Clark v. Ohio Dept. of Transp. , 2011 Ohio 6895 ( 2011 )


Menu:
  • [Cite as Clark v. Ohio Dept. of Transp., 
    2011-Ohio-6895
    .]
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    ALAN CLARK
    Plaintiff
    v.
    OHIO DEPT. OF TRANSPORTATION
    Defendant
    Case No. 2011-05467-AD
    Acting Clerk Daniel R. Borchert
    MEMORANDUM DECISION
    {¶1}     Plaintiff, Alan Clark, filed this action against defendant, Department of
    Transportation (ODOT), contending the right front tire on his vehicle was damaged as a
    proximate result of negligence on the part of ODOT in maintaining a hazardous
    condition in a construction area on State Route 2 in Lake County. Plaintiff related his
    car was damaged when the vehicle struck a large pothole in the traveled portion of the
    roadway. Plaintiff recalled the specific damage incident occurred on December 14,
    2009. Plaintiff submitted a copy of a police report which establishes two other vehicles
    also hit the pothole near the same time, at approximately 7:51 a.m. In his complaint,
    plaintiff requested damages in the amount of $374.72, the total cost of a replacement
    tire and related automotive repairs. The filing fee was paid.
    {¶2}     Defendant acknowledged that the area where plaintiff’s stated property
    damage event occurred was located within the limits of a working construction project
    under the control of ODOT contractor, Anthony Allega Cement Contractor/Great Lakes
    Construction (Allega). Defendant explained this particular construction project “dealt
    with grading, draining, paving with asphalt concrete on an asphalt concrete base in part,
    paving with reinforced concrete paving in part, noise barrier, reinforced concrete
    retaining walls, MSE walls and rehabilitating existing structures between mileposts 3.32
    to 7.75 (on State Route 2) in Lake County.” Defendant asserted Allega, by contractual
    agreement, was responsible for roadway damage, occurrences, or mishaps within the
    construction zone. Therefore, ODOT argued Allega is the proper party defendant in this
    action. Defendant implied all duties, such as the duty to inspect, the duty to warn, the
    duty to maintain, and the duty to repair defects were delegated when an independent
    contractor takes control over a particular section of roadway. All work by the contractor
    was to be performed in accordance with ODOT mandated specifications and
    requirements and subject to ODOT approval. Furthermore, defendant maintained an
    onsite personnel presence in the construction project area.
    {¶3}   For plaintiff to prevail on a claim of negligence, he must prove, by a
    preponderance of the evidence, that defendant owed him a duty, that it breached that
    duty, and that the breach proximately caused his injuries.      Armstrong v. Best Buy
    Company, Inc., 
    99 Ohio St. 3d 79
    , 
    2003-Ohio-2573
    ,¶8 citing Menifee v. Ohio Welding
    Products, Inc. (1984), 
    15 Ohio St. 3d 75
    , 77, 15 OBR 179, 
    472 N.E. 2d 707
    . Plaintiff
    has the burden of proving, by a preponderance of the evidence, that he suffered a loss
    and that this loss was proximately caused by defendant’s negligence. Barnum v. Ohio
    State University (1977), 76-0368-AD. However, “[i]t is the duty of a party on whom the
    burden of proof rests to produce evidence which furnishes a reasonable basis for
    sustaining his claim. If the evidence so produced furnishes only a basis for a choice
    among different possibilities as to any issue in the case, he fails to sustain such
    burden.” Paragraph three of the syllabus in Steven v. Indus. Comm. (1945), 
    145 Ohio St. 198
    , 
    30 O.O. 415
    , 
    61 N.E. 2d 198
    , approved and followed.
    {¶4}   Defendant has the duty to maintain its highways in a reasonably safe
    condition for the motoring public. Knickel v. Ohio Department of Transportation (1976),
    
    49 Ohio App. 2d 335
    , 3 O.O. 3d 413, 
    361 N.E. 2d 486
    . However, defendant is not an
    insurer of the safety of its highways. See Kniskern v. Township of Somerford (1996),
    
    112 Ohio App. 3d 189
    , 
    678 N.E. 2d 273
    ; Rhodus v. Ohio Dept. of Transp. (1990), 
    67 Ohio App. 3d 723
    , 
    588 N.E. 2d 864
    . The duty of ODOT to maintain the roadway in a
    safe drivable condition is not delegable to an independent contractor involved in
    roadway construction. ODOT may bear liability for the negligent acts of an independent
    contractor charged with roadway construction.         Cowell v. Ohio Department of
    Transportation, Ct. of Cl. No. 2003-09343-AD, jud, 
    2004-Ohio-151
    . Despite defendant’s
    contention that ODOT did not owe any duty in regard to the construction project,
    defendant was charged with duties to inspect the construction site and correct any
    known deficiencies in connection with particular construction work.       See Roadway
    Express, Inc. v. Ohio Dept. of Transp. (June 28, 2001), Franklin App. 00AP-1119.
    {¶5}   Alternatively, defendant argued that neither ODOT nor Allega had any
    knowledge “of potholes on SR 2” prior to plaintiff’s incident. Defendant contended that
    plaintiff failed to produce evidence establishing his property damage was attributable to
    conduct on the part of ODOT or Allega.
    {¶6}   Defendant submitted an email from Allega representative, Carmen C.
    Carbone, regarding his knowledge of roadway conditions on State Route 2 at the time
    and location of plaintiff’s incident. Carbone reported that the pothole on State Route 2
    that plaintiff’s vehicle struck must have occurred “sometime over night or early morning
    hours. As soon as we were notified of the pothole, Allega immediately began repairing
    the roadway.    Allega had no prior knowledge or indication of any hazard on the
    roadway.”
    {¶7}   In order to find liability for a damage claim occurring in a construction
    area, the court must look at the totality of the circumstances to determine whether
    ODOT acted in a manner to render the highway free from an unreasonable risk of harm
    for the traveling public. Feichtner v. Ohio Dept. of Transp. (1995), 
    114 Ohio App. 3d 346
    , 
    683 N.E. 2d 112
    .       In fact, the duty to render the highway free from an
    unreasonable risk of harm is the precise duty owed by ODOT to the traveling public
    under both normal traffic and during highway construction projects. See e.g. White v.
    Ohio Dept. of Transp. (1990), 
    56 Ohio St. 3d 39
    , 42, 
    564 N.E. 2d 462
    .
    {¶8}   To prove a breach of the duty to maintain the highways, plaintiff must
    prove, by a preponderance of the evidence, that defendant had actual or constructive
    notice of the precise condition or defect alleged to have caused the accident. McClellan
    v. ODOT (1986), 
    34 Ohio App. 3d 247
    , 
    517 N.E. 2d 1388
    . Defendant is only liable for
    roadway conditions of which it has notice but fails to reasonably correct. Bussard v.
    Dept. of Transp. (1986), 
    31 Ohio Misc. 2d 1
    , 31 OBR 64, 
    507 N.E. 2d 1179
    .
    {¶9}      Generally, to recover in a suit involving damage proximately caused by
    roadway conditions including potholes, plaintiff must prove that either: 1) defendant had
    actual or constructive notice of the pothole and failed to respond in a reasonable time or
    responded in a negligent manner, or 2) that defendant, in a general sense, maintains its
    highways negligently.     Denis v. Department of Transportation (1976), 75-0287-AD.
    There is no evidence ODOT or Allega had actual notice of the potholes or other defects
    prior to plaintiff’s incident at 7:51 a.m. on December 14, 2009. Therefore, in order to
    recover plaintiff must produce evidence to prove constructive notice of the defect or
    negligent maintenance.
    {¶10} “[C]onstructive notice is that which the law regards as sufficient to give
    notice and is regarded as a substitute for actual notice or knowledge.” In re Estate of
    Fahle (1950), 
    90 Ohio App. 195
    , 197-198, 
    47 O.O. 231
    , 
    105 N.E. 2d 429
    . “A finding of
    constructive notice is a determination the court must make on the facts of each case not
    simply by applying a pre-set-time standard for the discovery of certain road hazards.”
    Bussard at 4.
    {¶11} Generally, the trier of fact is precluded from making an inference of
    defendant’s constructive notice, unless evidence is presented in respect to the time the
    defective condition developed. Spires v. Ohio Highway Department (1988), 
    61 Ohio Misc. 2d 262
    , 
    577 N.E. 2d 458
    . To find constructive notice of a defect, evidence must
    establish that sufficient time has elapsed after the dangerous condition appears, so that
    under the circumstances defendant should have acquired knowledge of its existence.
    Guiher v. Dept. of Transportation (1978), 78-0126-AD.        Ordinarily size of a defect
    (pothole) is insufficient to show notice or duration of existence. O’Neil v. Department of
    Transportation (1988), 
    61 Ohio Misc. 2d 287
    , 
    587 N.E. 2d 891
    . “Obviously, the requisite
    length of time sufficient to constitute constructive notice varies with each specific
    situation.” Danko v. Ohio Dept. of Transp. (Feb. 4, 1993), Franklin App. 92AP-1183.
    There is no evidence ODOT or Allega had constructive notice of any defects on State
    Route 2.
    {¶12} Defendant may bear liability if it can be established if some act or
    omission on the part of ODOT or its agents was the proximate cause of plaintiff’s injury.
    This court, as the trier of fact, determines questions of proximate causation. Shinaver v.
    Szymanski (1984), 
    14 Ohio St. 3d 51
    , 14 OBR 446, 
    471 N.E. 2d 477
    . Evidence
    available tends to point out the roadway was maintained property under ODOT
    specifications.   Plaintiff failed to prove his damage was proximately caused by any
    negligent act or omission on the part of ODOT or its agents. See Wachs v. Dept. of
    Transp., Dist. 12, Ct. of Cl. No. 2005-09481-AD, 
    2006-Ohio-7162
    ; Vanderson v. Ohio
    Dept. of Transp., Ct. of Cl. No. 2005-09961-AD, 
    2006-Ohio-7163
    ; Shiffler v. Ohio Dept.
    of Transp., Ct. of Cl. No. 2007-07183-AD, 
    2008-Ohio-1600
    .
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    ALAN CLARK
    Plaintiff
    v.
    OHIO DEPT. OF TRANSPORTATION
    Defendant
    Case No. 2011-05467-AD
    Acting Clerk Daniel R. Borchert
    ENTRY OF ADMINISTRATIVE DETERMINATION
    Having considered all the evidence in the claim file and, for the reasons set forth
    in the memorandum decision filed concurrently herewith, judgment is rendered in favor
    of defendant. Court costs are assessed against plaintiff.
    ________________________________
    DANIEL R. BORCHERT
    Acting Clerk
    Entry cc:
    Alan Clark                                        Jerry Wray, Director
    5508 Wilson Drive                                 Department of Transportation
    Mentor, Ohio 44060                                1980 West Broad Street
    Columbus, Ohio 43223
    8/2
    Filed 8/9/11
    Sent to S.C. reporter 1/3/12
    

Document Info

Docket Number: 2011-05467-AD

Citation Numbers: 2011 Ohio 6895

Judges: Borchert

Filed Date: 8/9/2011

Precedential Status: Precedential

Modified Date: 10/30/2014