002-Ohio-5179, 
    783 N.E.2d 523
    , at ¶62,
    quoting Tabar v. Charlie's Towing Serv., Inc. (1994), 
    97 Ohio App. 3d 423
    , 428, 
    646 N.E.2d 1132
    . However, "[t]here is no inflexible rule as to the measure of damages for a
    - 14 -
    wrongful conversion." Modarelli v. Fullerton Transfer & Storage Limited, Inc. (May 30,
    1978), 7th Dist. No. 77 CA 128. See, also, Fulks v. Fulks (1953), 
    95 Ohio App. 515
    , 
    121 N.E.2d 180
    , at paragraph two of the syllabus. The Ninth District Court of Appeals held
    that "[a] plaintiff may recover lost profits for conversion where lost profits may be naturally
    expected to flow from the conversion and they are reasonably ascertainable." Digital &
    Analog Design Corp. v. N. Supply Co. (Digital & Analog I) (Nov. 25, 1987), 9th Dist. No.
    4213, reversed in part on other grounds, Digital & Analog Design Corp. v. N. Supply Co.
    (Digital & Analog II) (1989), 
    44 Ohio St. 3d 36
    , 
    540 N.E.2d 1358
    . See, also, Schaffer v.
    First Merit Bank, N.A., 
    186 Ohio App. 3d 173
    , 2009-Ohio-6146, 
    927 N.E.2d 15
    , at ¶29.
    {¶53} Here, lost profits would be expected to result from the conversion. Acme
    converted topsoil from Saunders, who is in the business of selling topsoil. Saunders had
    already sold some of the soil from the Canfield football field and had equipment on
    Schrum's property in order to process the soil in preparation to sell it, which Acme knew
    about. The issue here, however, is whether the lost profits are reasonably ascertainable.
    {¶54} In Digital & Analog II, the Ohio Supreme Court affirmed the jury's award of
    lost profits as a component of compensatory damages. 
    Id. at 42.
    In determining whether
    the company demonstrated lost profits with reasonable certainty, the Court observed that
    to prove lost profits, a party must show: "(a) what he would have received from the
    performance so prevented, but also (b) what such performance would have cost him (or
    the value to him of relief therefrom). Unless he proves both of those facts, he cannot
    recover as damages the profits he would have earned from full performance of the
    contract." Allen, Heaton & McDonald, Inc. v. Castle Farm Amusement Co. (1949), 
    151 Ohio St. 522
    , 
    86 N.E.2d 782
    , at paragraph three of the syllabus. The Court concluded
    that evidence that fails to meet this standard is speculative and an insufficient basis for an
    award of lost profits. Digital & Analog II at 40.
    {¶55} Therefore, Saunders needed to show the amount of the soil remaining in
    June of 2007 that he could have sold, the sale price of the soil, and his costs in
    processing the soil. Regarding the sale price for the soil, Saunders testified that he
    usually sells processed soil for $17 per cubic yard. However, he sold processed soil from
    - 15 -
    the Canfield football field to Foust for $14 per cubic yard because of the quantity sold and
    the short distance the soil needed to be transported. He further testified that the current
    value of the soil he sold to Foust was anywhere between $17 and $26 per cubic yard.
    Thus, Saunders has not proven the value of the processed soil with reasonable certainty.
    {¶56} Notwithstanding Saunders's evidence regarding the amount of topsoil and
    its sale price, Saunders has failed to provide any evidence regarding his costs in
    processing and selling the topsoil.      The topsoil stored on Schrum's property was
    unprocessed, and Saunders testified that he planned to process this soil and mix it with
    compost before selling it, but failed to provide any evidence on the amount of these costs.
    Therefore, there is an insufficient basis in the record for an award of lost profits.
    {¶57} However, as 
    discussed supra
    , the general measure of damages for
    conversion is the fair market value of the item at the time it was converted. Allied
    Erecting & Dismantling 
    Co., supra
    , at ¶62. "An award of damages must be shown with a
    reasonable degree of certainty and in some manner other than mere speculation,
    conjecture, or surmise." Elias v. Gammel, 8th Dist. No. 83365, 2004-Ohio-3464, at ¶25.
    Damages are not speculative when they can be "computed to a fair degree of probability."
    Allied Erecting & Dismantling Co. at ¶65. However, if the appellant "establishes a right to
    damages, that right will not be denied because the damages cannot be calculated with
    mathematical certainty." 
    Id. at ¶64,
    quoting Hollobaugh v. D&V Trucking (May 8, 2001),
    7th Dist. No. 99 CA 303.
    {¶58} In order to prove the value of the soil at the time Acme converted it,
    Saunders needed to prove both the amount of the soil that Acme converted and the unit
    price of the soil. Saunders first calculated the amount of soil originally removed from the
    Canfield football field. He based his calculation of hours worked by Acme and R & J on
    their invoices as stipulated to by Acme. Saunders based the number of loads per hour
    upon the trip tickets, but not all of the trip tickets recorded the number of loads. Zarlenga
    also testified that the hash marks on the trip tickets were not precise because the truck
    drivers might forget to record their loads. This produced a low estimate for the number of
    loads per hour. Saunders based this calculation using an average load capacity of the
    - 16 -
    trucks based on information he received from several trucking companies and also upon
    Zarlenga's testimony regarding the amount his trucks could carry. Again, this figure
    provided a low estimate of trucks' load capacity. Saunders also calculated the amount of
    soil he removed from the field based upon the trip tickets and his own knowledge of his
    trucks' capacity and hours worked. While this calculation of the amount of soil removed
    from the Canfield football field was not precise, mathematical certainty is not required.
    Thus, Saunders calculated the amount of soil originally removed from the field to a fair
    degree of probability.
    {¶59} Saunders then calculated the soil remaining on Schrum's property in June
    of 2007 when Acme converted it, by deducting the amount of soil he sold to Foust,
    donated to Canfield Township, removed for his personal use, and transported to Barth
    Farms. Although he testified that he had no records of the soil that he donated and his
    calculation of this soil varied by 24 cubic yards from his deposition testimony to his trial
    testimony, again, mathematical precision is not required.
    {¶60} Significantly, Saunders testified that soil was removed from the west side of
    the pile by an unknown party. Although Saunders agreed to use a figure of five percent
    missing from the pile, this calculation was mere conjecture, based upon simply viewing
    the pile rather than any definitive calculations. Although he testified that he could judge
    what percentage was missing based on the contour of the pile, he also stated that it was
    difficult to judge the depth of the pile. Finally, Saunders testified that he allowed Schrum
    to take soil from the pile, but he did not know how much Schrum took.
    {¶61} Thus, Saunders's calculation of the amount of soil that Acme converted was
    based upon conjecture. Saunders could only roughly estimate the percentage missing
    from the west end of the pile and he had no idea how much soil Schrum took. Moreover,
    Zarlenga testified that the pile of soil remaining in June of 2007 had other soil mixed in,
    and Saunders did not consider this in his calculation of soil removed from the Schrum
    property. Although Zarlenga testified that he had trip tickets from June of 2007 when he
    removed the soil, Saunders's counsel did not subpoena the correct documents.
    Saunders could have used these trip tickets as a basis to calculate the amount of the soil
    removed; and it is the appellant's burden to prove its damages with reasonable certainty,
    - 17 -
    and Saunders here has failed to subpoena the correct documents.
    {¶62} In addition to proving the amount of soil Acme removed from Schrum's
    property, it is also Saunders's burden to prove the value of the soil at the time it was
    converted. His testimony regarding the value of the topsoil he sold to Foust is irrelevant
    because he sold processed soil to Foust, whereas the basis of his conversion claim is the
    unprocessed soil removed from Schrum's property. He testified that there is no difference
    in value between processed and unprocessed topsoil, but then later testified that he does
    not sell unprocessed soil because he has a machine to process the soil so that customers
    will not have problems with it. Moreover, Zarlenga testified that unprocessed topsoil is
    worth less than processed topsoil. As noted in the magistrate’s decision, Altiere testified
    that his company sells unprocessed topsoil for less than it sells his “supersoil.” Thus,
    Saunders's figure of $17 for processed topsoil is not the correct value of the unprocessed
    topsoil at the time it was converted. Therefore, the trial court properly concluded that the
    value of unprocessed topsoil is speculative.
    {¶63} Saunders argues that the trial court erred in awarding him only nominal
    damages and abused its discretion in finding that the soil had no value. However, the trial
    court did not find that the soil had no value, but rather found that the value of the soil was
    speculative: "There is testimony in this case that the unit value of this soil was anywhere
    from zero to $27.00 per cubic yard, that the market was 'glutted' with soil at the time, and
    that the soil was worth only what it cost to haul away." Furthermore, a trial court may
    award nominal damages when "some injury has been done, the extent of which the
    evidence fails to show." Lacey v. Laird (1956), 
    166 Ohio St. 12
    , 
    139 N.E.2d 25
    , at
    paragraph two of the syllabus. In a conversion action, if the complainant does not prove
    compensatory damages, the trial court should only award nominal damages in recognition
    of the complaining party's right and the violation of such right by offending party. Fisher v.
    Barker, 
    159 Ohio App. 3d 745
    , 2005-Ohio-1039, 
    825 N.E.2d 244
    , at ¶11.
    {¶64} Thus, since Saunders has failed to prove his damages with reasonable
    certainty, the trial court did not err in awarding only nominal damages. Accordingly,
    Saunders's first assignment of error is meritless.
    - 18 -
    Unjust Enrichment Damages
    {¶65} In its second assignment of error, Saunders asserts:
    {¶66} "The trial court erred when it awarded judgment to The Acme Company."
    {¶67} Saunders alleges the trial court erred in awarding judgment in Acme's favor
    for unjust enrichment and for the amount in R & J's accounts receivable. Specifically, that
    because there was no meeting of the minds between him and Acme there was no
    contract; and Acme merely sued on an account, it did not set forth a claim for unjust
    enrichment in its complaint. These arguments will be discussed in turn.
    {¶68} Saunders is correct that no contract existed between him and Acme.
    Zarlenga testified that the first time he contacted Saunders was when he sent the invoice
    to him after the services had already been performed. Thus, the issue remains whether
    Acme properly asserted a claim for unjust enrichment.
    {¶69} The Ohio Supreme Court held in Hambleton v. R.G. Barry Corp. (1984), 
    12 Ohio St. 3d 179
    , 
    465 N.E.2d 1298
    : “In Hummel v. Hummel (1938), 
    133 Ohio St. 520
    , 525,
    
    14 N.E.2d 923
    , this court observed that liability in quasi-contract ‘arises out of the
    obligation cast by law upon a person in receipt of benefits which he is not justly entitled to
    retain * * *.’” 
    Id. at 183.
    The Court then adopted the court of appeals’ iteration of the
    elements of a claim for quasi-contract, or unjust enrichment, as "(1) a benefit conferred by
    a plaintiff upon a defendant; (2) knowledge by the defendant of the benefit; and (3)
    retention of the benefit by the defendant under circumstances where it would be unjust to
    do so without payment ('unjust enrichment')." 
    Id. When determining
    whether there is
    sufficient evidence to support a claim for unjust enrichment, a reviewing court will not
    reverse a judgment "supported by some competent, credible evidence going to all the
    essential elements of the case." Dixon v. Smith (1997), 
    119 Ohio App. 3d 308
    , 318, 
    695 N.E.2d 284
    , quoting C.E. Morris Co. v. Foley Constr. Co. (1978), 
    54 Ohio St. 2d 279
    , 
    376 N.E.2d 578
    , at syllabus. Finally, Ohio is a notice pleading state, and only requires a
    complaint to include, “a short and plain statement of the claim showing that the party is
    entitled to relief, * * *.” Civ.R. 8(A).
    {¶70} In its complaint, Acme alleged in regards to the services it provided
    - 19 -
    Saunders:
    {¶71} "1. On or about June 17, 2006, Plaintiff provided services to the Defendant
    as shown by Exhibits 'A' and 'B' attached hereto and incorporated herein.
    {¶72} "4. Despite Plaintiff's demand for payment, Defendant has refused to pay
    the balance due for the services rendered.
    {¶73} "5. Defendant now owes the Plaintiff the sum of THREE THOUSAND
    EIGHT HUNDRED FORTY-NINE DOLLARS and 25/100 ($3,849.25) for services
    rendered to the Defendant by the Plaintiff * * *."
    {¶74} Applying the Ohio Supreme Court’s analysis in Hambleton, and the notice
    pleading requirements of Civ.R. 8(A), Acme has sufficiently pled a claim for unjust
    enrichment. Acme’s complaint alleges that it conferred a benefit upon Saunders, i.e.,
    transporting the excavated topsoil to Schrum’s property; Saunders knew of the benefit
    since he refused to pay for the benefit; and that Saunders had not paid for that benefit.
    Thus, Saunders would be unjustly enriched for not paying for Acme’s services. See also
    HLC Trucking v. Harris, 7th Dist. No. 01 BA 37, 2003-Ohio-694, at ¶24-27.
    {¶75}    Second, Saunders asserts that Acme's purchase of R & J's accounts
    receivable was not an asset purchase or the negotiation of commercial paper. Saunders
    further argues that even if it were, this disputed account does not fall under the definition
    of commercial paper and was not transferable or negotiable pursuant to R.C 1303.03 and
    R.C. 1303.21. However, this transfer was not a negotiation of commercial paper; but
    rather, R & J assigned its rights to payment under its contract with Saunders.
    {¶76}    "It is long-standing tradition in the common law that all contract rights may
    be assigned except under three conditions. First, if there is clear contractual language
    prohibiting assignment, an assignment will not be enforced. Second, an assignment must
    not materially change the duty of the obligor, materially increase the insurer's burden or
    risk under the contract, materially impair the insurer's chance of securing a return on
    performance, or materially reduce the contract's value. Third, the assignment will not be
    valid if it is forbidden by statute or by public policy." Pilkington N. Am., Inc. v. Travelers
    Cas. & Sur. Co., 
    112 Ohio St. 3d 482
    , 2006-Ohio-6551, 
    861 N.E.2d 121
    , at ¶36.
    - 20 -
    {¶77}     There was nothing in the contract between Saunders and R & J prohibiting
    assignment, and this assignment of payment rights did not materially change Saunders's
    duty because Acme sought payment for the account receivable in its complaint in the
    same amount of the services that R & J provided to Saunders. Only the right to payment
    was assigned; the services had already been performed and the assignment did not
    change the contract's value. Furthermore, the assignment of an accounts receivable
    does not appear to be forbidden by statute or by public policy. See Schofield v. Benton
    (Aug. 20, 1992), 10th Dist. No. 92AP-161 (upholding assignment of the contractual right
    to collect payment for services that had already been performed).             Accordingly,
    Saunders's argument regarding Acme’s unjust enrichment claim and the judgment on the
    accounts receivable are meritless.
    {¶78}     In sum, Saunders's arguments are meritless. Saunders did not prove lost
    profits damages with reasonable certainty because it failed to provide any evidence as to
    its costs in processing the topsoil and the sale price of the topsoil appeared to be
    speculative. Saunders also did not sufficiently prove general conversion damages
    because its evidence regarding the amount and value of the unprocessed topsoil was
    speculative. Acme sufficiently pled a claim for unjust enrichment, and R & J properly
    assigned its right to payment from Saunders to Acme. Accordingly, the judgment of the
    trial court is affirmed.
    Waite, P.J., concurs with attached concurring opinion.
    Vukovich, J., concurs.
    Waite, P.J., concurring.
    {¶79} Although I agree with the majority’s interpretation of the procedural issues in
    this case, as well as most of the legal principles cited, there is an additional legal
    framework that I would add that helps explain the final decision in this appeal. A brief
    recitation of some of the relevant facts follows: David Mosure, working for Canfield High
    - 21 -
    School, gave Saunders permission to haul away topsoil from the school football field as
    new turf was being installed. Saunders had two days to haul the dirt away. Saunders
    then entered into an oral contract with R&J Trucking to perform the actual hauling.
    Saunders and R&J disagreed over the number of trucks necessary for the project, but
    R&J was ultimately responsible for doing the hauling. R&J concluded that it would take
    six trucks, but R&J could not provide all the trucks needed.
    {¶80} R&J then entered into an arrangement with Acme to provide three additional
    trucks for the project. Although Daniel Zarlenga, the president of Acme, testified that he
    did not contract with R&J to work on the project, it is difficult to interpret the facts in the
    overall record to reflect anything other than that Acme was operating as a subcontractor
    for R&J. Acme worked on the project under the terms of the contract that R&J had with
    Saunders, and at the request and authority of R&J.
    {¶81} The project utilized six trucks over the course of two days. Saunders did not
    pay either R&J or Acme for the hauling services that were performed. R&J sent
    Saunders a bill for $3,078.01. Acme sent Saunders a bill for $3,849.25. R&J then
    assigned its breach of contract claim to Acme, and Acme paid R&J $3,078.01 for that
    assignment. A lawsuit ensued in which Acme attempted to recover the money owed to
    R&J, as well as asserting a claim of unjust enrichment for the use of Acme’s three trucks
    during the project.
    {¶82} I would characterize these facts from the following legal perspective: The
    $3,078.01 that Acme paid to R&J appears to have been the consideration given on an
    oral assignment of a chose of action based on a breach of contract. An assignment is
    - 22 -
    defined as a transfer to another person of the whole of any property or right therein.
    Black's Law Dictionary (6th Ed.1990) 119. A valid assignment may be oral or written, and
    should satisfy the requirements of a contract, i.e., the legality of object, capacity of
    parties, consideration, and meeting of the minds. 6 Ohio Jurisprudence 3d (2011),
    Assignments, Section 25. An assignment, no matter how informal, may be found when
    there is intent on the part of the assignor to assign the rights in question, an intent on the
    part of the assignee to be assigned the rights in question, and valuable consideration
    exchanged. Id.; see also, Morris v. George C. Banning, Inc. (1947), 
    77 N.E.2d 372
    , 374,
    
    49 Ohio Law. Abs. 530
    .
    {¶83} “Any right of action arising out of contract may be assigned. 6A Corpus
    Juris Secundum (1975) 641, Assignments, Section 36. Furthermore, ‘any words or
    transactions which show an intention on one side to assign and an intention on the other
    to receive, if there is a valuable consideration, will operate as an effective equitable
    assignment.’ Morris v. George Banning, Inc. (App.1947), 
    49 Ohio Law. Abs. 530
    , 533, 
    77 N.E.2d 372
    , 374.” Langhals v. Holt Roofing Co. (1988), 
    47 Ohio App. 3d 114
    , 116, 
    547 N.E.2d 401
    ; see also Farley v. Gary Nichols Builders, 9th Dist. No. 99CA007530.
    {¶84} Acme also sued Saunders for its own work as a subcontractor on the
    project. This claim was correctly brought as an unjust enrichment claim. When a
    subcontractor is not paid by the contractor and the owner has not paid the contractor for
    some aspect of the job at issue, the subcontractor can look to the owner for payment
    under a theory of unjust enrichment. See Meridien Marketing Group, Inc. v. J&E Bldg.
    Group, Inc., 2d Dist. No. 2011-CA-02, 2011-Ohio-4872; Ross-Co Redi Mix Co. v.
    - 23 -
    Steveco, Inc. (Feb.6, 1996), 4th Dist. No. 95CA3; Brower Prods. Inc. v. Musilli (May 21,
    1999), 2d Dist. Nos. 98CA58 and 98CA59.
    {¶85} Since there are two distinct claims that are before us, the majority Opinion is
    correct in discussing both a contract claim (along with the assignment of that claim), and
    an unjust enrichment claim. However, the majority interprets the facts so that the unjust
    enrichment claim is independent of the contract claim and glosses over the question of
    assignment, whereas I interpret the two claims as interrelated. However we look at the
    facts, though, the majority and I agree that there are two issues raised by Acme, here,
    one for breach of contract and one for unjust enrichment, and judgment was properly
    granted in favor of Acme on both claims. I concur with the majority on all other matters
    discussed in the Opinion.