Accurate Elec. Constr., Inc. v. Ohio State Univ. ( 2016 )


Menu:
  • [Cite as Accurate Elec. Constr., Inc. v. Ohio State Univ., 2016-Ohio-8329.]
    ACCURATE ELECTRIC                                       Case No. 2014-00961
    CONSTRUCTION, INC.
    Referee Dale A. Crawford
    Plaintiff
    DECISION OF THE REFEREE
    v.
    THE OHIO STATE UNIVERSITY
    Defendant
    {¶1} Now before the Court is Defendant’s Motion for Summary Judgment
    regarding Plaintiff’s Count III (Breach of Express and Implied Warranty) and Count IV
    (Breach of Duty of Good Faith and Fair Dealing).                      On August 18, 2016, the Court
    recommended that Defendant’s Motion for Summary Judgment be granted as to Count I
    (Breach of Contract) and Count II (Equitable Adjustment). The Court then ordered the
    Parties to file briefs regarding the remaining claims. The Court has reviewed those
    briefs and for the reasons explained below recommends that Defendant’s Motion for
    Summary Judgment be granted as to all of Plaintiff’s claims.
    Summary Judgment Standard
    {¶2} Under Civ.R. 56(C), summary judgment is proper “if the pleadings,
    depositions, answer to interrogatories, written admissions, affidavits, transcripts of
    evidence, and written stipulations of fact, if any, timely filed in the action, show that
    there is no genuine issue as to any material fact and that the moving party is entitled to
    judgment as a matter of law.” Thus, in order to determine whether Defendant is entitled
    to judgment as a matter of law pursuant to Civ.R. 56(C), the Court must ascertain
    whether the evidentiary materials presented by Defendant show that there is no genuine
    issue as to any material fact involved in the case. In making this determination, it is
    necessary to analyze the landmark Ohio Supreme Court decision which addresses the
    Case No. 2014-00961                        -2-                                  DECISION
    “standards for granting summary judgment when the moving party asserts that the
    nonmoving party has no evidence to establish an essential element of the nonmoving
    party’s case.” Dresher v. Burt, 
    75 Ohio St. 3d 280
    , 285, 1996-Ohio-107, 
    662 N.E.2d 264
    (1996); see also Saxton v. Navistar, Inc., 2013-Ohio-352, 
    986 N.E.2d 611
    (10th Dist.), ¶
    7.
    {¶3} In Dresher, the Ohio Supreme Court held:
    {¶4} “[T]he moving party bears the initial responsibility of informing the trial court
    of the basis for the motion, and identifying those portions of the record before the trial
    court which demonstrate the absence of a genuine issue of fact on a material element
    of the nonmoving party’s claim. * * * [T]he moving party bears the initial burden of
    demonstrating that there are no genuine issues of material fact concerning an essential
    element of the opponent’s case. To accomplish this, the movant must be able to point
    to evidentiary materials of the type listed in Civ.R. 56(C) that a court is to consider in
    rendering summary judgment. * * * The assertion must be backed by some evidence of
    the type listed in Civ.R. 56(C) which affirmatively shows that the nonmoving party has
    no evidence to support that party’s claims.” 
    Dresher, supra, at 292-293
    .
    {¶5} In interpreting the United States Supreme Court decision in Celotex v.
    Catrett, 
    477 U.S. 317
    , 
    106 S. Ct. 2548
    (1986), the Dresher Court found no express or
    implied requirement in Civ.R. 56 that the moving party support its motion with affidavits
    or other similar materials negating the opponent’s claim. 
    Dresher, supra, at 291-292
    .
    Furthermore, the Dresher Court stated that it is not necessary that the nonmoving party
    produce evidence in a form that would be admissible at trial in order to avoid summary
    judgment. 
    Id. at 289,
    quoting Celotex. In sum, the Dresher Court held that the burden
    on the moving party may be discharged by “showing”–that is, pointing out to the Court–
    that there is an absence of evidence to support the nonmoving party’s case. 
    Id. Case No.
    2014-00961                            -3-                                 DECISION
    {¶6} “If the moving party fails to satisfy its initial burden, the motion for summary
    judgment must be denied.” 
    Id. at 293.
    If the moving party has satisfied its initial burden,
    the nonmoving party has a reciprocal burden as outlined in Civ.R. 56(E):
    {¶7} “When a motion for summary judgment is made and supported as provided
    in this rule, an adverse party may not rest upon mere allegations or denials of his
    pleadings, but the party’s response, by affidavit or as otherwise provided in this rule,
    must set forth specific facts showing that there is a genuine issue for trial. If the party
    does not so respond, summary judgment, if appropriate, shall be entered against the
    party.”
    Count III: Breach of Express and Implied Warranties
    {¶8} The Supreme Court of Ohio has held that “there can be no implied
    covenants in a contract in relation to any matter specifically covered by the written terms
    of the contract itself.” Hamilton Ins. Servs. v. Nationwide Ins. Cos., 
    86 Ohio St. 3d 270
    ,
    
    714 N.E.2d 898
    , 1999-Ohio-162, citing Kachelmacher v. Laird, 
    92 Ohio St. 324
    , 
    110 N.E. 933
    (1915).
    {¶9} In fact, the concept that no implied covenants exists between the Parties is
    memorialized in the contract in question.         Article 4.1 states, in part: “[t]he Contract
    Documents embody the entire understanding of the parties and form the basis of the
    Contract between the University and the Contractor.”
    {¶10} Plaintiff describes the alleged breach of warranties in Paragraphs 42-46 of
    its Complaint:
    a. 42. OSU breached its obligation to Accurate to provide Accurate
    with a site upon which Accurate could perform its work without
    hindrance, interference, or delay and to do those things which it
    promised to do at such time and in such manner as would not
    hinder, interfere, or delay accurate.
    Case No. 2014-00961                          -4-                                DECISION
    b. 43. OSU breached its obligation to Accurate by unreasonably
    denying Accurate’s legitimate claims for additional compensation
    necessary to meet the mandated contractual end dates.
    c. 44. OSU breached its obligation to Accurate to promote teamwork,
    cooperation, and respect amongst all of the contractors on the
    Project.
    d. 45. OSU breached its obligations to Accurate when it failed to
    schedule and coordinate the Project so as not to make the
    performance more difficult and costly than anticipated.
    {¶11} In support of its position that Defendant failed to provide a site upon which
    it could work Plaintiff relies on Valentine Concrete, Inc. v. Ohio Dept. of Administrative
    Serv., 62 Ohio Misc.2d 591 (Ohio Ct. Cl. 1991). The Court finds there is no genuine
    issue of material fact regarding whether or not Plaintiff waived its right to pursue an
    Article 8 claim related to breach of contract, the claim for a breach of good faith and fair
    dealing must be dismissed. In Valentine, this Court granted summary judgment in favor
    of the plaintiff because Valentine Concrete, Inc. proved that it was damaged by delays
    on the project and it was not the cause of said delays.
    {¶12} This case is distinguishable from Valentine in that the plaintiff in that case
    alleged breached of contract and did not bring claims for an alleged breach of
    warranties. Therefore, the Court’s finding in favor of the plaintiff was based on the
    terms of the contract and not on any implied or express warranties. The Court has
    already dismissed Plaintiff’s claims related to breach of contract.
    {¶13} Plaintiff’s claims arise from facts similar to those in Valentine, wherein the
    contractor was damaged by delay caused by Defendant. However, Plaintiff was aware
    of the claim described in paragraph 42, throughout the Project, yet failed to give timely
    notice of its claim pursuant to Article 8.
    {¶14} Plaintiff also claims that it was denied additional compensation related to
    Change Order 363, which extended milestone dates without compensating the
    contractors for any costs associated with the changed dates. Plaintiff was aware of the
    Case No. 2014-00961                            -5-                             DECISION
    potential claim when it refused to sign Change Order 363 on or about February 13,
    2013, yet Plaintiff did not assert its claim under Article 8 until several months after the
    contract was completed. Plaintiff has failed to demonstrate how its breach of warranty
    claim is any different than its breach of contract claim as it pertains to the changes in
    schedule referenced in paragraphs 43 and 45 of its Complaint.
    {¶15} Regarding paragraph 44 of the Complaint, Plaintiff has likewise failed to
    demonstrate how the alleged breach of warranty is separate and distinct from its breach
    of contract claim.    In fact, Plaintiff cites to Articles 4.4.2 and 4.4.3 of the General
    Conditions for the proposition that Defendant failed to conduct a partnering meeting and
    develop a partnering agreement.
    {¶16} Pursuant to the holding in Hamilton Ins. Servs., there can be no implied
    covenant, such as an implied duty to “promote teamwork, cooperation, and respect
    amongst all of the contractors on the Project,” where the contract specifically addresses
    the subject matter in question.
    {¶17} Article 4.4.2 explains that the purpose of the partnering agreement is to
    “build cooperative relationships between the Project’s key stakeholders, avoid or
    minimize disputes, and nurture a more collaborative ethic characterized by trust,
    cooperation and teamwork.” Therefore, this claim is not a breach of warranty; rather, it
    is based on an alleged breach of contract. Plaintiff was aware of this alleged breach
    and the lack of partnering agreement at the onset of the Project, and failed to give
    timely notice of this claim under Article 8.
    Count IV: Breach of the Duty of Good Faith and Fair Dealing
    {¶18} The covenant of good faith is part of a contract claim and it does not stand
    alone as a separate cause of action from a breach of contract claim. DVCC, Inc. v.
    Med. Coll., 10th Dist. Franklin No. 05AP-237, 2006-Ohio-945; Interstate Gas Supply,
    Inc. v. Calex Corp., 10th Dist. Franklin No. 04AP-980, 2006-Ohio-638, citing Lakota
    Local Sch. Dist. Bd. of Educ. v. Brickner, 
    108 Ohio App. 3d 637
    , 
    671 N.E.2d 578
    (6th
    Case No. 2014-00961                          -6-                                DECISION
    Dist.1996). “[T]here is an implied duty of good faith and fair dealing in every contract.”
    However, this duty “is part of a [breach of] contract claim and does not stand alone.”
    
    Lakota, 671 N.E.2d at 584
    .
    {¶19} Accordingly, as the Court already found, there is no genuine issue of
    material fact regarding whether or not Plaintiff waived its right to pursue an Article 8
    claim related to breach of contract, the claim for a breach of good faith and fair dealing
    must consequentially be dismissed.
    Conclusion
    {¶20} For the above-mentioned reasons, the Court finds that there exist no
    genuine issues of material fact regarding Counts III (Breach of Express and Implied
    Warranties) and IV (Breach of Duty of Good Faith and Fair Dealing). Accordingly, it is
    recommended that OSU’s Motion for Summary Judgment be granted as to these
    claims.
    {¶21} A party may file written objections to the magistrate’s decision within 14
    days of the filing of the decision, whether or not the court has adopted the decision
    during that 14-day period as permitted by Civ.R. 53(D)(4)(e)(i). If any party timely files
    objections, any other party may also file objections not later than ten days after the first
    objections are filed. A party shall not assign as error on appeal the court’s adoption of
    any factual finding or legal conclusion, whether or not specifically designated as a
    finding of fact or conclusion of law under Civ.R. 53(D)(3)(a)(ii), unless the party timely
    and specifically objects to that factual finding or legal conclusion within 14 days of the
    filing of the decision, as required by Civ.R. 53(D)(3)(b).
    DALE A. CRAWFORD
    Referee
    Case No. 2014-00961              -7-                                DECISION
    cc:
    Jason R. Harley                   James E. Rook
    Peter D. Welin                    William C. Becker
    250 West Street, Suite 550        Assistant Attorneys General
    Columbus, Ohio 43215              150 East Gay Street, 18th Floor
    Columbus, Ohio 43215-3130
    Filed November 18, 2016
    Sent to S.C. Reporter 12/22/16
    

Document Info

Docket Number: 2014-00961

Judges: Crawford

Filed Date: 11/18/2016

Precedential Status: Precedential

Modified Date: 12/22/2016