Booth v. Duffy Homes, Inc. , 185 Ohio App. 3d 260 ( 2009 )


Menu:
  • Klatt, Judge.

    {¶ 1} This matter is before us pursuant to an order of remand from the Supreme Court of Ohio in Booth v. Duffy Homes, Inc., 121 Ohio St.3d 358, 2009-Ohio-1392, 904 N.E .2d 535, for consideration of whether our prior judgment in this case should be modified in view of Martin v. Design Constr. Servs., Inc., 121 Ohio St.3d 66, 2009-Ohio-1, 902 N.E.2d 10. For the following reasons, we decline to modify our judgment. However, in view of Martin, we modify our decision.1

    2} The procedural and factual background of this case are set out in Booth v. Duffy Homes, Inc., Franklin App. No. 07AP-680, 2008-Ohio-5261, 2008 WL 4517808. Therefore, we need not repeat that background here.

    {¶ 3} The Booths asserted a claim against Duffy Homes for breach of warranty “against inadequate lot drainage.” They sought money damages for injury to their home resulting from that breach. Specifically, the Booths sought to recover the costs to restore the property to the warranted condition. The Booths presented evidence that the cost to restore the property to the warranted condition was $300,000. It was undisputed that the Booths had purchased the home for $410,000. The trial court was obligated to instruct the jury on the correct measure of damages applicable to the Booths’ claim.

    {¶ 4} In our original majority opinion, we held that the trial court failed to properly instruct the jury on the measure of damages applicable to the Booths’ breach-of-warranty claim. We held that Ohio Collieries Co. v. Cocke (1923), 107 Ohio St. 238, 140 N.E. 356, stated the general rule for the measure of damages for injuries to real property. That rule is as follows:

    If the injury is susceptible of repair, the measure of damages is the reasonable cost of restoration, plus reasonable compensation for the loss of the use of the property between the time of the injury and the restoration, unless such cost of restoration exceeds the difference in the market value of the property before and after the injury, in which case the difference in market value becomes the measure.

    Id. at 248-249, 140 N.E. 356.

    {¶ 5} We noted, however, that the diminution in market value discussed in Ohio Collieries is not necessarily an absolute limit on the recovery of damages for injury to real property. Where such a limitation would prevent fair compensa*262tion, some courts have upheld damage awards that exceeded the diminution in market value of the real property. See, e.g., Thatcher v. Lane Constr. Co. (1970), 21 Ohio App.2d 41, 50 O.O.2d 95, 254 N.E.2d 703; Northwestern Ohio Natural Gas Co. v. First Congregational Church of Toledo (1933), 126 Ohio St. 140, 184 N.E. 512; Prawdzik v. II Ent., Inc., Franklin App. No. 03AP-1044, 2004-Ohio-3318, 2004 WL 1405570, ¶ 13. Nevertheless, we stated that the relationship between the repair costs and the diminution in market value of the real property remains a benchmark consideration for the trier of fact in awarding damages. Therefore, even when there is evidence that might justify a damage award greater than the diminution in market value, the damage award cannot be grossly disproportionate to the value of the real property. Booth at ¶ 21. Because the trial court failed to give a jury instruction based upon Ohio Collieries, we held that the trial court erred. Id. at ¶ 26. Accordingly, we sustained Duffy Homes’ first assignment of error, reversed the $300,000 judgment in favor of the Booths, and remanded the case to the trial court for further proceedings to determine the amount of compensation the Booths should receive for Duffy Homes’ breach of warranty.2

    {¶ 6} Shortly after the entry of our judgment in this case, the Supreme Court of Ohio decided Martin, 121 Ohio St.3d 66, 2009-Ohio-1, 902 N.E.2d 10. In Martin, the court addressed the following certified issue:

    [I]n an action for temporary damages to a noncommercial real property, [is] a failure to prove the difference between the fair market value of the whole property just before the damage was done and immediately thereafter * * * fatal to the claim?

    Id. at ¶ 1.

    {¶ 7} In holding that the Martins did not have to prove diminution in market value to recover damages for temporary injury to their real property, the court analyzed Ohio Collieries and subsequent case law that addressed the applicable measure of damages for temporary (repairable) injuries to real property.

    {¶ 8} Citing First Congregational Church, 126 Ohio St. 140, 184 N.E. 512, and Apel v. Katz (1998), 83 Ohio St.3d 11, 697 N.E.2d 600, the court noted that since Ohio Collieries, it has shifted away from a strict-diminution-of-market-value approach to a reasonable-cost-of-repair approach when deciding the measure of compensation for temporary damages to noncommercial real property. Martin at ¶ 17-22. The court explained:

    Now we make express what First Congregational and Apel implied. The rule expressed in Ohio Collieries, that damages for temporary injury to property *263cannot exceed the difference between market value immediately before and after the injury, is limited. In an action based on temporary injury to noncommercial real estate, a plaintiff need not prove diminution in the market value of the property in order to recover the reasonable costs of restoration, but either party may offer evidence of diminution of the market value of the property as a factor bearing on the reasonableness of the cost of restoration. While evidence of loss in market value of the property may be relevant, the essential inquiry is whether the damages sought are reasonable. Either party may introduce evidence to support or refute claims of reasonableness, including evidence of the change in market value attributable to the temporary injury. But proof of diminution in value is not a required element of the injured party’s case.

    Id. at ¶ 24-25.

    {¶ 9} Pursuant to Martin, the measure of damage for temporary injury to noncommercial real property is the reasonable cost of restoration. The trier of fact may consider a variety of factors, including evidence of the change in market value attributable to the temporary injury, in determining whether the damages sought are reasonable.

    {¶ 10} Applying this rule to the facts presented in Martin, the court noted that the trial court instructed the jury that the Martins should be made whole, provided that their expenses were reasonable. Id. at ¶ 26. The court also noted that the damage award appeared reasonable under the circumstances.

    The jury award of $11,770 equals the amount that the Martins paid to repair the defects to a house purchased for $167,000. Although Design Construction offered evidence that the repairs could have been performed for less, it appears that the jury found that the Martins’ expenditures were appropriate. Therefore, it is reasonable to assume that the damages awarded by the jury represented the reasonable costs incurred by the Martins to repair the deficiencies in the structure of the garage.

    Id. at ¶ 27.

    {¶ 11} In the case at bar, we must now determine whether the trial court properly instructed the jury on the applicable measure of damages as articulated in Martin. We find that it did not.

    {¶ 12} The trial court instructed the jury on the applicable measure of damages as follows:

    In a breach of contract case, damages may be awarded in an amount you find is sufficient to place Mr. and Mrs. Booth in the same position in which they would have been if their contract had been fully performed by Duffy Homes. *264Damages must, however, be limited to those damages that are reasonably certain and reasonably foreseeable.
    You may only award damages that were the natural and probable result of the breach of the contract or that were reasonably within the contemplation of the parties as the probable result of the breach of the warranty in the home purchase contract.
    Finally, members of the jury, you may only award damages whose existence and amount have been proven to you by the plaintiffs with reasonable certainty. You may not award damages that are remote or merely speculative.

    {¶ 13} Although the trial court instructed the jury that it could award only damages that were reasonably certain and reasonably foreseeable, it failed to include the critical concept articulated in Martin — “the reasonableness of the cost of restoration.” As emphasized in Martin, “the essential inquiry is whether the damages sought are reasonable” under the circumstances. Id. at ¶ 24-25. Damages could be reasonably foreseeable and reasonably certain, but still be unreasonable because of other factors. These factors might include the value of the real property and the cost to restore the property to the warranted condition. Because the trial court failed to instruct the jury on the correct measure of damages applicable to the Booths’ breach-of-warranty claim, we sustain Duffy Homes’ first assignment of error.

    {¶ 14} In its second assignment of error, Duffy Homes contended that the jury’s award of $300,000 was against the manifest weight of the evidence. In our prior decision, we found that assignment of error moot because the trial court erred in its jury charge, thereby requiring a reversal of the damage award and a remand for a new trial on damages. Because we again sustain Duffy Homes’ first assignment of error, its second assignment of error remains moot.

    {¶ 15} For the foregoing reasons, we sustain Duffy Homes’ first assignment of error, thereby rendering moot Duffy Homes’ second assignment of error. We reverse the $300,000 judgment in favor of the Booths and remand this matter to the trial court for further proceedings to determine the reasonable cost of restoration of the Booths’ real property.

    Judgment reversed and cause remanded.

    Sadler, J., concurs. French, P.J., dissents.

    . Martin does not require us to reconsider that portion of our judgment that addressed the Booths’ conditional cross-appeal. In their conditional cross-appeal, the Booths contended that the trial court erred by granting summary judgment in Duffy Homes’ favor on their consumer-sales-practices-act claim. Martin does not impact our prior disposition of the Booths’ single assignment of error in their conditional cross-appeal.

    . Duffy Homes does not challenge the liability finding in this appeal.

Document Info

Docket Number: No. 07AP-680

Citation Numbers: 185 Ohio App. 3d 260, 923 N.E.2d 1175

Judges: French, Klatt, Sadler

Filed Date: 12/22/2009

Precedential Status: Precedential

Modified Date: 10/18/2024