Boone Coleman Constr., Inc. v. Piketon , 2016 Ohio 1557 ( 2016 )


Menu:
  • [Cite as Boone Coleman Constr., Inc. v. Piketon, 2016-Ohio-1557.]
    IN THE COURT OF APPEALS OF OHIO
    FOURTH APPELLATE DISTRICT
    PIKE COUNTY
    BOONE COLEMAN                                     :       Case No. 13CA836
    CONSTRUCTION, INC.,
    Plaintiff-Appellant,                      :
    v.                                        :       DECISION AND
    JUDGMENT ENTRY
    VILLAGE OF PIKETON, OHIO,                         :
    Defendant-Appellee.                    :
    APPEARANCES:
    Stephen C. Rodeheffer and John A. Gambill, Portsmouth, OH, for appellant.
    Eric B. Travers and Timothy A. Kelley, Kegler Brown Hill & Ritter, L.P.A., Columbus,
    OH, for appellee.
    Harsha, J.
    {¶1}    This cause is before us on remand from the Supreme Court of Ohio. In
    Boone Coleman Constr., Inc. v. Piketon, 2014-Ohio-2377, 
    13 N.E.3d 1190
    (4th Dist.),
    we sustained that portion of Boone Coleman’s first assignment of error contesting the
    trial court’s awarding of liquidated damages to Piketon on a public-road-construction
    contract. We held that the $277,900 amount of liquidated damages was so manifestly
    unreasonable and disproportionate to the contract price of $683,300 that it constituted
    an unenforceable penalty, and reversed that portion of the trial court’s summary
    judgment enforcing the liquidated-damages provision. We affirmed the remainder of the
    judgment. On review the Supreme Court of Ohio vacated that part of our judgment that
    held the liquidated-damages provision constituted an unenforceable penalty. The court
    remanded the cause to us to reconsider the liquidated-damages provision in light of its
    Pike App. No. 13CA836                                                                           2
    opinion. Boone Coleman v. Piketon, __ Ohio St.3d __, 2016-Ohio-628, __ N.E.3d __, ¶
    42.
    A. ANALYSIS
    {¶2}    The applicable test to determine whether a contractual provision should be
    considered a liquidated-damages provision or an unenforceable penalty is set forth in
    Samson Sales, Inc. v. Honeywell, Inc., 
    12 Ohio St. 3d 27
    , 
    465 N.E.2d 392
    (1984),
    syllabus:
    Where the parties have agreed on the amount of damages, ascertained by
    estimation and adjustment, and have expressed this agreement in clear
    and unambiguous terms, the amount so fixed should be treated as
    liquidated damages and not as a penalty, if the damages would be (1)
    uncertain as to amount and difficult of proof, and if (2) the contract as a
    whole is not so manifestly unconscionable, unreasonable, and
    disproportionate in amount as to justify the conclusion that it does not
    express the true intention of the parties, and if (3) the contract is
    consistent with the conclusion that it was the intention of the parties that
    damages in the amount stated should follow the breach thereof.
    The Supreme Court held that we properly applied the first and third parts of the Samson
    Sales test. But, the Supreme Court held that we erred in applying the second part of the
    test. 
    Id. at ¶
    31. Upon remand, it is apparent that application of the principles set forth
    in the Supreme Court’s opinion demands the conclusion that “the contract as a whole is
    not so manifestly unconscionable, unreasonable, and disproportionate in amount as to
    justify the conclusion that it does not express the true intention of the parties.” Id at ¶
    syllabus. 1
    1
    As the Supreme Court noted, determining whether the stipulated sum is an unenforceable penalty or an
    enforceable provision for liquidated damages is a “difficult problem,” i.e. “it is sometimes difficult to
    determine whether the terms actually provide for damages or for a penalty.” Id at ¶ 16 and 28. Thus
    prospective vision, rather than hindsight, is critical to the analysis.
    Pike App. No. 13CA836                                                              3
    {¶3}   As the Supreme Court observed at ¶ 30-33 of its decision (footnote
    omitted):
    {¶ 30} * * * Piketon and Boone Coleman did not contract for a lump sum.
    Rather, the parties contracted for a per diem measure of damages which,
    as Chief Justice Marshall recognized, is more likely to be an enforceable
    liquidated-damages provision than an unenforceable penalty: “[T]he
    agreement to pay a specified sum weekly during the failure of the party to
    perform the work, partakes much more of the character of liquidated
    damages than the reservation of a sum in gross.” Tayloe v. T. & S.
    Sandiford, 
    20 U.S. 13
    , 18, 
    7 Wheat. 13
    , 
    5 L. Ed. 384
    (1822). * * *
    {¶ 31} More importantly, the appellate court's myopic focus on the
    reasonableness of the total amount of liquidated damages in application,
    rather than on the reasonableness of the per diem amount in the contract
    terms, was not proper. The correct analysis looks at whether it was
    conscionable to assess $700 per day in liquidated damages for each day
    that the contract was not completed rather than looking at the aggregate
    amount of the damages awarded. Accord Carrothers Constr. 
    Co., 288 Kan. at 759
    , 
    207 P.3d 231
    .
    {¶ 32} Although per diem amounts vary greatly in the case law, courts
    have upheld liquidated-damages provisions in public-construction
    contracts with per diem amounts similar to those at issue here. See, e.g.,
    Sec. Fence Group, Inc. v. Cincinnati, 1st Dist. Hamilton No. C–020827,
    2003-Ohio-5263, 
    2003 WL 22270179
    (enforcing a per diem liquidated-
    damages provision in a public-bridge-replacement project that imposed
    $600 per day); see also Carter Steel & Fabricating Co. v. Ohio Dept. of
    Transp., 102 Ohio Misc.2d 1, 
    721 N.E.2d 1115
    (Ct. of Cl.1999) (impliedly
    recognizing the validity of a liquidated-damages per diem provision in
    bridge-construction project that imposed $600 in liquidated damages per
    day, but refusing to enforce it against subcontractor who had no control
    over delay); Hovas 
    Constr., 111 So. 3d at 667
    (upholding as reasonable a
    $500 per diem assessment of liquidated damages in public-construction
    contract); Carrothers Constr. 
    Co., 288 Kan. at 759
    , 
    207 P.3d 231
    ($850
    Pike App. No. 13CA836                                                               4
    per diem assessment of liquidated damages held reasonable in public-
    construction contract). In fact, courts have upheld far greater amounts of
    per diem damages in construction contracts. See, e.g., Dade Cty. Pub.
    Health 
    Trust, 577 So. 2d at 638
    (upholding as “perfectly reasonable” a
    liquidated-damages provision imposing $2,500 in damages per day in
    public-construction project for medical facility); Bethlehem Steel Corp. v.
    Chicago, 
    350 F.2d 649
    (7th Cir.1965) (upholding a liquidated-damages
    provision imposing $1,000 in damages per day in public-construction
    project for elevated highway, even though contractor's delay did not
    prevent highway from opening to public on date scheduled). See also
    Unruh & Worden, 34 Santa Clara L.Rev. 1, at fn. 1 (in commercial
    construction contracts, “a typical per diem liquidated damages provision
    might provide that the general contractor pay the owner/developer
    $10,000 for each calendar day” of delay).
    {¶ 33} Moreover, the per diem liquidated damages imposed by the
    contract between Piketon and Boone Coleman reflect the Ohio
    Department of Transportation's 2013 Construction and Material
    Specifications. Those specifications not only require liquidated damages
    be deducted from any sum owed the contractor for each day by which the
    contractor exceeds the completion date, but set out the specific amount of
    the per diem damages. The per diem damages are thus consistent with
    Ohio public policy.
    {¶4}   As the Supreme Court ultimately concluded, Boone Coleman “may not
    avoid the result of the valid liquidated-damages provision it negotiated through counsel.”
    
    Id. at ¶
    41. Echoing their determination, we conclude the liquidated damages provision
    of $700 per day for delay beyond the contract deadline was reasonable.
    CONCLUSION
    {¶5}   Applying the principles elucidated in the Supreme Court’s decision, we
    hold that the trial court correctly determined that the summary-judgment evidence
    established that the liquidated-damages provision in the public-works-construction
    Pike App. No. 13CA836                                                                5
    contract was enforceable under the Samson Sales test. Therefore, we overrule Boone
    Coleman’s assignments of error and affirm in toto the judgment of the trial court.
    JUDGMENT AFFIRMED.
    Pike App. No. 13CA836                                                             6
    JUDGMENT ENTRY
    It is ordered that the JUDGMENT IS AFFIRMED and that Appellant shall pay the
    costs.
    The Court finds there were reasonable grounds for this appeal.
    It is ordered that a special mandate issue out of this Court directing the Pike
    County Court of Common Pleas to carry this judgment into execution.
    Any stay previously granted by this Court is hereby terminated as of the date of
    this entry.
    A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of
    the Rules of Appellate Procedure.
    Abele, J.: Concurs in Judgment and Opinion.
    *Ringland, J.: Concurs in Judgment Only.
    For the Court
    BY: ________________________________
    William H. Harsha, Judge
    NOTICE TO COUNSEL
    Pursuant to Local Rule No. 14, this document constitutes a final judgment
    entry and the time period for further appeal commences from the date of filing
    with the clerk.
    *Robert P. Ringland, from the Twelfth Appellate District, sitting by assignment of The
    Supreme Court of Ohio in the Fourth Appellate District.
    

Document Info

Docket Number: 13CA836

Citation Numbers: 2016 Ohio 1557

Judges: Harsha

Filed Date: 4/15/2016

Precedential Status: Precedential

Modified Date: 4/15/2016