Menard, Inc. v. DiPaolo Indus. Dev., L.L.C. , 2023 Ohio 1188 ( 2023 )


Menu:
  • [Cite as Menard, Inc. v. DiPaolo Indus. Dev., L.L.C., 
    2023-Ohio-1188
    .]
    IN THE COURT OF APPEALS OF OHIO
    ELEVENTH APPELLATE DISTRICT
    TRUMBULL COUNTY
    MENARD, INC.,                                          CASE NO. 2022-T-0032
    Plaintiff-Appellee,
    Civil Appeal from the
    - vs -                                         Court of Common Pleas
    DIPAOLO INDUSTRIAL
    DEVELOPMENT, LLC,                                      Trial Court No. 2015 CV 00169
    Defendant-Appellant.
    OPINION
    Decided: April 10, 2023
    Judgment: Affirmed in part, reversed in part, and remanded
    Julian T. Emerson, Reminger Co., LPA, 101 West Prospect Avenue, Suite 1400,
    Cleveland, OH 44115 (For Plaintiff-Appellee).
    Michael A. Partlow, 112 South Water Street, Suite C, Kent, OH 44240 (For Defendant-
    Appellant).
    MATT LYNCH, J.
    {¶1}     Defendant-appellant, DiPaolo Industrial Development, LLC, appeals the
    judgment of the Trumbull County Court of Common Pleas in favor of plaintiff-appellee,
    Menard, Inc. For the following reasons, we affirm in part and reverse in part the judgment
    of the lower court and remand for further proceedings consistent with this opinion.
    {¶2}     On January 29, 2015, Menard filed a Complaint against DiPaolo Industrial
    raising claims of Breach of Contract (Count I), Breach of Express Warranty (Count II),
    Indemnification (Count III), and Conversion (Count IV). The Complaint was based on the
    following allegations: “Menard and Defendant entered into a written agreement * * * for
    work to be performed by DiPaolo at a new Menard’s location in Warren, Ohio * * *, the
    scope of which included demolition, concrete-crushing, salvage, storage, and milling of
    asphalt services. * * * As a result of DiPaolo’s failure to timely complete its work despite
    Menard’s requests, Menard was compelled to hire another contractor to complete
    DiPaolo’s work and correct defective and non-conforming work.”
    {¶3}   On December 16, 2015, DiPaolo Industrial filed an Answer and
    Counterclaim raising claims for Breach of Contract (Count One), Unjust Enrichment
    (Count Two), Foreclosure of Mechanic’s Lien (Count Three), and Defamation of
    Character (Count Four). DiPaolo asserted that it performed its obligations under the
    contract and Menard had failed to remit payment pursuant to its terms. Furthermore, it
    was alleged that “DiPaolo and Menard agreed [per change orders] to DiPaolo performing
    additional work on the project related to the original demolition scope of the work” and
    “Menard failed to timely approve and remit payment for the Change Orders.”
    {¶4}   On October 17, 2017, the trial court granted partial summary judgment in
    favor of Menard on DiPaolo’s claims for Breach of Contract and Unjust Enrichment with
    respect to the change orders only.
    {¶5}   On July 26 and 27, and on October 11, 2018, trial was held before a
    magistrate.
    {¶6}   On May 13, 2019, the Magistrate’s Decision was issued. The magistrate
    found in favor of Menard with respect to both the claims of the Complaint and
    Counterclaim based on the following Findings of Fact:
    2
    Case No. 2022-T-0032
    1. James Carlson is the Assistant General Manager of Store
    Planning and Construction for Plaintiff.1
    2. Sergio DiPaolo is the Managing Member of Defendant.
    3. Plaintiff issued an October 1, 2013 “Invitation to Bid” packet of
    documents for potential bidders, which comprised of demolition
    plans, site plans, environmental report, soils report, specifications,
    and a sample contract.
    ***
    5. Defendant received and reviewed the Invitation to Bid documents
    before entering into contract with Plaintiff.
    ***
    11. The Invitation to Bid stated, “The work to be performed hereunder
    should be commenced and completed on or before the dates as
    shown in the contract. The general contractor agrees that time is of
    the essence and that the times stated shall only be modified by
    written agreement of the parties. Completion means all work
    including punch list item complete and all inspections complete. The
    contractor agrees that the owner will suffer financial loss if the project
    is not completed on the completion date.”
    ***
    16. Sergio DiPaolo reviewed the contract and signed the contract on
    behalf of Defendant.
    ***
    18. The contract entered into was to be enforced in conjunction with
    the Invitation to Bid documents.
    19. The contract was for the sum of $286,000.
    ***
    22. Per the contract, “Contractor shall not perform any extra or
    additional work or changes from the contract documents unless
    previously authorized in writing by an AIA change order signed by
    1. References to the trial transcript and exhibits included in the Magistrate’s Decision are omitted
    throughout the Findings of Fact.
    3
    Case No. 2022-T-0032
    Troy       Anderson,     the      General       Manager    Store
    Planning/Design/Construction. Portions of change order work are
    subject to merchandise credit check. Owner’s project managers are
    not authorized to approve changes in the work.”
    23. Defendant admitted that nowhere in the contract does it state
    Defendant could perform additional work simply off a verbal
    communication go ahead.
    24. Per the contract, “The work to be performed hereunder shall be
    commenced by November 11, 2013, and have demolition completed
    on or before December 27, 2013, and complete crushing by January
    31, 2014 (“Agreement Period”). CONTRACTOR agrees that TIME
    IS OF THE ESSENCE and that the above stated dates shall not be
    modified unless the modification is in writing and signed by the
    OWNER and CONTRACTOR. Inclement weather shall not be
    considered as a cause for an extension of time or completion of the
    work.”
    25. Plaintiff contends that time was of the essence for completion of
    the work because Plaintiff intended on constructing a new Menard
    store once demolition was completed.
    26. When Defendant returned the signed contract, he also included
    an “addendum” dated November 11, 2013 which purported to extend
    the time period for crushing the asphalt due to adverse weather
    conditions. The addendum was not signed by Defendant or any
    representative of Plaintiff. Defendant contends that because Plaintiff
    never informed him that the addendum was rejected that it is binding
    on the parties. However, Jim Carlson specifically testified that the
    proper protocol to change or add terms to the contract would be for
    Troy Anderson to agree to it and sign off on any change.
    27. Per the contract, “Contractor shall indemnify and hold harmless
    owner, its agents and its employees from any and all liability,
    damages, expenses, claims, demands, actions, or cause of action,
    including attorney fees, arising out of the performance of the Contract
    Documents, Agreement and/or work hereunder, whether such
    liability, damages, expenses, claims, demands, actions or causes of
    action are caused by contractor, its subcontractors, or lower tiered
    contractors, or their agents or employees, owner, its agents and its
    employees, or any persons acting on their behalf of owner and/or
    contractor.”
    28. Defendant admitted that similar to the Invitation to Bid
    documents, the contract once again laid out the payment procedure,
    4
    Case No. 2022-T-0032
    which was the usual AIA payment procedure that Defendant was
    accustomed to from other projects.
    29. Defendant received a December 17, 2013 correspondence from
    Plaintiff returning Defendant’s first payment application because it
    did not properly follow the payment procedure in the contract.
    30. Defendant understood Plaintiff’s rationale for rejecting the first
    payment application and had no issues.
    31. Upon remedying the issues with payment application one,
    Defendant resubmitted and was paid $143,590.50.
    32. Defendant received a January 31, 2014 correspondence from
    Plaintiff that expressed concerns Plaintiff was having with
    Defendant’s work as it pertained to the project.          [Similar
    correspondence was received by the Defendant on April 3, April 25,
    May 6, and May 16.]
    33. Defendant received a March 12, 2014 seven-day notice letter
    from Plaintiff that expressed concerns Plaintiff was having with
    Defendant’s work as it pertained to the project, along with a list of
    items that still needed to be completed. [A similar seven-day notice
    was received by the defendant on April 8.]
    34. Defendant received a March 17, 2014 correspondence from
    Plaintiff regarding the rejection of pay application 2.
    35. Upon remedying pay application 2 in accordance with the
    contract, Defendant resubmitted pay application 2 and was paid
    $70,902.
    ***
    41. Defendant admitted that it was possible the list of contractual
    items in the May 16, 2014 correspondence still had not been
    completed by Defendant.
    42. Defendant received a May 22, 2014 correspondence from
    Plaintiff regarding back charges for the contractual work Defendant
    did not perform which Plaintiff paid McConnell Excavating to
    complete.
    43. Defendant received a May 29, 2014 correspondence from
    Plaintiff titled “Final Notice Breach of Contract/ Abandonment of
    Property/ Trespass to Chattels”, which stated “This serves as your
    5
    Case No. 2022-T-0032
    final notice that DiPaolo Industrial Development has failed to fulfill its
    obligations under the contract and impaired Menard, Inc. in its use of
    its property including the certain premises located at 2057 Elm Road,
    Cortland, Ohio, and implements that belong to that property…
    Please remove construction equipment and other property left
    behind at the above site within five days of the date of this letter and
    remit the property of Menard, Inc., including the fencing that you
    possess. The failure to timely make these actions will result in a
    lawsuit against you where Menard, Inc., will seek judgment against
    you and avail itself of all potential remedies and recover for all
    available costs.”
    44. Defendant received a July 8, 2014 correspondence from Plaintiff
    rejecting pay applications 3, 4, and 5 because they did not comply
    with the contract.
    45. Defendant attempted to bill Plaintiff for final payment despite
    admittedly not completing all of its contractual work. [In total, Plaintiff
    paid Defendant two payments under the contract in the amount of
    $143,590.50 and $70,902, totaling $214,492.50.]
    ***
    51. According to Plaintiff, Plaintiff withheld payment from Defendant
    because of defective work not remedied and a reasonable indication
    that the work would not be completed within the agreement period.
    ***
    54. Plaintiff terminated the contract with Defendant because it
    determined that Defendant did not complete its contractual work and
    would not be able to complete its contractual work on time.
    ***
    65. Plaintiff hired McConnell Excavating to complete Defendant’s
    contractual work. [Plaintiff made three payments to McConnell
    Excavating in the amounts of $16,245, $117,944.50, and $3,215.34
    for completing Defendant’s contractual work.]
    ***
    74. Plaintiff back charged Defendant total amounts of $17,869.50,
    $129,738.95, and $3,536.87, which included the three payments
    made to McConnell Excavating and the contractual 10%
    administrative fee.
    6
    Case No. 2022-T-0032
    ***
    75. Defendant admitted that it did not leave the site and remove all
    of its machinery until mid-May to early June 2014.
    76. Defendant admitted that it did not complete all its contractual
    work and went through various items that were not completed.
    77. Defendant removed fencing from the demolition project without
    permission.
    78. Plaintiff made repeated requests that Defendant return the
    fencing.
    79. Defendant admitted that it never returned the fencing or
    reimbursed Plaintiff for the fencing it took.
    80. Defendant admitted that it never informed Plaintiff of the location
    of the fence to enable Plaintiff to retrieve the fence.
    81. Defendant admitted that it no longer has control of the facility
    where the fencing is currently stored.
    82. The replacement value of the fencing is approximately $25,000.
    ***
    85. No evidence was presented that Plaintiff published a false
    statement about Defendant.
    {¶7}    On October 7, 2019, a second Magistrate’s Decision was issued awarding
    damages. Menard was awarded a total of $274,379.88, representing $69,357.82 for
    contractual or construction damages2, $25,000 for conversion, and $180,022.06 for
    attorney fees.
    2. This figure was based on the original contractual price of $286,000 plus $8,000 for additional work
    performed by DiPaolo for a total contract price of $294,000. From this figure was subtracted the
    $214,492.50 Menard paid to DiPaolo and $148,865.32 in back charges as a result of hiring McConnell
    Excavating to complete the contractual work.
    7
    Case No. 2022-T-0032
    {¶8}   On March 21, 2022, after hearing DiPaolo Industrial’s objections to the
    Magistrate’s Decisions, the trial court adopted both Decisions.
    {¶9}   On April 19, 2022, DiPaolo Industrial filed a Notice of Appeal. On appeal,
    DiPaolo Industrial raises the following assignments of error:
    [1.] The trial court [erred] by granting partial summary judgment to
    plaintiff on defendant’s counterclaims.
    [2.] The trial court’s decision that defendant breached its contract
    with plaintiff is not supported by the weight of the evidence and is
    contrary to Ohio law.
    [3.] The trial court’s findings that defendant removed salvaged
    fencing from the jobsite without permission to do so and that plaintiff
    was damaged in the sum of $25,000 are not supported by [the]
    manifest weight of the evidence.
    [4.] The trial court erred as a matter of law by awarding counsel fees
    to plaintiff.
    [5.] The trial court’s determination that defendant had produced no
    evidence indicating that plaintiff published a false and defamatory
    statement regarding defendant is not supported by the manifest
    weight of the evidence.
    {¶10} In the first assignment of error, DiPaolo argues the trial court erred by
    granting partial summary judgment with respect to its counterclaims for Breach of
    Contract and Unjust Enrichment.
    {¶11} Summary judgment is appropriate when “there is no genuine issue as to
    any material fact and * * * the moving party is entitled to judgment as a matter of law,” i.e.,
    when “reasonable minds can come to but one conclusion and that conclusion is adverse
    to the party against whom the motion for summary judgment is made, that party being
    entitled to have the evidence or stipulation construed most strongly in the party’s favor.”
    8
    Case No. 2022-T-0032
    Civ.R. 56(C). An appellate court’s “review of a summary-judgment ruling is de novo.”
    Fradette v. Gold, 
    157 Ohio St.3d 13
    , 
    2019-Ohio-1959
    , 
    131 N.E.3d 12
    , ¶ 6.
    {¶12} In the course of the parties’ dealings with each other, DiPaolo Industrial
    submitted eight Change Orders to Menard for additional work not contemplated by the
    original Construction Contract.     This Contract provided as follows with respect to
    additional work:
    ARTICLE 2: CHANGES IN THE WORK –
    OWNER [Menard], without invalidating this contract, may, at
    any time, order changes in the work within the general scope of this
    contract. CONTRACTOR [DiPaolo] shall not perform any extra or
    additional work or changes from the Contract Documents
    unless previously authorized in writing by an AIA change order
    signed by Troy Anderson, the General Manager Store
    Planning/Design /Construction. Portions of change order work
    are subject to merchandise credit check. OWNER’s project
    managers are not authorized to approve changes in the work.
    {¶13} With respect to such contractual provisions, the Ohio Supreme Court has
    held: “It is universally recognized that where a building or construction contract, public or
    private, stipulates that additional, altered, or extra work must be ordered in writing, the
    stipulation is valid and binding upon the parties, and no recovery can be had for such
    work without a written directive therefore in compliance with the terms of the contract,
    unless waived by the owner or employer.” Foster Wheeler Enviresponse, Inc. v. Franklin
    Cty. Convention Facilities Auth., 
    78 Ohio St.3d 353
    , 360, 
    678 N.E.2d 519
     (1997). Under
    the first assignment of error, DiPaolo asserts “the question presented is whether or not
    material questions of fact exist as to Menard’s waiver of the change order procedures
    contained in the original contract between the parties.” Assignments of Error and Brief of
    Appellant, at 17.
    9
    Case No. 2022-T-0032
    {¶14} With respect to waiver of such contractual provisions, the Ohio Supreme
    Court has held: “It is familiar law that stipulations in written contracts may be waived by
    the parties, and that a construction placed by the parties upon a written contract in the
    progress of its performance, with full knowledge of all the circumstances, will be binding.
    * * * This rule is peculiarly just when applied to building contracts, when changes are
    made, the necessity for which develops as the work progresses, and while the parties are
    intent on the accomplishment of the undertaking, no fraud or undue advantage being
    shown.” Expanded Metal Fireproofing Co. v. Noel Constr. Co., 
    87 Ohio St. 428
    , 440, 
    101 N.E. 348
     (1913).
    {¶15} This court has similarly held: “‘A provision in a construction contract that
    change orders be reduced to writing and signed by the parties may be waived. The
    requirement will be considered to have been waived by the parties when there is clear
    and convincing evidence showing that the alterations were made with the knowledge and
    participation of all concerned, no fraud having been shown.’” (Emphasis added.) Wells
    Fargo Bank, N.A. v. Smith, 11th Dist. Trumbull No. 2010-T-0051, 
    2012-Ohio-1672
    , ¶ 42,
    citing Frantz v. Van Gunten, 
    36 Ohio App.3d 96
    , 
    521 N.E.2d 506
    , syllabus (3d Dist.1987).
    This court explained, “[b]y requiring evidence as to subsequent acts of the ‘opposing’
    party, a proper balance is reached between the enforcement of the basic purpose of the
    clause and the concern that a party could agree to both the oral waiver and modification,
    and then ‘hide’ behind the ‘no oral modification’ clause in order to avoid enforcement.” Id.
    at ¶ 46; Foster at 364 (“mere knowledge, and even acquiescence, is not enough for
    recovery”). Compare 2A Bruner & O’Connor on Construction Law, Waiver of written
    change order requirements, Section 7:250 (“Many construction contracts require that in
    10
    Case No. 2022-T-0032
    order for a contractor to be entitled to compensation for performing extra work, the work
    must first be authorized by a written change order. The intent behind these provisions is
    to protect the owner from surprise claims for extra work. To this extent, these provisions
    fulfill a legitimate and useful purpose.     Nevertheless, these provisions have been
    employed to shield an owner from having to pay a contractor for work that was clearly
    beyond the scope of the contract. This is an area where the courts often employ equity
    in the form of finding that the written authorization requirement was waived by the party
    seeking to enforce its terms.”).
    {¶16} DiPaolo Industrial’s managing member, Sergio DiPaolo, testified by
    deposition that change orders were approved verbally by either Menard’s project
    manager, Brad Wondra, or assistant general manager, Jim Carlson. DiPaolo testified
    that generally the terms for the additional work were negotiated with either Wondra or
    Carlson and then a written change order would be submitted by DiPaolo Industrial for
    signature by general manager, Troy Anderson. However, only one of the eight change
    orders was ever signed.
    {¶17} The first change order involved additional grading or clearing an area on the
    south side of the construction site for the installation of a gas line. A November 18, 2013
    email from Wondra to DiPaolo stated: “Can you get me a price on that grading * * * by
    Friday? I need to get this work done so utilities can come in to relocate the gas line toward
    the property line.” DiPaolo testified regarding the negotiations with Wondra: “We spoke
    about it. He asked me about it, it had to be done, give me a price. I gave him a price.
    And then he responded back, sounds good, okay, we’re good to go on that.” A December
    9, 2013 email from Wondra to DiPaolo stated: “Jim [Carlson] gave me the go ahead on
    11
    Case No. 2022-T-0032
    the extra work on the south side of the property ($6,000). Go ahead and start mobilizing.”
    Carlson, in his deposition, affirmed that he spoke with Anderson about the additional work
    and that DiPaolo Industrial was authorized to do the work. DiPaolo Industrial did not
    submit a written change order until March 25, 2014, and Anderson did not sign the order
    until April 18, 2014.   According to the terms of the Construction Contract, DiPaolo
    Industrial should not have been authorized to commence the work until Anderson had
    signed the change order.
    {¶18} The second change order involved the removal of a pylon sign. DiPaolo
    testified that Wondra verbally approved this change order. Carlson testified that “the cost
    [to remove the sign] was approved by Troy Anderson to go ahead with that.” DiPaolo
    claimed a change order was submitted but never returned.
    {¶19} On April 10, 2014, Wondra emailed DiPaolo and copied both Carlson and
    Anderson: “On December 9th, we approved change order #1 for the regrading over on the
    south side of the property. I will submit to Troy to sign. On the AIA change order form
    #2, I do not know what this all entails. Why is it going to cost me [an] additional $6,000
    to remove[] the other pylon sign. Please advise. Work Order-Excavation [third change
    order]- We will not sign. Per the contract plans, you were supposed to remove the utilities
    and backfill your trenches properly. Work Order-Asphalt [fourth change order]- We are
    not opposed to this as an extra for the asphalt. In the existing parking lot, there is a total
    of 7ʺ of asphalt that needs to be milled. However, we will not agree to a change order on
    a per day basis. We will only agree on a fixed cost.”
    {¶20} The foregoing evidence is sufficient to raise a genuine issue of material fact
    as to whether Menard waived the contractual provision that additional work had to be
    12
    Case No. 2022-T-0032
    approved by Anderson in writing prior to the commencement of the work. Such was not
    the procedure followed by either of the parties in the course of performance of the
    contract. It is noted that the contract specifically stated that project managers could not
    approve changes in the work. See Foster, 78 Ohio St.3d at 364, 
    678 N.E.2d 519
     (“[i]t is
    generally recognized that, in the absence of an express authority, an engineer, architect,
    superintendent or inspector in charge of or assigned to public building or construction
    work has no power to waive or modify a stipulation requiring a written order for alterations,
    even where that person may authorize alterations in writing”). However, the evidence in
    the present case is that Wondra would consult with Carlson, an assistant general
    manager, before conveying approval to DiPaolo Industrial. Moreover, Carlson would
    consult with Anderson regarding the change orders, and Anderson was the Menard
    representative with authority to approve change orders. The significant point is that all
    levels of Menard’s management were actively aware of and/or participating in the
    authorization of additional work contrary to the terms of Article 2. In these circumstances,
    summary judgment on the issue of waiver was not appropriate as to any of the purported
    change orders to which DiPaolo claims Menard agreed.3
    {¶21} We emphasize that there is evidence from which it could be reasonably
    inferred that Anderson was being consulted about change orders and giving his approval
    without regard for the contractual procedure.                Giving DiPaolo the benefit of such
    inferences, Anderson approved the first two change orders through Carlson without
    3. We are aware that, in the final judgment after trial, the contract price was adjusted to incorporate the
    cost of some of the additional work performed by DiPaolo Industrial. We are also aware that whether
    Menard ever agreed to the terms of the change orders and whether DiPaolo Industrial completed the work
    proposed in the change orders are also in dispute. Our ruling here is limited to whether the issue of waiver
    could be decided as a matter of law.
    13
    Case No. 2022-T-0032
    requiring a written AIA change order. Nor does the evidence substantiate the claim that
    Menard merely “acquiesce[d]” to DiPaolo’s performance of additional work. In the case
    of the first change order, Menard approached DiPaolo and requested “a price” for
    additional grading. The price for the second change order was approved by Anderson
    and accepted by DiPaolo, although Wondra appears to have been unaware of the
    agreement. In almost every case, Menard was active in negotiating the terms and
    compensation for the performance of additional work. If Anderson was approving the
    additional work without requiring written change orders (at least until DiPaolo requested
    payment), a genuine issue of material fact exists on the waiver issue and summary
    judgment should have been denied.
    {¶22} DiPaolo Industrial also argues the lower court erred by granting summary
    judgment on its unjust enrichment claims on the grounds that “each change work order is
    a contract in and of itself.” Assignments of Error and Brief of Appellant, at 20-21. We
    disagree. Regardless of whether a change order contains the elements of a separate
    contract, the subject of additional work is one that is encompassed by the original
    contract.   See Conditions of the Contract / Instructions to Bidders, Change Order
    Procedure 5.A (“[t]he change order shall clearly state the original contract amount, revised
    contract amount and any extension or reduction in the schedule”).
    {¶23} “Generally, Ohio law does not permit recovery under the theory of unjust
    enrichment when an express contract covers the same subject matter.” Bunta v. Superior
    VacuPress, L.L.C., __ Ohio St.3d __, 
    2022-Ohio-4363
    , __ N.E.3d __, ¶ 36; Jochum v.
    Howard Hanna Co., 11th Dist. Lake No. 2020-L-077, 
    2020-Ohio-6676
    , ¶ 45.                “The
    doctrine of unjust enrichment is limited when an express contract exists that concerns the
    14
    Case No. 2022-T-0032
    same subject because ‘“the parties have fixed their contractual relationship in an express
    contract,”’ and thus, ‘“there is no reason or necessity for the law to supply an implied
    contractual relationship between them.’” (Citation omitted.) Bunta at ¶ 39.
    {¶24} To the extent indicated above, the first assignment of error is with merit.
    {¶25} DiPaolo Industrial’s second, third and fifth assignments of error challenge
    various aspects of the lower court’s judgment as being contrary to the weight of the
    evidence.
    {¶26} “Weight of the evidence concerns ‘the inclination of the greater amount of
    credible evidence, offered in a trial, to support one side of the issue rather than the other.
    It indicates clearly to the jury that the party having the burden of proof will be entitled to
    their verdict, if, on weighing the evidence in their minds, they shall find the greater amount
    of credible evidence sustains the issue which is to be established before them. Weight
    is not a question of mathematics, but depends on its effect in inducing belief.’” State v.
    Thompkins, 
    78 Ohio St.3d 380
    , 387, 
    678 N.E.2d 541
     (1997), quoting Black’s Law
    Dictionary 1594 (6th Ed.1990).
    {¶27} “[I]n determining whether the judgment below is manifestly against the
    weight of the evidence, every reasonable intendment and every reasonable presumption
    must be made in favor of the judgment and the finding of facts. * * * If the evidence is
    susceptible of more than one construction, the reviewing court is bound to give it that
    interpretation which is consistent with the verdict and judgment, most favorable to
    sustaining the verdict and judgment.” Seasons Coal Co., Inc. v. Cleveland, 
    10 Ohio St.3d 77
    , 80, 
    461 N.E.2d 1273
     (1984), fn.3, quoting 5 Ohio Jurisprudence 3d, Appellate Review,
    Section 603, at 191-192 (1978); Eastley v. Volkman, 
    132 Ohio St.3d 328
    , 2012-Ohio-
    15
    Case No. 2022-T-0032
    2179, 
    972 N.E.2d 517
    , ¶ 21.
    {¶28} In the second assignment of error, DiPaolo Industrial disputes the finding
    that it was in breach of the Construction Contract for defective work and for not completing
    its work within the agreed period. Underlying DiPaolo Industrial’s claims is the further
    alleged error that the trial court failed to give effect to the addendum submitted by DiPaolo
    Industrial with the signed Contract. The Contract itself provided that the Agreement
    Period for completing the work was between November 11, 2013, and January 31, 2014,
    and that time was of the essence. The addendum provided that “we [the parties] had
    both agreed to leave the Asphalt in place until the weather breaks in late February or
    early March,” and “[c]rushing of concrete will commence during January, although if the
    temperature falls below 20 degrees Fahrenheit the process will stop.” According to
    DiPaolo Industrial, “[w]ith the Addendum in effect, there was simply no firm date by which
    the crushing part of the operation had to be completed. * * * While Plaintiff may have
    alleged that the opening of its store was delayed, * * * Plaintiff’s own witness testified that
    the store opened on time and other evidence indicated that, if any undue delay did occur,
    it was the fault of Plaintiff’s general contractor [McConnell Excavating] rather than
    Defendant. Consequently, Plaintiff had absolutely no right to discontinue payments to
    Defendant and Defendant had every right to stop working.” Assignments of Error and
    Brief of Appellant, at 23-24.
    {¶29} The evidence is equivocal as to whether the addendum became part of the
    parties’ Contract. When the Contract was submitted to DiPaolo Industrial, it had already
    been signed by Menard. DiPaolo signed and returned the Contract but included the
    unsigned addendum with the Contract.          The signed Contract does not indicate the
    16
    Case No. 2022-T-0032
    existence of any amendments or addendum. Carlson denies that Menard agreed to the
    terms of the addendum. DiPaolo contends that the terms of the addendum were agreed
    to prior to the signing of the Contract. Given these circumstances, the addendum could
    be construed either as a conditional acceptance of the Contract or as a proposed
    amendment thereto.      As a conditional acceptance, it could be argued that Menard
    implicitly accepted the terms of the addendum by proceeding to have DiPaolo Industrial
    commence demolition. As a proposed amendment, the addendum failed to adhere to the
    procedures set forth in the Contract for amendment or to receive any recognition by
    Menard.
    {¶30} It is generally recognized that, “[i]n accordance with general contract
    principles, if the acceptance modifies or alters the terms set forth in the application, then
    the acceptance is deemed a rejection and counteroffer, which must be accepted by the
    applicant in order to be effective as a contract.” (Citation omitted.) Livi Steel, Inc. v. Bank
    One, Youngstown, N.A., 
    65 Ohio App.3d 581
    , 588, 
    584 N.E.2d 1267
     (11th Dist.1989);
    Mentor Exempted Village School Dist. Bd. of Edn. v. Lake Cty. Edn. Serv. Ctr. Governing
    Bd., 
    2016-Ohio-7649
    , 
    74 N.E.3d 706
    , ¶ 78 (11th Dist.). Conversely, under the parol
    evidence rule, “a party who has entered into a written contract [is prohibited] from
    contradicting the terms of the contract with evidence of alleged or actual agreements.”
    (Citation omitted.) Williams v. Spitzer Autoworld Canton, L.L.C., 
    122 Ohio St.3d 546
    ,
    
    2009-Ohio-3554
    , 
    913 N.E.2d 410
    , ¶ 14.           Moreover, it is not entirely certain if the
    addendum was understood in the technical sense of “a thing that is added or to be added,”
    i.e., additional terms added to the original contract, or as an amendment of the original
    contract. Gutierrez-Gordillo v. Tomo Hibachi Restaurant and Lounge, L.L.C., 2018-Ohio-
    17
    Case No. 2022-T-0032
    2941, 
    118 N.E.3d 301
    , ¶ 11 (8th Dist.) (“[a]lthough ‘addendum’ and ‘amendment’ are legal
    terms of art, the parties did not give any indication that they intended that an ‘addendum’
    to the operating agreement would not be the same as an ‘amendment’”).
    {¶31} This issue, however, need not be determined by this Court. The evidence
    of record supports the finding that DiPaolo Industrial failed to complete its work under the
    Contract before quitting the worksite in early May, and thus substantiates the breach by
    DiPaolo Industrial regardless of whether the addendum is given effect.
    {¶32} On the date that work was to be completed under the terms of the Contract,
    January 31, Menard sent a letter to DiPaolo Industrial stating the following: “This letter is
    to inform DiPaolo Industrial Development of the concerns Menard, Inc. has with the
    demolition of the old Wal-Mart building at 2057 Elm Road. * * * You are understaffed on
    this demolition project. I understand that we have been shut down for a week due to the
    extreme cold weather but there was no ambition to get caught up once the weather broke.
    When I was onsite on January 30th, it was 30 degrees out and only 2 people were working
    on pulverizing the concrete slabs. No one was working on disassembling the Garden
    Center, removing the parking lot light fixtures, or removing underground utilities. Please
    forward me an updated schedule and how you are going to get caught back up, to be
    finished no later than March 1st.” At trial, DiPaolo testified that he had no issues with the
    content of this letter.
    {¶33} On March 12, 2014, Menard sent a “7-day notice” to DiPaolo Industrial
    detailing items which have been completed and advising that “[t]hese items must be 100%
    completed otherwise Menard, Inc. will be forced to bring in another contractor at your
    expense.”
    18
    Case No. 2022-T-0032
    {¶34} On April 3, 2014, Menard advised DiPaolo Industrial that the general
    contractor “will start mobilizing for the new store starting Monday, April 7 th,” and “[y]ou
    must have all work completed and your material and equipment out next week.” Corey
    Frasier, the general superintendent for McConnell Excavating, testified at trial that
    McConnell Excavating began work on site in the first week of April 2014. Frasier also
    testified to work completed by McConnell Excavating that was left undone by DiPaolo
    Industrial. DiPaolo complained that the presence of McConnell Excavating on site, in
    addition to the way in which McConnell Excavating performed demolition work, delayed
    and hindered DiPaolo Industrial from completing its own contract work. However, under
    the terms of the addendum, at this point DiPaolo had had a full month to complete its
    work which should have consisted of removing asphalt and crushing concrete.
    {¶35} DiPaolo testified at trial that DiPaolo Industrial quit the worksite in the first
    week of May because he did not believe Menard would pay him anything further and
    returned during the next two to three weeks to remove equipment. At the time DiPaolo
    Industrial quit the work site, DiPaolo acknowledged that there was work under the
    Contract that had not been completed, although the extent of that work was disputed.
    {¶36} Given the foregoing record, we conclude that the finding that DiPaolo
    Industrial was in breach is supported by the weight of the evidence regardless of whether
    the addendum was in effect. Two months from early March, when according to the
    addendum any work that was suspended on account of cold weather should have
    recommenced, was a reasonable period of time for DiPaolo Industrial to complete its
    work. Whether the new store opened on schedule is not material to the issue of breach,
    as the record demonstrates DiPaolo Industrial needed to complete its work so that the
    19
    Case No. 2022-T-0032
    general contractor could begin its work.
    {¶37} The second assignment of error is without merit.
    {¶38} In the third assignment of error, DiPaolo Industrial argues that the finding of
    conversion with respect to the fencing was against the weight of the evidence.
    {¶39} According to the terms of the Contract, certain items from the demolition
    project, including wrought-iron fencing at issue herein, were reserved by Menard as
    salvage. DiPaolo Industrial stored the fencing offsite until a time at which it was agreed
    that Menard would collect the fencing and other salvaged material. DiPaolo Industrial
    returned the items to the work site, but Menard did not provide enough transportation to
    remove it. Therefore, DiPaolo Industrial returned it to storage at 408 Dana Street.
    Carlson testified that Menard repeatedly asked for the fencing to be returned and was
    willing to pick up the fencing but did not know where it was being stored. Carlson
    estimated the value of the fencing at $25,000. DiPaolo testified that he would not return
    the fencing unless Menard agreed to pay for the cost of transportation. DiPaolo admitted
    that he did not inform Menard of where the fencing was located and that the building
    where it is located is no longer under DiPaolo Industrial’s control.
    {¶40} Conversion is defined as “the wrongful exercise of dominion over property
    to the exclusion of the rights of the owner, or withholding it from his possession under a
    claim inconsistent with his rights.” Joyce v. Gen. Motors Corp., 
    49 Ohio St.3d 93
    , 96, 
    551 N.E.2d 172
     (1990).
    Conversion * * * requires nothing more than the defendant
    possessing a plaintiff’s chattel and being unwilling to give it back.
    See Keeton, Prosser & Keeton on Torts (1984), 88 et seq. Sec. 15-
    Conversion. There is no requirement that the personal property be
    wrongfully obtained. Although a demand and refusal to return the
    personal property is ordinarily necessary to prove conversion, acts
    20
    Case No. 2022-T-0032
    by a defendant which are inconsistent with the right of a plaintiff’s
    ownership are sufficient to satisfy this requirement.
    Kiss v. Dick Baker Dodge, 6th Dist. Erie No. E-98-027, 
    1998 WL 904920
    , *3; Baltimore &
    Ohio RR. Co. v. O’Donnell, 
    49 Ohio St. 489
    , 
    32 N.E. 476
     (1892), paragraph two of the
    syllabus (“[a]ny wrongful exercise of dominion over chattels in exclusion of the rights of
    the owner, or withholding of them from his possession under a claim inconsistent with his
    rights, constitutes a conversion”).
    {¶41} We find that the evidence of record supports a finding of conversion. There
    was evidence that DiPaolo wrongfully refused to return the fencing to Menard and/or
    enable Menard to reclaim it when asked by Menard. Moreover, Carlson, as assistant
    general manager of the project, was competent to provide an estimate of the value of the
    fencing (of course, not being able to access the fencing, its value could not be properly
    appraised). Compare Tokles & Son, Inc. v. Midwestern Indemn. Co., 
    65 Ohio St.3d 621
    ,
    627, 
    605 N.E.2d 936
     (1992) (“[w]e know of no reason for withholding information from a
    jury’s consideration or for requiring a corporate officer to qualify as an expert in all cases
    before testifying as to the value of corporate property”).
    {¶42} The third assignment of error is without merit.
    {¶43} In the fifth assignment of error, DiPaolo Industrial argues that the judgment
    in favor of Menard as to its counterclaim for defamation is against the weight of the
    evidence.
    {¶44} At trial, DiPaolo testified that he viewed a news segment on 27 WKBN in
    which a spokesperson for Menard was “talking about this lawsuit * * * and that Mr. DiPaolo
    had stolen fencing and other items from the property.” After contacting the news station,
    it was learned that the video of the segment was no longer available. DiPaolo Industrial
    21
    Case No. 2022-T-0032
    introduced a couple of print articles regarding the lawsuit which included the allegation
    that DiPaolo Industrial had unlawfully removed $25,000 in fencing belonging to Menard.
    Additionally, DiPaolo testified that Wondra filed a complaint with law enforcement
    regarding the fencing and that he was questioned by the police about the fencing.
    DiPaolo Industrial contends the foregoing “supports the proposition that Plaintiff was
    alleging that Defendant had actually stolen materials.” Assignments of Error and Brief of
    Appellant, at 29.
    {¶45} “In Ohio, defamation occurs when a publication contains a false statement
    ‘made with some degree of fault, reflecting injuriously on a person’s reputation, or
    exposing a person to public hatred, contempt, ridicule, shame or disgrace, or affecting a
    person adversely in his or her trade, business or profession.’” (Citation omitted.) Am.
    Chem. Soc. v. Leadscope, Inc., 
    133 Ohio St.3d 366
    , 
    2012-Ohio-4193
    , 
    978 N.E.2d 832
    , ¶
    77. “To establish defamation, the plaintiff must show (1) that a false statement of fact
    was made, (2) that the statement was defamatory, (3) that the statement was published,
    (4) that the plaintiff suffered injury as a proximate result of the publication, and (5) that the
    defendant acted with the requisite degree of fault in publishing the statement.” (Citation
    omitted.) 
    Id.
    {¶46} Menard counters, and we agree, that the allegedly defamatory statements
    fall under the scope of absolute privilege which provides that “a claim alleging that a
    defamatory statement was made in a written pleading does not state a cause of action
    where the allegedly defamatory statement bears some reasonable relation to the judicial
    proceeding in which it appears.” Surace v. Wuliger, 
    25 Ohio St.3d 229
    , 233, 
    495 N.E.2d 939
     (1986). The allegedly defamatory statement published in the news articles related to
    22
    Case No. 2022-T-0032
    the pending litigation and so falls within the scope of the privilege. Am. Chem. Soc. at ¶
    86 (“[c]onsidering the article as a whole and the fact that the article contained a true and
    accurate summary of the legal proceedings at the time, we hold that the statements in the
    article are, as a matter of law, not defamatory”). Whatever statements Wondra may have
    made to law enforcement would be similarly protected. Fisher v. Ahmed, 2020-Ohio-
    1196, 
    153 N.E.3d 612
    , ¶ 40 (9th Dist.) (“[a]s a matter of public policy, an absolute privilege
    protects statements that report a possible crime, because a privilege under such
    circumstances encourages ‘“the reporting of criminal activity by removing any threat of
    reprisal in the form of civil liability”’) (citation omitted).
    {¶47} The fifth assignment of error is without merit.
    {¶48} In the fourth assignment of error, DiPaolo Industrial asserts that the award
    of attorney fees is in error as “Plaintiff has provided insufficient proof of these damages
    and, further, an award of such would be against Ohio public policy.” Assignments of Error
    and Brief of Appellant, at 25.
    {¶49} “Ohio has long adhered to the ‘American rule’ with respect to recovery of
    attorney fees: a prevailing party in a civil action may not recover attorney fees as a part
    of the costs of litigation.” Wilborn v. Bank One Corp., 
    121 Ohio St.3d 546
    , 2009-Ohio-
    306, 
    906 N.E.2d 396
    , ¶ 7. “However, there are exceptions to this rule.” 
    Id.
     “Exceptions
    to the rule allow fee-shifting and taxing attorney fees as costs (1) if there has been a
    finding of bad faith; (2) if a statute expressly provides that the prevailing party may recover
    attorney fees; and (3) if the parties’ contract provides for fee-shifting.” (Emphasis added.)
    J.B.H. Properties, Inc. v. N.E.S. Corp., 11th Dist. Lake No. 2007-L-024, 
    2007-Ohio-7116
    ,
    ¶ 8.
    23
    Case No. 2022-T-0032
    {¶50} The parties’ Contract herein provides:
    ARTICLE 5: INDEMNIFICATION
    [1] CONTRACTOR [DiPaolo Industrial] shall indemnify and
    hold harmless OWNER [Menard], its agents and its employees from
    any and all liability, damages, expenses, claims, demands, actions
    or causes of action, including attorney fees, arising out of the
    performance of the Contract Documents, Agreement and/or Work
    hereunder, whether such liability, damages, expenses, claims,
    demands, actions or causes of action are caused by
    CONTRACTOR, its subcontractors, or lower tiered contractors, or
    their agents or employees, OWNER, its agents and its employees,
    or any persons acting on behalf of OWNER and/or CONTRACTOR.
    [2] In the event of failure by CONTRACTOR to defend OWNER
    against any such claim upon ten (10) days written notification of
    OWNER requesting that CONTRACTOR do so, OWNER shall be
    entitled to directly settle any such claim. [3] CONTRACTOR waives
    any right to dispute the amount of any settlements made by OWNER
    under this provision and acknowledges that OWNER is entitled to
    deduct the full amount of any such settlements from the Contract
    Sum as defined below. [4] If Final Payment, as defined herein, has
    already been made by OWNER to CONTRACTOR, CONTRACTOR
    agrees to reimburse OWNER the full amount of any settlement within
    ten (10) days after receipt of invoice from OWNER.
    (Emphasis added.)
    {¶51} The issue is whether Article 5 is a fee shifting provision and, if so, under
    what circumstances.
    {¶52} In contract cases in which the parties intend a fee-shift when they are
    involved in litigation over contract performance, we typically see the following type of
    language: “indemnification from and against claims, damages, losses and expenses,
    including but not limited to its actual attorney fees incurred, arising out of or resulting from
    performance of the contract or out of the actual or alleged failure of the contractor or
    subcontractor to perform any obligations under the contract or subcontract documents.”
    {¶53} By contrast, “[i]ndemnity arises from contract, either express or implied, and
    24
    Case No. 2022-T-0032
    is the right of a person who has been compelled to pay what another should have paid,
    to require complete reimbursement.” Worth v. Aetna Cas. & Sur. Co., 
    32 Ohio St.3d 238
    ,
    240, 
    513 N.E.2d 253
     (1987). “Indemnity agreements are interpreted in the same manner
    as other contracts.” Ferguson v. Boron, 
    2018-Ohio-69
    , 
    105 N.E.3d 424
    , ¶ 47 (7th Dist.).
    “The true nature of an indemnity relationship is determined by the intent of the parties
    expressed within the language of the agreement.” 
    Id.
     “[A]ll the words used [must] be
    taken in their ordinary and popular sense,” Glaspell v. Ohio Edison Co., 
    29 Ohio St.3d 44
    ,
    47, 
    505 N.E.2d 264
     (1987), and “[w]hen a [writing] is worded in clear and precise terms;
    when its meaning is evident, and tends to no absurd conclusion, there can be no reason
    for refusing to admit the meaning which such [writing] naturally presents.” Lawler v. Burt,
    
    7 Ohio St. 340
    , 350 (1857).
    {¶54} Further, “parties ‘have a fundamental right to contract freely with the
    expectation that the terms of the contract will be enforced.’ Nottingdale Homeowners’
    Assn., Inc. v. Darby, 
    33 Ohio St.3d 32
    , 36, 
    514 N.E.2d 702
     (1987)[.] * * * To that end,
    parties to a contract may include contractual terms that abrogate the common law. Paul
    Cheatham I.R.A. v. Huntington Natl. Bank, 
    157 Ohio St.3d 358
    , 
    2019-Ohio-3342
    , 
    137 N.E.3d 45
    , ¶ 30. ‘[B]ut the intent to do so must be clearly indicated.’ 
    Id.
     This principle
    applies to contractual indemnification agreements. * * * [T]he ‘nature of an indemnity
    relationship is determined by the intent of the parties as expressed by the language used’
    in the agreement. Worth[, supra, at] 240 * * *. [A court] cannot ascertain the parties’
    intent without looking at the words that they used to express their intent. Kelly v. Med.
    Life Ins. Co., 
    31 Ohio St.3d 130
    , 132, 
    509 N.E.2d 411
     (1987) (‘The intent of the parties to
    a contract is presumed to reside in the language they chose to employ in the agreement’).”
    25
    Case No. 2022-T-0032
    Wildcat Drilling, L.L.C. v. Discovery Oil & Gas, L.L.C., 
    164 Ohio St.3d 480
    , 2020-Ohio-
    6821, 
    173 N.E.3d 1156
    , ¶ 14.
    {¶55} When read as a whole and in context, Article 5 provides for third-party
    indemnification only. It is not an indemnification clause for attorney fees incurred in
    enforcing the contract between the two contracting parties.        The first sentence is
    unambiguously written to require DiPaolo to indemnify and hold Menard harmless from
    “liability, damages, expenses, claims, demands, actions or causes of action, including
    attorney fees, arising out of the performance of the Contract Documents, Agreement
    and/or Work” regardless of who caused the claim to arise, even including Menard. The
    first sentence must be read in context with the balance of the article. For instance, the
    second sentence describes what Menard may do in the event DiPaolo fails to “defend”
    Menard against “any such claim”—the list stated in sentence one—Menard may directly
    settle the claim. The third sentence provides that DiPaolo waives the right to contest the
    amount of the settlement and that Menard may deduct the amount from the total contract
    sum. The fourth sentence allows a claw-back of the settlement amount in the event final
    payment has been made to DiPaolo.
    {¶56} Ohio case law does not provide an interpretation of the precise language
    drafted by Menard; however, cases in other states do. The critical term in Article 5 is
    “defend,” which indicates the clause’s application to third party claims. This term would
    have no effect in a direct action between the parties. “Obviously, in a direct action
    between the parties, neither party would be interested in tendering its defense or being
    defended by the other party.” Canopy Corp. v. Symantec Corp., 
    395 F.Supp.2d 1103
    ,
    1115 (D.Utah 2005).
    26
    Case No. 2022-T-0032
    {¶57} Further, “[c]onstruing the indemnification clause ‘as pertaining only to third-
    party suits affords a fair meaning to all of the language employed by the parties in the
    contract and leaves no provision without force and effect.’” 
    Id. at 1116
    , quoting Oscar
    Gruss & Son, Inc. v. Hollander, 
    337 F.3d 186
    , 200 (2d Cir.2003) (holding that an
    indemnification clause was confined to third-party claims and did not permit an attorney
    fee award in a first-party lawsuit); accord Hooper Assocs., Ltd. v. AGS Computers, Inc.,
    
    74 N.Y.2d 487
    , 
    548 N.E.2d 903
     (1989) (“To extend the indemnification clause to require
    defendant to reimburse plaintiff for attorney’s fees in the breach of contract action against
    defendant would render these provisions meaningless because the requirement of notice
    and assumption of the defense has no logical application to a suit between the parties.”).
    {¶58} Based on the express language of Article 5 and the inapplicability of any
    other section of the contract that references attorney fees, there is no need to consider
    DiPaolo’s public policy or evidentiary arguments.
    {¶59} The fourth assignment of error is with merit.
    {¶60} For the foregoing reasons, the judgment of the Trumbull County Court of
    Common Pleas is affirmed in part and reversed in part. This matter is remanded for
    further proceedings consistent with this opinion. Costs to be taxed between the parties
    equally.
    JOHN J. EKLUND, P.J., concurs,
    MARY JANE TRAPP, J., concurs in part and dissents in part with a Concurring/Dissenting
    Opinion.
    ____________________________________________
    27
    Case No. 2022-T-0032
    MARY JANE TRAPP, J., concurs in part and dissents in part with a Concurring/Dissenting
    Opinion.
    {¶61} I concur with the majority’s analysis and disposition regarding DiPaolo’s
    second through fifth assignments of error as well as the unjust enrichment portion of
    DiPaolo’s first assignment of error. I depart ways with the majority on the breach of
    contract portion of DiPaolo’s first assignment of error. Specifically, I disagree with the
    majority’s determination that the record on summary judgment creates a genuine issue
    of material fact as to whether Menard waived the written change order requirement in the
    parties’ contract.
    {¶62} The majority correctly begins its analysis with the Supreme Court of Ohio’s
    decision in Foster Wheeler Enviresponse, Inc. v. Franklin Cty. Convention Facilities Auth.,
    
    78 Ohio St.3d 353
    , 
    678 N.E.2d 519
     (1997), which states:
    {¶63} “It is universally recognized that where a building or construction contract,
    public or private, stipulates that additional, altered, or extra work must be ordered in
    writing, the stipulation is valid and binding upon the parties, and no recovery can be had
    for such work without a written directive therefor in compliance with the terms of the
    contract, unless waived by the owner or employer.” Id. at 360-361.
    {¶64} The rationale for this principle is as true today as it was over 125 years ago
    when the Supreme Court of Ohio decided Ashley v. Henahan, 
    56 Ohio St. 559
    , 
    47 N.E. 573
     (1897):
    {¶65} “The primary purpose of requiring written authorization for alterations in a
    building or construction contract is to protect the owner against unjust and exorbitant
    28
    Case No. 2022-T-0032
    claims for compensation for extra work. It is generally regarded as one of the most
    effective methods of protection because such clauses limit the source and means of
    introducing additional work into the project at hand. It allows the owner to investigate the
    validity of a claim when evidence is still available and to consider early on alternative
    methods of construction that may prove to be more economically viable. It protects
    against runaway projects and is, in the final analysis, a necessary adjunct to fiscal
    planning.” Foster Wheeler at 363-364, citing Ashley at 572-573.
    {¶66} In this case, Article 2 of the parties’ contract, entitled “Changes in the Work,”
    provides as follows:
    {¶67} “[Menard], without invalidating this contract, may, at any time, order
    changes in the work within the general scope of this contract. [DiPaolo] shall not
    perform any extra or additional work or changes from the Contract Documents
    unless previously authorized in writing by an AIA change order signed by Troy
    Anderson, the General Manager Store Planning/Design/Construction. Portions of
    change order work are subject to merchandise credit check. [Menard]’s project
    managers are not authorized to approve changes in the work.” [Bolding sic.]
    {¶68} Thus, pursuant to Article 2, Troy Anderson was the only person who could
    authorize additional work on Menard’s behalf, and his authorization was required to be
    set forth in a signed and written AIA change order.
    {¶69} The majority also correctly notes that an owner may waive this type of
    contractual provision. See Foster Wheeler at 360 (“unless waived by the owner”). In
    those situations, “‘proof of a waiver must either be in writing, or by such clear and
    convincing evidence as to leave no reasonable doubt about it.’” Id. at 364, quoting Ashley
    29
    Case No. 2022-T-0032
    at paragraph five of the syllabus. “Mere knowledge, and even acquiescence, is not
    enough for recovery.” Id. In addition, “‘“[e]quivocal conduct, or conduct of doubtful import,
    is not sufficient.”’” Id., quoting Ashley at 574, quoting O’Keefe v. St. Francis’ Church, 
    59 Conn. 551
    , 561, 
    22 A. 325
     (1890).
    {¶70} In this case, there was no written waiver of Article 2. Instead, DiPaolo
    contends that Menard waived the written change order procedure because Jim Carlson,
    assistant general manager of store planning/construction, verbally approved change
    order nos. 2, 5, 6, and 7, and Brad Wondra, project manager, verbally approved change
    order nos. 3 and 4.
    {¶71} Critically, the plain language of Article 2 explicitly notified DiPaolo that only
    Mr. Anderson was authorized to approve changes in the work on Menard’s behalf and
    that Menard’s project managers were not authorized to do so, making any approval from
    Mr. Carlson and Mr. Wondra legally ineffective.
    {¶72} DiPaolo also contends that “[a]t every juncture,” Mr. Carlson and Mr.
    Wondra informed it “that Troy Anderson was both advised of the proposed change work
    orders, had approved such change work orders and that copies of such would be
    forthcoming.”
    {¶73} The evidentiary quality material submitted on summary judgment does not
    support this contention. Contrary to the majority’s determination, the most that can be
    inferred from the record is that Mr. Anderson was copied on some of the email
    correspondence among DiPaolo, Mr. Wondra, and Mr. Carlson regarding additional work.
    {¶74} Further, the majority appears to presume that Mr. Anderson was authorized
    to waive the written change order requirement. According to the Supreme Court of Ohio,
    30
    Case No. 2022-T-0032
    however, “[i]t is generally recognized that, in the absence of express authority, an
    engineer, architect, superintendent or inspector in charge of or assigned to * * *
    construction work has no power to waive or modify a stipulation requiring a written order
    for alterations, even where that person may authorize alterations in writing.” Foster
    Wheeler at 364. Here, the contract identified Mr. Anderson as “the General Manager
    Store Planning/Design/Construction,” which indicates he fit within the purview of this rule.
    See 
    id.
        There was no provision granting authority to Mr. Anderson to waive the
    requirement for a written and signed change order. Rather, as stated, Mr. Anderson’s
    express authority was limited to authorizing additional work set forth in a signed and
    written AIA change order. See 
    id.
    {¶75} For the foregoing reasons, the trial court’s granting of summary judgment
    to Menard on the issue of change orders was correct as a matter of contractual
    interpretation and, thus, as a matter of law. Accordingly, I would overrule DiPaolo’s first
    assignment of error in its entirety.
    31
    Case No. 2022-T-0032