Jatsek Constr., Co., Inc. v. Burton Scot Contrs., L.L.C. ( 2012 )


Menu:
  • [Cite as Jatsek Constr., Co., Inc. v. Burton Scot Contrs., L.L.C., 
    2012-Ohio-3966
    .]
    Court of Appeals of Ohio
    EIGHTH APPELLATE DISTRICT
    COUNTY OF CUYAHOGA
    JOURNAL ENTRY AND OPINION
    No. 98142
    JATSEK CONSTRUCTION CO., INC.
    PLAINTIFF-APPELLEE
    vs.
    BURTON SCOT CONTRACTORS, LLC, ET AL.
    DEFENDANTS-APPELLANTS
    JUDGMENT:
    REVERSED AND REMANDED
    Civil Appeal from the
    Cuyahoga County Court of Common Pleas
    Case No. CV-758171
    BEFORE: Jones, J., Blackmon, A.J., and Boyle, J.
    RELEASED AND JOURNALIZED: August 30, 2012
    ATTORNEYS FOR APPELLANTS
    Andrew J. Natale
    Philip J. Truax
    Frantz Ward LLP
    2500 Key Center
    127 Public Square
    Cleveland, Ohio 44114
    ATTORNEYS FOR APPELLEES
    For Jatsek Construction Co.
    John R. Christie
    Stafanik & Christie
    1375 East Ninth Street, Suite 2450
    Cleveland, Ohio 44114
    City of Warren
    James A. Climer
    Mazanec, Raskin & Ryder Co, L.P.A.
    100 Franklin’s Row
    34305 Solon Road
    Solon, Ohio 44139
    For Cuyahoga County
    Colleen Majeski
    Assistant County Prosecutor
    Justice Center, 9th Floor
    1200 Ontario Street
    Cleveland, Ohio 44113
    For Lorain County
    Daniel F. Petticord
    Lorain County Prosecutors Office
    225 Court Street, 3rd Floor
    Elyria, Ohio 44035
    LARRY A. JONES, SR., J.:
    {¶1} This case came to be heard upon the accelerated calendar pursuant to App.R.
    11.1 and Loc.R. 11.1.
    {¶2} Defendants-appellants, Burton Scot Contractors, L.L.C. and Westfield
    Insurance Company (collectively “Burton Scot”) appeal from the trial court’s judgment
    denying Burton Scot’s motion to stay proceedings pending arbitration. We reverse and
    remand.
    I. Procedural History and Facts
    {¶3} In June 2011, plaintiff-appellee Jatsek Construction Company, Inc. initiated
    this action against the Burton Scot defendants and three other defendants: Cuyahoga
    County, Lorain County, and the city of Warren. According to the complaint, Burton Scot
    was the general contractor for three separate public improvement projects.      The first
    project was for the resurfacing of Russia Road in Lorain County; the second project was
    for the resurfacing of Usher Road in Cuyahoga County; and the third project was for work
    to be completed for the Greenway bike trail (“Greenway project”) in the city of Warren.
    The Greenway project is the subject of this appeal.
    A.     Jatsek’s Complaint Against Burton Scot Relative to the Greenway Project
    {¶4} According to Jatsek’s complaint, it was contacted by Burton Scot to submit a
    subcontractor bid for the Greenway project. Jatsek submitted a bid, but Burton Scot
    informed the company that it was attempting to find a different contractor for the work.
    Jatsek’s complaint further alleged that Burton Scot contacted Jatsek again and submitted a
    proposed subcontract agreement for some, but not all, of the work previously bid on by
    Jatsek.
    {¶5} Jatsek alleged that it informed Burton Scot that, because of the lapse of time
    from the initial discussions to the proposed amended contract, it was “unable to perform
    the tasks as originally bid.” Complaint, ¶ 40. According to Jatsek’s complaint, “Burton
    Scot requested that Jatsek perform whatever duties it was able to, with the understanding
    that the bid prices for the work performed would be honored.” Id. at ¶ 41.
    {¶6} The complaint alleged that Jatsek modified the proposed subcontract and
    submitted it to Burton Scot. “Jatsek did complete the tasks it agreed to in the modified
    subcontract agreement, although Burton Scot never executed the document and thus no
    contract was ever formed.” Id. at ¶ 43.        Jatsek further alleged that it was not paid for
    its work. According to Jatsek, it “understood, by the acts, words, and deeds of Burton
    Scot that it would be paid the unit prices as set forth in the original bid and in the various
    proposed subcontracts.” Id. at ¶ 44.
    B.    Burton Scot’s Answer and Motion to Stay
    {¶7} Burton Scot answered, and relative to the Greenway project, admitted that
    Jatsek performed work on the project, but had not been paid. In its motion to stay
    proceedings pending arbitration, Burton Scot contended that the subcontract agreement
    required mandatory and binding arbitration. Burton Scot submitted the affidavit of its
    vice president in support of the motion to stay.     The vice president averred that on May
    26, 2010, Jatsek submitted a bid proposal for the Greenway project, Burton Scot accepted
    the bid on August 5, 2010, and issued the written contract for the project to Jatsek on
    September 17, 2010.
    {¶8} The vice president further averred that Jatsek began working at the Greenway
    project on October 18, 2010, and on October 30, 2010, issued its first invoice for work
    performed on the project.      According to the vice president, on November 7, 2010, Jatsek
    executed and returned the written contract.      In executing the contract, however, Jatsek
    made handwritten modifications to certain provisions in the contract.        The vice president
    averred that those modifications were not acceptable to Burton Scot and Burton Scot did
    not consent in writing to them.
    {¶9} Burton Scot also submitted the written contract in support of its motion to
    stay.   Paragraph 31 of the contract provided in relevant part as follows:
    At the sole option of Contractor, any and all claims, disputes, controversies,
    demands, and causes of action of whatever nature, kind or description
    arising from or relating to this Agreement, including without limitation
    contract, equity, tort or legal claims, and further including without limitation
    claims relating to rights of payment or interpretations hereof, shall be
    submitted to mandatory and binding arbitration in the Cleveland Tribunal of
    the American Arbitration Association in accordance with the Construction
    Industry Arbitration Rules of the American Arbitration Association. The
    decision and Award of the Arbitrator(s) shall be final and binding on
    Contractor and Subcontractor, and the decision and Award may be reduced
    to judgment and enforced in any Court of competent jurisdiction.
    {¶10} The contract was signed and dated (November 7, 2010) by Jatsek’s vice
    president, but was not signed by a Burton Scot representative.               The contract had
    handwritten changes, but not to the arbitration provision.
    {¶11} Jatsek opposed the motion to stay. The company argued that Burton Scot
    never executed the agreement, but even if a contract was formed, Jatsek was entitled to
    judgment because there was no dispute that it performed the work agreed to under the
    contract, but had not been paid.
    {¶12} The trial court ruled that no contract existed for the Greenway project.           The
    motion for stay was therefore denied as it related to that project.1 For its sole assigned
    error, Burton Scot contends that:       “The trial court erred as a matter of law in denying
    Appellant Burton Scot Contractors, LLC’s Motion to Stay Proceedings Pending
    Arbitration as it relates to the City of Warren Greenway Bike Trail public improvement
    project in Warren, Ohio.”
    II. Law and Analysis
    {¶13} Burton Scot notes that there is a split of authority on whether this court’s
    standard of review is abuse of discretion or de novo. Burton Scot contends that the split
    is “immaterial” to this case because reversal is required under either standard.         Jatsek, on
    the other hand, contends that this court has “consistently reviewed the denial of a motion
    to stay proceedings under an abuse of discretion standard.”
    {¶14} In McCaskey v. Sanford-Brown College, 8th Dist. No. 97261,
    
    2012-Ohio-1543
    , this court recently held that the standard of review in these type of cases
    depends on the type of question raised regarding the applicability of the arbitration
    1
    A stay was granted, however, relative to the other two projects. Jatsek had also filed a
    motion for partial summary judgment relative to the Greenway project, which the trial court granted.
    That portion of the trial court’s judgment is not a final appealable order and therefore is not now
    before this court.
    provision. This court noted that when the issue to be resolved involves “whether a party
    has agreed to submit an issue to arbitration,” a de novo standard applies. Id. at ¶ 7, citing
    Shumaker v. Saks Inc., 
    163 Ohio App.3d 173
    , 
    2005-Ohio-4391
    , 
    837 N.E.2d 393
     (8th Dist.)
    and Vanyo v. Clear Channel Worldwide, 
    156 Ohio App.3d 706
    , 
    2004-Ohio-1793
    , 
    808 N.E.2d 482
     (8th Dist.).
    {¶15} In this case, the trial court ruled that no contract existed for the Greenway
    project; that is, that the parties did not agree to submit to arbitration any disputes relative
    to the project.   Thus, we review the trial court’s decision de novo.      A de novo review
    involves “an appeal in which the appellate court uses the trial court’s record but reviews
    the evidence and law without deference to the trial court’s rulings.”            Black’s Law
    Dictionary 94 (7th Ed.2001).     The issue to be decided in our review is whether a contract
    existed between Jatsek and Burton Scot for the Greenway project. We find that it did.
    {¶16} In so finding, we follow this court’s precedent as set forth in G. Herschman
    Architects, Inc. v. Ringco Mfg. Co., Inc., 8th Dist. No. 67758, 
    1995 Ohio App. LEXIS 1940
     (May 11, 1995). In Herschman, Herschman and Ringco entered into discussions in
    an attempt to reach an agreement through which Herschman would provide Ringco with
    architectural services in the design of department store display stands. Pursuant to their
    discussions, Herschman faxed to Ringco a proposal, dated June 23, 1992, in which it
    outlined the scope of, as well as fees for, the project.
    {¶17} The parties engaged in negotiations of the June 23 proposal, and on June 29,
    1992, Herschman sent a revised proposal to Ringco. The parties did not sign the revised
    June 29 proposal; nonetheless, Herschman began working on the project as outlined in the
    proposal. Herschman exceeded the number of hours as set forth in the June 29 proposal
    in performing its duties.       The parties attempted to come to an agreement on the
    reasonable value of Herschman’s services, but did not, and Herschman filed suit.                The
    matter proceeded to trial, and the trial court entered judgment in favor of Herschman.
    {¶18} On appeal, Ringco argued that the parties never agreed to Herschman’s June
    29 proposal and, therefore, no written contract between the parties existed.             This court
    disagreed and found that the “terms of the final agreement were reflected in the June 29,
    1992 proposal.”     Id. at *10. In so finding, this court reasoned that “conduct sufficient to
    show agreement, including performance, is a reasonable mode of acceptance” of an offer.
    Id. at *9, citing Am. Bronze Corp. v. Streamway Prod., 
    8 Ohio App.3d 223
    , 
    456 N.E.2d 1295
    , paragraph two of the syllabus (8th Dist.1982). In Herschman, it was
    undisputed by the parties that [Herschman] did engage in the performance of
    work for the design and manufacture of the display stands. Upon the
    beginning of the work by [Herschman], there was in effect an actual implied
    contract that Ringco acquiesced to by its language and conduct.
    
    Id.
    {¶19} Similarly, in this case, it is undisputed that Jatsek performed work on the
    Greenway project.      On the authority of Herschman, upon the start of the work by Jatsek,
    an actual implied contract was formed to which the parties acquiesced.2
    2
    See also Nagle Heating & Air Conditioning Co. v. Heskett, 
    66 Ohio App.3d 547
    , 
    585 N.E.2d 866
     (4th Dist.1990) and Hocking Valley Community Hosp. v. Community Health Plan of Ohio, 4th
    Dist. No. 02CA28, 
    2003-Ohio-4243
    , both holding that an unexecuted written contract is enforceable if
    the parties proceeded to act as if the contract was in effect.
    {¶20} Jatsek alternatively urges that if we find that a contract existed between the
    parties, that “such agreement ‘must yield, at times, when justified by public policy
    considerations of judicial economy.’” Jatsek’s appellate brief, p.4, quoting Dynamark
    Sec. Ctrs., Inc. v. Charles, 9th Dist. No. 21254, 
    2003-Ohio-2156
    , ¶ 12. Dynamark
    presented a different scenario, however, than is presented here.
    {¶21} In Dynamark, the plaintiffs, a franchiser and its subsidiary, entered into a
    franchise agreement with the defendant in 1993; the agreement contained an arbitration
    clause.     In 1996, a dispute between the parties arose, and resulted in the plaintiffs suing
    the defendant in 1997. Various pretrial proceedings were had, including the filing of and
    ruling on motions for summary judgment, an injunction proceeding, and mediation.
    After numerous continuances were sought by both parties, and granted, the case was
    ultimately set to proceed to trial on February 6, 2002. On January 22, 2002, the plaintiffs
    filed a motion to stay pending arbitration, which the trial court denied.
    {¶22} The Ninth Appellate District upheld the denial.    In doing so, the appellate
    court reviewed for an abuse of discretion; our review here, however, is de novo.          The
    appellate court applied the doctrine of waiver in finding that the trial court had not abused
    its discretion. The Ninth District found that the plaintiffs “acted in a manner inconsistent
    with their right to seek arbitration, rather than litigation, to resolve their contract dispute
    with [the defendant].” Id. at ¶ 15. Specifically, the plaintiffs did the following: (1) filed
    the complaint, rather than pursue arbitration in 1997; (2) did not raise the arbitration
    provision as an affirmative defense in their answer to the defendant’s counterclaims; (3)
    went through years of trial preparation, including extensive discovery, motion practice,
    and numerous hearings; (4) filed an amended complaint; and (5) mediated the dispute.
    {¶23} On that record, the appellate court found that the plaintiffs “waived their
    right to arbitration [because] they did not properly raise the arbitration provision before the
    trial court, but instead actively participated in preparing for litigation of the case for five
    years.” Id. at ¶ 19.
    {¶24} This case presents a factual background distinguishable from Dynamark for
    three reasons. First, the party seeking to enforce the arbitration provision, Burton Scot,
    did not initiate the action as in Dynamark; rather it was defending against the action.
    Second, Jatsek filed the action in June 2011, and Burton Scot filed its motion to stay in
    July 2011, a stark contrast to the five-year delay in Dynamark.           And third, because
    Burton Scot filed its motion to stay approximately one month after Jatsek filed the action,
    pretrial proceedings here were scant, as opposed to the extensive proceedings that were
    had in Dynamark. Thus, disallowing arbitration in this case would not advance public
    policy considerations of judicial economy.
    {¶25} Moreover, resolving disputes through arbitration is generally favored in the
    law. Williams v. Aetna Fin. Co., 
    83 Ohio St.3d 464
    , 471, 
    1998-Ohio-294
    , 
    700 N.E.2d 859
    . There is a strong presumption in favor of arbitration, and any doubt should be
    resolved in favor of arbitrability. Melia v. OfficeMax N. Am. Inc., 8th Dist. No. 87249,
    
    2006-Ohio-4765
    , ¶15, citing Neubrander v. Dean Witter Reynolds, Inc., 
    81 Ohio App.3d 308
    , 
    610 N.E.2d 1089
     (9th Dist.1992).
    {¶26} In light of the above, the trial court erred in denying Burton Scot’s motion to
    stay pending arbitration. Burton Scot’s sole assignment of error is therefore sustained.
    {¶27} Judgment reversed; case remanded.
    It is ordered that appellants recover of appellees costs herein taxed.
    The court finds there were reasonable grounds for this appeal.
    It is ordered that a special mandate issue out of this court directing the Cuyahoga
    County Court of Common Pleas to carry this judgment into execution.
    A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of the
    Rules of Appellate Procedure.
    LARRY A. JONES, SR., JUDGE
    PATRICIA ANN BLACKMON, A.J., and
    MARY J. BOYLE, J., CONCUR
    

Document Info

Docket Number: 98142

Judges: Jones

Filed Date: 8/30/2012

Precedential Status: Precedential

Modified Date: 10/30/2014