ABV Corp. v. Cantor , 2023 Ohio 3363 ( 2023 )


Menu:
  • [Cite as ABV Corp. v. Cantor, 
    2023-Ohio-3363
    .]
    COURT OF APPEALS OF OHIO
    EIGHTH APPELLATE DISTRICT
    COUNTY OF CUYAHOGA
    ABV CORPORATION, DBA, ABV                            :
    CONTRACTORS CO.,
    :
    Plaintiff-Appellee,                             No. 112237
    :
    v.
    :
    NEIL CANTOR, ET AL.,
    :
    Defendants-Appellants.
    JOURNAL ENTRY AND OPINION
    JUDGMENT: AFFIRMED
    RELEASED AND JOURNALIZED: September 21, 2023
    Civil Appeal from the Cuyahoga County Court of Common Pleas
    Case No. CV-21-954180
    Appearances:
    Diemert & Associates Co., L.P.A., Joseph W. Diemert, Jr.,
    and Richard S. LaPilusa, for appellee.
    Meyers, Roman, Friedberg & Lewis; Ronald P. Friedberg;
    and Amily A. Imbrogno, for appellants.
    MICHELLE J. SHEEHAN, P.J.:
    Defendants-appellants Neil and Dolores Cantor appeal from a
    judgment of the trial court in favor of plaintiff-appellee ABV Corporation d.b.a. ABV
    Contractors Co. (“ABV”) after a jury trial. The Cantors argue that the jury’s finding
    that they breached their contract with ABV is against the manifest weight of the
    evidence. They also claim they should have been awarded damages equal to the
    amount of the balance they owed under the final invoice as well as attorney fees
    based on the jury’s finding that ABV violated the Ohio Consumer Sales Practices Act
    (“CSPA”). Having reviewed the record and applicable law, we find no merit to the
    appeal and affirm the trial court’s judgment.
    In 2019, the Cuyahoga County mandated all houses utilizing septic
    tanks to connect to the county’s sewer lines. In July 2020, ABV provided a proposal
    to the Cantors for the sewer conversion work, which included the scope, terms, costs,
    and specifications of the project and estimated the cost to be $8,500.          ABV
    performed the work over a three-day period in May 2021. On the first day of the
    project, a county inspector visited the site and determined the sewer project
    required additional work not included in the proposal. ABV alleges that the Cantors
    approved the additional work, and it is undisputed the cost of the additional work
    was not discussed by the parties. The final cost for the sewer conversion work
    totaled $20,195. While satisfied with ABV’s work, the Cantors would only pay
    $10,000, leaving a balance of $10,195.
    ABV filed the instant complaint to recover the balance of $10,195,
    raising claims of breach of contract and unjust enrichment. The Cantors filed an
    answer and a four-count counterclaim alleging breach of contract (Count 1), a
    violation of CSPA (Count 2), fraudulent misrepresentation and inducement
    (Count 3), and negligent misrepresentation and inducement (Count 4). During the
    trial, the trial court dismissed the Cantors’ counterclaim for breach of contract and
    the Cantors withdrew Counts 3 and 4.
    The matter proceeded to a jury trial. The jury found the Cantors
    breached the contract and awarded ABV $10,195. The jury, however, found ABV
    violated the CSPA, but only awarded the statutory damages of $200.
    On appeal, the Cantors raise the following assignments of error:
    I.     The trial court erred in disallowing, as recoverable actual
    damages under Appellants’ Ohio Consumer Sales Practices Act
    (“CSPA”) claim against appellee, any amount(s) found to be due
    and owing from appellants to Appellee with respect to
    Appellee’s invoice.
    II.    The trial court erred in failing to treble, pursuant to R.C.
    1345.09(B), Appellant’s actual CSPA damages encompassing
    the amount(s) found to be due and owing from Appellants to
    Appellee with respect to Appellee’s invoice.
    III.   The jury’s determination that Appellee’s violation of the CSPA
    resulted from a “bona fide error notwithstanding the
    maintenance of procedures reasonably adopted to avoid the
    error” pursuant to R.C. 1345.11(A) was against the manifest
    weight of the evidence.
    IV.    The trial court erred in failing to award Appellants their
    reasonable attorney[] fees pursuant to R.C. 1345.09(F)(2).
    V.     The jury’s determination that the appellants breached their
    contract with Appellee was against the manifest weight of the
    evidence.
    For ease of discussion, we address first the fifth assignment of error
    regarding ABV’s breach-of-contract claim against ABV.
    Breach-of-Contract Claim: Manifest Weight of the Evidence
    Under the fifth assignment of error, the Cantors argue there was no
    evidence presented to suggest the contract was modified to include the additional
    work for a final price of $20,195 and, therefore, the jury’s finding that the Cantors
    breached the contract in failing to pay that amount is against the manifest weight of
    the evidence.
    A. Standard of Review
    When reviewing a claim that a jury verdict in a civil trial is against the
    weight of the evidence, an appellate court weighs the evidence and all reasonable
    inferences, considers the credibility of witnesses and determines whether in
    resolving conflicts in the evidence, the jury clearly lost its way and created such a
    manifest miscarriage of justice that the conviction must be reversed and a new trial
    ordered. Eastley v. Volkman, 
    132 Ohio St.3d 328
    , 
    2012-Ohio-2179
    , 
    972 N.E.2d 517
    ,
    ¶ 20. In determining whether the judgment is against the manifest weight of the
    evidence, “‘“every reasonable intendment and every reasonable presumption must
    be made in favor of the judgment and the finding of facts.”’” 
    Id.,
     quoting Seasons
    Coal Co., Inc. v. Cleveland, 
    10 Ohio St.3d 77
    , 80, 
    461 N.E.2d 1273
     (1984), fn. 3,
    quoting 5 Ohio Jurisprudence 3d, Appellate Review, Section 60, at 191-192 (1978).
    Furthermore, in a civil case, the burden of proof is by a
    preponderance of the evidence, rather than beyond a reasonable doubt. Eastley at
    ¶ 19. Preponderance of the evidence means “the greater weight of the evidence, or
    evidence that leads the trier of fact to find that the existence of a contested fact is
    more probable than its nonexistence.” Croone v. Arif, 8th Dist. Cuyahoga No.
    101103, 
    2014-Ohio-5546
    , ¶ 18, citing State v. Stumpf, 
    32 Ohio St.3d 95
    , 102, 
    512 N.E.2d 598
     (1987).
    B. Trial Evidence
    ABV’s July 2020 proposal provides the scope of the sewer conversion
    work in the first sentence: ABV was to “install new 6” SDR-35 PVC pipe from
    sanitary sewer cleanout to edge of asphalt driveway.” The proposal states the quote
    was based on “connecting [the sewer line] to edge of driveway” and that the extent
    of the pipe work is “[t]o be determined on site by Cuyahoga County Inspector, [who
    is to] verify [that] existing pipes under driveway to foundation are clean and working
    properly.” Another sentence in the proposal states, “Note: Proposal price does not
    include: rock excavation, concrete and/or asphalt work, unknown underground
    obstacles, landscaping and/or seeding.” A clause regarding modification states that
    “[a]ny deviations from the above specifications shall be executed only upon written
    instructions as and become extra charge.”
    The proposal estimates the cost of the sewer connection to the edge
    of the driveway to be $8,500 and it contains a statement that the estimate “does not
    include material price increases or additional labor and materials which may be
    required should unforeseen problems arise after the work has started.”
    ABV acknowledges there was no written estimate for the additional
    work of connecting the sewer to the foundation of the house as determined by the
    county inspector, who visited the site on the first day of the project, but alleges that
    the Cantors were aware of the necessity of the additional work and authorized it.
    Cesare Frabotta and Bruno Frabotta testified on ABV’s behalf.
    a. Cesare Frabotta
    Cesare Frabotta testified that the company was founded by his
    brothers in 1974. The company’s work includes sewer connections, concrete work,
    excavating, and septic systems. He testified he has been in this line of work for 32
    years and the company has an “A plus” Better Business Bureau rating and “100
    percent Recommended” from “HomeAdvisor.”
    Cesare described the work involved in converting a septic tank to a
    sewer line as follows: after the county installs a new sewer line for a residence to
    connect to, his company would excavate and find the connection to the new sewer,
    extend a new sewer pipe from that location to the line coming out of the residence,
    either outside the foundation or by the driveway, and then “abandon” the septic tank
    by removing any connections, demolish the components, and fill the space in with
    on-site materials.
    Cesare testified that during a sewer project, underneath gas, electric,
    and water lines between the residence and the road could be discovered and
    therefore he would always insert a clause in the work proposal that the company
    would not be responsible for underground lines or obstacles. He testified this is a
    standard practice for the industry.
    The final invoice of $20,195 itemizes the work and charges as follows:
    “pump out existing septic, multiflow & lift tank” ($680); “additional sewer from
    drive edge to foundation (remove asphalt, all excavation, premium fill in drive area
    & cross storm sewer” ($7,480); “cleanout near foundation” ($650); fill tanks with
    premium stone rather than demo and damage extremely large tree” ($2,650);
    “replant large very old ornamental tree” ($485).
    The most substantial charge in the final invoice involves connecting
    the sewer pipe to the foundation of the house rather than to the edge of the driveway
    as originally proposed. Cesare testified as follows:
    I proposed to install the proper piping and bedding as per county
    specs from the connection out at the road to the edge of his horseshoe
    driveway, on the city side of the edge, because we had done other
    projects in other cities in the years past where the section underneath
    a driveway or a patio or an addition was considered a financial
    hardship for the homeowners. So in individual cases, they would
    allow those pipes to stay in place to keep the cost to the homeowners
    less. So that’s what I quoted, going up to the edge of the driveway, but
    I put a specific note in my proposal saying that when we started the
    work, it would be reevaluated by the county and whether or not
    additional work needed to be done. I didn’t put a number on it,
    because at that time I didn’t know what it was going to be or how much
    it would cost.
    Cesare testified that was why the proposal contained the provision
    that the quote was based on a connection to the edge of driveway only, which was to
    be approved by the county inspector. He testified that he and the Cantors spoke
    many times before and after the proposal was made. The possibility that the county
    may require additional work came up several times in their conversations; the
    Cantors never asked about the price for the additional work, and he never specified
    it.
    On day one of the project, the county inspector came to the site to
    inspect the condition of the clay pipe underneath the Cantors’ yard and informed
    ABV that the clay pipe must be replaced and the new sewer pipe was to be connected
    all the way to the foundation of the house rather than the edge of the driveway. The
    requirement doubled the length of the job. Cesare also explained that the Cantors’
    driveway is a horseshoe-shaped driveway, which created additional work because it
    involved extra excavated materials to be hauled off the property. Cesare testified the
    work was labor-intensive and involved a large area underneath the yard, causing a
    significant increase in the price.
    Cesare immediately informed Neil of the city’s requirement of the
    additional connection. Neil’s reaction was “do whatever you’ve got to do to get the
    job done.” Cesare took it as an authorization to proceed with the additional work.
    Cesare testified that the sewer conversion for the Cantors’ residence
    was the very first one they did on this section of the street in Pepper Pike and that
    he used the same estimating method for the Cantors’ property as similar projects in
    the past. He testified that ABV performed 12 to 15 sewer conversion projects
    between 2020 and 2021 in Pepper Pike. He was asked if he received complaints
    from any other customers but did not answer due to the objection from the Cantors’
    counsel.
    Regarding the remaining itemized charges in the final invoice, Cesare
    testified that Neil wished to use ABV’s contractor for the work of pumping out the
    septic tank and Cesare added the contractor’s bill to the invoice. Furthermore, the
    septic tank to be demolished was located near a large old oak tree, five feet in
    diameter, which surrounded the entire tank. Because the only way to access the
    septic tank and demolish it properly would be to cut the oak tree down at a high cost,
    Cesare suggested to Neil that ABV would obtain permission from the county to fill
    the tank with premium stones instead of demolishing and excavating the tank. The
    county approved of the plan. Finally, a large lilac tree was in the path of the new
    sewer pipe and it had to be excavated and replanted.
    The sewer conversion project was completed in three days. The
    Cantors were home when ABV performed the work. Neil came out of the house to
    watch the work often, interacting with Cesare and his brother Bruno and asking
    questions. Neil watched the excavation and installation of the pipe up to the
    foundation of the house and never indicated any hesitation over the work.        The
    Cantors were satisfied with the work, except for the sprinklers, which were dug up
    during the excavation.
    A week later, ABV sent the Cantors the final invoice of $20,195.
    Cesare testified that the invoice was “very fair” because the connection of the sewer
    pipe to the foundation of the house through the front yard involved significantly
    more work than the connection to the driveway and he charged on a time-and-
    materials basis. Neil wanted ABV to lower the price because he felt the price was
    unfair and unreasonable. He also claimed ABV damaged certain items which
    required repairment. The Cantors paid a total of $10,000 and refused to pay the
    remaining balance of $10,195.
    When asked why he did not put the additional work and charges in
    writing after the county inspector determined that the sewer pipe must be connected
    to the foundation of the house, Cesare testified as follows:
    Well, like I stated before, we are a small company. I was on the job all
    three days. We started in the morning and worked throughout the day
    and it just — there wasn’t any time to go back and sit at my computer
    and do a proper cost analysis and come up with a price, because
    basically it was a time-and-material basis for the extra work. That’s
    why I never — I don’t have anything in writing for the additional work,
    but I was never told to stop. I was never told [“]give me numbers
    before you proceed[”]. It was just an unspoken — I said, hey, we have
    got to do extra work; and when he told me, don’t kill me and I trust
    you, I assumed that we had authorization to proceed to complete the
    work as required.
    Cesare testified he advised the Cantors that the additional work would
    be charged on a time-and-material basis, and he did not provide them with specific
    numbers ahead of time because the Cantors never asked him to put in writing the
    cost for the additional work.
    Under cross-examination, the defense counsel showed Cesare four
    proposals he submitted to other homeowners in Pepper Pike, in which the
    homeowners were quoted the price for the connection of the sewer pipe to the
    foundation of the house. On redirect, Cesare explained that, in one of these
    proposals, he was asked by the homeowner to connect the sewer to the house; in the
    other proposals, the pipe was entirely underneath the grass, and in such cases, the
    sewer pipe is required to connect to the foundation of the house, regardless of
    whether it is a clay pipe. The Cantors’ house was different in that it had a circular
    driveway and he had been unaware that it was mandatory for clay pipes to be
    replaced because in his experience, replacement of clay pipes was not always
    mandatory. Regarding his testimony that the county inspector determined that the
    existing clay pipe must be replaced, Cesare testified that he had not been aware that
    it was mandatory to replace clay pipes in all instances and acknowledged that he did
    not make any inquiry before the bidding.
    b. Bruno Frabotta
    Bruno Frabotta, Cesare’s brother and founder and president of ABV,
    testified he started the company in 1974. He was also personally involved in the
    Cantors’ sewer conversion project, being on the site during the entire project. He
    interacted with the Cantors throughout the project, they never stopped or
    complained about the work ABV was performing, and they seemed pleased with the
    result.1
    c. Neil Cantor
    The defense presented one witness. Neil, a retired dentist who has
    lived in the subject house for 45 years, testified that when Cesare came to his house
    to discuss the sewer conversion project, Cesare told his wife that “he was going to
    have to go to the foundation of the house.” When ABV submitted its proposal, he
    understood he would pay $8,500 “plus contingencies” for the work. He did not
    recall ABV informing him that additional work would need to be performed but
    1 At the end of the testimony presented by ABV, the Cantors moved for directed verdict
    on the breach-of-contract and unjust-enrichment claims. The court denied the motion.
    added that “it might have been said informally, but it was never said formally to me.”
    When he received the final invoice, “it was like someone punching [him] in the solar
    plexus.” He told Cesare that Cesare should have known before the project began
    that the piping must be connected to the foundation of the house. Regarding the
    charge for filling the septic tank with premium stone, he knew the county approved
    of it but did not understand why premium stone was necessary. He testified that he
    decided to pay $10,000 on the final invoice, $1,500 more than the original estimate.
    Neil testified that after the project was completed, the Pepper Pike
    mayor’s secretary told him the mandate for replacing clay pipes went into effect in
    January 2020.    He also testified that when he received the proposal, he did not
    question the scope of the proposal because he did not know what the requirements
    were and he “had confidence that ABV was going to comply.”
    Neil acknowledged that he did not have a problem with the work
    performed by ABV. Asked if he could dispute the charges for the work, Neil stated
    “I can’t dispute it because I have no idea.” He also acknowledged the city of Pepper
    Pike provided $5,000 for reimbursement to residents for repairs to the yard,
    driveway, and shrubs, and he received $5,000 from the city. He admitted he
    authorized and approved of the additional work beyond the scope of the original
    proposal. He did not ask for written estimates for the additional work because it was
    not his responsibility to ask for them. He believed it was Cesare’s responsibility to
    “broach that subject.” When asked about the charge of replanting the large lilac tree,
    Neil testified he did authorize the work but Cesare gave him the impression that he
    was doing them a favor.
    C. Manifest Weight of the Evidence
    The Cantors claim the jury’s determination that they breached their
    contract with ABV in failing to pay the remaining balance of $10,195 for the sewer
    work is against the manifest weight of the evidence. While ABV argues the parties’
    contract had been modified by their conduct, the Cantors claim that they never
    assented to the scope of work or the price.
    “‘Essential elements of a contract include an offer, acceptance,
    contractual capacity, consideration (the bargained for legal benefit and/or
    detriment), a manifestation of mutual assent and legality of object and of
    consideration.’” Kostelnik v. Helper, 
    96 Ohio St.3d 1
    , 
    2002-Ohio-2985
    , 
    770 N.E.2d 58
    , ¶ 16, quoting Perlmuter Printing Co. v. Strome, Inc., 
    436 F.Supp. 409
    , 414
    (N.D.Ohio 1976). To establish a breach-of-contract claim, a party must demonstrate
    the nonbreaching party performed the contractual obligations, the other party failed
    to fulfill its contractual obligations without legal excuse, and the nonbreaching party
    suffered damages from the breach. Carbone v. Nueva Constr. Group, L.L.C., 2017-
    Ohio-382, 
    83 N.E.3d 375
    , ¶ 14 (8th Dist.).
    Furthermore, “[p]arties may implicitly modify an agreement by their
    actions.”   St. Marys v. Auglaize Cty. Bd. of Commrs., 
    115 Ohio St.3d 387
    ,
    
    2007-Ohio-5026
    , 
    875 N.E.2d 561
    , ¶ 39. A modification of the original agreement
    may be manifested by a continued, different course of performance. 
    Id.
    Moreover, while there is a no-oral-modification clause in the July
    2020 proposal, “no-oral-modification and written waiver provisions, like any other
    contractual provision, can be waived by the parties.” 3637 Green Rd. Co. v.
    Specialized Component Sales Co., 
    2016-Ohio-5324
    , 
    69 N.E.3d 1083
    , ¶ 22 (8th
    Dist.), citing e.g., Snowville Subdivision Joint Venture Phase I v. Home S & L of
    Youngstown, 8th Dist. Cuyahoga No. 96675, 
    2012-Ohio-1342
    , ¶ 15-17; Home S & L
    of Youngstown v. Snowville Subdivision Joint Venture, 8th Dist. Cuyahoga No.
    97985, 
    2012-Ohio-4594
    , ¶ 29-31; and Vivi Retail, Inc. v. E & A Northeast Ltd.
    Partnership, 8th Dist. Cuyahoga No. 90527, 
    2008-Ohio-4705
    , ¶ 30 (“waiver of a
    contract term can occur when a party conducts itself in a manner inconsistent with
    an intention to insist on that term”). See also Star Leasing Co. v. G&S Metal
    Consultants, Inc., 10th Dist. Franklin No. 08AP-713, 
    2009-Ohio-1269
    , ¶ 25 (noting
    the disfavor that courts have traditionally afforded no-oral-modification clauses in
    written contracts and the resulting principle that a no-oral-modification clause can
    be waived by oral agreement like any other term in a contract). Moreover, “the issue
    of whether a no-oral-modification clause is waived is a question of fact.” Kwikcolor
    Sand v. Fairmount Minerals Ltd., 8th Dist. Cuyahoga No. 96717, 
    2011-Ohio-6646
    ,
    ¶ 19.
    The issue in this breach-of-contract case is whether the contract was
    modified to include the additional work required by the county. Regarding contract
    modification, the trial court instructed the jury as follows:
    The terms of a contract may be changed upon the mutual agreement
    of the parties and may occur through words or conduct, expressly or
    by implication.
    You may find that the parties intended to modify their contract when
    the County determined that more work would be required to make the
    sanitary sewer conversion project comply with County requirements.
    In order to prove its claim, ABV must prove by the greater weight of
    the evidence that the parties agreed to modify their contract.
    The Cantors claim that any modification of the contract’s
    specifications had to be in writing. You may find, however, — you may
    find, however, that the Cantors waived that right by their own acts or
    or actions.
    By waiver, we mean a voluntary relinquishment of a known right.
    The Cantors do not challenge the jury instructions regarding contract
    modification and waiver, but only that the jury’s finding in favor of ABV is against
    the manifest weight of the evidence.      ABV contends that the trial testimony
    establishes that the parties’ contract was modified orally when Cesare Frabotta
    communicated to the Cantors that the county required the additional work beyond
    the scope of the original proposal and advised them of the time and materials basis
    for the additional cost.
    Having reviewed the trial transcript thoroughly, we agree that ABV
    introduced sufficient evidence to demonstrate that the parties’ conduct implicitly
    modified their original contract and that the Cantors, by their conduct, waived the
    no-oral-modification clause. Neil was present at the site during the three-day period
    ABV performed the sewer conversion work. Cesare conversed with him throughout
    the project and consulted with him regarding the necessity of additional work as the
    project progressed. Neil never challenged the additional work being performed.
    The Cantors also argue they did not agree to the increased price for
    the extended work. While the price is an essential element of a contract, when a
    contract for services does not specify the price to be paid, “‘the law invokes the
    standard of reasonableness, and the fair value of the services is recoverable.’” A N
    Bros. Corp. v. Total Quality, LLC, 
    2016-Ohio-549
    , 
    59 N.E.3d 758
    , ¶ 27 (12th Dist.),
    quoting Dixon v. Kittle, 
    109 Ohio App. 257
    , 259, 
    164 N.E.2d 806
     (4th Dist.1959)
    (where labor or materials are furnished upon request and no price is agreed upon,
    the law will imply an agreement to pay what they are reasonably worth), and Dayton
    White Trucks, Inc. v. Fed. Pacific Elec. Co., 2d Dist. Montgomery No. 4885, 
    1975 Ohio App. LEXIS 6158
    , 3 (Sept. 30, 1975) (where a contract for services does not
    specify the price to be paid therefor, there is an implied promise to pay a reasonable
    price for such services). See also Oglebay Norton Co. v. Armco, Inc., 8th Dist.
    Cuyahoga No. 54917, 
    1989 Ohio App. LEXIS 1365
    , 19 (Apr. 13, 1989) (“Generally,
    when a contract fails to mention price, the law implies that the parties intended a
    reasonable price.”).
    Here, Cesare testified he advised Neil that the cost for the additional
    work would be based on a labor-and-materials basis. Cesare also testified at great
    length regarding each additional task itemized in the final invoice. The Cantors
    claim they did not consent to the total price of the work performed. They, however,
    presented no evidence to challenge the reasonableness of the cost calculated by ABV
    on a labor-and-materials basis. Having reviewed the evidence presented at trial, we
    cannot say that the jury’s finding in favor of ABV on its breach-of-contract claim is
    against the manifest weight of the evidence warranting a reversal of the jury verdict
    and a remand for a new trial. The fifth assignment of error is without merit.
    CSPA Claims and Damages for Violations
    In their counterclaim, the Cantors alleged ABV violated the CSPA.
    The CSPA is codified in R.C. 1345.01, et seq. R.C. 1345.02(A) states that “[n]o
    supplier shall commit an unfair or deceptive act or practice in connection with a
    consumer transaction. Such an unfair or deceptive act or practice by a supplier
    violates this section whether it occurs before, during, or after the transaction.” The
    CSPA “prohibits unfair or deceptive acts or practices and unconscionable acts or
    practices by suppliers in consumer transactions.” Einhorn v. Ford Motor Co., 
    48 Ohio St.3d 27
    , 29, 
    548 N.E.2d 933
     (1990).
    “‘A violation of the CSPA does not depend on any contractual or
    quasi-contractual claims; rather, it is a separate cause of action and legal claim.’”
    Nelson v. Pieratt, 12th Dist. Clermont No. CA2011-02-011, 
    2012-Ohio-2568
    , ¶ 12,
    quoting Hudson-Wobbecke Ents., Inc. v. Burwell, 5th Dist. Richland Nos. 06-CA-
    58 and 06-CA-50, 
    2007-Ohio-1728
    , ¶ 38.
    The Cantors alleged, and the jury found, that ABV engaged in
    deceptive practices in violation of Ohio Adm.Code 109:4-3-05(D)(3). The rule
    addresses when the supplier must obtain authorization from the consumer for price
    increases regarding any additional, unforeseen, but necessary repairs when the cost
    of those repairs amounts to ten percent or more (excluding tax) of the original
    estimate. It states:
    (D) In any consumer transaction involving the performance of any
    repair or service it shall be a deceptive act or practice for a supplier to:
    ***
    (3) Fail, in those cases where an estimate has been requested by a
    consumer, and the anticipated cost of the repair or service exceeds
    fifty dollars, to obtain oral or written authorization from the consumer
    for the anticipated cost of any additional, unforeseen, but necessary
    repairs when the cost of those repairs amounts to ten per cent or more
    (excluding tax) of the original estimate[.]
    Under the CSPA, a consumer claiming unfair or deceptive acts or
    practices may rescind the transaction or recover “actual economic damages.”
    R.C. 1345.09(A).       Furthermore, the award of damages may be trebled.
    R.C. 1345.09(B) provides that in certain cases, a consumer may recover “three times
    the amount of the consumer’s actual economic damages or two hundred dollars,
    whichever is greater.”2
    2 Treble damages may be awarded where
    the violation was an act or practice to be declared deceptive or
    unconscionable by rule adopted under division (B)(2) of section 1345.05 of
    the Revised Code before the consumer transaction on which the action is
    based, or an act or practice determined by a court of this state to violate
    section 1345.02, 1345.03, or 1345.031 of the Revised Code and committed
    after the decision containing the determination has been made available for
    public inspection under division (A)(3) of section 1345.05 of the Revised
    Code[.]
    R.C. 1345.09(B).
    The trial court, based on its determination that the Cantors did not
    suffer any actual economic damages, instructed the jury that if it was to find ABV to
    have violated the ten percent rule in Adm.Code 109:4-3-05(D)(3), it should award
    the statutory damages of $200 for the violation. ABV does not challenge the jury’s
    finding that its conduct violated the rule.3 The only CSPA issue on appeal is the
    amount of damages for ABV’s violation.
    As the Supreme Court of Ohio explained, “statutory damages in the
    amount of $200 are an alternative to actual damages, and, thus, $200 is the
    minimum award for a CSPA violation under R.C. 1345.09(B). In other words, if
    actual damages are not proven or if three times the consumer’s damages is less than
    $200, then $200 will be awarded.” Whitaker v. M.T. Automotive, Inc., 
    111 Ohio St.3d 177
    , 
    2006-Ohio-5481
    , 
    855 N.E.2d 825
    , ¶ 17. Accordingly, if the Cantors cannot
    prove actual economic damages, they will be awarded the statutory award of $200
    for ABV’s violation of the CSPA.
    3 We note that the first sentence of the July 2020 proposal provides the specific scope of
    the contract as connecting the sewer to the edge of the driveway and provides an
    estimated contract price of $8,500 for the work. While the final invoice price is $20,195,
    substantially exceeding ten percent of the original estimate, there was no estimate given
    for the pipe from the edge of the driveway to the foundation of the house. The Cantors
    never requested an estimate for the additional work, and therefore, it would be impossible
    to apply Adm.Code 109:4-3-05 to determine if the cost exceeds the original estimate. See
    Sterling Constr., Inc. v. Alkire, 12th Dist. Madison No. CA2016-12-032, 
    2017-Ohio-7213
    ,
    ¶ 10 (the homeowner never requested an estimate from the contractor and therefore, it is
    impossible to apply Ohio Adm.Code 109:4-3-05(D)(3) to the case at bar; “there is
    insufficient evidence to establish that more than a 10% increase occurred when no original
    estimate was provided”). ABV, however, does not challenge the jury’s finding.
    While the Cantors argue their actual economic damages is $10,195,
    the remaining balance of the invoice, the trial court determined that the Cantors
    failed to prove that they suffered actual economic damages and instructed the jury
    that, if it found ABV to have violated the CSPA, it should award $200 for the
    violation. Under the first and second assignments of error, the Cantors argue the
    trial court erred in not allowing them to recover the remaining balance of the invoice
    as the actual economic damages and in failing to award treble damages ($30,585)
    pursuant to R.C. 1345.09(B).
    A. Whether Appellants Proved Actual Economic Damages
    Under both assignments of error, the issue is whether the Cantors
    proved they suffered actual economic damages in the amount of $10,195. If they
    failed to prove it, the statutory award of $200 would be appropriate as damages for
    ABV’s violation of the CSPA.
    The trial court’s application of a measure of damages presents a legal
    question subject to a de novo review. Younker v. Hayes, 
    2018-Ohio-835
    , 
    108 N.E.3d 258
    , ¶ 13 (9th Dist.).         See also Fleischer v. George, 9th Dist. Medina
    No. 09CA0057-M, 
    2010-Ohio-3941
    , ¶ 18 (whether treble damages under the CSPA
    are appropriate is a question of law and is reviewed de novo).
    Pursuant to R.C. 1345.09(G), “actual economic damages” for purpose
    of the CSPA means “damages for direct, incidental, or consequential pecuniary
    losses resulting from a violation of Chapter 1345 of the Revised Code * * *.”
    The Cantors contend that $10,195 was their actual economic damages
    resulting from ABV’s violation of the CSPA. The Cantors effectively claim that they
    are damaged to the extent of the amount they still owed under the invoice after
    paying $10,000 toward the sewer conversion work, without presenting evidence to
    show that the price of the work performed by ABV should be $1o,000 and therefore
    any excess amount would be considered their loss.
    Our research does not reveal any case law supporting the Cantors’
    claim that the actual economic damages for ABV’s violation of the ten percent rule
    under the circumstances of this case is the remaining balance they owed, where the
    work had been performed to their satisfaction. The Cantors cite Fleischer, supra, to
    support their claim. In that case, however, plaintiff homeowner presented evidence
    of expenditures he undertook due to the defendant contractor’s violation of the
    CSPA. The expenditures included hiring a new general contractor to complete the
    defective construction, payments to the unpaid subcontractors, and payments for
    architect reports to evaluate the condition of the construction project. As such,
    Fleischer is not applicable.     Accordingly, we agree with the trial court’s
    determination that the Cantors failed to prove that they suffered actual economic
    damages of $10,195 for purposes of R.C. 1345.09(A).
    “In order to award treble damages, there must be a finding of actual
    damages.” Williams v. Kia of Bedford, 
    2018-Ohio-283
    , 
    104 N.E.3d 924
    , ¶ 24 (8th
    Dist.). Because the Cantors failed to prove actual economic damages resulting from
    ABV’s CSPA violation, the trial court appropriately determined that the jury should
    award $200 in statutory damages should it find ABV to have violated the CSPA. The
    first and second assignments of error are without merit.
    B. Attorney Fees: Whether Appellee’s Violation of the CSPA Is a
    “Bona Fide Error”
    The third and fourth assignments concern attorney fees. After the
    trial, the Cantors moved for an award of attorney fees pursuant to
    R.C. 1345.09(F)(2) and the trial court denied it.
    Under the CSPA, the court may award a prevailing consumer a
    reasonable attorney fee if the supplier “has knowingly committed an act or practice
    that violates [the CSPA].” (Emphasis added.) R.C. 1345.09(F)(2).
    However, R.C. 1345.11(A) provides for a defense for the supplier.
    [I]f a supplier shows by a preponderance of the evidence that a
    violation resulted from a bona fide error notwithstanding the
    maintenance of procedures reasonably adopted to avoid the error,
    * * * no party shall be awarded attorney’s fees, and monetary recovery
    shall not exceed the amount of actual damages resulting from the
    violation.
    (Emphasis added.) R.C. 1345.11(A).
    Here, the jury, through its answer to the interrogatories, found in
    favor of the Cantors on the CSPA claim, finding that ABV failed to provide an
    estimate to the Cantors for the anticipated cost of additional work exceeding ten
    percent of the original estimate, in violation of R.C. 1345.02(A). The jury also found
    ABV violated the CSPA “knowingly.” However, it found the violation to be a “bona
    fide error notwithstanding the maintenance of procedures reasonably adopted to
    avoid the error.”
    The Cantors argue that the jury’s finding that ABV’s violation
    “resulted from a bona fide error notwithstanding the maintenance of procedures
    reasonably adopted to avoid the error,” which precluded attorney fees, is against the
    manifest weight of the evidence. They argue there was no evidence presented to
    indicate   that   ABV     had    any    procedures     in   place    to   avoid    the
    Adm.Code 109:4-3-05(D)(3) violation or that the violation was a result of deviations
    from the procedure. The Cantors also argue the jury’s finding that ABV knowingly
    violated the CSPA is irreconcilable with the finding that the violation was a bona fide
    error. They contend that, because the violation did not result from a bona fide error,
    they should be awarded attorney fees pursuant to R.C. 1345.09(F)(2).
    “A bona fide error is one made in good faith, despite procedures to
    avoid the error.” Anousheh v. Planet Ford, Inc., 2d Dist. Montgomery Nos. 21960
    and 21967, 
    2007-Ohio-4543
    , ¶ 26. ABV contends they showed by a preponderance
    of the evidence that the violation resulted from a bona fide error. The original
    proposal contemplates a procedure where any work in deviation from the specifics
    provided in the proposal to be performed only upon written instructions. ABV
    admitted there was no written instruction for any additional work, but it points to
    Cesare’s testimony that ABV verbally appraised Neil Cantor immediately of the
    necessity of any additional task whenever it arose before proceeding to perform the
    work. Cesare also testified that the excavation work was performed within a three-
    day period of time and he was on the site the entire time without the ability to return
    to the office to prepare a written proposal for each additional unforeseen deviation
    from the original proposal. The jury found ABV, while violating Adm.Code 109:4-3-
    05(D)(3), acted in good faith despite the procedure in place to avoid the CSPA
    violation. Applying the manifest-weight standard, we cannot say that the jury
    “clearly lost its way and created such a manifest miscarriage of justice that the
    conviction must be reversed and a new trial ordered.”
    The Cantors also argue the jury’s finding that ABV violated the CSPA
    “knowingly” is irreconcilable with its finding that the violation was a bona fide error.
    The jury found ABV knowingly proceeded to perform the additional work without a
    written estimate in violation of Ohio Adm.Code 109.4-3-05(D)(3), but it did so in
    good faith.
    For purposes of R.C. 1345.09(F), “knowingly” means that the
    “‘supplier need only intentionally do the act that violates the Consumer Sales
    Practices Act. The supplier does not have to know that his conduct violates the law
    * * *.’” Parks v. Aburahma, 
    2022-Ohio-4253
    , 
    202 N.E.3d 92
    , ¶ 15 (11th Dist.),
    quoting Einhorn, 48 Ohio St.3d at 30, 
    548 N.E.2d 933
    .
    To award attorney fees to a consumer under the CSPA, the trial court
    must find that the supplier knowingly committed an act or practice that violated the
    CSPA and that no bona fide error defense in R.C. 1345.11(A) applies. Shumaker v.
    Hamilton Chevrolet, Inc., 
    184 Ohio App.3d 326
    , 
    2009-Ohio-5263
    , 
    920 N.E.2d 1023
    ,
    ¶ 16 (4th Dist.). The “knowingly” finding and the “bona fide error” finding are
    separate and distinct. Accordingly, we find no merit to the Cantors’ argument that
    once the jury found that ABV knowingly performed additional work without
    providing an estimate, it must also find the act was not committed in good faith.4
    The third and fourth assignments of error are overruled.
    For all the foregoing reasons, we affirm the judgment of the trial
    court.
    Judgment affirmed.
    It is ordered that appellee recover of appellants costs herein taxed.
    The court finds there were reasonable grounds for this appeal.
    It is ordered that a special mandate issue out of this court directing the
    common pleas court to carry this judgment into execution.
    4 The Cantors cite Swift v. Allied Pest Control, Inc., 2d Dist. Montgomery No. 18311, 2001-
    Ohio-1462, to support their claim.             Our review, however, indicates Swift is
    distinguishable. In that case, while defendant pest control company applied the pesticide
    outside the house, the chemical leaked into the basement. The company’s employees may
    have been aware of it but did nothing to remedy the problem and told the homeowners it
    was safe to stay in the house. A few days later, an employee came to clean the areas with
    a bleach mixture but failed to follow the instructions for its proper application. The
    homeowners subsequently suffered significant health problems. The jury was asked in
    interrogatory regarding the following allegedly unfair/deceptive acts: (1) representation
    to the homeowners that the work would be performed in accordance with all regulations;
    (2) a failure to inform the homeowners of the spill immediately; and (3) misinforming
    them of the safety of the home. The jury was also asked regarding the following
    unconscionable acts: specifically informing the homeowners that (1) it was safe to remain
    in their home after the spill and that (2) the chemical had been cleaned up. The jury found
    that “an unconscionable act was knowingly committed,” and that “an unfair/deceptive act
    was committed, and that ‘the’ violation was the result of a bona fide error.” After
    reviewing several cases involving findings of “knowingly” and “bona fide error,” the court
    in Swift concluded that “under the facts of this case, the interrogatories are contradictory
    and insufficient to reach a conclusion on the issue of treble damages and attorney fees.”
    (Emphasis added.) Id. at 14. Swift is not applicable here.
    A certified copy of this entry shall constitute the mandate pursuant to Rule 27
    of the Rules of Appellate Procedure.
    __________________________________
    MICHELLE J. SHEEHAN, PRESIDING JUDGE
    LISA B. FORBES, J., and
    MICHAEL JOHN RYAN, J., CONCUR
    

Document Info

Docket Number: 112237

Citation Numbers: 2023 Ohio 3363

Judges: Sheehan

Filed Date: 9/21/2023

Precedential Status: Precedential

Modified Date: 10/5/2023