Cook v. ProBuild Holdings, Inc. ( 2014 )


Menu:
  • [Cite as Cook v. ProBuild Holdings, Inc., 
    2014-Ohio-3518
    .]
    IN THE COURT OF APPEALS OF OHIO
    TENTH APPELLATE DISTRICT
    Tiff J. Cook et al.,                                :
    Plaintiffs-Appellants,              :
    No. 13AP-430
    v.                                                  :           (C.P.C. No. 12CVH-2943)
    ProBuild Holdings, Inc. et al.,                     :        (ACCELERATED CALENDAR)
    Defendants-Appellees.               :
    D E C I S I O N
    Rendered on August 14, 2014
    Onda, LaBuhn, Rankin & Boggs Co., LPA, and Patrick H.
    Boggs, for appellants Tiff and Lesa Cook.
    Mollica Gall Sloan & Sillery Co., LPA, and Andrew J. Mollica,
    for appellee Pomar, L.P.
    Finney, Stagnaro, Saba & Patterson Co., L.P.A., Jeffrey M.
    Nye, and Paul T. Saba, for appellee Builder Services Group
    Inc. dba Gale Insulation.
    Weston Hurd LLP, Kevin R. Bush, Steven G. Carlino, and
    Nathaniel W. Jackson, for appellee Remedics, Inc. dba
    Remedics Restoration & Remedics Restoration Carolinas,
    LLC.
    Weston Hurd LLP, and W. Charles Curley, for appellee
    Colonial Heating & Cooling Co., Inc.
    APPEAL from the Franklin County Court of Common Pleas.
    No. 13AP-430                                                                                          2
    BROWN, J.
    {¶ 1} This is an appeal by plaintiffs-appellants, Tiff J. Cook and Lesa D. Cook,
    from entries of the Franklin County Court of Common Pleas granting motions for
    judgment on the pleadings filed by defendants-appellees, Builders Flooring, Inc.
    ("Builders Flooring"), Ratcliff-Midkiff Masonry, Inc. ("Ratcliff-Midkiff"), Pomar, L.P.
    ("Pomar"), and Gale Insulation, Inc. ("Gale Insulation"), and granting motions for
    summary judgment filed by defendants-appellees, Colonial Heating & Cooling ("Colonial
    Heating"), and Remedics, Inc., dba Remedics Restoration and Remedics Restoration
    Carolinas, LLC (collectively "Remedics").
    {¶ 2} On March 7, 2012, appellants filed a complaint, naming as defendants
    ProBuild Holdings, Inc. ("ProBuild"), aka Khempco Building Supply Limited Partnership
    ("Khempco Building"), Blaine Ruble, Colonial Heating, Ratcliff-Midkiff, Builders
    Flooring, Remedics, Builder Services Group, Inc. ("Builder Services"), aka Masco
    Contractor Services, Inc. ("Masco"), aka, Gale Insulation, and Interior Surfaces.1 The
    complaint alleged causes of action against the named defendants for breach of contract,
    breach of warranty, promissory estoppel, failure to perform in a workmanlike
    manner/negligence, negligence per se, and negligent hiring, retention and supervision.
    {¶ 3} Appellants' complaint sets forth the following factual allegations.                 On
    December 1, 2004, appellants and DiYanni Brothers ("DiYanni"), a general contractor,
    entered into an agreement whereby DiYanni agreed to design, construct, and sell to
    appellants a "Designer Series Hanover A" single-family home on a lot located in
    Pickerington, Ohio, for the purchase price of $364,400. (Complaint, ¶ 19.) Appellees
    served as subcontractors and material suppliers on DiYanni's residential construction
    projects, and DiYanni entered into a number of contractor agreements with appellees to
    provide labor and materials for the construction of appellants' residence. DiYanni and
    appellees broke ground on January 26, 2005; thereafter, "[a] number of serious problems
    arose during the Project as a result of occurrences, poor workmanship, negligence, and
    the use of substandard materials by Defendants." (Complaint, ¶ 26.)
    {¶ 4} As the project neared completion, a third-party investor "refused to close on
    the transaction due to the ongoing construction occurrences, problems and deficiencies."
    1   Appellants subsequently filed a notice of dismissal of their claims against Interior Surfaces.
    No. 13AP-430                                                                             3
    (Complaint, ¶ 27.) As a result, appellants were "left to find a new lender and finance the
    purchase of the Premises themselves." (Complaint, ¶ 28.) On August 4, 2005, appellants
    and DiYanni entered into a new real estate purchase agreement for the construction,
    purchase, and sale of a home, which included a one-year limited warranty and a ten-year
    structural warranty. Closing occurred on August 12, 2005, but "the construction defects
    and deficiencies were never resolved." (Complaint, ¶ 31.)
    {¶ 5} After failing to resolve the construction issues, appellants filed a complaint
    against DiYanni on October 8, 2008, asserting claims for "failure to perform in a
    workmanlike manner/negligence, breach of contract, breach of express warranty,
    negligent misrepresentation, violation of Ohio's Consumer Sales Practices Act, and
    intentional misrepresentation/concealment." (Complaint, ¶ 32.) DiYanni, in turn, filed a
    third-party complaint for indemnity, contribution, set-off, and subrogation against some
    of the contractors, including Khempco Building, Ratcliff-Midkiff, Gale Insulation,
    Colonial Heating, Lloyd Shaffer Stucco & Stone ("Lloyd Shaffer"), and Zarley, Inc.
    {¶ 6} Appellants subsequently settled their claims against DiYanni. As part of the
    settlement, DiYanni paid appellants the sum of $20,000 and assigned to appellants "all
    rights, claims, and causes of action it had, or may have in the future, against contractors
    and/or suppliers that were involved in the Project regarding the Premises, the Project, the
    Franklin County Litigation and/or the AAA Arbitration proceedings, including any and all
    rights, claims, and causes of action arising under the Contractor Agreements at issue in
    this litigation." (Complaint, ¶ 37.)
    {¶ 7} On July 25, 2011, the parties filed a stipulated notice of settlement and
    dismissal, whereby appellants dismissed their claims against DiYanni with prejudice, and
    DiYanni dismissed its third-party claims against Zarley and Lloyd Shafer with prejudice.
    DiYanni further dismissed its third-party claims against Ratcliff-Midkiff, Khempco
    Building and Gale Insulation without prejudice.
    {¶ 8} On July 24, 2012, the parties filed a stipulation of substitution/amendment
    of party, stipulating that defendant ProBuild, aka Khempco Building, was improperly
    identified as a defendant and that a successor entity, Pomar, was the appropriate
    defendant. On October 2, 2012, Remedics filed a motion for partial judgment on the
    pleadings, asserting in part that any potential recovery by appellants was limited to the
    No. 13AP-430                                                                            4
    $20,000 right DiYanni assigned to appellants. On October 4, 2012, Ratcliff-Midkiff filed
    a motion to join in Remedics' motion for partial judgment on the pleadings. Appellants
    filed a memorandum contra the motion for partial judgment on the pleadings.
    {¶ 9} On October 16, 2012, Pomar filed a motion for judgment on the pleadings,
    pursuant to Civ.R. 12(C), arguing that appellants' claims were released in the settlement
    with DiYanni and that the claims were time-barred. On December 11, 2012, Remedics
    filed a motion for summary judgment. On December 12, 2012, Gale Insulation and Masco
    filed a motion for judgment on the pleadings. Also on that date, Masco and Colonial
    Heating filed motions for summary judgment. Appellants filed responses opposing the
    motions for summary judgment and judgment on the pleadings. On January 4, 2013,
    appellants and Masco filed a stipulated dismissal of all appellants' claims against Masco
    with prejudice.
    {¶ 10} On March 13, 2013, the trial court filed an entry granting the motions for
    summary judgment filed by Remedics and Colonial Heating, as well as the motions for
    judgment on the pleadings filed by Gale Insulation and Pomar. In its decision, the court
    determined in part that the four-year statute of limitations under R.C. 2305.09(D) was
    applicable to appellants' claims, and that all of the claims (filed approximately six and
    one-half years after the cause of action accrued) fell outside the applicable statutes of
    limitations. The trial court further determined that appellants' claims were "not saved by
    the savings statute or tolled by R.C. 1312.08."
    {¶ 11} Following that entry, the trial court held a status conference with the
    remaining parties, who agreed that the court's March 13, 2013 order would be dispositive
    of all remaining claims held by appellants. The court subsequently granted Ratcliff-
    Midkiff's leave to file motions for summary judgment and judgment on the pleadings, and
    also granted Builders Flooring's leave to file a motion for judgment on the pleadings. On
    May 1, 2013, the trial court granted the motions for judgment on the pleadings filed by
    Builders Flooring and Ratcliff-Midkiff.
    {¶ 12} On appeal, appellants set forth the following three assignments of error for
    this court's review:
    I. THE TRIAL COURT ERRED IN RULING THAT
    APPELLANTS' CLAIMS FOR BREACH OF CONTRACT AND
    FAILURE TO PERFORM IN A WORKMANLIKE MANNER
    No. 13AP-430                                                                                5
    ARE SUBJECT         TO     A   FOUR-YEAR        STATUTE       OF
    LIMITATIONS.
    II. THE TRIAL COURT ERRED IN HOLDING THAT NONE
    OF THE CLAIMS WERE TOLLED BY OHIO REVISED CODE
    SECTION 1312.08.
    III. THE TRIAL COURT ERRED IN HOLDING THAT NONE
    OF THE CLAIMS WERE SAVED BY THE SAVINGS
    STATUTE, OHIO REVISED CODE SECTION 2305.19.
    {¶ 13} Colonial Heating presents the following two "cross-assignments of error" for
    this court's review:
    1. Because DiYanni had no rights against Colonial which it
    could assign to Appellants, the trial court erred by not
    entering summary judgment in favor of Colonial Heating &
    Cooling on that basis.
    2. Because DiYanni did not provide notice of its intent to settle
    with Appellants to Colonial, the trial court erred by not
    applying the notice requirement of Globe Indemnity Co. v.
    Schmitt, 
    142 Ohio St. 595
     (1944) and by not entering
    summary judgment in favor of Colonial Heating & Cooling on
    that basis.
    {¶ 14} At issue on appeal are rulings by the trial court granting motions for
    judgment on the pleadings and summary judgment in favor of appellees. Civ.R. 12(C)
    allows for judgment on the pleadings where the trial court, "construing the material
    allegations in the complaint in favor of the nonmoving party as true, finds beyond doubt
    that 'the plaintiff could prove no set of facts in support of his claim that would entitle him
    to relief.' " Common Cause/Ohio v. Ohio Elections Comm., 
    150 Ohio App.3d 31
    , 2002-
    Ohio-5965, ¶ 14 (10th Dist.), quoting State ex rel. Midwest Pride IV, Inc. v. Pontious, 
    75 Ohio St.3d 565
    , 570 (1996). Summary judgment under Civ.R. 56(C) is appropriate when:
    "(1) no genuine issue of material fact remains to be litigated; (2) the moving party is
    entitled to judgment as a matter of law; and (3) construing the evidence most strongly in
    favor of the nonmoving party, it appears that reasonable minds could only conclude in
    favor of the moving party." McGrath v. Bassett, 
    196 Ohio App.3d 561
    , 
    2011-Ohio-5666
    ,
    ¶ 28 (8th Dist.). This court reviews de novo a trial court's entry of judgment on the
    No. 13AP-430                                                                                              6
    pleadings, pursuant to Civ.R. 12(C), and a court's grant of summary judgment pursuant
    to Civ.R. 56(C). Id. at ¶ 27.
    {¶ 15} Under the first assignment of error, appellants assert the trial court erred in
    ruling that their claims for breach of contract and failure to perform in a workmanlike
    manner are subject to Ohio's four-year statute of limitations for a tort action. Appellants
    argue that the court should have instead applied the 15-year statute of limitations for a
    claim based on breach of a written contract.
    {¶ 16} R.C. 2305.09(D) provides a four-year statute of limitations "[f]or an injury
    to the rights of the plaintiff not arising on contract." Former R.C. 2305.06 established a
    15-year limitations period for actions on a contract in writing.2
    {¶ 17} Appellants asserted before the trial court that their claims for breach of
    contract and failure to perform in a workmanlike manner arose ex contractu, and,
    therefore, the 15-year statute of limitations applied. In support, appellants argued that a
    line of Ohio cases recognized a distinction between an action by a vendee against a
    vendor-builder of an already constructed residence and an action involving an agreement
    to construct a home in the future.
    {¶ 18} The trial court rejected appellants' argument, holding that the four-year
    statute of limitations under R.C. 2305.09(D) was applicable to their claims for breach of
    contract and failure to perform in a workmanlike manner. Specifically, the court found
    "no logical policy to support differentiating," for purposes of the applicable statute of
    limitations, between an action for the purchase of a previously constructed home and an
    action for a contract to construct a home in the future, as "[i]n each case, the cause of
    action arises in tort."
    {¶ 19} In general, "[t]he duty to perform in a workmanlike manner is imposed by
    common law upon builders and contractors." Zanesville Glass Supply, Inc. v. Goff, 5th
    Dist. No. CT2007-0026, 
    2008-Ohio-1243
    , ¶ 40, citing Mitchem v. Johnson, 
    7 Ohio St.2d 66
     (1966). In Velotta v. Leo Petronzio Landscaping, Inc., 
    69 Ohio St.2d 376
     (1982),
    paragraph one of the syllabus, the Supreme Court of Ohio held: "An action by a vendee
    against the builder-vendor of a completed residence for damages proximately caused by
    2 The Ohio General Assembly amended R.C. 2305.06, effective September 28, 2012, and the amended
    version now states in part that an action on a contract or promise in writing "shall be brought within eight
    years after the cause of action accrued."
    No. 13AP-430                                                                              7
    failure to construct in a workmanlike manner using ordinary care -- a duty imposed by
    law -- is an action in tort to which the four-year statute of limitations set forth in R.C.
    2305.09(D) applies." The Supreme Court in Velotta further observed: "The obligation to
    perform in a workmanlike manner using ordinary care may arise from or out of a
    contract, i.e., from the purchase agreement, but the cause of action is not based on
    contract; rather, it is based on a duty imposed by law." (Emphasis added.) Id. at 378.
    While Velotta involved the sale of an already completed residence, the Supreme Court
    stated in a footnote: "We express no opinion as to whether a different result would be
    reached were the contract herein one to build a residence in the future or one to complete
    a partially constructed residence." Id. at 379, fn. 2.
    {¶ 20} In Barton v. Ellis, 
    34 Ohio App.3d 251
    , 253 (10th Dist.1986), this court had
    occasion to consider the holding in Velotta, noting that application of the duty to perform
    in a workmanlike manner "has resulted in a distinction between the sale of a completed
    residence on the one hand, and the contracting for future construction services on the
    other." In discussing this distinction, we held:
    Absent express or implied warranties as to the quality or
    fitness of work performed, the liability of a builder-vendor of a
    completed structure for failure to exercise reasonable care to
    perform in a workmanlike manner sounds in tort, and arises
    ex delicto. The essential allegation is that the builder-vendor's
    negligence proximately causes the vendee's damages. Velotta
    * * *. By contrast, in the provision of future services, liability
    arises ex contractu as an implied bargain, * * * provision,
    condition, or term of sale.
    (Emphasis sic.) 
    Id.
    {¶ 21} In Kishmarton v. William Bailey Constr., Inc., 
    93 Ohio St.3d 226
     (2001),
    the issue before the Supreme Court was whether, when a vendee and vendor-builder enter
    into an agreement for the future construction of a residence, the vendee's cause of action
    against the builder for breach of the duty to construct the residence in a workmanlike
    manner arises in contract or tort. The Supreme Court specifically noted that its earlier
    decision in Velotta "did not address the nature of an action by a vendee against the
    builder-vendor for breach of a contract to build a residence in the future." Id. at 228. The
    Court thus sought to "close the loop" generated by Velotta. Id. In resolving this issue, the
    No. 13AP-430                                                                                                  8
    Supreme Court held: "Where the vendee and builder-vendor enter into an agreement for
    the future construction of a residence, the vendee's claim for breach of an implied duty to
    construct the house in a workmanlike manner arises ex contractu." Id. at paragraph one
    of the syllabus.
    {¶ 22} In recognizing this distinction, the Court in Kishmarton discussed the
    nature of the consideration supporting the particular agreements. Specifically, the Court
    noted that in situations such as Velotta (i.e., involving the sale of an already completed
    residence), "the consideration for the purchase price was the structure, a finished
    product." Kishmarton at 228. By contrast, where the parties enter into an agreement for
    work to be performed in the future, " 'the consideration is the services * * * [to] be
    performed by the contractor. * * * While the contractor is still required to perform the
    services in a workmanlike manner, the quality of the product will be governed by the
    language of the contract itself.' " Id., quoting Vistein v. Keeney, 
    71 Ohio App.3d 92
    , 105
    (11th Dist.1990). The Court further noted: "The contract governs the warranty of good
    workmanship; therefore, the warranty of good workmanship arises from the contract. It
    can hardly be otherwise." Kishmarton at 228-29.3
    {¶ 23} In a recent decision, Jones v. Centex Homes, 
    132 Ohio St.3d 1
    , 2012-Ohio-
    1001, syllabus, the Supreme Court held that "[a] home builder's duty to construct a house
    in a workmanlike manner using ordinary care is a duty imposed by law, and a home
    buyer's right to enforce that duty cannot be waived." In its decision, the Court reiterated
    language in Velotta that, "although the obligation to construct in a workmanlike manner
    may arise from a contract, the cause of action is not based on contract but on a duty
    imposed by law." Id. at ¶ 9, citing Velotta at 378-79.
    {¶ 24} Appellees cite to the above language in Centex, i.e., that the cause of action
    is based on a duty imposed by law, as supporting their contention that the four-year
    statute of limitations should apply to appellants' claims for breach of contract and failure
    to perform in a workmanlike manner. As previously noted, however, the Velotta Court's
    3 In Kishmarton, the court cited with approval various Ohio appellate decisions, including this court's
    decisions in Barton and Lloyd v. William Fannin Builders, Inc., 
    40 Ohio App.2d 507
     (10th Dist.1973). In
    Lloyd, this court held that where the parties had entered into a contract for the sale of a residence to be
    constructed by the builder-vendor, the obligation to construct in a workmanlike manner arises ex contractu,
    and therefore is not subject to a four-year statute of limitations but rather the 15-year statute of limitations
    for breach of contract.
    No. 13AP-430                                                                                                 9
    recognition of a "duty imposed by law" was in the context of "[a]n action by a vendee
    against the builder-vendor of a completed residence." Velotta at paragraph one of the
    syllabus. Similarly, the facts of Centex involved an action by a homeowner for the sale of
    an already constructed home, and the Court did not have occasion to address a contract
    for future services; nor did the Court in Centex discuss or purport to overrule its earlier
    holding in Kishmarton (i.e., that the liability of a home builder under a contract for the
    future construction of a residence arises ex contractu, and that such claim is governed by
    the language of the parties' agreement). Upon consideration, we do not construe Centex
    as negating the distinction recognized in Kishmarton, as well as by other Ohio courts,
    between the nature of an action by a vendee against the builder-vendor of a completed
    residence and an action by a vendee against the builder-vendor for breach of a contract to
    build a residence in the future.4
    {¶ 25} Under Ohio law, in order to ascertain the applicable statute of limitations,
    "it is necessary to determine the true nature or subject matter of the acts giving rise to the
    complaint." Doe v. First United Methodist Church, 
    68 Ohio St.3d 531
    , 536 (1994). While
    "[t]orts arise from the breach of certain duties of conduct that are imposed by law for the
    protection of all persons within range of the harm * * * [c]ontractual duties, on the other
    hand, arise from the specific agreement of the parties to the contract." Kocisko v. Charles
    Shutrump & Sons Co., 
    21 Ohio St.3d 98
    , 99 (1986).
    {¶ 26} Here, appellants' claims for breach of contract and failure to perform in a
    workmanlike manner arise out of the contractor agreements entered between the general
    contractor (DiYanni) and its subcontractors (appellees) for future construction services,
    and we conclude that the nature of the liability is ex contractu, governed by the statute of
    limitations for contracts. We therefore conclude that the trial court erred in applying the
    four-year statute of limitations to appellants' claims for breach of contract and failure to
    perform in a workmanlike manner. Accordingly, we reverse the trial court's grant of
    judgment on the pleadings and summary judgment in favor of appellees with respect to
    those claims, and remand for further proceedings.
    4 We note that in Centex the Supreme Court observed that it saw "no legal impediment" to the fact the
    purchase contracts in that case offered a detailed limited warranty; the narrow issue before the court, rather,
    was "only to determine whether a home buyer can waive his right to enforce the builder's legal duty to
    construct the house in a workmanlike manner using ordinary care." Id. at ¶ 11.
    No. 13AP-430                                                                                             10
    {¶ 27} Based upon the foregoing, we sustain appellants' first assignment of error.
    {¶ 28} Under the second assignment of error, appellants contend the trial court
    erred in failing to find that R.C. 1312.08 tolled the limitations period with respect to some
    of their claims, including those subject to a four-year statute of limitations. By way of
    background, appellants argued before the trial court that they sent a letter to the
    contractor, DiYanni, dated July 31, 2008, regarding notice of alleged defects, and that
    such notice triggered the tolling provision under Ohio's "right to cure defect" law (R.C.
    Chapter 1312). The trial court rejected appellants' attempt to invoke the statute's tolling
    provision, concluding that appellees did not fall under the statutory definition of a
    "general contractor."
    {¶ 29} R.C. Chapter 1312 sets forth certain procedures whereby an "owner" must
    provide a "residential contractor" with notice and an opportunity to repair construction
    defects prior to bringing a legal action.5 In accordance with R.C. 1312.04, "an owner may
    not commence arbitration or litigation against a builder of a residential building until 60
    days after providing the builder with notice of the alleged construction defects." Quetot v.
    M&M Homes, Inc., 1st Dist. No. 
    12 CO 1
    , 
    2013-Ohio-752
    , ¶ 14. R.C. Chapter 1312 contains
    a tolling provision, which states in part: "All applicable statutes of limitation or repose are
    tolled from the time the owner sends a notice of defect to a contractor pursuant to section
    1312.04 of the Revised Code until the owner has complied with this chapter." R.C.
    1312.08(A). Upon receiving notice, the builder must provide a response, and "[i]f the
    builder fails to respond or disputes the claim, an owner is deemed to have complied with
    the statute and may commence suit." Quetot at ¶ 14.
    {¶ 30} R.C. Chapter 1312 "applies only to an owner and a residential contractor
    who enter into a contract for the construction or the substantial rehabilitation of a
    residential building."       R.C. 1312.02.        Pursuant to R.C. 1312.01(E), a "[r]esidential
    contractor" is defined as "a person or entity who, for pay, enters into a contract with an
    owner for the construction or the substantial rehabilitation of a residential building and
    who has primary responsibility for the construction or substantial rehabilitation of a
    residential building."
    5 Pursuant to R.C. 1312.01(C), "[o]wner" means "an owner or a prospective owner of a residential building or
    a dwelling unit in a residential building who enters into a contract with a residential contractor for the
    construction or substantial rehabilitation of that residential building or unit."
    No. 13AP-430                                                                                 11
    {¶ 31} In the instant case, pursuant to the allegations in the complaint, DiYanni, as
    contractor, entered into a number of separate contractor agreements with various
    appellees who served as subcontractors on DiYanni's residential construction projects. As
    noted, R.C. Chapter 1312 is only applicable with respect to an owner and residential
    contractor who enter into a contract for construction of a residential building. R.C.
    1312.02. Appellants, however, as "owner[s]," did not enter into contracts with any of the
    appellees.
    {¶ 32} While acknowledging they have no contractual privity with appellees,
    appellants seek to avail themselves of the tolling provision based upon the assignment
    from DiYanni. Under Ohio law, however, an assignee "stands in the shoes of the assignor
    and can obtain no greater rights against another than the assignor had." W. Broad
    Chiropractic v. Am. Family Ins., 10th Dist. No. 07AP-721, 
    2008-Ohio-2647
    , ¶ 15, citing
    Citizens Fed. Bank, F.S.B. v. Brickler, 
    114 Ohio App.3d 401
     (2d Dist.1996). Here, while
    DiYanni assigned to appellants all the rights, claims, and causes of action it had against its
    subcontractors, DiYanni itself is not an "owner" under the statutory definition, i.e., it
    could not have asserted tolling rights against appellees under R.C. Chapter 1312.
    Accordingly, we find no error with the trial court's determination that the tolling provision
    of R.C. 1312.08 does not apply to appellants' claims.
    {¶ 33} Appellants' second assignment of error is without merit and is overruled.
    {¶ 34} Under the third assignment of error, appellants challenge the trial court's
    determination that Ohio's savings statute, R.C. 2305.19, is inapplicable.         Appellants
    contend that the original 2008 action and the refiled 2012 case involve the same or
    similar claims, as well as the same parties, for purposes of invoking the savings statute.
    {¶ 35} R.C. 2305.19(A) states in part:
    In any action that is commenced or attempted to be
    commenced, if in due time a judgment for the plaintiff is
    reversed or if the plaintiff fails otherwise than upon the
    merits, the plaintiff or, if the plaintiff dies and the cause of
    action survives, the plaintiff's representative may commence a
    new action within one year after the date of the reversal of the
    judgment or the plaintiff's failure otherwise than upon the
    merits or within the period of the original applicable statute of
    limitations, whichever occurs later.
    No. 13AP-430                                                                                12
    {¶ 36} In general, the savings statute "operates in favor of a plaintiff who
    commenced an action within the proper time limits; who failed other than upon the
    merits; and who refiles within one year." Wasserman, Wasserman, Bryan & Landry v.
    Midwestern Indemn. Ins. Co., 6th Dist. No. L-87-078 (Feb. 5, 1988). Under Ohio law,
    "[t]he savings statute applies when the original suit and the new action are substantially
    the same." Children's Hosp. v. Ohio Dept. of Welfare, 
    69 Ohio St.2d 523
    , 525 (1982).
    However, the savings statute is not applicable when "the parties and relief sought in the
    new action are different from those in the original action." 
    Id.
     at paragraph one of the
    syllabus.
    {¶ 37} In the instant case, in rejecting appellants' contention that the savings
    statute was applicable, the trial court relied upon Children's Hosp. and Natl. Fire Ins. Co.
    v. Joslyn Mfg. Co., 
    25 Ohio App.2d 13
     (9th Dist.1971). In Natl. Fire, the court determined
    that, for purposes of the savings statute, the assignee of a claim was not the same party as
    the original plaintiff. Specifically, the court held that "the phrase, 'the plaintiff * * * may
    commence a new action * * *' does not mean an assignee of a portion of the claim, or one
    to whom the original plaintiff sold an interest in the action." Id. at 15.
    {¶ 38} According to the allegations in the complaint, appellants' 2008 action
    named only DiYanni as a defendant, i.e., appellants brought no claims against appellees at
    that time. Further, while appellants seek to step into the shoes of DiYanni (based upon its
    third-party complaint in the 2008 case), we find no error with the trial court's reliance
    upon Natl. Fire in determining that appellants, as assignees of a claim, were not the same
    party to the original action for purposes of invoking the savings statute. We note that in
    Children's Hosp., the Supreme Court cited with approval Natl. Fire, and this court has
    similarly followed the holding in that case. See Snyder v. Lyons, 10th Dist. No. 92AP-790
    (Dec. 17, 1992) (relying upon Natl. Fire in finding that insurer-subrogee was not same
    party as the insured for purposes of the savings statute). Other appellate courts have also
    adopted the reasoning in Natl. Fire. See, e.g., Wasserman (appellant law firm, having
    obtained interest in action as assignee of the original plaintiff, was "not the plaintiff as
    contemplated by R.C. 2305.19"). Accordingly, the trial court did not err in holding that,
    pursuant to Natl. Fire, the savings statute did not operate to save appellants' claims.
    {¶ 39} Appellants' third assignment of error is without merit and is overruled.
    No. 13AP-430                                                                               13
    {¶ 40} Having addressed each of appellants' assignments of error, we note that
    Colonial Heating did not file a cross-appeal, but has presented two "cross-assignments of
    error" for review. Under its "cross-assignments of error," Colonial Heating contends that:
    (1) DiYanni had no legal ability to assign its right to indemnity against Colonial Heating,
    and that (2) even assuming a valid assignment by DiYanni to appellants, DiYanni failed to
    provide Colonial Heating with notice of its intent to settle. In a similar vein, other
    appellees raise alternative arguments in support of affirmance of the trial court's decision.
    Specifically, Remedics contends that: (1) there was no enforceable agreement between it
    and DiYanni, (2) appellants released all of their claims against the subcontractors,
    (3) appellants' potential recovery is limited to $20,000, and (4) Remedics was never a
    proper party. Finally, Gale Insulation argues that the real estate purchase agreement was
    merged into the deed, thereby precluding any claims for breach of contract, and that, in
    the alternative, appellants' aggregate damages are limited to $20,000.
    {¶ 41} Based upon its determination that all of appellants' causes of action were
    filed outside the applicable statute of limitations, the trial court did not address the above
    arguments raised by the various appellees. Because the trial court did not consider these
    arguments, we decline to address them at this time "in the first instance." Benjamin v.
    Ernst & Young, L.L.P., 10th Dist. No. 06AP-1244, 
    2007-Ohio-4176
    , ¶ 18.              See also
    Stratford Chase Apts. v. Columbus, 
    137 Ohio App.3d 29
    , 33 (10th Dist.2000), quoting
    Murphy v. Reynoldsburg, 
    65 Ohio St.3d 356
    , 360 (1992) ("Even though a reviewing court
    considers a summary judgment motion de novo, Civ.R. 56(C) 'mandates that the trial
    court make the initial determination whether to award summary judgment; the trial
    court's function cannot be replaced by an "independent" review of an appellate court.' ");
    Schmucker v. Kurzenberger, 9th Dist. No. 10CA0045, 
    2011-Ohio-3741
    , ¶ 14 ("Because the
    trial court did not consider the alternative grounds for summary judgment as asserted by
    [defendant] we decline to do so in the first instance."). Rather, upon remand, the trial
    court can address appellees' alternative arguments, as necessary.
    {¶ 42} Based upon the foregoing, we sustain appellants' first assignment of error,
    appellants' second and third assignments of error are overruled, the judgment of the
    Franklin County Court of Common Pleas is affirmed in part and reversed in part, and this
    No. 13AP-430                                                                        14
    matter is remanded to that court for further proceedings in accordance with law,
    consistent with this decision.
    Judgment affirmed in part and reversed in part;
    cause remanded.
    KLATT and CONNOR, JJ., concur.