Evans Landscaping, Inc. v. Stenger , 2011 Ohio 6033 ( 2011 )


Menu:
  • [Cite as Evans Landscaping, Inc. v. Stenger, 
    2011-Ohio-6033
    .]
    IN THE COURT OF APPEALS
    FIRST APPELLATE DISTRICT OF OHIO
    HAMILTON COUNTY, OHIO
    EVANS LANDSCAPING, INC.,                             :          APPEAL NO. C-110104
    TRIAL NO. A-0910954
    Plaintiff-Appellant,                       :
    vs.                                          :
    TONY STENGER,                                        :             O P I N I O N.
    and                                          :
    SHARLA STENGER,                                      :
    Defendants-Appellees.                      :
    Civil Appeal From: Hamilton County Court of Common Pleas
    Judgment Appealed From Is: Affirmed in Part, Reversed in Part, and Cause
    Remanded
    Date of Judgment Entry on Appeal: November 23, 2011
    Anthony J. Muto, for Plaintiff-Appellant,
    David M. Blank, for Defendants-Appellees.
    Please note: This case has been removed from the accelerated calendar.
    OHIO FIRST DISTRICT COURT OF APPEALS
    FISCHER, Judge.
    {¶1}   Plaintiff-appellant Evans Landscaping, Inc., (“Evans”) appeals the trial
    court’s judgment awarding defendants-appellees Tony and Sharla Stenger (the
    “Stengers”) $42,490 on their breach-of-contract and nuisance counterclaims against
    Evans relating to the construction of a pond. Evans also appeals the trial court’s
    judgment awarding Evans $8,389 on its claim for breach of contract against the
    Stengers for unpaid landscaping work. For the reasons discussed below, we reverse
    that part of the trial court’s judgment awarding the Stengers loss-of-use and
    annoyance-and-inconvenience damages, and we also reverse the trial court’s
    judgment awarding Evans $8,389, instead of $8,329. We affirm the remainder of
    the trial court’s judgment.
    Factual and Procedural Background
    {¶2}   In 2008, the Stengers hired David Habig of Evans to perform
    numerous landscaping services for their home in Walton, Kentucky, including
    constructing a fish pond, installing a fire pit and stone bench, and delivering plants.
    Evans estimated that the pond would cost the Stengers $20,000 to $25,000. The
    parties did not enter into a written contract, and instead Evans sent the Stengers
    invoices as the work progressed. Evans began the landscaping work, and at first the
    Stengers were pleased with Habig’s management.
    {¶3}   By mid-June 2008, Evans had completed the pond. Soon after the
    completion date, however, the pond began to leak. Evans tried multiple times to find
    the source of the leak, and also made multiple repairs, but the water level of the pond
    continued to drop inexplicably. The water level fell so low that, as Mrs. Stenger
    testified, the pond was “nothing but green scum.” Because of the unsightly pond,
    2
    OHIO FIRST DISTRICT COURT OF APPEALS
    and the mosquitoes that swarmed around it, the Stengers could not use their
    backyard. The Stengers became increasingly frustrated with Evans’s attempts to
    repair the pond, and eventually, they stopped making payments on the invoices that
    Evans sent to them.
    {¶4}   Evans filed a complaint in Hamilton County Municipal Court in March
    2009 against Mr. Stenger, which Evans eventually amended to add claims against
    Mrs. Stenger as well. The amended complaint alleged that the Stengers owed Evans
    $11,525.86, plus interest, on three invoices for the pond, plants, mulching, and the
    stone bench. Evans also alleged that the Stengers owed $8,798.77 for plants under a
    fourth invoice.
    {¶5}   In June 2009, well after the filing of the initial complaint, Evans’s
    workers attempted to repair the pond once again, and in doing so, left dead fish
    scattered in the Stengers’ backyard. As a result of this repair attempt, the Stengers
    had a meeting with Habig and another Evans employee to discuss the pond. When
    the Stengers could not reach a solution with Evans, they decided to rebuild the pond
    themselves.
    {¶6}   Mrs. Stenger testified that, before beginning the rebuilding project, she
    and her husband had hired Chris Dickerson of Gardens of Water to design the pond
    and to give advice on the proper method of construction. Dickerson charged the
    Stengers $4,272.80 for his services. The Stengers deconstructed and reconstructed
    the pond in 16 days with the help of hired workers, and they completed the pond by
    October 2009 at a cost of $24,990. Mrs. Stenger testified that she kept notes on all
    the expenses incurred as a result of the project, which included replacement fish,
    3
    OHIO FIRST DISTRICT COURT OF APPEALS
    materials, equipment rental, payments made to hired workers for their labor, as well
    time spent for their own labor.
    {¶7}   The pond was not the only problem that the Stengers had with Evans’s
    performance. Evans also delivered various plants to the Stengers, which Evans had
    guaranteed would live for at least one year. The Stengers received the invoice for the
    plants in October 2009 in the amount of $8,798.77. Mrs. Stenger testified that not
    all of the invoiced plants were delivered, that some of the plants were returned, and
    that some of the plants did not live through the one-year period.
    {¶8}   The Stengers filed counterclaims against Evans for breach of contract
    with regard to the construction of the pond, and for nuisance, alleging that Evans
    had had a duty to construct the pond in a workmanlike manner and that Evans had
    breached that duty, negligently creating a nuisance on their property. The Stengers
    also alleged a breach-of-contract claim with regard to the plants. The action was
    eventually transferred to the Hamilton County Court of Common Pleas, where it
    proceeded to a bench trial.
    {¶9}   At trial, Habig testified that he was not experienced in pond
    construction and that, because the pond had continually leaked, at some point it had
    to be reconstructed. Habig took issue with the Stengers’ calculation of damages. He
    testified that, in his opinion, the Stengers could have deconstructed and
    reconstructed the pond in less time and for less money. Habig also testified as to the
    unpaid invoices owed to Evans. Contrary to the Stengers’ allegations, Habig testified
    that all the invoiced plants had been delivered.
    {¶10} The trial court determined that the Stengers had proved their breach-
    of-contract claim with regard to the pond. The trial court found that the pond had
    4
    OHIO FIRST DISTRICT COURT OF APPEALS
    not been constructed as agreed. From this finding, the trial court concluded that
    Evans owed the Stengers cost-to-repair damages in the amount of $24,990.
    {¶11} The trial court also determined that the Stengers had proved that
    Evans had negligently created a nuisance on the Stengers’ property. The trial court
    found that the Stengers had been subjected to annoyance and inconvenience by the
    failed repair attempts, and that the Stengers had suffered the loss of the use of their
    property. The trial court concluded that the Stengers had suffered $10,000 and
    $7,500 in damages for their loss of use and for their annoyance and discomfort,
    respectively.
    {¶12} The trial court also found that Evans had not delivered all the plants as
    agreed upon, and that not all of the delivered plants had lived through the one-year
    guaranteed period. The trial court found that the Stengers had acknowledged that
    they owed Evans $8,389, which included mulching, installing the stone bench, and
    the cost of the plants less those plants that had not been delivered or had not lived.
    The trial court then entered judgment for Evans on its breach-of-contract claim in
    the amount acknowledged by the Stengers. Evans now appeals from the trial court’s
    judgment.
    Contract Damages Versus Tort Damages
    {¶13} In Evans’s first assignment of error, Evans argues that the trial court
    erred in awarding the Stengers damages for nuisance and for loss of use.
    {¶14} Evans argues that under the rule in Ohio Collieries Co. v. Cocke (1923),
    
    107 Ohio St. 238
    , 
    140 N.E. 356
    , where real property has been damaged, although not
    irreparably, the property owner is limited to damages for the reasonable cost to
    restore the property and for the reasonable value of the loss of use of the property
    5
    OHIO FIRST DISTRICT COURT OF APPEALS
    during the damaged period. The Stengers respond that the Ohio Collieries rule has
    been expanded to allow for the recovery of damages for personal annoyance and
    discomfort. See, e.g., Denoyer v. Lamb (1984), 
    22 Ohio App.3d 136
    , 138-139, 
    490 N.E.2d 615
     (applying 4 Restatement of the Law 2d, Torts (1965), Section 929, which
    allows damages for costs to repair the property, loss of use of the property, and
    personal annoyance and discomfort in cases where property has been damaged, but
    not totally destroyed).
    {¶15} Although the parties seemingly agree that the Ohio Collieries rule of
    damages in a tort action applies to the Stengers’ counterclaims, we determine that
    the Ohio Collieries rule has no applicability in this situation, and that the Stengers
    are limited to the recovery of contract damages only.
    {¶16} The Stengers’ counterclaims alleged claims under both tort and
    contract law. The Stengers alleged a breach-of-contract claim against Evans for its
    failure to complete the construction of the pond as expected. They also alleged that
    Evans had had a duty to construct the pond in a workmanlike manner, and that
    Evans had breached that duty, negligently creating a nuisance on their property. In
    general, where a contract action exists against a breaching party, a tort claim based
    upon the same underlying actions cannot coexist with the contract action, unless the
    breaching party also breached a duty owed independent of the contract. Textron Fin.
    Corp. v. Nationwide Mut. Ins. Co. (1996), 
    115 Ohio App.3d 137
    , 151, 
    684 N.E.2d 1261
    . The only duty alleged to have been breached by Evans was the duty to perform
    in a workmanlike manner.
    {¶17} The duty of a builder or contractor to perform in a workmanlike
    manner is implied by the common law. Barton v. Ellis (1986), 
    34 Ohio App.3d 251
    ,
    6
    OHIO FIRST DISTRICT COURT OF APPEALS
    252, 
    518 N.E.2d 18
    , citing Mitchem v. Johnson (1966), 
    7 Ohio St.2d 66
    , 
    218 N.E.2d 594
    ; Velotta v. Leo Petronzio Landscaping, Inc. (1982), 
    69 Ohio St.2d 376
    , 
    433 N.E.2d 147
    . In Kishmarton v. William Bailey Constr., Inc., 
    93 Ohio St.3d 226
    , 2001-
    Ohio-1334, 
    754 N.E.2d 785
    , paragraph one of the syllabus, the supreme court held
    that where a home builder and resident enter into an agreement for the future
    construction of a home, the resident’s cause of action for breach of an implied duty to
    build the home in a workmanlike manner arises out of the contract, ex contractu. By
    contrast, the supreme court held in Velotta, 69 Ohio St.2d at paragraph one of the
    syllabus, that “[a]n action by a vendee against the builder-vendor of a completed
    residence for damages proximately caused by failure to construct in a workmanlike
    manner using ordinary care * * * is an action in tort * * *.” (Emphasis added).
    Therefore, if two parties enter into an agreement in which one party promises to
    build something in the future, the duty to build in a workmanlike manner arises out
    of the contract. If parties enter into an agreement in which one party promises to sell
    something that has already been constructed at the time of contracting, the
    workmanlike-manner duty arises in tort.
    {¶18} Evans and the Stengers contracted for the future construction of the
    pond, and therefore Evans’s duty to perform in a workmanlike manner in
    constructing the pond arose out of the parties’ agreement. See, also, Hanna v.
    Groom, 10th Dist. No. 07AP-502, 
    2008-Ohio-765
    , ¶21 (applying Kishmarton and
    determining that “because the paving contract was for future services, plaintiff’s
    implied duty to perform in a workmanlike manner arose ex contractu as an implied
    bargain * * *.”).
    7
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶19} Because the only duty identified by the Stengers in their
    counterclaim—the duty to perform in a workmanlike manner—arises out of the
    parties’ agreement, the Stengers cannot rely on the breach of this duty as the basis
    for their nuisance claim. Textron Fin. Corp., 115 Ohio App.3d at 151. The Stengers
    must rely on an independent duty to succeed on their nuisance claim. See Neville v.
    City of Wyoming, 1st Dist. No. C-020064, 
    2002-Ohio-4936
    , ¶13 (a qualified-
    nuisance claim requires a showing of negligence). Without identifying any other
    duty alleged to have been breached, independent of those arising out of the contract,
    the Stengers are limited to recovery under contract principles.
    {¶20} In Kishmarton, the supreme court addressed the damages available in
    a contract action.    The Kishmarton court adopted Restatement of the Law 2d,
    Contracts (1981), Section 353, which states that “[r]ecovery for emotional
    disturbance will be excluded unless the breach also caused bodily harm or the
    contract or the breach is of such a kind that serious emotional disturbance was a
    particularly likely result.” 93 Ohio St.3d at 230. The supreme court determined that
    damages for loss of enjoyment of a residence and annoyance and discomfort were
    not properly recoverable as emotional-distress damages in a contract action absent
    the required showing under Section 353. Id. at 230.
    {¶21} Applying Section 353 to the instant matter, no evidence exists in the
    record that Evans’s breach of contract caused bodily harm to the Stengers or that
    serious emotional disturbance was a likely result of Evans’s breach. Therefore, we
    must reverse that part of the trial court’s judgment awarding the Stengers $10,000
    for loss of use of their property, and $7,500 for annoyance and inconvenience. We
    sustain Evans’s first assignment of error.
    8
    OHIO FIRST DISTRICT COURT OF APPEALS
    Cost-to-Repair Damages
    {¶22} In Evans’s second assignment of error, Evans argues that the trial
    court erred in awarding the Stengers $24,990 for the cost to repair the pond. Evans
    first argues that the trial court erred in awarding cost-to-repair damages where no
    evidence was presented on the diminution in value of the property. We will not
    address this issue because Evans withdrew it at oral argument.
    {¶23} Secondly, Evans contends that expert testimony was required to
    determine the appropriate manner in which to repair the leaking pond, and to
    determine the reasonableness of the Stengers’ repair costs.            Without expert
    testimony, Evans argues, the Stengers’ actions in repairing the pond could have been
    excessive and unnecessary.      Evans further argues that the trial court erred in
    accepting the Stengers’ calculation of hours, rate of pay, and equipment needed to
    repair the pond, because the Stengers were not qualified experts on pond
    construction.
    {¶24} We review a trial court’s decision admitting or excluding evidence for
    an abuse of discretion. Beard v. Meridia Huron Hosp., 
    106 Ohio St.3d 237
    , 2005-
    Ohio-4787, 
    834 N.E.2d 323
    , ¶20. Evid.R. 702 permits expert testimony where the
    subject matter is outside the realm of a layperson’s common knowledge or
    experience. Ohio law does not require expert testimony on all issues of cost-to-repair
    damages. As noted by the Second Appellate District in a case dealing with termite
    damage to residential property, “[e]xpert testimony is not always required to
    establish the necessity of repairs or the reasonableness of the costs incurred to repair
    * * *.” McCoy v. Good, 2d Dist. No. 06-CA-34, 
    2007-Ohio-327
    , ¶21.
    9
    OHIO FIRST DISTRICT COURT OF APPEALS
    {¶25} Evans places primary reliance on Hellkamp v. Boiman (1970), 
    25 Ohio App.2d 117
    , 
    267 N.E.2d 323
    , in arguing that the Stengers were required to present
    expert testimony on the issue of cost-to-repair damages. In Hellkamp, the trial court
    ordered specific performance on a real-estate purchase contract in favor of the
    Hellkamps, the buyers. In addition to awarding specific performance, the trial court
    also awarded monetary damages to the Hellkamps for, among other items, damage
    sustained to the driveway. When Mr. Hellkamp was asked if he had an opinion as to
    the value he would place on repairing the driveway, he replied, “[a] couple hundred
    dollars.” Id. at 122. This court determined that the trial court erred in permitting
    Mr. Hellkamp to testify “when there was no testimony by him that he was qualified
    as an expert to determine the fair and reasonable repair costs of the driveway.” Id.
    {¶26} Unlike Hellkamp, where Mr. Hellkamp had yet to repair the driveway
    and was merely speculating as to the cost to repair, in this case, the Stengers actually
    repaired the pond themselves. The trial court could have reasonably inferred from
    the evidence presented, without the aid of expert testimony, that the repairs to the
    pond performed by the Stengers were necessary. Evans’s representative, Habig,
    testified that Evans was not experienced in constructing ponds, and that the pond
    kept leaking despite multiple efforts by Evans to find a solution. Habig testified that,
    because of the leaks, at some point the pond would have had to have been
    deconstructed and then reconstructed. The Stengers testified that they, along with
    hired workers, based on the advice of Gardens of Water, deconstructed and
    reconstructed the pond, and that the pond no longer leaks.
    {¶27} Evans also argues that the trial court erred in allowing Mrs. Stenger,
    who was not a qualified expert, to testify as to the “outrageously large number of
    10
    OHIO FIRST DISTRICT COURT OF APPEALS
    hours of labor and excessive equipment use * * *.” Mrs. Stenger testified that she
    and Mr. Stenger spent $24,990 in deconstructing and reconstructing the pond.
    Evans had the opportunity to attack the reasonableness of these repair costs through
    cross-examination and through the testimony of its own witnesses. Evans did not
    present any expert witnesses; however, Evans rebutted the Stengers’ damages
    calculation with testimony from Habig that he believed the pond could have been
    deconstructed and reconstructed in a shorter period of time, and that the workers
    could have been paid less per hour. Nevertheless, the amount that the Stengers
    spent to repair the pond, $24,990, is not out of proportion to the $20,000-to-
    $25,000 estimate that Evans gave to the Stengers initially to construct the pond.
    Therefore, we cannot determine that the trial court erred in deciding the necessity
    and reasonableness of the cost-to-repair damages without the aid of expert
    testimony.
    {¶28} Finally, Evans argues that the Stengers failed to prove their cost-to-
    repair damages with reasonable certainty, as they are required to do in a contract
    action. Texatron Fin. Corp., 115 Ohio App.3d at 144. Evans argues that the Stengers’
    damages were speculative and unsupported because the Stengers only provided the
    court with handwritten notes, and no invoices, time sheets, or canceled checks.
    {¶29} Evans’s argument that the Stengers failed to establish their damages
    with reasonable certainty is not well taken. The Stengers testified as to the damages
    incurred, and the detailed notes kept by Mrs. Stenger regarding those damages were
    accepted as evidence. We cannot hold that the Stengers’ evidence was speculative,
    even if not corroborated with other evidence, because it was evidence of actual
    expenses incurred. We overrule Evans’s second assignment of error.
    11
    OHIO FIRST DISTRICT COURT OF APPEALS
    Manifest Weight of the Evidence
    {¶30} In Evans’s third assignment of error, it contends that the trial court
    erred in awarding Evans only $4,660 on its breach-of-contract claim against the
    Stengers for plant delivery. We will not reverse a trial court’s award on manifest-
    weight grounds as long as the award is supported by some competent, credible
    evidence. C.E. Morris Co. v. Foley Constr. Co. (1978), 
    54 Ohio St.2d 279
    , 
    376 N.E.2d 578
    , syllabus. Evans did not dispute at trial that it had delivered various plants to
    the Stengers, and that Evans had guaranteed the plants for one year. Mrs. Stenger
    testified that not all of the invoiced plants had been delivered, that some of the plants
    had been returned, and that some of the plants had not lived through the one-year
    period.
    {¶31} The trial court clearly chose to believe Mrs. Stenger’s testimony
    regarding the amount owed to Evans. The trial court stated on the record that it
    found that the Stengers owed Evans $4,600 for the plants, in accordance with Mrs.
    Stenger’s testimony. The trial court’s findings of fact and conclusions of law were
    inconsistent with the trial court’s statements on the record, in that the written
    findings provided that the Stengers owed $4,660 for the plants.          Therefore, we
    sustain Evans’s third assignment of error to the limited extent that no competent,
    credible evidence existed for the trial court’s written findings that the Stengers owed
    $4,660 for the plants, instead of $4,600.
    {¶32} In conclusion, the portion of the trial court’s judgment awarding the
    Stengers $10,000 for loss of use of their property and $7,500 for annoyance and
    inconvenience is reversed, and the portion of the trial court’s judgment awarding
    Evans $8,389 on its breach-of-contract claim is reversed, and the cause is remanded
    12
    OHIO FIRST DISTRICT COURT OF APPEALS
    to the trial court. We order the trial court on remand to enter judgment for Evans on
    its breach-of-contract claim in the amount of $8329—instead of $8389, and further
    order the trial court to enter judgment for the Stengers on their claims in the amount
    of $24,990. We affirm the remainder of the judgment of the trial court.
    Affirmed in part, reversed in part, and cause remanded.
    DINKELACKER, P.J., and SUNDERMANN, J., concur.
    Please Note:
    The court has recorded its own entry on the date of the release of this opinion.
    13