Meccon, Inc. v. Univ. of Akron , 2012 Ohio 6334 ( 2012 )


Menu:
  • [Cite as Meccon, Inc. v. Univ. of Akron, 
    2012-Ohio-6334
    .]
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    MECCON, INC., et al.
    Plaintiffs
    v.
    THE UNIVERSITY OF AKRON
    Defendant
    Case No. 2008-08817
    Judge Alan C. Travis
    Magistrate Lewis F. Pettigrew
    JUDGMENT ENTRY
    {¶ 1} Plaintiffs, Meccon, Inc. and Ronald Bassak (Meccon), brought this action
    against defendant, The University of Akron (Akron), alleging that Akron wrongfully
    awarded a public improvement contract in violation of the competitive bidding processes
    prescribed by the Ohio Revised Code.
    {¶ 2} The case was remanded to this court in Meccon v. Univ. of Akron, 
    126 Ohio St.3d 231
    , 
    2010-Ohio-3297
    . Upon remand, the case was tried to a magistrate of the
    court. On July 9, 2012, the magistrate issued a decision recommending judgment in
    favor of defendant.        On the same date, pursuant to Civ.R. 53(D)(4)(e)(i), the court
    adopted the magistrate’s recommendation and entered judgment for defendant.
    {¶ 3} Civ.R. 53(D)(3)(b)(i) states, in part: “A party may file written objections to a
    magistrate’s decision within fourteen days of the filing of the decision, whether or not the
    court has adopted the decision during that fourteen-day period as permitted by Civ.R.
    53(D)(4)(e)(i).     If any party timely files objections, any other party may also file
    objections not later than ten days after the first objections are filed.” On July 23, 2012,
    plaintiffs filed their objections to the decision of the magistrate adopted by the court.
    Case No. 2008-08817                        -2-                                   ENTRY
    Portions of the trial transcript were previously filed with the court on March 26, 2012.
    On August 9, 2012, with leave of court, defendant filed its response.
    {¶ 4} The procedural history of this case was set forth in the magistrate’s
    decision. In summary, on August 6, 2008, Meccon filed both a verified complaint and a
    motion for a temporary restraining order. After a hearing on Meccon’s motion, this court
    granted Akron’s motion to dismiss for lack of subject matter jurisdiction and Meccon’s
    appeal eventually reached the Supreme Court of Ohio. See 
    id.
    {¶ 5} In its decision, the Supreme Court of Ohio stated:
    {¶ 6} “We conclude that reasonable bid-preparation costs may be recovered if the
    rejected bidder promptly sought but was denied a timely injunction to suspend the
    public-improvement project pending resolution of the dispute and a court later
    determines that the bidder was wrongfully rejected by the public authority but injunctive
    relief is no longer available because the project has already been started or is
    completed under a contract awarded to another bidder.
    {¶ 7} “* * *
    {¶ 8} “Injunctive relief must be promptly sought as a precondition to those
    damages, however. The university contends that Meccon waited two full months after
    the bids were opened to seek injunctive relief.        Meccon states that it requested
    injunctive relief four business days after it learned that the university had awarded the
    plumbing, fire-protection, and HVAC contracts in violation of the state’s competitive-
    bidding laws. Whether Meccon was timely in its pursuit of injunctive relief satisfying this
    precondition for an award of its bid-preparation costs as damages is a matter that has
    Case No. 2008-08817                               -3-                                          ENTRY
    not yet been addressed by any court. Consequently, a remand to the Court of Claims to
    consider this matter is required.” Id. at ¶ 1, 20.1
    {¶ 9} The magistrate found that Meccon knew on or before June 13, 2008, both
    that Akron intended to award the HVAC contract to S.A. Comunale in violation of R.C.
    9.31 and that Meccon was the next lowest bidder for the HVAC contract. Accordingly,
    the magistrate found that Meccon’s right to seek injunctive relief arose on June 13,
    2008, at the latest.      Because Meccon did not file its claim for injunctive relief until
    August 6, 2008, the magistrate determined that Meccon did not “promptly seek”
    injunctive relief.
    {¶ 10} In its objections, Meccon asserts that the factual findings made by the
    magistrate “are absurd” and that the decision “makes a mockery of the judicial system.”
    With due respect to counsel, the court must disagree with that characterization.
    {¶ 11} Meccon’s objections appear to be based upon its belief that it had no duty
    to seek injunctive relief until Akron gave it “official notification of its decision to illegally
    award the contract to S.A. Comunale.” (Meccon’s Objections, p. 3.) Because Meccon
    filed suit four business days after it received Akron’s July 26, 2008 letter, Meccon
    reasons that it fulfilled its obligation to promptly seek injunctive relief.
    {¶ 12} In Meccon, supra, the Supreme Court of Ohio drew from the “well-
    established principle of mitigation of damages” in holding that a wrongfully rejected
    bidder must first seek injunctive relief before recovering bid preparation costs. Id. at ¶
    14. “For if injunctive relief is timely granted, then a wrongfully rejected bidder will have
    avoided the damages that would otherwise flow from the public authority’s wrongful
    conduct by preventing the improper awarding of the contract or suspending the contract
    before it has been performed to such an extent that the bid award is no longer subject to
    1
    In the court’s April 12, 2011 decision, plaintiffs’ motion for summary judgment was granted, in
    part, and the court found that defendant violated R.C. 9.31 by awarding the HVAC contract to S.A.
    Comunale.
    Case No. 2008-08817                         -4-                                     ENTRY
    timely correction.” Id. Further, the wrongfully rejected bidder must pursue injunctive
    relief in a “timely and good-faith manner” in order to be able to recover bid preparation
    costs. Id. at ¶ 15.
    {¶ 13} Injunctive relief serves an important function. “It is clear that in the context
    of competitive bidding for public contracts, injunctive relief provides a remedy that
    prevents excessive costs and corrupt practices, as well as protects the integrity of the
    bidding process, the public, and the bidders. Moreover, the injunctive process and the
    resulting delays serve as a sufficient deterrent to a municipality’s violation of
    competitive-bidding laws.” Cementech, Inc. v. City of Fairlawn, 
    109 Ohio St.3d 475
    ,
    
    2006-Ohio-2991
    , ¶ 11. However, a party seeking the extraordinary remedy of injunction
    must act promptly. “In a construction-related case, if an unsuccessful bidder seeking to
    enjoin the construction of a public-works project fails to obtain a stay of the construction
    pending judicial resolution of its claims challenging the decision, and construction
    commences, the unsuccessful bidder’s action will be dismissed as moot.” State ex rel.
    Gaylor, Inc. v. Goodenow, 
    125 Ohio St.3d 407
    , 
    2010-Ohio-1844
    , ¶ 11, citing TP
    Mechanical Contrs. v. Franklin Cty. Bd. of Commrs., 10th Dist. No. 08AP-108, 2008-
    Ohio-6824, ¶ 20.
    {¶ 14} The necessary corollary to timely injunctive relief is that the aggrieved
    party act promptly in seeking that relief. Hence, it is the obligation of a wrongfully
    rejected bidder who knows that a public authority violated state competitive-bidding laws
    in awarding a public-improvement contract to act “promptly” and seek injunctive relief.
    Meccon, supra. If the rejected bidder fails to act promptly and the successful bidder
    commences to work on the project, injunctive relief is not available. See State ex rel.
    Gaylor, 
    supra.
    {¶ 15} At trial, Ronald Bassak, president of Meccon, Inc., agreed that shortly after
    the June 3, 2008 opening of the bids, he knew S.A. Comunale could not perform the
    plumbing contract as bid. (Excerpt of testimony of Ronald Bassak, Transcript, p. 46-
    Case No. 2008-08817                       -5-                                   ENTRY
    47.) As a result, Bassak contacted David Pierson of Akron and pointed out that if S.A.
    Comunale were to withdraw the plumbing bid, the company would be ineligible to
    maintain any of their other bids, including their HVAC bid. (Bassak Transcript, p. 48.)
    This conversation and Bassak’s awareness of the problem occurred “just after” June 3,
    2008. (Bassak Transcript, p. 50.) On June 13, 2008, several days after the bids were
    opened and following his telephone call to Akron, Bassak followed up by writing a letter
    to Akron protesting the decision to award S.A. Comunale the HVAC contract. (Plaintiffs’
    Exhibit 9.) Bassak conceded that he knew that S.A. Comunale’s bid “was against the
    law.” (Bassak Transcript, p. 89-90.) Thus, from the evidence before the court, it is
    uncontested that somewhere between the opening of the bids on June 3, 2008, and
    Bassak’s protest letter of June 13, 2008, Meccon was aware that there were
    irregularities in the bids of S.A. Comunale and that an award of a contract to that bidder
    would be unlawful.
    {¶ 16} During this time, S.A. Comunale, as low bidder, began preparing to
    undertake the public improvement project. Sherman Mattocks, S.A. Comunale’s vice
    president and manager of the mechanical HVAC, testified that as of August 6, 2008,
    S.A. Comunale was 80 percent mobilized on site. Further, Mattocks explained that S.A.
    Comunale had executed contracts with contractors, its employees had expended 512
    man hours, and it had purchased materials by August 6, 2008.
    {¶ 17} Contrary to Meccon’s view, the time to “promptly” seek injunctive relief did
    not begin when Meccon received “official notification” from Akron that S.A. Comunale
    was awarded the contract. The time for prompt legal action is when the rejected bidder
    becomes aware that an unlawful bid has been declared the low and successful bid. By
    June 13, 2008, Meccon was aware that awarding the contract to S.A. Comunale would
    violate the terms of the competitive bidding law. Once Meccon was aware that the
    legality of the S.A. Comunale bid was at issue, Meccon was obligated to take legal
    action to prevent the execution of that contract. By waiting until the successful bidder
    had purchased equipment and materials, and thereby had begun the initial phase of the
    Case No. 2008-08817                        -6-                                    ENTRY
    project, Meccon failed to act promptly to enjoin the illegalities of which it now complains.
    See Gaylor, 
    supra;
     Suburban Maintenance & Constr., Inc. v. Ohio Dept. of Transp., Ct.
    of Cl. No. 2011-08709, 
    2012-Ohio-3993
    .
    {¶ 18} Meccon also objects to the magistrate’s “undetermined tangent” relating to
    protest procedures. Meccon argues that the magistrate erred in stating that “[t]here is
    no question in this case that Meccon’s bid was rejected because it was not the lowest
    bid.” (Decision of the Magistrate, p. 7.) S.A. Comunale was apparently the lowest
    bidder on the HVAC bid and Meccon was the second lowest bidder. Further, Meccon
    contends that it promptly sought injunctive relief because it received Akron’s July 26,
    2008 letter relieving Meccon of its bid guaranty on July 30, 2008, and filed its complaint
    on August 6, 2008. As previously discussed, the court agrees with the magistrate’s
    determination that Meccon did not promptly seek injunctive relief because of the
    knowledge it had, on or before June 13, 2008, of the award of the contract to S.A.
    Comunale. Accordingly, Meccon’s objection shall be overruled.
    {¶ 19} Finally, Meccon objects to the case law cited in the magistrate’s decision
    to support the assertion that a court must find when the party seeking injunctive relief
    received actual or constructive knowledge of the impending injury to determine when
    the right to such relief arose. The magistrate cited Ohio Hosp. Assn. v. Ohio Bur. of
    Workers’ Comp., 10th Dist. No. 06AP-471, 
    2007-Ohio-1499
    , and Ohio Civ. Rights
    Comm. v. Triangle Real Estate Servs., 10th Dist. No. 06AP-157, 
    2007-Ohio-1809
    .
    Inasmuch as this is a case of first impression, no case law exists as to the precise
    timing required for a rejected bidder to “promptly” seek injunctive relief.            The
    magistrate’s use of the signal “see” before the citations indicates that an inference must
    be made to support the assertion. The court finds that such examples are instructive in
    determining when the time begins to “promptly” seek injunctive relief. As stated above,
    promptly seeking injunctive relief is necessary in order to mitigate damages and such
    timing began when Meccon became aware that an award to S.A. Comunale would be
    Case No. 2008-08817                         -7-                                    ENTRY
    unlawful. Accordingly, the court finds that Meccon’s objection is without merit and it
    shall be overruled.
    {¶ 20} Upon review of the record, the transcript, the magistrate’s decision and the
    objections, the court finds that the magistrate has properly determined the factual issues
    and appropriately applied the law. Plaintiffs’ objections are OVERRULED. Therefore,
    pursuant to Civ.R. 53(D)(4)(e)(i), the court hereby “adheres to the judgment previously
    entered.”
    _____________________________________
    ALAN C. TRAVIS
    Judge
    cc:
    Andrew R. Fredelake                            Gabe J. Roehrenbeck
    Peter D. Welin                                 41 South High Street, Suite 1700
    240 North Fifth Street, Suite 300              Columbus, Ohio 43215-6101
    Columbus, Ohio 43215
    Mark R. Wilson                                 Michael W. Currie
    William C. Becker                              6235 Westerville Road, Suite 200
    Assistant Attorneys General                    Westerville, Ohio 43081
    150 East Gay Street, 18th Floor
    Columbus, Ohio 43215-3130
    007
    Filed September 21, 2012
    To S.C. Reporter January 28, 2013