Aggressive Mechanical, Inc. v. Ohio School Facilities Comm. , 2012 Ohio 6332 ( 2012 )


Menu:
  • [Cite as Aggressive Mechanical, Inc. v. Ohio School Facilities Comm., 
    2012-Ohio-6332
    .]
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    AGGRESSIVE MECHANICAL, INC.
    Plaintiff
    v.
    OHIO SCHOOL FACILITIES COMMISSION
    Defendant
    Case No. 2010-12745
    Judge Joseph T. Clark
    Magistrate Holly True Shaver
    DECISION OF THE MAGISTRATE
    {¶ 1} Plaintiff brought this action alleging breach of contract.                   The issues of
    liability and damages were bifurcated and the case proceeded to trial on the issue of
    liability.
    {¶ 2} On May 2, 2007, plaintiff entered into a contract with defendant for the
    heating, ventilation, and air-conditioning (HVAC) work of a public improvement project
    known as Southwood Elementary School.                      The project called for multiple prime
    contractors and consisted of both the renovation of an existing building and the
    construction of a new, 20,000 square foot addition. The total HVAC contract price was
    $1,767,000. The work was to be completed within 532 days after plaintiff’s receipt of
    the notice to proceed, unless an extension of time were granted. The construction
    manager, Smoot Elford Resources (SER) was responsible for monitoring the project
    schedule for defendant.
    {¶ 3} On June 18, 2007, the notice to proceed was issued, which resulted in a
    contract end date of November 14, 2008. The work was to begin on the third floor of
    the existing building and then flow in a logical sequence down through the lower floors
    Case No. 2010-12745                        -2-                                 DECISION
    and out into the new building as work was completed by predecessor trades. However,
    from the outset, the project experienced delays due to problems with the design. An
    updated schedule was issued on May 14, 2008, and a recovery schedule was issued on
    September 11, 2008.
    {¶ 4} On October 2, 2008, SER issued Construction Bulletin 63 (CB 63), which
    extended the contract 110 working days (159 calendar days) to April 22, 2009.
    (Defendant’s Exhibit DD.)     Prior to the issuance of CB 63, SER had advised the
    contractors that a bulletin would be issued to extend the contract and invited the
    contractors to submit pricing for additional costs related to the extension. In response,
    plaintiff submitted a pricing proposal to SER in the amount of $107,976.15.
    (Defendant’s Exhibit F.) On December 18, 2008, Peggy Murphy, Project Manager for
    SER, issued a letter to plaintiff’s owner, Kevin Hall, wherein she rejected plaintiff’s
    pricing proposal.   SER explained that plaintiff’s method of calculation was not an
    acceptable means of determining costs for the extension of contract time per the
    change order pricing guidelines set forth in Article 7.6 of the contract’s General
    Conditions (GC). SER directed plaintiff to revise and resubmit its costs associated with
    CB 63. (Defendant’s Exhibit H.) On January 22, 2009, plaintiff submitted a revised
    proposal in the amount of $81,703.12. (Defendant’s Exhibit F2.)
    {¶ 5} On February 13, 2009, SER rejected plaintiff’s revised pricing.           SER
    referred plaintiff to GC Sections 7.6.6 and 7.6.7 for allowable costs. In an email from
    Murphy, she stated: “SER and the Owner agree that there are probable costs due for
    the extension of time on this project, but they must be within the structure of the contract
    and properly documented.” (Defendant’s Exhibit I.)
    {¶ 6} On another matter, on April 21, 2009, Keith Davis, SER’s on-site
    superintendent, sent Hall an email requesting something in writing that stated that
    plaintiff’s work would not be completed by the April 22, 2009 finish date. Davis advised
    Hall to list “all items for which your work is being held up by other trades. This is
    Case No. 2010-12745                        -3-                                DECISION
    important to identify all items that will not be completed by the scheduled finish date and
    a reason for the item’s status.” (Defendant’s Exhibit K.) In response, Hall sent the
    following email: “This is to notify that Aggressive [M]echanical’s work on the southwood
    elem project will not be complete by the April 22 2009 finish date due to change order
    work[.] We will be working on bulletin 82#, bulletin 79#, bulletin 75#, this work should
    be completed by 5-5-09 we will also have a little control and balance work to finish.” 
    Id.
    {¶ 7} On July 17, 2009, SER sent plaintiff a letter wherein SER adjusted plaintiff’s
    figures and issued a proposed change order for CB 63 in the amount of $13,879.20.
    (Defendant’s Exhibit L.) Plaintiff refused to sign the proposed change order. On July
    30, 2009, Joe Studer, Project Engineer for SER, sent plaintiff an email confirming
    plaintiff’s rejection of SER’s proposed change order, wherein he stated: “The change
    order previously sent will not be executed and I will delete it from our system. I will
    arrange to have a field level Article 8 meeting at SER’s office, just let me know when
    works best for you.” (Defendant’s Exhibit Z2.)
    {¶ 8} After Studer’s email, no correspondence regarding CB 63 occurred between
    the parties until November 24, 2009, when plaintiff sent SER a letter requesting an
    Article 8 hearing on its CB 63 claim in the amount of $81,703.12. In the letter, plaintiff
    notified SER of an additional claim for an extension of time from April 22 to August 3,
    2009 and related costs for that time period in the amount of $75,605.53. (Defendant’s
    Exhibit M.) The itemized costs for the CB 63 claim were based on a time period of 110
    days and included a daily cost for punch list items and close out, a 10 percent general
    overhead charge for those two items, a profit of five percent of that total amount, a
    monthly cost for attending progress meetings, a monthly charge for “gangbox and
    tools,” a daily cost for extended supervision, a $42,000 charge for demobilization and
    remobilization, and a charge for bond and insurance. The itemized costs for the second
    claim included the same categories as the CB 63 claim but were based on a time period
    of 103 calendar days. 
    Id.
    Case No. 2010-12745                       -4-                                DECISION
    {¶ 9} On December 16, 2009, SER sent plaintiff a letter addressing plaintiff’s two
    claims separately. First, with regard to the request for an equitable adjustment as a
    result of CB 63, SER advised plaintiff to follow the specific requirements set forth in GC
    Article 8. Murphy stated: “Please understand, that while the time constraints outlined [in
    Article 8 of the contract] have been grossly surpassed, the Construction Manager, the
    Architect and the Co-Ownership Team will consider your claim if properly documented
    and supported.”    (Defendant’s Exhibit N.)   Second, with regard to the claim for an
    extension of time and related costs, SER also advised plaintiff to review the
    requirements as set forth in Article 8. Murphy stated: “Without a clear and substantiated
    claim of the damages being sought, your request cannot realistically be evaluated.
    Please be aware that to date, other than a very brief email sent exclusively to our on-
    site superintendent on April 22, 2009, the Project has received no other written
    communication regarding this claim and presently, Aggressive Mechanical still has
    outstanding Contract Work which the completion of is in no way being impeded by the
    Project.” 
    Id.
    {¶ 10} On March 1, 2010, plaintiff filed two Article 8 claims with SER: one
    regarding its rejected CB 63 pricing and the other regarding the extension of time
    referred to in its November 24, 2009 letter.      In both claims, plaintiff provided the
    following language to correspond with GC Section 8.1.2.2: “The above extension of time
    is due to many changes in the contract documents, changes in work and delays in work
    caused by design issues and the very extensive time that was taken in resolving job
    issues, resulting in the very slow progress of the job. We have provided estimate work
    sheets for our claim of time extension. We have estimated our claim from our approved
    schedule of values like we have done other Columbus Public School jobs. We used this
    same format for Burroughs Elementary School, etc. which was approved by SER and
    CPS. It is our hope and intent, that this issue can be resolved at the first step in the
    dispute procedure. We are convinced that the extension of time in dispute is not our
    Case No. 2010-12745                                -5-                                        DECISION
    responsibility to burden the cost. Aggressive supplied the man power and equipment to
    perform our work by the original completion date.                   Therefore a request of contract
    adjustment is appropriate.” (Defendant’s Exhibits O and O2.)
    {¶ 11} On March 15, 2010, SER held a preliminary Article 8 meeting to review
    plaintiff’s claims. At the meeting, SER requested that plaintiff provide revised pricing to
    include budgeted costs versus actual costs on the project. (Defendant’s Exhibit Q). On
    March 17, 2010, SER sent a letter to Hall stating that the first field level Article 8 hearing
    was set for March 23, 2010.1 (Defendant’s Exhibit R.) Plaintiff responded to SER’s
    request for revised pricing and submitted its actual costs versus its budgeted costs for
    the project. (Defendant’s Exhibits T and U.) On March 30, 2010, defendant and SER
    held a field level Article 8 meeting with plaintiff to further review plaintiff’s claims based
    on the newly submitted pricing. After the March 30, 2010 meeting, SER did not ask
    plaintiff for any additional information.
    {¶ 12} On May 6, 2010, Thomas Sisterhen, Senior Project Manager with SER,
    issued a letter to plaintiff wherein he stated that in response to the field level Article 8
    hearing, SER could not recommend a settlement. SER rejected both claims on the
    basis of insufficient documentation. Sisterhen also stated that the two Article 8 claims
    had not been submitted separately as SER had requested. Sisterhen stated, in relevant
    part: “As we discussed, the documentation presented by Aggressive in support of your
    response to the extension of time directed by Bulletin 63 is tainted with an additional
    claim for costs reported to have been sustained for added manpower and inefficiencies
    experienced by the Project. The additional ‘claim’ and the response to Bulletin 63 are
    two distinct and separate items that must be supported as such. We also discussed our
    concern that the back-up documentation that has been submitted is not sufficient in
    either application.
    1
    At trial, the parties stipulated that the date of the letter was March 17, 2010, not 2009.
    Case No. 2010-12745                               -6-                                      DECISION
    {¶ 13} “This completes the job site dispute resolution procedure of General
    Conditions Article 8.2. You are encouraged to review your options as outlined in Article
    8.3 and 8.4.”2       (Defendant’s Exhibit W.)           Plaintiff did not file an appeal to the
    commission and the school district board as set forth in GC Section 8.3, but rather filed
    its complaint in this court on December 13, 2010.
    {¶ 14} Plaintiff asserts that defendant breached the contract when it failed to
    compensate plaintiff for costs incurred as a result of delays on the project that were
    caused by the architect and owner.               Plaintiff also asserts that defendant owes it
    damages for unpaid base contract work performed, along with a claim for unpaid
    retainage.    Defendant counters that plaintiff breached the contract when it failed to
    follow the mandates of GC Articles 6, 7, and 8. Defendant also argues that the court
    lacks jurisdiction over plaintiff’s claims in that it failed to exhaust its administrative
    remedies before filing suit.
    EXHAUSTION OF REMEDIES
    {¶ 15} At the close of plaintiff’s case, defendant moved the court to dismiss this
    action pursuant to Civ.R. 41(B)(2) on the ground that upon the facts and the law, plaintiff
    had shown no right to relief. Defendant argued that the court lacked subject matter
    2
    GC Section 8.3 states:
    “APPEAL TO COMMISSION AND SCHOOL DISTRICT BOARD
    “8.3 .1 The Contractor may appeal the recommendation of the Construction Manager about a
    Change Order by providing written notice to the Commission and the School District Board within 30 days
    of the date of the Construction Manager’s recommendation.
    “8.3.2 The Commission and the School District Board shall, within 30 days of receipt of the
    Contractor’s notice, schedule a meeting in an effort to resolve the dispute or render a decision on the
    dispute, unless an agreement is made between the Contractor, the School District Board, and the
    Commission to extend such time limit. The purpose of the meeting shall be to settle the issues in dispute.
    Chapter 119, ORC, shall not be applicable to any such meeting.
    “8.3.3 The Commission and the School District Board shall, within 60 days of any meeting
    scheduled pursuant to paragraph GC 8.3 .1, render a decision on the dispute, unless an agreement is
    made between the Contractor, the Commission, and the School District Board to extend such time limit.
    “8.3.4 The decision of the Commission and the School District Board shall be final and
    conclusive, subject to trial in a court of competent jurisdiction.”
    Case No. 2010-12745                               -7-                                      DECISION
    jurisdiction over plaintiff’s claims in that plaintiff had failed to exhaust its administrative
    remedies as required by R.C. 153.12(B)3 before filing suit. At trial, Hall admitted that
    after SER denied plaintiff’s Article 8 claims, plaintiff did not appeal SER’s decision to the
    Commission and the School District Board as outlined in Section 8.3 of the contract.
    Instead, plaintiff filed its complaint in this court.
    {¶ 16} As the Tenth District Court of Appeals has stated: “If * * * only an actual
    final decision from the state could be deemed a rejection for purposes of when a cause
    of action accrues, then the parties would be permitted to delay a decision indefinitely,
    preclude the exhaustion of administrative remedies, and either forestall final resolution
    of the claim through litigation or, at the least, render dubious the date the cause of
    action accrued. Such an interpretation nullifies the ostensible purpose of R.C.
    153.16(B): to ensure a remedy against the state for claimants such as plaintiff by
    defining when administrative remedies are exhausted, the cause of action accrues, and
    a cause of action may be filed in the Court of Claims. Under the statutory provisions at
    issue, the state is aware it must resolve disputes within 120 days or face legal action, so
    its failure to determine a claim before that 120-day period lapses, in effect, rejects the
    claim, withholds money allegedly owed to the plaintiff, and permits the plaintiff to
    institute an action against the state.” Painting Co. v. Ohio State Univ., 10th Dist. No.
    09AP-78, 
    2009-Ohio-5710
    , 
    2009 Ohio App. LEXIS 4809
    , ¶13.
    {¶ 17} In this case, plaintiff submitted notice of an Article 8 claim to SER on
    November 24, 2009, plaintiff filed its written Article 8 claims on March 1, 2010, SER
    rejected plaintiff’s claims on May 6, 2010, and plaintiff filed its complaint in this court on
    December 13, 2010. The 120-day period starts when a notice of claim is filed. See
    R.E. Schweitzer Construction Co. v. Univ. of Cincinnati, 10th Dist. No. 10AP-954, 2011-
    3
    R.C. 153.12(B) states, in relevant part: “If a dispute arises between the state and a contractor
    concerning the terms of a public improvement contract let by the state or concerning a breach of the
    contract, and after administrative remedies provided for in such contract and any alternative dispute
    resolution procedures provided in accordance with guidelines established by the director of administrative
    Case No. 2010-12745                               -8-                                      DECISION
    Ohio-3703, 
    2011 Ohio App. LEXIS 3122
    , ¶ 25.                       By operation of law, plaintiff’s
    administrative remedies were deemed exhausted on March 24, 2010, 120 days after it
    submitted its notice of Article 8 claims, despite the fact that plaintiff did not pursue the
    appeal process set forth in GC Section 8.3. “R.C. 153.12(B) and 153.16(B)4, construed
    together, provide that any claim submitted under a public works contract with the state
    necessarily will accrue, at the latest, by the end of the 120-day statutory period when,
    by operation of law, all administrative remedies are deemed exhausted under R.C.
    153.16(B), the claim is deemed rejected, and money the state allegedly owes is
    deemed withheld.” Painting Co., supra, ¶ 14. Accordingly, defendant’s argument that
    plaintiff failed to exhaust its administrative remedies by failing to appeal SER’s decision
    does not divest the court of jurisdiction over plaintiff’s claims. Defendant’s motion to
    dismiss is DENIED.
    LAW
    {¶ 18} The purpose of contract construction is to give effect to the intention of the
    parties, and such intent “is presumed to reside in the language they chose to employ in
    the agreement.” Stoll v. United Magazine Co., 10th Dist. No. 03AP-752, 2004-Ohio-
    2523, 
    2004 Ohio App. LEXIS 2129
    , ¶ 7. In construing a written agreement, common
    words appearing in the written instrument are to be given their plain and ordinary
    meaning “unless manifest absurdity results, or unless some other meaning is clearly
    evidenced from the four corners of the documents.” ld. at ¶ 8, citing Alexander v.
    Buckeye Pipe Line Co., 
    53 Ohio St.2d 241
     (1978), paragraph two of the syllabus.
    services are exhausted, the contractor may bring an action to the court of claims in accordance with
    Chapter 2743. of the Revised Code.”
    4
    R.C. 153.16(B) states: “Notwithstanding any contract provision to the contrary, any claim
    submitted under a public works contract that the state or any institution supported in whole or in part by
    the state enters into for any project subject to sections 153.01 to 153.11 of the Revised Code shall be
    resolved within one hundred twenty days. After the end of this one hundred twenty-day period, the
    contractor shall be deemed to have exhausted all administrative remedies for purposes of division (B) of
    section 153.12 of the Revised Code.”
    Case No. 2010-12745                         -9-                                DECISION
    Additionally, a court is not required to go beyond the plain language of an agreement to
    determine the parties’ rights and obligations if a contract is clear and unambiguous.
    Custom Design Technologies, Inc. v. Galt Alloys, Inc., 5th Dist. No. 2001CA00153,
    
    2002-Ohio-100
    , 
    2002 Ohio App. LEXIS 43
    . “If a contract is clear and unambiguous,
    then its interpretation is a matter of law and there is no issue of fact to be determined.”
    Inland Refuse Transfer Co. v. Browning-Ferris Industries of Ohio, Inc., 
    15 Ohio St.3d 321
    , 322 (1984), citing Alexander, supra.
    CONSTRUCTION BULLETIN 63
    {¶ 19} SER issued CB 63 on October 2, 2008, which extended the contract time.
    GC Section 7.1.1 states: “The School District Board, without invalidating the Contract,
    may order changes in the Work consisting of additions, deletions or other revisions,
    subject to approval by the Commission. To the extent the Contract Time or Contract
    Price is affected, the Contract may be equitably adjusted by Change Order in
    accordance with this Article.”       The court finds that this contract language is
    unambiguous. Thus, any costs that were associated with CB 63 were to be addressed
    as an equitable adjustment pursuant to the change order provisions of Article 7.
    {¶ 20} Hall testified that he had used an approved schedule of values to calculate
    proposed change orders on other projects for the Columbus Public Schools in the past,
    and that the pricing had been accepted on those jobs. According to Hall, he did not
    believe that plaintiff was required to follow Article 7 to price its proposed change orders.
    Hall admitted that he priced the claim according to plaintiff’s schedule of values, but that
    Murphy requested that he price it according to the change order pricing guidelines
    contained in Article 7.
    {¶ 21} GC Section 7.6, titled “Change Order Pricing Guidelines,” sets forth the
    method for pricing change orders. GC Section 7.6.3 states: “For each change, the
    Contractor shall furnish a detailed, written Proposal itemized according to these Pricing
    Guidelines. * * * In order to expedite the review and approval process, all Proposals
    Case No. 2010-12745                              - 10 -                                   DECISION
    shall be prepared in the categories and in the order listed below.                      These pricing
    Guidelines are intended to establish the maximum amount which the School District and
    the Commission will pay for any Change Order, including without limitation all amounts
    for interference, delay, hindrance, or disruption of the Work. * * *” The court finds that
    the language in GC Section 7.6 of the contract is unambiguous. Accordingly, plaintiff
    was required to use the pricing guidelines in Article 7, not plaintiff’s own schedule of
    values, to calculate its proposal in response to CB 63.
    {¶ 22} Murphy used the Pricing Guidelines to calculate a proposed change order
    in the amount of $13,879.20, which was rejected by plaintiff. GC Section 7.4.8 states:
    “If the Contractor does not agree with the School District Board’s determination under
    paragraph GC 7.4.7, [adjustment of Contract Price associated with the adjustment of
    Contract Time] the Contractor shall request an equitable adjustment of the Contract
    under GC Article 8. * * *” The court finds that the language in GC Section 7.4.8 is
    unambiguous. Accordingly, when the parties could not reach an agreement on pricing
    for a change order as a result of CB 63, GC Section 7.4.8 required plaintiff to request an
    equitable adjustment of the contract under GC Article 8. Plaintiff clearly did so in this
    case on March 1, 2010, when it submitted a formal claim letter.
    {¶ 23} Defendant asserts that plaintiff cannot prevail on its Article 8 claim with
    regard to CB 63 because it failed to comply with the 10-day notice requirement in Article
    8.1.1.5 In response, plaintiff argues that defendant waived strict compliance with the
    notice requirements of Article 8.1.1 by its words and actions. Specifically, plaintiff points
    5
    GC Section 8.1.1 states: “Any request for equitable adjustment of Contract shall be made in
    writing to the Architect, through the Construction Manager, and filed prior to Contract Completion,
    provided the Contractor notified the Architect, through the Construction Manager, no more than ten (10)
    days after the initial occurrence of the facts which are the basis of the claim. To the fullest extent
    permitted by law, failure of the Contractor to timely provide such notice and a contemporaneous
    statement of damages shall constitute a waiver by the Contractor of any claim for additional
    compensation or for mitigation of Liquidated Damages.” GC Section 8.1.2 states: “In every such written
    claim filed in accordance with paragraph GC 8.1.1, the Contractor shall provide the following information
    to permit evaluation of the request for equitable adjustment of the Contract.”
    Case No. 2010-12745                      - 11 -                             DECISION
    to SER’s December 16, 2009 letter wherein Murphy stated: “while the time constraints
    outlined [in Article 8 of the contract] have been grossly surpassed, the Construction
    Manager, the Architect and the Co-Ownership Team will consider your claim if properly
    documented and supported.” (Defendant’s Exhibit N.) “[W]aiver of a contract provision
    may be express or implied. * * * ‘[W]aiver by estoppel’ exists when the acts and conduct
    of a party are inconsistent with an intent to claim a right, and have been such as to
    mislead the other party to his prejudice and thereby estop the party having the right
    from insisting upon it. * * * Waiver by estoppel allows a party’s inconsistent conduct,
    rather than a party’s intent, to establish a waiver of rights. * * * Whether a party’s
    inconsistent conduct constitutes waiver involves a factual determination, * * * and such
    a factual determination is properly made by the trier of fact.” Lewis & Michael Moving
    and Storage, Inc. v. Stofcheck Ambulance Serv., Inc., 10th Dist. No. 05AP-662, 2006-
    Ohio-3810, 
    2006 Ohio App. LEXIS 3775
    , ¶ 29-30. (Internal citations omitted; emphasis
    in original.) Waiver is an affirmative defense and defendant bears the burden of proving
    such defense at trial. See Cleveland Constr., Inc. v. Kent State Univ., 10th Dist. No.
    09AP-822, 
    2010-Ohio-2906
    , 
    2010 Ohio App. LEXIS 2407
    , ¶ 48.
    {¶ 24} At trial, Murphy testified that CB 63 was issued because in the summer of
    2008 it became clear that the original contract end date could not be met. Murphy
    attributed the need for a time extension to the architect’s failure to timely answer
    requests for information (RFIs) that various contractors had submitted during the
    project. Murphy also testified that the contractors were informed in advance that a
    bulletin would be issued to extend the contract end date and that the contractors were
    encouraged to submit pricing in response to the bulletin. Murphy did not testify that
    plaintiff or any other contractor was responsible for delays on the project which led to
    the contract end date being extended.
    {¶ 25} The evidence shows that plaintiff submitted a request for an Article 8
    hearing to SER on November 24, 2009.         In the November 24, 2009 letter, plaintiff
    identified two claims: one with regard to CB 63, and another with regard to an additional
    Case No. 2010-12745                        - 12 -                               DECISION
    extension of time past April 22, 2009, and related damages.             At the time it was
    submitted, SER was aware that no agreement had been reached with regard to CB 63
    at the Article 7 stage and that the claim remained unresolved. Indeed, Studer’s July 30,
    2009 email shows that SER expected plaintiff’s claim regarding CB 63 to proceed to the
    Article 8 stage, inasmuch as Studer inquired about plaintiff’s availability for a field level
    Article 8 meeting.   In the December 26, 2009 letter, SER acknowledged that even
    though plaintiff’s Article 8 request was untimely, SER would consider plaintiff’s CB 63
    claim if it were properly documented. Based upon the evidence presented, the court
    finds that defendant waived the 10-day notice requirement set forth in Article 8 with
    regard to the CB 63 claim. SER’s conduct as shown in the July 30 and December 16,
    2009 correspondence is inconsistent with an intent to claim strict compliance with the
    10-day notice requirement in Article 8. Indeed, the parties engaged in the Article 8 field
    level process in an effort to compromise the CB 63 claim. Therefore, the court finds that
    defendant waived the 10-day notice requirement with regard to plaintiff’s Article 8 claim
    for CB 63.
    {¶ 26} During the Article 8 process, defendant requested additional information
    from plaintiff in an effort to compromise the claim.        Hall testified credibly that he
    attempted to comply with Article 8 during the meetings about plaintiff’s claims, but he
    felt that SER was never satisfied with any of the information that plaintiff submitted to
    substantiate its claims. Murphy also testified credibly that she and Hall went back and
    forth in an effort to come to a resolution, but that they were not “on the same page”
    regarding plaintiff’s claim.    It is clear to the court that while plaintiff requested
    compensation for items that were not included in Article 7’s change order pricing
    guidelines, such as punch lists and closeout, many of the items that plaintiff requested
    were recoverable costs, such as overhead and profit. Murphy consistently testified that
    SER was trying to decipher plaintiff’s claims, had requested that they be in a certain
    format, and that although plaintiff did provide additional information, the form of the
    Case No. 2010-12745                       - 13 -                              DECISION
    information did not comply with her request. The evidence shows that the parties had
    substantially different ways of analyzing the information and significant disputes on what
    was a proper measure of damages with regard to CB 63.
    {¶ 27} Based upon the evidence presented, the court finds that plaintiff has
    proven, by a preponderance of the evidence, that CB 63 was issued as a result of
    delays caused by the owner. The court further finds that plaintiff has proven both that
    defendant waived the 10-day notice requirement in GC Section 8.1.1, and that plaintiff
    complied with Sections 8.1.1 and 8.1.2 by filing its written claim on March 1, 2010.
    Moreover, the court finds that defendant’s failure to provide a written recommendation
    about a change order for plaintiff’s Article 8 claim with regard to CB 63 was a breach of
    GC Section 8.2.3 and that defendant’s failure to recommend any compensation for that
    claim violates the prohibition of the waiver of liability for delay as set forth in R.C.
    4113.62, inasmuch as defendant denied plaintiff compensation for delay on the project
    that was caused by the owner. Accordingly, plaintiff is entitled to compensation for
    damages it incurred as a result of CB 63. The court finds that defendant’s refusal to
    compensate plaintiff for CB 63 on the basis that plaintiff failed to comply with the
    requirements of Article 8 is without merit. Indeed, “an owner cannot cause a delay, and
    then avoid the natural consequences for causing the delay by using boilerplate contract
    language.”   Cleveland Constr., Inc. v. Ohio Pub. Emples. Ret. Sys., 10th Dist. No.
    07AP-574, 
    2008-Ohio-1630
    , 
    2008 Ohio App. LEXIS 1403
    , ¶ 19. The court further finds
    that defendant acknowledged that plaintiff was owed at least $13,879.20 with regard to
    CB 63 when it was engaged in the Article 7 process. Accordingly, defendant’s failure to
    compensate plaintiff for costs it incurred as a result of CB 63 was a breach of contract.
    {¶ 28} Inasmuch as the court has found that the contract language in Article 7 is
    unambiguous, plaintiff shall be limited by the change order pricing guidelines in GC
    Section 7.6 when presenting its claim for damages related to CB 63.
    Case No. 2010-12745                          - 14 -                                DECISION
    EXTENSION OF TIME AND RELATED DAMAGES
    {¶ 29} The second claim for which plaintiff requested an Article 8 hearing in its
    November 24, 2009 letter was an extension of time from April 22, 2009 to August 3,
    2009, along with a claim for damages in the amount of $75,605.53.                 (Defendant’s
    Exhibit M.) For the following reasons, the court finds that plaintiff failed to prove by a
    preponderance of the evidence that defendant waived the contractual requirements
    found in Articles 6, 7, or 8, and, therefore, plaintiff cannot prevail on this claim.
    {¶ 30} The court notes that on April 22, 2009, plaintiff sent SER the following
    email: “This is to notify that Aggressive [M]echanical’s work on the southwood elem
    project will not be complete by the April 22 2009 finish date due to change order work[.]
    We will be working on bulletin 82#, bulletin 79#, bulletin 75#, this work should be
    completed by 5-5-09 we will also have a little control and balance work to finish.”
    (Defendant’s Exhibit K.)
    {¶ 31} GC Section 7.4.5.2 states: “By signing a Change Order, the Contractor
    irrevocably certifies that the scope of the change in the Work, the associated adjustment
    Contract Time (if any), and the associated adjustment of the Contract Price (if any) are
    completely satisfied, and waives all rights to seek a further adjustment of the Contract
    Time, the Contract Price, or both, at a later date with respect to the associated change
    in the Work.” At trial, Hall admitted that change orders were issued in connection with
    Bulletins 82, 79, and 75, and that plaintiff was paid in accordance with such change
    orders even though plaintiff’s work was not complete by April 22, 2009. The court finds
    that the language in GC Section 7.4.5.2 is unambiguous.                Inasmuch as plaintiff
    accepted payment for the change orders issued with regard to bulletins 82, 79, and 75,
    plaintiff has waived any additional compensation with regard to those claims.
    {¶ 32} Furthermore, to the extent that plaintiff seeks damages related to the
    delayed completion of the work, Section 6.4.1 of the contract states: “Any request by the
    Case No. 2010-12745                               - 15 -                                     DECISION
    Contractor for an extension of time shall be made in writing to the Construction Manager
    no more than ten (10) days after the initial occurrence of any condition which, in the
    Contractor’s opinion, entitles the Contractor to an extension of time. Failure to timely
    provide such notice to the Construction Manager shall constitute a waiver by the
    Contractor of any claim for extension, damages or mitigation of Liquidated Damages, to
    the fullest extent permitted by law.” Although plaintiff notified SER on April 22, 2009
    that it was continuing to work on the project past the contract end date, Hall admitted at
    trial that the first notice of a claim with regard to a request for an extension of time from
    April 22 to August 3, 2009 was made on November 24, 2009.
    {¶ 33} Additionally, GC Section 6.4.2 outlines the requirements that must be
    contained in the request.6 Hall’s April 22, 2009 email does not contain the required
    information as set forth in Section 6.4.2.1-9 of the contract. The court finds that the
    language in Article 6 is unambiguous. Therefore, inasmuch as plaintiff failed to comply
    with the requirements of Article 6 with respect to a time extension from April 22 to
    August 3, 2009, plaintiff’s claim in this regard has been waived.
    {¶ 34} With regard to plaintiff’s Article 8 claim for damages related to such
    extension in the amount of $75,605.53, plaintiff failed to comply with the 10-day notice
    requirements of Article 8. Although plaintiff argues that SER waived strict compliance
    with Article 8, the court finds that neither Studer’s July 30, 2009 email nor Murphy’s
    December 15, 2009 letter constitutes conduct inconsistent with an intent to enforce the
    notice requirements of Article 8. Studer’s email related solely to the unresolved change
    order contemplated by CB 63. Murphy’s letter separated plaintiff’s two claims, and with
    regard to plaintiff’s claim for an extension of time and related damages, she advised
    plaintiff to review the requirements as set forth in Article 8 and stated: “[w]ithout a clear
    and substantiated claim of the damages being sought, your request cannot realistically
    6
    GC Sections 6.4.2.1-6.4.2.9 set forth the specific information that the request for an extension of
    time must include, such as nature of the interference, disruption, hindrance or delay; the identification of
    Case No. 2010-12745                             - 16 -                                  DECISION
    be evaluated.      Please be aware that to date, other than a very brief email sent
    exclusively to our on-site superintendent on April 22, 2009, the Project has received no
    other written communication regarding this claim and presently, Aggressive Mechanical
    still has outstanding Contract Work which the completion of is in no way being impeded
    by the Project.” 
    Id.
     SER’s conduct with regard to plaintiff’s request for an extension of
    time and related damages shows that it did not have timely notice of this claim and that
    it did not waive its right to enforce the contractual provisions regarding notice.
    {¶ 35} Inasmuch as plaintiff has failed to comply with the contractual
    requirements and has failed to prove that defendant waived such compliance, plaintiff’s
    claim for an extension of time from April 22 to August 3, 2009, and related damages
    must fail.
    {¶ 36} Lastly, at trial, plaintiff presented some evidence with regard to unpaid
    contract balance and retainage, but it is unclear to the court what amount remains
    outstanding. Therefore, the parties shall be permitted to present evidence regarding
    those claims at the damages trial.
    {¶ 37} For the foregoing reasons, the court finds that plaintiff has proven its
    claims regarding CB 63, contract balance, and retainage by a preponderance of the
    evidence and, accordingly, judgment is recommended in favor of plaintiff.
    {¶ 38} A party may file written objections to the magistrate’s decision within 14
    days of the filing of the decision, whether or not the court has adopted the decision
    during that 14-day period as permitted by Civ.R. 53(D)(4)(e)(i). If any party timely files
    objections, any other party may also file objections not later than ten days after the first
    objections are filed. A party shall not assign as error on appeal the court’s adoption of
    any factual finding or legal conclusion, whether or not specifically designated as a
    finding of fact or conclusion of law under Civ.R. 53(D)(3)(a)(ii), unless the party timely
    the reason for the delay; activities on the construction schedule that may be affected; the recommended
    action to minimize delay, etc.
    Case No. 2010-12745                        - 17 -                            DECISION
    and specifically objects to that factual finding or legal conclusion within 14 days of the
    filing of the decision, as required by Civ.R. 53(D)(3)(b).
    _____________________________________
    HOLLY TRUE SHAVER
    Magistrate
    cc:
    David A. Beals                                Douglas M. Beard
    Jon C. Walden                                 Michael F. Copley
    Assistant Attorneys General                   1015 Cole Road
    150 East Gay Street, 18th Floor               Galloway, Ohio 43119
    Columbus, Ohio 43215-3130
    002
    Filed September 18, 2012
    To S.C. Reporter January 28, 2013
    

Document Info

Docket Number: 2010-12745

Citation Numbers: 2012 Ohio 6332

Judges: Shaver

Filed Date: 9/18/2012

Precedential Status: Precedential

Modified Date: 10/30/2014