  • [Cite as Kirkner Elec., Inc. v. Rydarowicz, 2020-Ohio-3362.]
    IN THE COURT OF APPEALS OF OHIO
    SEVENTH APPELLATE DISTRICT
    COLUMBIANA COUNTY
    KIRKNER ELECTRIC INC.,
    Plaintiff-Appellee,
    v.
    JOHN RYDAROWICZ, JENNIFER RYDAROWICZ
    Defendants-Appellants.
    OPINION AND JUDGMENT ENTRY
    Case No. 19 CO 0041
    Civil Appeal from the
    Columbiana County Municipal Court of Columbiana County, Ohio
    Case No. 2018 CV F 000420
    BEFORE:
    Gene Donofrio, Cheryl L. Waite, Carol Ann Robb, Judges.
    JUDGMENT:
    Affirmed
    Atty. Fredric Kannensohn, Atty. Samuel Jordan, 4531 Belmont Avenue, Suite 2C,
    Youngstown, Ohio 44505, for Plaintiff-Appellee and
    Atty. Mark Lavelle, 940 Windham Court, Suite 7, Youngstown, Ohio 44512, for
    Defendants-Appellants.
    –2–
    Dated:
    June 12, 2020
    Donofrio, J.
    {¶1}     Defendants-appellants, John and Jennifer Rydarowicz, appeal from a
    Columbiana County Municipal Court judgment in favor of plaintiff-appellee, Kirkner
    Electric, Inc., on appellee’s claim for unjust enrichment, following a bench trial.
    {¶2}     Appellants began construction of their new home in 2016. Appellants
    hired Digger Quality Homes (Digger) to frame the house. On Digger’s recommendation,
    appellants contacted appellee to handle the electrical work.
    {¶3}     In March 2016, appellants met with Brant Griffith. Griffith has worked as
    an electrician for appellee for over 18 years and was in charge of this project. The parties
    agreed that appellee would do the electrical work for the new home. But they never
    entered into a written contract.
    {¶4}     According to Griffith, appellant John Rydarowicz initially told him the house
    was going to be approximately 2,000 square feet. Griffith estimated the project at $5 per
    square foot and gave appellants an estimate of $10,000 to complete the electrical work.
    When Griffith later went to the site of the new house, after it had been framed, he saw
    that the house was actually closer to 3,000 square feet. Griffith then told appellants that
    the project was going to cost more than the $10,000 he initially quoted them.
    {¶5}     According to John, when he and his wife met with Griffith, Griffith told him
    the price would be $10,000 “give or take.” He stated that Griffith never told him a price
    per square foot. John also stated he gave every contractor who worked on his house a
    set of blueprints, which listed the square footage of the house as 2,912 square feet.
    {¶6}     In October 2016, appellee sent appellants the first bill in the amount of
    $7,452.42. Appellants paid the first bill in full. At that point, the project was not yet
    complete and appellants knew they still owed more for the electrical work.
    {¶7}     In March 2017, the project was complete. Appellee sent appellants the
    second bill in the amount of $9,633.09. According to John, they were surprised at the
    amount appellee said they owed. John stated that he contacted Griffith, who told him
    they would work something out. John further stated that he contacted appellee’s owner
    Case No. 19 CO 0041
    –3–
    who told him to pay what he thought was fair. Appellants made payments of $2,500 and
    $3,000 on the second bill.
    {¶8}     Appellee then filed a complaint against appellants asserting a claim for
    unjust enrichment and seeking judgment in the amount of $4,133.09, the balance
    remaining on the second bill, plus interest.
    {¶9}     The matter proceeded to a bench trial where the court heard testimony
    from Griffith, John, and Jenna. The court found that appellee competently performed the
    electrical work and billed appellants in accordance with industry standards. The court
    determined it would be unjust to permit appellant to benefit from the work without
    payment. Therefore, the court awarded judgment in favor of appellee in the amount of
    $4,133.09 with interest.
    {¶10}    Appellants filed a timely notice of appeal on October 15, 2019. They now
    raise a single assignment of error for this court’s review.
    {¶11}    Appellants’ assignment of error states:
    THE TRIAL COURT ERRED IN FINDING THE MANIFEST WEIGHT
    OF PLAINTIFF-APPELLEES [sic.] EVIDENCE PROVED ALL THE
    ELEMENTS OF UNJUST ENRICHMENT.
    {¶12}    Appellants agree that appellee conferred a benefit on them and that they
    knew of the benefit. But they argue that the trial court’s finding that it would be unjust for
    them not to make an additional $4,133.09 payment to appellee was against the manifest
    weight of the evidence. Appellants contend the court accepted Griffith’s testimony as
    truthful and disregarded John’s testimony.       They assert the court accepted John’s
    testimony that the work was completed as expected but that it disregarded John’s
    testimony that appellee’s owner told him to pay what was fair. Moreover, appellants argue
    the trial court rewarded appellee for “sloppy business practices” by awarding it a 70-
    percent increase beyond the initial quote when there was no written contract for the job.
    {¶13} When reviewing civil appeals from bench trials, an appellate court applies
    a manifest weight standard of review. Revilo Tyluka, L.L.C. v. Simon Roofing & Sheet
    Metal Corp., 
    193 Ohio App. 3d 535
    , 2011-Ohio-1922, 
    952 N.E.2d 1181
    (8th Dist.), citing
    App.R. 12(C), Seasons Coal v. Cleveland, 
    10 Ohio St. 3d 77
    , 
    461 N.E.2d 1273
    (1984).
    Case No. 19 CO 0041
    –4–
    Judgments supported by some competent, credible evidence going to all the material
    elements of the case must not be reversed as being against the manifest weight of the
    evidence. C.E. Morris Co. v. Foley Constr. Co., 
    54 Ohio St. 2d 279
    , 
    376 N.E.2d 578
    ,
    syllabus (1978). See, also, Gerijo, Inc. v. Fairfield, 
    70 Ohio St. 3d 223
    , 226, 
    638 N.E.2d 533
    (1994). Reviewing courts must oblige every reasonable presumption in favor of the
    lower court's judgment and finding of facts. 
    Gerijo, 70 Ohio St. 3d at 226
    (citing Seasons
    Coal 
    Co., supra
    ). In the event the evidence is susceptible to more than one interpretation,
    we must construe it consistently with the lower court's judgment.
    Id. In addition,
    the
    weight to be given the evidence and the credibility of the witnesses are primarily for the
    trier of the facts. Kalain v. Smith, 
    25 Ohio St. 3d 157
    , 162, 
    495 N.E.2d 572
    (1986).
    {¶14} We must examine the evidence presented at trial in examining whether the
    trial court’s judgment was against the manifest weight of the evidence.
    {¶15} Griffith was appellee’s sole witness. Griffith testified that he first met with
    appellants in March 2016. (Tr. 9). He stated that there was no general contractor on the
    job. (Tr. 10). Instead, he simply met with appellants and they told him what they wanted
    in their new home. (Tr. 10). Griffith guesstimated that he met with appellants on three
    occasions before he started work at their new house. (Tr. 11). Griffith testified that he
    never saw a set of plans for the house during these meetings. (Tr. 11).
    {¶16} Griffith testified that the parties never entered into a written contract. (Tr.
    12). He stated that appellants told him the house was going to be 2,000 square feet. (Tr.
    12). Believing the house would be approximately 2,000 square feet, Griffith estimated a
    cost of $10,000 to $12,000 based on $5 per square foot. (Tr. 12, 29).
    {¶17} Griffith stated that he realized the house was more than 2,000 square feet
    when he went to the house to start the “rough in.” (Tr. 14). This occurred in June 2016.
    (Tr. 15). At that point, Griffith stated he told appellants the project was going to cost more
    than he had originally quoted but he did not tell them how much more at that time. (Tr.
    15, 30). He stated that appellants did not voice any complaints to him at that time. (Tr.
    17).
    {¶18} Griffith testified that $5 per square foot was an industry average for
    Mahoning and Columbiana County at that time for this type of electrical work. (Tr. 31).
    Case No. 19 CO 0041
    –5–
    {¶19} As to the money paid to appellee, Griffith testified that appellee sent
    appellants a bill in September 2016, for $7,452 after the “rough in” was complete, which
    appellants paid in full. (Tr. 17; Ex. A). Appellee sent appellants a second bill in March
    2017, after the entire job was complete for $9,633.09. (Tr. 17; Ex. A). Appellants paid
    $2,500 toward the second bill in July 2017 and another $3,000 toward the second bill in
    September 2017.      (Tr. 17; Ex. A). Griffith stated there still remained a balance of
    $4,133.09, which appellants have not paid. (Tr. 17; Ex A).
    {¶20} Griffith also testified regarding Exhibit E, which included copies of the work
    cards for the three electricians who worked on appellants’ house. The work cards
    reflected 289 total hours worked. (Tr. 19-20; Ex. E). And Griffith testified as to Exhibits F
    and G, which were invoices from YESCO and receipts from Home Depot for materials for
    the project. (Tr. 21-22; Ex. F, G). Finally, he testified that the standard markup on
    supplies is 15 percent. (Tr. 22-23).
    {¶21} Next, John testified for appellants. John stated that he and Jenna were the
    general contractors for their new house. (Tr. 35-36). They contacted appellee to do the
    electrical work based on a referral from a contractor they had hired to frame the house.
    (Tr. 36). John stated that they met with Griffith and Griffith told them the project would
    cost $10,000 “give or take.” (Tr. 38). John testified that was the only time the parties
    discussed the price before the final bill. (Tr. 38). He stated that the original plans were
    never modified. (Tr. 38). He stated that he gave every contractor a set of plans that
    showed the house was to be 2,912 square feet. (Tr. 46-47). John testified that Griffith
    never gave him a specific price per square foot and never told him there was a 15 percent
    markup on supplies. (Tr. 39).
    {¶22} John testified that when he received the first bill for $7,452, he paid it. (Tr.
    39). He believed the first bill was for the “roughing” and he knew that there would still be
    another bill when the project was completed. (Tr. 40). When he received the second bill
    for $9,633.09, however, he was surprised by the amount. (Tr. 40). John testified that he
    contacted Griffith, who told him they would work something out. (Tr. 40). Several months
    later, John stated that he spoke with appellee’s owner who told him to pay what he thought
    was fair. (Tr. 41). John stated that after they paid $5,500 toward the second bill, he
    thought the matter was settled. (Tr. 41).
    Case No. 19 CO 0041
    –6–
    {¶23}    Finally, John testified that he was not taking issue with the quality of the
    work or the number of hours worked. (Tr. 47).
    {¶24}    Jenna also testified. She stated the only time Griffith ever mentioned that
    the project would cost more than $10,000 was when they were walking through the house
    and she informed him of where she wanted lights located and he told her it would be “a
    little more than” $10,000. (Tr. 50).
    {¶25} Unjust enrichment exists when the plaintiff demonstrates: (1) a benefit to
    the defendant conferred by the plaintiff; (2) knowledge by the defendant of the benefit;
    and (3) retention of the benefit by the defendant under circumstances where it would be
    unjust to do so without payment. Hambleton v. R.G. Barry Corp., 
    12 Ohio St. 3d 179
    , 183,
    
    465 N.E.2d 1298
    (1984).
    {¶26} In this case, appellants concede that elements one and two were met.
    They agree that appellee conferred a benefit on them and they knew of the benefit.
    Furthermore, appellants do not take issue with the quality of appellee’s work or the
    number of hours it took to complete the project.
    {¶27} The only issue then is whether there is competent, credible evidence
    supporting the trial court’s finding that retention of the benefit by appellants without
    payment of the remainder of the bill would be unjust.
    {¶28} Appellants’ argument here is that the trial court erred in believing Griffith’s
    testimony in full and not believing all of John’s testimony. But the trier of fact is free to
    believe all, part, or none of each witnesses' testimony. State v. Matthews, 7th Dist.
    Mahoning No. 08-MA-49, 2009-Ohio-3254, ¶ 55, citing State v. Nichols, 
    85 Ohio App. 3d 65
    , 76, 
    619 N.E.2d 80
    (4th Dist.1993). Thus, it was up to the trial court, as the finder of
    fact, to determine whether Griffith’s and John’s testimonies were accurate as to each of
    the matters they testified to.
    {¶29} Griffith testified that the $10,000 price he quoted appellants was based on
    appellants’ representation that their new house was to be 2,000 square feet. He further
    testified that once he learned that the house was actually almost 3,000 square feet, he
    told appellants the price was going to increase.        Appellee then billed appellants in
    accordance with industry standards for the amount of hours worked.
    Case No. 19 CO 0041
    –7–
    {¶30} Because Griffith’s testimony supports the trial court’s judgment, the court’s
    judgment is not against the manifest weight of the evidence. We are to give every
    reasonable presumption in favor of the trial court’s judgment and finding of facts. 
    Gerijo, 70 Ohio St. 3d at 226
    (citing Seasons Coal 
    Co., supra
    ). In conducting a manifest weight
    of the evidence review in a civil case, “[a] finding of an error of law is a legitimate ground
    for reversal, but a difference of opinion on credibility of witnesses and evidence is not.”
    Seasons 
    Coal, 10 Ohio St. 3d at 81
    . Thus, even if this court may have reached a different
    conclusion, we could not reverse on that basis.
    {¶31} Accordingly, appellants’ sole assignment of error is without merit and is
    overruled.
    {¶32} For the reasons stated above, the trial court’s judgment is hereby affirmed.
    Waite, P. J., concurs.
    Robb, J., concurs.
    Case No. 19 CO 0041
    [Cite as Kirkner Elec., Inc. v. Rydarowicz, 2020-Ohio-3362.]
    For the reasons stated in the Opinion rendered herein, the sole assignment of
    error is overruled and it is the final judgment and order of this Court that the judgment
    of the Columbiana County Municipal Court of Columbiana County, Ohio, is affirmed.
    Costs to be taxed against the Appellants.
    A certified copy of this opinion and judgment entry shall constitute the mandate
    in this case pursuant to Rule 27 of the Rules of Appellate Procedure. It is ordered that
    a certified copy be sent by the clerk to the trial court to carry this judgment into
    execution.
    NOTICE TO COUNSEL
    This document constitutes a final judgment entry.
    