Thernes v. United Local School Dist. Bd. of Edn. ( 2011 )


Menu:
  • [Cite as Thernes v. United Local School Dist. Bd. of Edn., 2011-Ohio-6216.]
    STATE OF OHIO, COLUMBIANA COUNTY
    IN THE COURT OF APPEALS
    SEVENTH DISTRICT
    STATE OF OHIO, ex rel., DONALD W.                       )
    THERNES, JR., SUPERINTENDENT,                           )
    MULTI-COUNTY JUVENILE ATTENTION                         )
    SYSTEM,                                                 )
    )             CASE NO. 0
    9 CO 33
            PLAINTIFF-APPELLANT,                            )
    )                     OPINION
    UNITED LOCAL SCHOOL DISTRICT                            )
    BOARD OF EDUCATION,                                     )
    )
    DEFENDANT-APPELLEE.                             )
    CHARACTER OF PROCEEDINGS:                               Civil Appeal from Court of Common
    Pleas of Columbiana County, Ohio
    Court Case No: 08CV591
    JUDGMENT:                                               Affirmed
    JUDGES:
    Hon. Gene Donofrio
    Hon. Cheryl L. Waite
    Hon. Mary DeGenaro
    Dated: December 5, 2011
    -2-
    APPEARANCES:
    For Plaintiff-Appellant               Attorney Michael P. Zirpolo
    Suite 206, Belden Village Tower
    4450 Belden Village Street, N.W.
    Canton, Ohio 44718
    For Defendant-Appellee                Attorney Christian M. Williams
    5005 Rockside Rd., Suite 260
    Cleveland, Ohio 44131-6808
    For Amicus Curiae                     Atty. Patrick J. Schmitz
    Ohio School Boards Association        Atty. Jenifer I. Stiff
    Scott, Scriven & Wahoff, LLP
    50 West Broad Street, Suite 2600
    Columbus, Ohio 43215
    For Amicus Curiae                     Atty. Thomas A. Luebbers
    County Commissioners Association of   Peck, Shaffer & Williams LLP
    Ohio                                  201 East Fifth Street
    Suite 900
    Cincinnati, Ohio 45202
    [Cite as Thernes v. United Local School Dist. Bd. of Edn., 2011-Ohio-6216.]
    DONOFRIO, J.
    Introduction
    {¶1}     Plaintiff-appellant, Donald W. Thernes Jr., Superintendent of the Multi-
    County Juvenile Attention System District (MCJAS), appeals a Columbiana County
    Common Pleas Court decision granting summary judgment in favor of defendant-
    appellee, United Local School District Board of Education (United). MCJAS operates
    juvenile facilities for the training, treatment, and rehabilitation of juveniles placed
    there by the juvenile courts of six counties in northeast Ohio. The school district of a
    child who is placed in such a facility is required to pay “the cost of educating the child
    based on the per capita cost of the educational facility” within the juvenile facility.
    R.C. 2151.362(B). The question this case presents is whether that cost includes
    administrative costs incurred by the juvenile facility in providing those educational
    services.
    Facts & Procedural History
    {¶2}     MCJAS is a multi-county district that operates facilities for the training,
    treatment, and rehabilitation of juveniles placed there by the juvenile courts of six
    counties in northeast Ohio.1 R.C. 2151.65. These counties are Carroll, Columbiana,
    Holmes, Stark, Tuscarawas, and Wayne.                     This case concerns one of MCJAS’s
    Columbiana County facilities – the Louis Tobin Attention Center (Tobin Center). The
    center includes an educational space for its juvenile residents. United is a local
    school district board of education which serves elementary and secondary school
    students in Columbiana County.
    {¶3}     Under Ohio law, MCJAS is required to provide a “program of education”
    for juveniles admitted to its facilities. R.C. 2151.653. Each school district with a child
    admitted in one of MCJAS’s facilities is statutorily required to pay the cost of the
    educational program MCJAS provides to the child.                         MCJAS is also statutorily
    authorized to change and/or supplement its relationship with one or all of the
    1. Portions of the underlying facts and procedural history of this case are taken from
    a previous appeal decided by this court concerning this case in State ex rel. Thernes
    v. United Local School Bd. Dist. of Edn., 7th Dist. No. 0
    7 CO 45
    , 2008-Ohio-6922.
    -2-
    applicable schools by contract whereby a school would directly provide the teachers,
    rather than reimbursement thereof.
    {¶4}   Finding itself in need of an educational program for the youth admitted
    to the Tobin Center, MCJAS contracted with United in 1998 to provide those
    services. Under the year-to-year agreement, United was responsible for devising
    and providing an educational program for students housed at the center and for
    hiring, providing, paying, and supervising teaching and other staff for the educational
    program at the center.      The contract also specifically provided that United was
    responsible for billing: “[United] shall assume the responsibility for billing outside
    school districts for the educational services provided. Such billing shall include a ten
    percent administrative cost.” (01/08/1998 Agreement for Educational Services for the
    Multi-County Juvenile Attention System, section 8.)      The contract did not further
    define the ten-percent administrative cost.
    {¶5}   The record indicates that the parties began to dispute cost issues
    during the 2004-2005 school year. As mentioned, United had a contractual duty to
    assume the center’s billing responsibilities for other school districts within the
    center’s domain. United alleged that it was unable to bill for its educational services,
    or for the 10% administrative cost, because the center would not release enrollment
    data for the other school districts.
    {¶6}   During the 2004-2005 school year, MCJAS proposed a new contract
    with section 8 changed to state, in pertinent part, the following: “The United Local
    District shall assume the responsibility for billing outside school districts for the
    educational services provided. Such billing shall include a 10% (of the cost of the
    Educational Program) administrative cost that will be paid to the Multi-County
    Juvenile Attention System.” United stated that it was unable to enter the proposed
    contract.
    {¶7}   Rather than pursue a breach-of-contract action, MCJAS sued United
    on July 17, 2006, seeking a declaratory judgment that the per capita cost of providing
    the educational facility at the Tobin Center for youth-residents of the United Local
    -3-
    School District admitted to the center included overhead, administrative, and
    operational costs borne by MCJAS.          In support, MCJAS relied solely on R.C.
    2151.357 (recodified as R.C. 2151.362 effective October 9, 2006) which allocated
    the cost of educating a child who had been removed from their resident school
    district:
    {¶8}   “Whenever a child is placed in a detention facility established under
    section 2152.41 of the Revised Code or a juvenile facility established under section
    2151.65 of the Revised Code, the child’s school district as determined by the court or
    the department, in the same manner as prescribed in division (A) of this section,
    shall pay the cost of educating the child based on the per capita cost of the
    educational facility within the detention home or juvenile facility.” R.C. 2151.357.
    {¶9}   United’s answer denied the allegations in the complaint, and requested
    that the court dismiss the case, pursuant to Civ.R. 12(B)(6), for failure to state a
    claim upon which relief could be granted for want of a real controversy or justiciable
    issue which would be terminated by a declaratory judgment.
    {¶10} On June 1, 2007, MCJAS notified United it was exercising its option to
    terminate their contract, effective at the end of the school year of 2008.
    {¶11} Both parties produced documents regarding the costs involved in the
    educational program at the Tobin Center. United submitted that the expenses of the
    educational program were salaries for a teacher, a teacher’s aide, a psychologist,
    educational supplies and educational equipment.
    {¶12} MCJAS submitted that administrative cost of the Tobin Center’s
    educational program included 10% of the salaries of the center’s direct care day staff
    (including secretary, administrator, cooks, nurses, and youth leaders), 10% of the
    salary of the suicide intervention specialist, 1% of the salaries of the center’s
    maintenance staff, 1% of the salaries of the center’s administrative staff (including
    superintendent,    director   of   detention,   director   of   administrative   support,
    administrative assistant, clerks, payroll, receptionist, and program analyst), 10% of
    the total operating expenses of the center (including office supplies, maintenance
    -4-
    supplies, general supplies, medical supplies, gasoline, data processing, building
    repair and services, licenses, property insurance, T-1 lines, and educational
    services), and 28% of the utility costs (including gas, electric, phones, and other
    utilities) based on the square footage of the educational facility within the center.
    {¶13} Subsequent to interrogatories, motions to compel, discovery, and
    extensions of time, the trial court set a deadline of October 19, 2007 for motions for
    summary judgment.       On October 17, 2007, MCJAS filed a motion for summary
    judgment, stressing that the action was not for breach of contract, and instead for a
    prospective construction of R.C. 2151.362 (formerly R.C. 2151.357).             MCJAS’s
    motion concluded by asking the court to direct United to include the center’s
    expenses in the total cost of the educational program, including “the educational
    space, adjunct detention and/or treatment staff, and administrative support for the
    educational program.”      MCJAS also asked the court to direct United to bill the
    outside school districts for the per capita cost of said total amount and to pay MCJAS
    the money United receives.
    {¶14} On October 19, 2007, United filed its own motion for summary
    judgment, indicating that the contract between the parties mooted the necessity and
    applicability of a judicial construction of R.C. 2151.362. United argued that there was
    no real controversy or justiciable issue between the parties which could be settled by
    the grant of a declaratory judgment.
    {¶15} That same day, the trial court gave notice of assignment to United for
    responses to MCJAS’s motion for summary judgment, with a deadline of December
    21, 2007. On November 29, 2007, the trial court filed a judgment entry in favor of
    MCJAS. The trial court noted that the statute “seems pretty clear on its face that the
    home school district of the child is to pay the entire cost of educating the child at the
    detention facility.   This would include the cost of any teachers, contract service,
    equipment facilities, administration, etc. In the instant situation this would be over
    and above the cost paid by the home district to the defendant for the teachers
    provided.    The statue [sic] obviously contemplates educational facility at the
    -5-
    detention facility and leaves to the trustees or superintendent the manner of
    accomplishing staffing such educational facility.”
    {¶16} The trial court stated that there was a real controversy between the
    parties and that an interpretation of the statute was necessary for the parties to
    understand their current relationship and future obligations.       The trial court then
    found that the matter was appropriate for declaratory judgment, and declared that
    R.C. 2151.362(B) “provides that the home district of a child placed in detention at the
    [MCJAS’s] facility shall pay the entire cost of educating that child based on the per
    capita cost which would include educational personnel costs, administration
    personnel costs, costs of physical facilities including buildings, utilities, machinery,
    etc. This is left to [MCJAS] to determine what those costs are and to recoup those
    from the child’s home district or is appropriate or can contract for.”
    First Appeal
    {¶17} On December 21, 2007, United filed a timely notice of appeal. While
    that appeal was pending, MCJAS and United negotiated a successor agreement to
    the 1998 agreement. This time, the parties more clearly defined the calculation of
    the cost for the education program:
    {¶18} “When calculating the total amount to be invoiced to all school districts
    having children using the educational program, United Local will utilize the following
    formula to calculate the per capita cost of the Tobin educational facility for purposes
    of O.R.C. §2151.362: United Local’s Annual Costs for the Educational Program +
    Ten Percent (10%) of United Local’s Annual Costs to Represent Multi-County’s
    Annual Costs of the Educational Program – Reimbursement to United Local from the
    State of Ohio (State Foundation Money) and Federal Title I-D funds = The amount to
    be billed by United Local to outside school districts ÷ School (Bed/Student
    Attendance at Tobin) Days = per capita cost of the Tobin Educational Facility”
    (07/31/2008 Agreement for Educational Services, section 5.)
    {¶19} On December 17, 2008, this court affirmed in part and reversed in part
    the trial court’s November 29, 2007 decision and remanded the case to the trial court
    -6-
    for “further consideration subsequent to [United] filing a response to [MCJAS’s]
    motion for summary judgment.” State ex rel. Thernes v. United Local School Bd.
    Dist. of Edn., 7th Dist. No. 0
    7 CO 45
    , 2008-Ohio-6922, at ¶49. This court held that
    MCJAS could seek declaratory judgment, but the trial court could not award
    summary judgment to MCJAS before the cutoff date for United to respond to
    MCJAS’s summary judgment motion and before United in fact responded to the
    motion.
    {¶20} On May 28, 2009, MCJAS filed its reply to United’s motion for summary
    judgment asserting that the court should issue a declaratory judgment because: (1)
    R.C. 2151.362 applies to the parties to this action, and to school districts having
    children who utilize the Tobin Center educational facility; (2) R.C. 2151.362(A)(1) and
    3313.64(C)(2) are applicable in determining which school district(s) are to bear the
    cost of the educational facility at the Tobin Center; (3) R.C. 2151.362(B) requires the
    school district of each child utilizing the Tobin Center educational facility to pay the
    cost of educating the child based on the per capita cost of said educational facility;
    and (4) that appellant incurs actual costs to provide and maintain the Tobin Center
    educational facility, and such costs shall be paid by the school districts having
    children in the Tobin Center who utilize its educational facility there.
    {¶21} On June 1, 2009, United filed its memorandum in opposition to
    MCJAS’s motion for summary judgment. United stressed that the court should deny
    MCJAS’s requested declaratory judgment as brought in its motion for summary
    judgment.      Moreover, it contended that to the extent the court issued any
    interpretation of R.C. 2151.362, such interpretation should narrowly construe R.C.
    2151.362(B) so as to require that any costs assessed by MCJAS are reasonable,
    and are not an unlawful tax which MCJAS has no statutory right to impose on United
    or any other area school district.
    {¶22} On September 18, 2009, the trial court reversed its prior decision. The
    trial court held that:
    -7-
    {¶23} “1.) §2151.362 applies to the parties of this action and to all school
    districts who have children in the Tobin Center. The Juvenile Court or Department of
    Youth Services determine which district must bear the costs.
    {¶24} “2.) The school districts are to bear the costs of the educational facility
    on a per capita basis, meaning each school district pays a portion of the costs of
    running the educational facility at the Tobin Center based on how many children it
    has in that center.
    {¶25} “3.) The Plaintiff-Relator [appellant] incurs actual costs to provide and
    maintain the educational facility.         The Plaintiff-Relator is not entitled to
    reimbursement for costs that it would incur whether or not it had a physical education
    facility within its walls. For instance, Plaintiff-Relator is not entitled to include costs
    for cafeteria workers or cafeteria facilities, security, administrative staff, programming
    staff, counseling staff, or physical facilities that would be provided regardless of
    whether there was an educational facility physically located within its building.
    {¶26} “On the other hand, if Plaintiff-Relator has to hire staff, create new
    facilities, or purchase new equipment solely for, or primarily to provide an educational
    facility, then it would be entitled to bill a cost of that expenditure prorated to the
    amount of use for education to the school districts as part of their per capita costs.”
    {¶27} Notably, the trial court observed that the educational services contract
    between the parties had expired. While that was reason enough for the court to
    opine that it would not venture to interpret that contract, the court noted that R.C.
    2151.653 specifically contemplates a juvenile facility contracting for the educational
    services it is required to provide and, to that extent, the cost of such services is
    entirely a matter of contract outside the ambit of R.C. 2151.653.
    Second (Current) Appeal
    {¶28} MCJAS filed a timely notice of appeal on October 5, 2009. The County
    Commissioners’ Association of Ohio filed an amicus curiae brief on behalf of
    MCJAS. The Ohio School Boards Association filed an amicus curiae brief in support
    of United.
    -8-
    {¶29} MCJAS’s sole assignment of error states:
    {¶30} “THE TRIAL COURT’S INTERPRETATION OF R.C. 2151.362(B) IS
    ERRONEOUS AS A MATTER OF LAW.”
    Standard of Review
    {¶31} Because statutory construction or interpretation is an issue of law, a
    reviewing court examines the lower court’s decision anew. Ceccarelli v. Levin, 
    127 Ohio St. 3d 231
    , 2010-Ohio-5681, 
    938 N.E.2d 342
    , ¶8. This means reviewing the
    decision independently, without deference to the lower court’s determination. In re
    J.L., 
    176 Ohio App. 3d 186
    , 2008-Ohio-1488, 
    891 N.E.2d 778
    , ¶33.
    {¶32} R.C. 2151.362(B) provides:
    {¶33} “Whenever a child is placed in a detention facility established under
    section 2152.41 of the Revised Code or a juvenile facility established under section
    2151.65 of the Revised Code, the child’s school district as determined by the court or
    the department, in the same manner as prescribed in division (A) of this section,
    shall pay the cost of educating the child based on the per capita cost of the
    educational facility within the detention home or juvenile facility.”
    {¶34} MCJAS argues that the language of the statute requires the school
    district to pay the cost of educating the child “based on the per capita cost” of the
    Tobin Center educational facility including, but not limited to, costs that are essential
    to the operation of any building, such as heat, electricity, water, maintenance and
    sewer, and insurance.       He argues that the trial court, in its second decision,
    completely ignored the phrase “based on the per capita costs of the educational
    facility within the detention home of juvenile facility.” Moreover, MCJAS contends
    that nowhere in this statute is there any language that would support the court’s
    conclusion that MCJAS “is not entitled to reimbursement for costs that it would incur
    whether or not it had a physical education facility within its walls.” (MCJAS’s Brief at
    11.)
    {¶35} In response, United argues that R.C. 2151.362, like other cost and fee
    statutes, should be narrowly and reasonably construed.           It points out that if the
    -9-
    General Assembly had intended for juvenile attention centers such as the Tobin
    Center to pass along the center’s general facility costs such as security, cafeteria
    services, and other services unrelated to the educational program, the statute would
    have stated as such. However, United continues, the statute only permits appellant
    to seek reimbursement for the “cost of educating the child based upon the per capita
    cost of the educational facility,” not the juvenile attention center facility as a whole.
    (Emphasis sic, United’s Brief at 12.)
    {¶36} MCJAS also argues that there is no language in the statute which
    would limit reimbursement “solely for, or primarily to provide an educational facility” at
    the Tobin Center.     MCJAS continues by arguing that “the court’s interpretation
    rewrites the statute to say: the child’s school district…shall pay the cost of educating
    the child based only on the direct costs of the educational facility…within the [Tobin
    Center].” (Emphasis sic, MCJAS’s Brief at 11).
    {¶37} “The principles of statutory construction require courts to first look at
    the specific language contained in the statute, and, if the language is unambiguous,
    to then apply the clear meaning of the words used.” Roxane Laboratories, Inc. v.
    Tracy (1996), 
    75 Ohio St. 3d 125
    , 127, 
    661 N.E.2d 1011
    . “Words and phrases shall
    be read in context and construed according to the rules of grammar and common
    usage.” R.C. 1.42.
    {¶38} Despite MCJAS’s extensive efforts to make it so, the language of R.C.
    2151.362(B) is not ambiguous. Reading the words and phrases of R.C. 2151.362(B)
    in context and construing them according to the rules of grammar and common
    usage, the cost of educating a child based on the per capita cost of the educational
    facility within a juvenile facility cannot be construed to include the administrative
    costs sought to be recovered by the facility.
    {¶39} R.C. 2151.362(B)’s use of the word “within” is instructive. The phrases
    “of the educational facility” and “within the home or facility” make it clear that the
    school district will bear the cost of education within the facility. It does not position
    - 10 -
    the school district or cost bearer to pay for those costs outside the scope of
    educating the child (i.e., administrative costs).
    {¶40} The reasoning behind the trial court’s conclusion that the educational
    cost referred to in R.C. 2151.362(B) does not include MCJAS’s administrative costs
    is sound. As the court aptly pointed out, the administrative costs MCJAS seeks to
    recoup through R.C. 2151.362(B) are costs it would bear whether or not the Tobin
    Center housed an educational facility. The court provided good examples of costs
    that the center would incur whether or not it had an educational facility, including
    costs of cafeteria workers or cafeteria facilities, security, administrative staff,
    programming staff, and counseling staff.
    {¶41} Common usage of the language employed by R.C. 2151.362(B) also
    supports the trial court’s conclusion that those costs that can be recouped from the
    child’s school district are those costs solely or primarily for the educational facility.
    The best example of those costs is the costs MCJAS incurred in its contract with
    United to provide the educational services.
    {¶42} In its supplemental appellate brief to this court, MCJAS also argues
    that the recent addition of subsection (C)(4) to R.C. 3313.64 supports it position.
    The Ohio Revised Code establishes who should pay the tuition of a student who
    does not reside in the district where his or her parents reside, a child who is in the
    permanent or legal custody of a government agency or person other than the child’s
    parent. R.C. 3313.64. In that instance, “the total educational cost to be paid for the
    child shall be determined by a formula approved by the department of education,
    which formula shall be designed to calculate a per diem cost for the educational
    services provided to the child for each day the child is served and shall reflect the
    total actual cost incurred in providing those services. The department shall certify
    the total educational cost to be paid for the child to both the school district providing
    the educational services and, if different, the school district that is responsible to pay
    tuition for the child. The department shall deduct the certified amount from the state
    basic aid funds payable under Chapter 3317 of the Revised Code to the district
    - 11 -
    responsible to pay tuition and shall pay that amount to the district providing the
    educational services to the child.” R.C. 3313.64(C)(4).
    {¶43} In response to R.C. 3313.64(C)(4), the Ohio Department of Education
    developed Form SF-14PD for the educating district to complete in order to obtain
    reimbursement for its educational services provided to nonresident children. The
    form has line items for “administrative costs,” “staff support cost,” “pupil support
    costs,” and “operations support cost.”
    {¶44} MCJAS’s reliance on R.C. 3313.64(C)(4) is misplaced.                     R.C.
    3313.64(C)(4) addresses the relationship between a child’s residential school district
    and the school district presently providing educational services to the child housed at
    a juvenile facility. In particular, it addresses the financial obligation owed by the
    school district where the child resided before they were placed in the juvenile facility
    to the school district which is presently providing educational services to the child at
    the juvenile facility. In this case, MCJAS operates a juvenile facility; it is not a school
    district. R.C. 3313.64(C)(4) does not specifically address any financial obligations
    owed to it as the operator of a juvenile facility. Likewise, the “administrative costs,”
    “staff support cost,” “pupil support costs,” and “operations support cost” referenced in
    Form SF-14PD are costs reimbursable to the educating school district, not the
    juvenile facility that houses the educational facility.
    {¶45} In sum, the trial court’s reading of R.C. 2151.362(B) was sound and
    well-reasoned. It employed the simple and clear meaning of the words used by R.C.
    2151.362(B), reading the words and phrases in context and construing them
    according to the rules of grammar and common usage. Consequently, the trial court
    did not err in its award of summary judgment in favor of United.
    {¶46} Accordingly, MCJAS’s sole assignment of error is without merit.
    - 12 -
    {¶47} The judgment of the trial court is hereby affirmed.
    Waite, P.J., concurs.
    DeGenaro, J., concurs.
    