McCarthy v. Ohio Dept. of Transp., Dist. 8 , 2010 Ohio 4789 ( 2010 )


Menu:
  • [Cite as McCarthy v. Ohio Dept. of Transp., Dist. 8, 
    2010-Ohio-4789
    .]
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    MICHAEL J. MCCARTHY
    Plaintiff
    v.
    OHIO DEPARTMENT OF TRANSPORTATION, DISTRICT 8
    Defendant
    Case No. 2010-02090-AD
    Deputy Clerk Daniel R. Borchert
    MEMORANDUM DECISION
    {¶ 1} On January 15, 2010, at approximately 5:30 a.m., plaintiff, Michael J.
    McCarthy, was traveling north on Interstate 75, “near Middletown, Oh” in a roadway
    construction area, when his 2004 Honda Odyssey minivan struck a pothole causing tire
    and wheel damage to the vehicle.                  Plaintiff contended his property damage was
    proximately caused by negligence on the part of defendant, Department of
    Transportation (ODOT), in maintaining a hazardous roadway condition in a working
    construction area on Interstate 75 in Warren County. Plaintiff seeks damage recovery
    in the amount of $574.78, the cost of replacement parts and related repair expenses.
    The filing fee was paid.
    {¶ 2} Defendant acknowledged the roadway area where plaintiff’s incident
    occurred was located within the limits of a working construction project under the control
    of ODOT contractor John R. Jurgensen Company (Jurgensen). Defendant explained
    this particular project “dealt with grading, draining, paving with asphalt concrete on I-75,
    interchange reconstruction of SR 122 and bridge replacements at several locations in
    Warren County.” According to defendant, the construction project limits “corresponds to
    state mileposts 32.10 to 40.50” on Interstate 75 and plaintiff’s incident occurred “around
    milepost 32.30,” a location within the construction area limits. Defendant asserted that
    this particular construction project was under the control of Jurgensen and consequently
    ODOT had no responsibility for any damage or mishap on the roadway within the
    construction project limits.     Defendant argued that Jurgensen, by contractual
    agreement, was responsible for maintaining the roadway within the construction zone.
    Therefore, ODOT contended that Jurgensen is the proper party defendant in this action.
    Defendant implied that all duties such as the duty to inspect, the duty to warn, the duty
    to maintain, and the duty to repair defects were delegated when an independent
    contractor takes control over a particular section of roadway. Furthermore, defendant
    contended that plaintiff failed to introduce sufficient evidence to prove his damage was
    proximately caused by roadway conditions created by ODOT or its contractors. All
    construction work was to be performed in accordance with ODOT requirements and
    specifications and subject to ODOT approval. Also evidence has been submitted to
    establish that ODOT personnel were present on site conducting inspection activities.
    {¶ 3} For plaintiff to prevail on a claim of negligence, he must prove, by a
    preponderance of the evidence, that defendant owed him a duty, that it breached that
    duty, and that the breach proximately caused his injuries.       Armstrong v. Best Buy
    Company, Inc., 
    99 Ohio St. 3d 79
    , 
    2003-Ohio-2573
    ,¶8 citing Menifee v. Ohio Welding
    Products, Inc. (1984), 
    15 Ohio St. 3d 75
    , 77, 15 OBR 179, 
    472 N.E. 2d 707
    . Plaintiff
    has the burden of proving, by a preponderance of the evidence, that he suffered a loss
    and that this loss was proximately caused by defendant’s negligence. Barnum v. Ohio
    State University (1977), 76-0368-AD. However, “[i]t is the duty of a party on whom the
    burden of proof rests to produce evidence which furnishes a reasonable basis for
    sustaining his claim. If the evidence so produced furnishes only a basis for a choice
    among different possibilities as to any issue in the case, he fails to sustain such
    burden.” Paragraph three of the syllabus in Steven v. Indus. Comm. (1945), 
    145 Ohio St. 198
    , 
    30 O.O. 415
    , 
    61 N.E. 2d 198
    , approved and followed. This court, as trier of
    fact, determines questions of proximate causation. Shinaver v. Szymanski (1984), 
    14 Ohio St. 3d 51
    , 14 OBR 446, 
    471 N.E. 2d 477
    .
    {¶ 4} Defendant had the duty to maintain its highways in a reasonably safe
    condition for the motoring public. Knickel v. Ohio Department of Transportation (1976),
    
    49 Ohio App. 2d 335
    , 3 O.O. 3d 413, 
    361 N.E. 2d 486
    . However, defendant is not an
    insurer of the safety of its highways. See Kniskern v. Township of Somerford (1996),
    
    112 Ohio App. 3d 189
    , 
    678 N.E. 2d 273
    ; Rhodus v. Ohio Dept. of Transp. (1990), 
    67 Ohio App. 3d 723
    , 
    588 N.E. 2d 864
    . The duty of ODOT to maintain the roadway in a
    safe drivable condition is not delegable to an independent contractor involved in
    roadway construction. ODOT may bear liability for the negligent acts of an independent
    contractor charged with roadway construction.         Cowell v. Ohio Department of
    Transportation, Ct. of Cl. No. 2003-09343-AD, jud, 
    2004-Ohio-151
    . Despite defendant’s
    contentions that ODOT did not owe any duty in regard to the construction project,
    defendant was charged with duties to inspect the construction site and correct any
    known deficiencies in connection with the particular construction work. See Roadway
    Express, Inc. v. Ohio Dept. of Transp. (June 28, 2001), Franklin App. 00AP-1119.
    {¶ 5} Alternatively, defendant denied that neither ODOT nor Jurgensen had any
    notice of the particular pothole prior to plaintiff’s property damage event. Defendant
    pointed out that ODOT records “indicate no calls or complaints were received regarding
    the pothole in question prior to Plaintiff McCarthy’s incident.” Defendant advised, “[i]t
    should be noted that this portion of I-75 has an average daily traffic volume of 72,000,
    however, no complaints were received (regarding a roadway defect) prior to plaintiff’s
    alleged incident.”
    Defendant contended plaintiff failed to offer any evidence of negligent roadway
    maintenance on the part of ODOT and failed to produce evidence to establish his
    property damage was attributable to conduct on either the part of ODOT or Jurgensen.
    {¶ 6} Defendant submitted a copy of an e-mail from Jurgensen Project
    Manager, Jason Mudd, who recorded Jurgensen was notified of a pothole “on NB I-75
    near SR-122” by the Ohio State Highway Patrol at approximately 9:00 p.m. on January
    14, 2010.    According to Mudd, that pothole was promptly patched by Jurgensen
    personnel, including himself, beginning at 9:45 p.m. Mudd noted that when the pothole
    was patched at 9:45 p.m. two lanes of traffic were closed “since the pothole was in the
    middle lane.” Mudd stated, “[t]he hole was rather large, approximately 3.5 ft. x 28 ft.”
    According to Mudd, the massive pothole “was excavated and cleaned out with a
    backhoe and cold patch material was put in so the road could be reopened.” Mudd
    related the pothole had formed in an existing area of pavement not presently under
    construction, and was completely repaired by 2:00 a.m. on January 15, 2010. Mudd
    pointed out Jurgensen employee “Ken Bolser was called at 6:00 a.m. informing him that
    the pothole (recurred)” and this time repairs were made by ODOT personnel using cold
    patch material. Mudd observed ODOT subsequently directed Jurgensen to close two
    lanes of traffic and repair the pothole with hot mix asphalt and these repairs were
    completed by 7:30 p.m. on January 15, 2010.            Submitted time sheets for work
    performed in patching the pothole on the night of January 14, 2010 reflect that four tons
    of cold mix material were used to implement repairs.
    {¶ 7} In order to find liability for a damage claim occurring in a construction
    area, the court must look at the totality of the circumstances to determine whether
    ODOT acted in a manner to render the highway free from an unreasonable risk of harm
    for the traveling public. Feichtner v. Ohio Dept. of Transp. (1995), 
    114 Ohio App. 3d 346
    , 
    683 N.E. 2d 112
    .        In fact, the duty to render the highway free from an
    unreasonable risk of harm is the precise duty owed by ODOT to the traveling public
    under both normal traffic and during highway construction projects. See e.g. White v.
    Ohio Dept. of Transp. (1990), 
    56 Ohio St. 3d 39
    , 42, 
    564 N.E. 2d 462
    .
    {¶ 8} In order to prove a breach of the duty to maintain the highways, plaintiff
    must prove, by a preponderance of the evidence, that defendant had actual or
    constructive notice of the precise condition or defect alleged to have caused the
    accident.   McClellan v. ODOT (1986), 
    34 Ohio App. 3d 247
    , 
    517 N.E. 2d 1388
    .
    Defendant is only liable for roadway conditions of which it has notice but fails to
    reasonably correct. Bussard v. Dept. of Transp. (1986), 
    31 Ohio Misc. 2d 1
    , 31 OBR
    64, 
    507 N.E. 2d 1179
    .
    {¶ 9} Generally, in order to recover in a suit involving damage proximately
    caused by roadway conditions including potholes, plaintiff must prove that either: 1)
    defendant had actual or constructive notice of the pothole and failed to respond in a
    reasonable time or responded in a negligent manner, or 2) that defendant, in a general
    sense, maintains its highways negligently.     Denis v. Department of Transportation
    (1976), 75-0287-AD. There is insufficient evidence ODOT or Jurgensen had actual
    notice the pothole had reformed prior to plaintiff’s incident at 5:30 am. on January 15,
    2010.    Therefore, in order to recover plaintiff must produce evidence to prove
    constructive notice of the defect or negligent maintenance.
    {¶ 10} “[C]onstructive notice is that which the law regards as sufficient to give
    notice and is regarded as a substitute for actual notice or knowledge.” In re Estate of
    Fahle (1950), 
    90 Ohio App. 195
    , 197-198, 
    48 O.O. 231
    , 
    105 N.E. 2d 429
    . “A finding of
    constructive notice is a determination the court must make on the facts of each case not
    simply by applying a pre-set time standard for the discovery of certain road hazards.”
    Bussard.
    {¶ 11} Generally, the trier of fact is precluded from making an inference of
    defendant’s constructive notice, unless evidence is presented in respect to the time the
    defective condition developed. Spires v. Ohio Highway Department (1988), 
    61 Ohio Misc. 2d 262
    , 
    577 N.E. 2d 458
    .
    {¶ 12} In order for there to be constructive notice, plaintiff must show sufficient
    time has elapsed after the dangerous condition appears, so that under the
    circumstances defendant should have acquired knowledge of its existence. Guiher v.
    Dept. of Transportation (1978), 78-0126-AD . Ordinarily size of a defect (pothole) is
    insufficient to show notice or duration of existence.         O’Neil v. Department of
    Transportation (1988), 
    61 Ohio Misc. 2d 287
    , 
    587 N.E. 2d 891
    . However, the massive
    size of a defect coupled with knowledge that the pothole presented a recurring problem
    is sufficient to prove constructive notice. Fite v. Ohio Dept. of Transp., Ct. of Cl. No.
    2009-05757-AD, 
    2009-Ohio-7124
    .
    {¶ 13} Additionally, plaintiff has produced evidence to infer defendant maintains
    the roadway negligently. Denis. Plaintiff’s evidence submitted shows that the particular
    damage-causing pothole was formed when an existing patch deteriorated. This fact
    alone does not provide conclusive proof of negligent maintenance. A pothole patch that
    deteriorates in less than ten days is prima facie evidence of negligent maintenance.
    Matala v. Ohio Department of Transportation, 2003-01270-AD, 
    2003-Ohio-2618
    ;
    Schrock v. Ohio Dept. of Transp., Ct. of Cl. No. 2005-02460-AD, 
    2005-Ohio-2479
    .
    Evidence has shown plaintiff’s vehicle was damaged by a pothole that had been
    patched at 9.45 p.m. on January 14, 2010 and the repair patch had failed by 5:30 a.m.
    on January 15, 2010. The fact that the pothole plaintiff’s car struck deteriorated in a
    time frame of less than five hours warrants application of the standard expressed in
    Matala; Fisher v. Ohio Dept. of Transp., Ct. of Cl. No. 2007-04869-AD, 
    2007-Ohio-5288
    ;
    Romes v. Ohio Dept. of Transp., Ct. of Cl. No. 2008-01826-AD, 
    2008-Ohio-4624
    .
    Defendant is liable to plaintiff for the damage claimed $574.78, plus the $25.00 filing fee
    which may be awarded as compensable costs pursuant to R.C. 2335.19. Bailey v. Ohio
    Department of Rehabilitation and Correction (1990), 
    62 Ohio Misc. 2d 19
    , 
    587 N.E. 2d 990
    .
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    MICHAEL J. MCCARTHY
    Plaintiff
    v.
    OHIO DEPARTMENT OF TRANSPORTATION, DISTRICT 8
    Defendant
    Case No. 2010-02090-AD
    Deputy Clerk Daniel R. Borchert
    ENTRY OF ADMINISTRATIVE
    DETERMINATION
    Having considered all the evidence in the claim file and, for the reasons set forth
    in the memorandum decision filed concurrently herewith, judgment is rendered in favor
    of plaintiff in the amount of $599.78, which includes the filing fee. Court costs are
    assessed against defendant.
    DANIEL R. BORCHERT
    Deputy Clerk
    Entry cc:
    Michael J. McCarthy             Jolene M. Molitoris, Director
    6468 Willow Bend Drive          Department of Transportation
    Liberty Twp., Ohio 45011        1980 West Broad Street
    Columbus, Ohio 43223
    RDK/laa
    Filed 6/8/10
    Sent to S.C. reporter 10/1/10
    

Document Info

Docket Number: 2010-02090-AD

Citation Numbers: 2010 Ohio 4789

Judges: Borchert

Filed Date: 6/8/2010

Precedential Status: Precedential

Modified Date: 10/30/2014