Davis v. J & J Concrete ( 2019 )


Menu:
  • [Cite as Davis v. J & J Concrete, 2019-Ohio-1407.]
    IN THE COURT OF APPEALS
    ELEVENTH APPELLATE DISTRICT
    TRUMBULL COUNTY, OHIO
    WILLIAM ROGER DAVIS,                                :    OPINION
    Plaintiff-Appellant,               :
    CASE NO. 2018-T-0074
    - vs -                                      :
    J&J CONCRETE, et al.,                               :
    Defendants-Appellees.              :
    Civil Appeal from the Trumbull County Court of Common Pleas, Case No. 2015 CV
    01992.
    Judgment: Affirmed.
    David L. Engler, Engler Law Firm, 181 Elm Road, N.E., Warren, OH 44483 (For Plaintiff-
    Appellant).
    Michael D. Rossi, Guarnieri & Secrest, PLL, 151 East Market Street, P.O. Box 4270,
    Warren, OH 44482 (For Defendants-Appellees).
    MARY JANE TRAPP, J.
    {¶1}      Appellant, William Roger Davis, appeals the judgment of the Trumbull
    County Court of Common Pleas adopting the magistrate’s $100 award of nominal
    damages in Mr. Davis’ breach of contract claim against appellee, J&J Concrete (“J&J”).
    For the following reasons, we affirm.
    Substantive and Procedural History
    {¶2}   Mr. Davis and J&J entered into a contract towards the end of 2013, whereby
    J&J agreed to pour a concrete mono slab foundation (a mono foundation is a combined
    footer and floor that is one unit and moves with the ground formed with a single pour of
    concrete) for Mr. Davis’ “Quonset hut.” A Quonset hut is a prefabricated storage structure
    made of steel that has a semicircular “bow” shape with all its weight on two sides. The
    parties agreed on a price of $9,500, which was increased to $10,000 when the foundation
    was laid.
    {¶3}   Mr. Davis purchased the Quonset hut kit and accompanying blueprints from
    a friend, and he used those blueprints and their specifications to obtain estimates from
    various contractors, including J&J. Mr. Davis later obtained a second set of blueprints
    directly from the manufacturer, American Steel, when he changed the design of the
    Quonset hut after the footer was poured in July of 2014.
    {¶4}   The original blueprints were not before the trial court, but the second set
    required the mono foundation to be at least 16 inches in depth. The parties stipulated
    that the 16-inch depth was a specification, together with a requirement that No. 6 rebar
    be incorporated into the foundation and that the foundation’s strength was to be no less
    than 2,500 psi (“per square inch” of concrete measures the “crush strength” of concrete).
    {¶5}   Mr. Davis was running electricity to the Quonset hut a few weeks after the
    structure was assembled when he noticed the mono foundation was not 16 inches all
    around.
    {¶6}   Mr. Davis filed a complaint against J&J in the Trumbull Court of Common
    Pleas alleging breach of contract, breach of warranty, fraud, and violation of the Ohio
    Consumer Sales Practice Act (“CSPA”) for J&J’s failure to lay down the foundation with
    2
    a 16-inch depth and omission of No. 6 rebar that was to be embedded in the foundation
    for beam strength.
    {¶7}   The case proceeded to a hearing before the magistrate where both parties
    presented witnesses, and a site view was conducted with parties actually digging five
    random holes for measurement and inspection by the magistrate.               The inspection
    revealed the concrete depth varied from 12 to 16 inches.
    {¶8}   Mr. Davis submitted two expert witnesses as to the cost of repair. The first,
    William Conger, owner of W.D.C. Concrete Inc., was also one of the contractors who
    initially submitted an estimate to lay down the foundation. Mr. Conger explained that the
    depth of a footer is important to protect structures from frost, especially in northeast Ohio.
    When structures are subjected to wet and then cold conditions, footers can buckle, twist,
    and at their worst, destroy a building. Footers are also meant to be completely smooth
    on the outside so that “the ground can move without moving the structure.” Mr. Conger
    opined that J&J failed to perform in a workmanlike manner because the foundation
    bubbled, was not the correct depth, and contained only 3/8 rebar, not the stronger No. 6
    rebar called for in the plans.
    {¶9}   John L. Miller, co-owner of J&J along with his wife, Cindy, disagreed with
    Mr. Conger’s assessment. Mr. Miller testified that any foundation that was not 40 or more
    inches, the minimum required to be below the frost level of Trumbull County, was
    considered a “floating foundation” or a “mono foundation.”       In his opinion, “the top just
    has to be square. What it looks like below ground level does not matter.” Mr. Miller also
    contested Mr. Davis’ and Mr. Conger’s testimony, contending that he installed No. 6 rebar.
    He did not have purchase tickets for the rebar (on which Mr. Conger based his testimony)
    3
    because Mr. Davis requested a materials list only after the fact, and he “didn’t purchase
    [the No.6 rebar] specifically for that job.” Mr. Miller supplied the No. 6 rebar from materials
    he had in his own inventory.
    {¶10} As to the cost of repair, Mr. Conger advocated dissembling the entire
    building, removing the defective foundation, re-pouring it, and lastly, reassembling the
    building. In his own words, “You cannot put a footer in after the fact.” Digging underneath
    and putting a new slab in would undermine the strength of the building. This undertaking
    would cost approximately $50,000.
    {¶11} The second expert to testify was the carpenter who assembled the Quonset
    hut, James R. Wakefield. Mr. Wakefield provided Mr. Davis with an estimate of $49,118
    to completely dissemble the structure, remove and then pour a new foundation, and
    finally, reassemble the building.
    {¶12} Both Mr. Davis and Mr. Miller agreed the foundation met the psi
    requirements of the contract since it had a psi of 4,500.
    {¶13} Both parties also agreed the foundation and, correspondingly, the Quonset
    hut, were undamaged and that the foundation served its purpose without fault since it was
    built over three years ago.
    {¶14} The magistrate issued her findings of fact and conclusions of law.             In
    addition to her findings regarding the parties’ agreement on three particular specifications
    for the foundation and her observations at the site view as to the depth variances, she
    also found that the lower portions of the concrete had a “rough, ‘bubbled,’ appearance.”
    The magistrate found Mr. Miller credibly testified that he did incorporate the No. 6 rebar
    and the foundation’s strength was 4,500 psi. Further, the Quonset hut served its intended
    4
    purpose, and there was no evidence of foundation cracks or other compromise of the
    building’s structural integrity. The magistrate also found Mr. Conger qualified as an expert
    in concrete, but not engineering, and was “not a competent expert to render an opinion
    as to the structural effects of an uneven footer of a Quonset hut.”
    {¶15} In her findings of law, the magistrate determined J&J did not materially
    breach the parties’ contract because it had substantially performed its obligations. While
    the cost of repairs is ordinarily the proper measure of damages for construction defects,
    the magistrate found this case does not support a damage award equaling the cost of
    replacement at the estimate given of $50,000. There was no credible evidence the
    contract failed its essential purpose and no evidence quantifying any harm from the faulty
    footers. Therefore, the magistrate concluded Mr. Davis was entitled to nominal damages
    only and awarded him $100 on the breach of contract claim.
    {¶16} After overruling Mr. Davis’ objections, the trial court adopted the
    magistrate’s findings of fact and conclusions of law. This appeal followed in which Mr.
    Davis raises the following assignment of error:
    {¶17} “The trial court committed reversible error in deciding that plaintiff-appellant
    was only entitled to recover nominal damages of One Hundred Dollars ($100.00).”
    Standard of Review
    {¶18} “On appeal, a trial court’s adoption of magistrate’s decision will not be
    overruled unless the trial court abused its discretion in adopting the decision.” Marble
    Builder Direct Internatl., Inc. v. Hauxhurst, 11th Dist. Lake No. 2011-L-040, 2012-Ohio-
    1674, ¶16, quoting Brown v. Gabram, 11th Dist. Geauga No. 2004-G-2605, 2005-Ohio-
    6416, ¶11, citing Lovas v. Mullet, 11th Dist. Geauga No. 2000-G-2289, 
    2001 Ohio App. 5
    LEXIS 2951, 5-6 (July 29, 2001). The term “abuse of discretion” is one of art, “connoting
    judgment exercised by a court, which does not comport with reason or the record.” 
    Id., citing State
    v. Underwood, 11th Dist. Lake No. 2008-L-113, 2009-Ohio-2089, ¶30, citing
    State v. Ferranto, 
    112 Ohio St. 667
    , 676-678 (1925). Stated differently, an abuse of
    discretion is the “trial court’s ‘failure to exercise sound, reasonable, and legal decision-
    making.’” 
    Id., citing State
    v. Beechler, 2d Dist. Clark No. 09-CA-54, 2010-Ohio-1900, ¶62,
    quoting Black Law’s Dictionary (8 Ed.Rev.2004) 11.
    Breach of Contract and Nominal Damages
    {¶19} In his sole assignment of error, Mr. Davis contests the magistrate’s award
    of nominal damages in the amount of $100 for J&J’s failure to pour a foundation 16 inches
    in depth. More specifically, Mr. Davis contends this was a material breach going to the
    heart of the contract and that the doctrine of substantial performance should not have
    been applied. Further, Mr. Davis argues the magistrate improperly excluded the expert
    testimony of his witness, Mr. Conger, a concrete contractor, as to the structural integrity
    of the structure and in awarding only nominal damages as to the cost of repair.
    Substantial Performance of Contract
    {¶20} “In Ohio, a ‘long and uniformly settled rule as to contracts requires only a
    substantial performance in order to recover upon such contract. Merely nominal, trifling,
    or technical departures are not sufficient to breach the contract.’” Warren Concrete and
    Supply, Inc. v. Strohmeyer Contracting, Inc., 11th Dist. Trumbull No. 2010-T-0004, 2010-
    Ohio-5395, ¶18, quoting Ohio Farmers’ Ins. Co. v. Cochran, 
    104 Ohio St. 427
    , (1922),
    paragraph two of the syllabus. “Substantial performance of a contract is interpreted to
    mean * * * that slight departures, omissions and inadvertences should be disregarded.”
    6
    
    Id., quoting Kichler’s,
    Inc. v. Persinger, 
    24 Ohio App. 2d 124
    , 126, (1st Dist.1970), see,
    also 
    Thompson, supra
    . “For the doctrine of substantial performance to apply, the part
    unperformed must not destroy the value or purpose of the contract.” Hansel v. Creative
    Concrete & Masonry Constr. Co., 
    148 Ohio App. 3d 53
    , 56, 2002-Ohio-198, ¶12 (10th
    Dist.). “Therefore, a ‘material breach’ or an error which goes to the heart of the contract
    will undermine a promisor’s claim despite his or her performance.” 
    Id. {¶21} “The
    question of whether a contractor has substantially performed under a
    contract is one of fact and degree. Hence, there is no ‘rule of thumb’ for determining
    whether obligations in an agreement have been substantially performed. Nevertheless,
    certain relevant factors are: the purpose of the contract; the desires being gratified by the
    contract; the excuse for deviating from the contract’s specifications; and the cruelty of
    requiring the promisor to strictly adhere versus the problems inherent in compelling the
    promisee to accept something less than that for which it bargained.” Warren Concrete at
    ¶19, citing O.W. Grun Roofing & Construction Co. v. Cope, 
    529 S.W.2d 258
    , 261
    (Tex.Civ.App.1975).
    {¶22} The parties in this case agree that Mr. Davis contracted for a mono
    foundation with a depth of 16-inches, that No. 6 rebar would be laid in the foundation for
    beam strength, and that the concrete strength of the foundation would have a psi of at
    least 2500.
    {¶23} There is no dispute that the foundation depth varies and is not uniformly 16-
    inches in depth. As for the No. 6 rebar, the magistrate found Mr. Miller’s testimony that
    he did incorporate it when laying the foundation credible. Lastly, the evidence reflected
    that the concrete strength of the foundation is 4,500 psi. Thus, the only defect in J&J’s
    7
    performance is the shallow foundation. Therefore, our analysis turns to whether the
    magistrate erred in finding this breach of performance immaterial.
    {¶24} “For the doctrine of substantial performance to apply, the part unperformed
    must not destroy the value or purpose of the contract.” Hansel at ¶12 (10th Dist.), citing
    F.C. Machine Tool & Design, Inc. v. Custom Design Technologies, Inc., 5th Dist. Stark
    No. 2001CA0019, 2001-Ohio-7047, citing Wengerd v. Martin, 9th Dist. Wayne No.
    97CA0046, 
    1998 WL 225107
    (May 6, 1998).
    {¶25} In 
    Hansel, supra
    , the Tenth District Court was confronted with a concrete
    driveway that was improperly poured. It was riddled with defects—cracking, scaling, and
    pitting. Despite the court’s finding that the contractor failed to perform in a workmanlike
    manner in finishing the driveway with proper techniques, and that it had additional
    problems with the misplacement of the wire mesh and an uneven subbase, the court
    found the evidence supported the magistrate’s conclusion that the contractor “had
    substantially performed under the contract in that the driveway had not failed in its
    essential purpose.” 
    Id. at ¶16.
    {¶26} Further, although the homeowners in Hansel submitted expert testimony
    that the driveway had suffered significant damage after only one or two years, the same
    expert also testified that the concrete itself was satisfactory. The crucial linchpin in Hansel
    was that while the homeowners “did not receive exactly what they bargained for, the
    driveway still met its essential purpose. There was no testimony that the driveway was
    unusable or would become so in the near future. Pictures admitted at trial showed some
    surface defects, but the driveway was clearly useable.” 
    Id. at ¶24.
    Thus, the court found
    that the contractor substantially performed under the contract and was entitled to be paid
    8
    for that performance “less an allowance for the defects in the performance or damages
    for failure to strictly comply with the contract.” 
    Id. at ¶25.
    {¶27} Similarly, here, we find the evidence supports the magistrate’s conclusion
    that J&J substantially performed under the contract in that the foundation has not failed
    its essential purpose. Undoubtedly, there is a construction defect because the foundation
    lacks the contracted for 16-inch depth, but there is no evidence this has rendered the
    foundation unusable. The essential purpose of the foundation is more than served since
    Mr. Davis has been unable to point to any damage to the foundation or the structure itself.
    Mr. Davis admitted there were no defects, cracks, or other damage to the structure three
    years later. The essential purpose of the Quonset hut as a storage unit is being met.
    Cost of Repair
    {¶28} The magistrate also correctly found there was no evidence as to the cost of
    repairs. The only evidence submitted in this case were two estimates for the complete
    removal and then reassembly of the foundation and Quonset hut.             The estimates,
    provided by Mr. Conger, a concrete contractor, and Mr. Wakefield, the carpenter who built
    the Quonset hut upon the foundation, were $50,000 and $49,118, respectively. But there
    were no estimates as to correcting the foundation itself, and no evidence of any damage
    quantifying the harm to the structure from the improperly laid foundation. Indeed, there
    is no evidence that any harm has even occurred.
    {¶29} “Ordinarily, the cost of repairs is the proper measure of damages for
    construction defects.” Hansel at ¶26, citing Barton v. Ellis, 
    34 Ohio App. 3d 251
    , 253 (10th
    Dist.1986). “Stated differently, the proper measure of damages is the reasonable cost of
    placing the building in the condition contemplated by the parties at the time they entered
    9
    into the contract.” 
    Id., citing Sites
    v. Moore, 
    79 Ohio App. 3d 694
    , 702 (4th Dist.1992),
    motion to certify overruled in 
    65 Ohio St. 3d 1465
    (1992).
    {¶30} It was Mr. Davis’ burden to prove damages. 
    Id. at ¶27,
    see, Akro-Plastics
    v. Drake Industries, 
    115 Ohio App. 3d 221
    , 226 (11th Dist.1996). Since there is no
    evidence of any harm from the defective foundation, there is no corresponding damage.
    Thus, we cannot say the magistrate erred in concluding that Mr. Davis is entitled to only
    nominal damages. See, The Toledo Group, Inc. v. Benton Industries, Inc., 87 Ohio
    App.3d 798, 807 (6th Dist.1993).
    Expert Testimony
    {¶31} Mr. Davis also contends the magistrate improperly diminished Mr. Conger’s
    testimony based on the fact that he is not a structural engineer. He argues Mr. Conger’s
    testimony is relevant insofar as the contract calls for a 16-inch footer and that “Conger
    was eminently qualified to testify about the failure of the footers to conform to the
    contractual requirements and the quality of J&J’s workmanship in installing the footers.”
    {¶32} We do not disagree with Mr. Davis’ argument regarding the relevance of Mr.
    Conger’s testimony. We do, however, disagree with his interpretation of the magistrate’s
    ruling regarding Mr. Conger’s testimony. Specifically, the magistrate was looking for
    competent expert opinion testimony that the foundation is compromising the structural
    integrity of the building that would necessitate a $50,000 award of damages.
    {¶33} As this court has observed in the past, while it can be argued that the cause
    and extent of damage from shallow footers is within the expertise of a concrete contractor
    whose business it is to pour footers or remediate damage caused by improperly installed
    footers, “* * * the law provides wide discretion to the trial court in determining the
    10
    necessary qualifications of an expert. The Supreme Court [of Ohio] has held that: the
    qualification or competency of a witness to testify as an expert or to give his opinion on a
    particular subject rests with the trial court, and, on appeal, its rulings with respect to such
    matters will ordinarily not be reversed unless there is a clear showing that the court
    abused its discretion.” Midwest Materials, Inc. v. Aetna Freight Lines, Inc., 11th Dist. Lake
    No. 9-021, 
    1982 WL 5659
    , at *1 (Sept. 24, 1982), citing Ohio Turnpike Commission v.
    Ellis, 
    164 Ohio St. 377
    (1955).
    {¶34} As noted earlier, “an abuse of discretion is the trial court’s ‘failure to exercise
    sound, reasonable, and legal decision-making.’” (Citations omitted.) Marble Builder
    Direct Internatl. at ¶16.
    {¶35} A review of Mr. Conger’s testimony reveals that he testified as to the
    foundation’s improper shallow depth and that twisting and/or cracks of the foundation
    could occur due to an improperly laid foundation from his experience as a concrete
    contractor. No evidence was presented of any harm caused by the variances in footer
    depth. Mr. Conger’s testimony only raised a possibility.
    {¶36} We find no abuse of discretion. The magistrate in the exercise of sound,
    reasonable, and legal decision-making allowed Mr. Conger’s testimony, assessed it and
    found that Mr. Conger, “while qualified as an expert in concrete, is not an engineer, and
    is not a competent expert to render an opinion as to the structural effects of an uneven
    footer of a Quonset hut.” Thus, the magistrate concluded “[t]he evidence in this case
    * * * does not support a damages award equaling the cost of replacement, here estimated
    at $50,000. There is no credible evidence that the contract failed its essential purpose.
    The concrete pad for the Quonset hut has served its intended purpose, and there is no
    11
    evidence of foundation cracks or other compromise of the building’s structural integrity.
    The only testimony of the effect of the uneven footer on the structural integrity of the
    Quonset hut (and therefore the need to disassemble the Quonset hut, re-pour the footer,
    and rebuild the Quonset hut) came from Mr. Conger, who is not an engineer, and to whom
    the magistrate does not find to be a credible expert to testify thereto. The original
    blueprints were not submitted into evidence. There was no testimony as to the cost to
    repair the foundation. Nor was there any testimony regarding the diminution in value of
    the real property.”
    {¶37} In summary, we cannot conclude the trial court abused its discretion in
    adopting the magistrate’s decision because Mr. Davis failed to submit any evidence that
    any harm, and correspondingly, damage has occurred from J&J’s breach of the contract
    in failing to pour a 16-inch foundation. J&J’s breach of the contract was not material, no
    harm to the foundation’s essential purpose was shown, and no evidence of damages was
    submitted. Under these circumstances, we cannot say the magistrate’s award of nominal
    damages only was in error or unsupported by the evidence.
    {¶38} Mr. Davis’ assignment of error is without merit.      The judgment of the
    Trumbull County Court of Common Pleas is affirmed.
    THOMAS R. WRIGHT, P.J.,
    TIMOTHY P. CANNON, J.,
    concur.
    12
    

Document Info

Docket Number: 2018-T-0074

Judges: Trapp

Filed Date: 4/15/2019

Precedential Status: Precedential

Modified Date: 4/22/2019