Eikenberry v. Municipality of New Lebanon , 2021 Ohio 453 ( 2021 )


Menu:
  • [Cite as Eikenberry v. Municipality of New Lebanon, 
    2021-Ohio-453
    .]
    IN THE COURT OF APPEALS OF OHIO
    SECOND APPELLATE DISTRICT
    MONTGOMERY COUNTY
    KEVIN EIKENBERRY                                    :
    :
    Plaintiff-Appellant                         :    Appellate Case No. 28856
    :
    v.                                                  :    Trial Court Case No. 2018-CV-3254
    :
    MUNICIPALITY OF NEW LEBANON,                        :    (Civil Appeal from
    et al.                                              :    Common Pleas Court)
    :
    Defendant-Appellee                          :
    ...........
    OPINION
    Rendered on the 19th day of February, 2021.
    ...........
    LOWELL T. WOODS, JR., Atty. Reg. No. 0068768 & JENNIFER D. BRUMBY, Atty. Reg.
    No. 0076440, 40 North Main Street, Suite 1700, Dayton, Ohio 45423
    Attorneys for Plaintiff-Appellant
    JAMES H. GORDON, JR., Atty. Reg. No. 0068454 & JEREMY R. KOPP, Atty. Reg. No.
    0090577, Two Miranova Place, Suite 300, Columbus, Ohio 43215
    Attorneys for Defendant-Appellee
    .............
    HALL, J.
    -2-
    {¶ 1} Kevin Eikenberry appeals the trial court’s grant of summary judgment to the
    Municipality of New Lebanon (“the city”) on his claim alleging that the city’s negligent
    failure to reinstate the lateral sewer service connection from his apartment building to the
    sewer main caused sewage to backup into the basement. The injury occurred in
    connection with the city’s efforts to rehabilitate the sewer main. The trial court concluded
    that the city, a political subdivision, was engaged in a governmental function, so it was
    immune from liability for any damages. We agree and affirm.
    I. Factual and Procedural Background
    {¶ 2} New Lebanon had a sewer system problem: rainwater was infiltrating the
    deteriorating sewer mains, which drew concern from the Environmental Protection
    Agency. Beginning in 2001, the city embarked on a project to fix the problem. Rather than
    replace the deteriorated piping with new, the city decided to rehabilitate it using cured-in-
    place pipe (CIPP), a widely used rehabilitation method that has the distinct advantage of
    requiring little excavation. Instead, a felt lining is inserted into the existing piping through
    a manhole or other access point, run along the piping, and attached to its inner walls. The
    lining is hardened and becomes, basically, a pipe within a pipe.
    {¶ 3} Phase 14 of the city’s “Sanitary Sewer Rehabilitation Project” began in 2018
    and involved the main sewer pipe running in front of an apartment building owned by
    Eikenberry. Insight Pipe Contracting, L.P. had been awarded the contract to install the
    CIPP. Insight first inspected the existing sewer pipe by running a video camera through
    it. This was done to ensure that the pipe was free from obstructions and to look for active
    lateral service connections, the means by which sewage makes its way from a building
    to the main sewer pipes. Because the lining would cover up any laterals, severing the
    -3-
    connection, a hole would later need to be cut in the hardened lining to reinstate service.
    During the prelining inspection of the piping in front of Eikenberry’s apartment building,
    Brian Minehart, who was overseeing the CIPP installation for Insight, saw the building’s
    service lateral. While the project specifications stated that the lateral was active, Minehart
    noticed a lot of debris in front of it, which suggested to him that it was inactive. Minehart
    contacted Scott Brock, the city’s service department superintendent, and explained the
    situation to him. After further investigation and discussion, Minehart and Brock concluded
    that the lateral was inactive, so no hole in the CIPP was cut for Eikenberry’s lateral and
    service was not reinstated.
    {¶ 4} But the lateral was active, and because it became blocked by the CIPP, raw
    sewage backed up into the apartment building. Neither the city’s insurer nor Insight’s
    insurer would cover the loss, each blaming the other. The city maintained that Insight was
    responsible for the damage, and Insight claimed that they city was responsible, and they
    refused to compensate Eikenberry for the damage. So Eikenberry sued them both for
    negligence and included claims for trespass and nuisance.1 The city moved for summary
    judgment on Eikenberry’s claims on immunity grounds. Eikenberry filed a cross-motion
    for partial summary judgment on the issue of the city’s liability. The trial court ultimately
    denied Eikenberry’s motion and granted the city summary judgment, concluding that the
    city was entitled to sovereign immunity.
    {¶ 5} Eikenberry appeals.
    1 The city filed cross-claims against Insight for breach of contract, contractual indemnity,
    common-law indemnity, contribution, and for declaratory judgment. Insight filed cross-
    claims against the city for indemnification or, alternatively, contribution, and for breach of
    contract.
    -4-
    II. Analysis
    {¶ 6} In his sole assignment of error, Eikenberry challenges the grant of sovereign
    immunity. We review issues of sovereign immunity de novo. See Hubbell v. City of Xenia,
    
    115 Ohio St.3d 77
    , 
    2007-Ohio-4839
    , 
    873 N.E.2d 878
    , ¶ 21.
    The Ohio Political Subdivision Tort Liability Act
    {¶ 7} The Ohio Political Subdivision Tort Liability Act, R.C. 2744.01 et seq., applies
    to Eikenberry’s claim. The parties agree that the city is a political subdivision, see R.C.
    2744.01(F), entitled to general immunity against damages claims for injury or loss to
    persons or property “allegedly caused by any act or omission of the political subdivision
    or an employee of the political subdivision in connection with a governmental or
    proprietary function.” R.C. 2744.02(A)(1). But the Act carves out an exception for those
    damages “caused by the negligent performance of acts by [the city’s] employees with
    respect to proprietary functions of the [city].” (Emphasis added.) R.C. 2744.02(B)(2).
    Accordingly, a city is immune from negligence claims that involve governmental functions
    but is not immune from negligence claims that involve proprietary functions.
    {¶ 8} The relevant function in this case involves a sewer system. A function that
    involves a sewer system could be either governmental or proprietary. It is a governmental
    function if it involves “[t]he provision or nonprovision, planning or design, construction, or
    reconstruction of a public improvement, including, but not limited to, a sewer system.”
    R.C. 2744.01(C)(2)(l). But the function is proprietary if it involves “[t]he maintenance,
    destruction, operation, and upkeep of a sewer system.” R.C. 2744.01(G)(2)(d).
    {¶ 9} Most of the leading immunity cases that relate to a sewer system involve
    damages caused because a political subdivision failed to act to remediate a problem that
    -5-
    arose out of a defective design or because a political subdivision failed to redesign or
    reconstruct the sewer system. See, e.g., Guenther v. Springfield Twp. Trustees, 2012-
    Ohio-203, 
    970 N.E.2d 1058
     (2d Dist.) (claiming that the township’s failure to maintain
    drainage tiles caused basement to flood); Essman v. City of Portsmouth, 4th Dist. Scioto
    No. 09CA3325, 
    2010-Ohio-4837
     (claiming that the city failed to act to accommodate an
    increase in population and a concomitant increase in the flow in the sewer system,
    resulting in a sewage backup); Coleman v. Portage Cty. Engineer, 
    133 Ohio St.3d 28
    ,
    
    2012-Ohio-3881
    , 
    975 N.E.2d 952
     (claiming that the county failed to keep a storm-sewer
    system functional). But Eikenberry’s claim was different. He alleged that the city’s positive
    action in making improvements to the sewer system caused the damage. See, e.g.,
    McCormick v. Flaugher, 5th Dist. Richland No. 18CA53, 
    2019-Ohio-1211
     (claiming that
    damages were the result of the city’s actions taken to resolve defects that the city had
    identified). We must review the evidence to determine the nature of the function at issue—
    governmental or proprietary—and whether that evidence was sufficient to support the
    grant of summary judgment.
    The legal framework
    {¶ 10} “Determining whether an allegation of negligence relates to the
    maintenance, operation, or upkeep of a sewer system or, instead, the design,
    construction, or reconstruction of a sewer system is not always a simple inquiry.” Essman
    at ¶ 32. Helpful to the determination here is the Ohio Supreme Court’s decision in
    Coleman v. Portage County Engineer, in which the Court distinguished between the
    “failure to upgrade” and “maintenance or upkeep.” The Court emphasized that upgrades
    and related improvements implicate governmental functions. Coleman at ¶ 24. And, citing
    -6-
    our decision in Guenther v. Springfield Township Trustees, the Court said that a claim
    sounds in maintenance when “remedying the sewer problem would involve little discretion
    but, instead, would be a matter of routine maintenance, inspection, repair, removal of
    obstructions, or general repair of deterioration.” Id. at ¶ 30.
    {¶ 11} Based on Coleman, then, the question for us is whether Eikenberry was
    injured in connection with the city’s redesign or reconstruction of the sewer system or in
    connection with “routine maintenance” being performed by the city.
    The evidence
    {¶ 12} Scott Brock, the city’s service department superintendent, testified in his
    deposition that the city was experiencing an infiltration problem with the sewer system
    caused by deteriorating piping. (Apparently, rainwater in the sewer lines created more
    costs in processing sewage.) Brian Minehart, who oversaw the CIPP rehabilitation for
    Insight, explained in his deposition that lining offers a solution to problems of infiltration,
    intrusion, and deterioration. The purpose of the lining, he said, is to upgrade, enhance,
    and improve the quality of the sewer main. Although there must be existing pipes in place,
    because the lining cannot be used alone as a substitute for a pipe, the lining actually
    enhances the quality of the existing sewer main pipes. The addition of the lining
    essentially creates a new “pipe-within-a-pipe” and ultimately upgrades the existing pipes
    by extending their lifespan. The lining changes the existing state of repair of the pipes,
    marking a substantial improvement to the pipes’ condition. The alternative to lining sewer
    pipes is removal and replacement. Minehart testified that, while removal and replacement
    may be a longer-term solution, the lining produced a similar result to replacement and
    was less burdensome in terms of cost and disruption for the city’s residents, because it
    -7-
    avoided the need to excavate streets and sidewalks.
    {¶ 13} The evidence showed that Phase 14 of the Sanitary Sewer Rehabilitation
    Project was a major capital improvements project with considerable expense. The project
    involved lining 2,822 feet of 15-foot sanitary sewer piping and the rehabilitation of 10
    manholes. New Lebanon had retained an engineer to create detailed specifications for
    the project and then solicited bids to perform the work from independent contractors. The
    city ultimately accepted Insight’s bid of $163,360. The city’s mayor and city council were
    intimately involved in both the project’s specifications and the acceptance of Insight’s bid.
    We note too that the project was funded with a state grant titled “Ohio Public Works
    Commission Project Grant Agreement State Capital Improvement Program”; according
    to the terms of the grant, the funds were to be designated for a “Capital Improvement
    Project.”
    {¶ 14} Finally, the evidence showed that the installation of the CIPP required
    special materials and specialized equipment. The lining was transported in a refrigerated
    truck from Insight’s facility in Pennsylvania to the job site in New Lebanon. The installation
    also required specialized equipment (e.g., steam hoses, shoes, banding, band clamps,
    bypass pumps, cones, domes, TV van with cutting capabilities, a steamer unit) all of which
    were supplied by Insight.
    The function at issue was governmental
    {¶ 15} The precise cause of Eikenberry’s injury was the allegedly negligent failure
    to reinstate service (by cutting a hole in the CIPP) for the lateral sewer line that connected
    his apartment building to the main sewer pipe. So the issue was not the CIPP per se.
    After all, Eikenberry would have suffered the same injury had the city instead excavated
    -8-
    the existing sewer pipe to which his lateral connected, replaced it with new pipe, and
    failed to reconnect his lateral. And if the city had instead done that, we think that there
    would be little question that the project was one of reconstruction.
    {¶ 16} Based on the nature and extent of the work involved, the specialized
    equipment necessary, and the involvement of the city’s highest governing authorities, we
    conclude the project here was much more than routine maintenance. What occurred was
    not “routine maintenance, inspection, repair, removal of obstructions, or general repair of
    deterioration.” Rather, the installation of the CIPP “updated” and “upgraded” the quality
    of New Lebanon’s sewer system. The city engaged in more than simple damage or
    deterioration repair. The rehabilitation of the sewer pipes was, in essence, an upgrade to
    the sewer system that changed the condition of the existing pipe. This does not align with
    the definition of maintenance or upkeep given by the Ohio Supreme Court in Coleman.
    The rehabilitation of the sewer pipes was far from routine but involved considerable
    discretion by the city. Moreover, the project was funded through a state grant for capital
    improvement projects, which also suggested that the work was better characterized as
    an improvement or upgrade to the sewer pipes. Based on the decisions and the reasoning
    articulated in Coleman and Guenther, we conclude that the rehabilitation of the sewer
    pipes using CIPP was more akin to reconstruction of a sewer system than routine
    maintenance and upkeep.
    The affidavit of Mark Schneider, P.E.
    {¶ 17} Finally, Eikenberry contends that the trial court erred by striking the affidavit
    of Mark Schneider, a licensed professional engineer with experience in public civil
    engineering projects. The city moved to strike the affidavit because it contained several
    -9-
    legal conclusions. The trial court granted the city’s motion without explanation.
    {¶ 18} Evidence submitted in connection with a summary-judgment motion must
    comply with Civ.R. 56(E), which pertinently provides that “[s]upporting and opposing
    affidavits shall be made on personal knowledge, [and] shall set forth such facts as would
    be admissible in evidence[.]” “Statements contained in affidavits must be based on
    personal knowledge and cannot be legal conclusions.” Brannon v. Rinzler, 
    77 Ohio App.3d 749
    , 756, 
    603 N.E.2d 1049
     (2d Dist.1991).
    {¶ 19} After making statements to establish his expertise in this matter,
    Schneider’s affidavit stated that he was asked to provide his “professional opinion
    concerning whether the Project represents the ‘construction or reconstruction of a sewer
    system,’ or, alternatively, represents the ‘maintenance, operation, and upkeep of a sewer
    system.’ ” (Schneider Aff. ¶ 9.) He gave his opinion near the end of the affidavit: “It is my
    professional opinion that the Project involves the maintenance and upkeep of a sewer
    system.” (Id. at ¶ 17.) There are a few other statements to the effect that the project
    involved maintenance, but most of the remaining statements in the affidavit stated facts
    supporting Schneider’s opinion.
    {¶ 20} The crucial statements in Schneider's affidavit -- that the work was
    maintenance – did not satisfy Civ.R. 56(E)’s personal-knowledge requirement but
    represented legal conclusions. Consequently, those conclusions could not be considered
    in the summary judgment analysis. What was presented in the affidavit might be called a
    “notarized legal argument.” The facts stated in the affidavit were not in dispute, and the
    question that remained was one of law. Whether Schneider, in his professional opinion,
    thought the work was maintenance did not create a factual question.
    -10-
    {¶ 21} Still, we agree that the trial court should not have struck the entire affidavit.
    It included several statements that were based on personal knowledge, so the court
    should have struck only the objectionable statements—the legal conclusions that the work
    was maintenance. In fact, this is what the court actually did in its analysis, judging from
    its written decision. The court cited Schneider’s affidavit and quoted factual statements
    from it, so it appears that the court considered the admissible statements and ignored the
    objectionable ones. In our de novo review, we do not see any prejudice from the court’s
    handling of the affidavit.
    III. Conclusion
    {¶ 22} “In order to prevail on a motion for summary judgment, there must be no
    genuine issue of material fact, the moving party must be entitled to judgment as a matter
    of law, and it must appear from the evidence, when viewing the evidence in favor of the
    nonmoving party, that reasonable minds can come only to a conclusion adverse to the
    nonmoving party.” A.J.R. v. Lute, Ohio Slip Opinion No. 
    2020-Ohio-5168
    , __ N.E.3d __,
    ¶ 15, citing Davis v. Loopco Industries, Inc., 
    66 Ohio St.3d 64
    , 65-66, 
    609 N.E.2d 144
    (1993).
    {¶ 23} Here, reasonable minds reviewing the evidence in this record—in a light
    most favorable to Eikenberry—could conclude only that Eikenberry’s harm was caused
    by city action that was part of a planned redesign or reconstruction of the sewer system.
    The rehabilitation of the sewer pipes using CIPP was not part of the city’s regular, routine
    maintenance or upkeep of its sewer system. Eikenberry’s harm was not caused by the
    city’s maintenance or operation of the sewer system. It did not arise from the city’s failure
    to repair damage to, inspect, remove obstructions, or remedy general deterioration of the
    -11-
    sewer system. Rather, his harm was caused in connection with the city's efforts to
    reconstruct its sewer system—a governmental function. Therefore, New Lebanon was
    immune from liability with respect to Eikenberry’s claim.
    {¶ 24} The assignment of error is overruled. The trial court properly granted
    summary judgment to New Lebanon on Eikenberry’s claims. The trial court’s judgment is
    affirmed.
    .............
    TUCKER, P.J. and DONOVAN, J., concur.
    Copies sent to:
    Lowell T. Woods, Jr.
    Jennifer D. Brumby
    James H. Gordon, Jr.
    Jeremy R. Kopp
    Brian McHenry
    Mark Craig
    Hon. Gerald Parker
    

Document Info

Docket Number: 28856

Citation Numbers: 2021 Ohio 453

Judges: Hall

Filed Date: 2/19/2021

Precedential Status: Precedential

Modified Date: 2/19/2021