Case Leasing & Rental, Inc. v. Ohio Dept. of Natural Resources ( 2011 )


Menu:
  • [Cite as Case Leasing & Rental, Inc. v. Ohio Dept. of Natural Resources, 
    2011-Ohio-1417
    .]
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    CASE LEASING & RENTAL, INC.
    Plaintiff
    v.
    OHIO DEPARTMENT OF NATURAL
    RESOURCES
    Defendant
    Case No. 2005-08034
    Judge Joseph T. Clark
    DECISION
    {¶ 1} On June 19, 2008, this court issued a liability determination in favor of
    plaintiff,1 an Ohio corporation and owner of an 87,500 square foot facility known as the
    Lake Front Racquet and Health Club (the RecPlex) in Celina, Ohio.
    {¶ 2} In July 2003, the RecPlex sustained extensive damage as a result of
    flooding that occurred after a severe storm passed through the area. The court found
    that defendant, the Ohio Department of Natural Resources (ODNR), was liable for such
    damage as a result of its negligent construction and maintenance of a spillway located
    near the RecPlex property.
    {¶ 3} On February 11, 2009, following the damages portion of the bifurcated
    trial, a magistrate of the court recommended judgment in the amount of $4,235,444,
    1
    References to “plaintiff” in this decision are to Tom Case, owner of plaintiff corporation, an entity
    separate from the Recplex.
    which consisted of $2,735,000 for diminution in value of the real property, $551,119 in
    personal property loss, $949,300 in interest costs on bank loans associated with
    restoration and repair of the property, and $25 for reimbursement of the court’s filing
    fee. The recommendation regarding the loss of market value was based upon a finding
    that plaintiff’s loss was permanent in nature inasmuch as neither the design nor the
    structure of the spillway were reasonably likely to change in the near future and
    continued intermittent flooding of the property was inevitable.
    {¶ 4} The parties filed timely objections to the magistrate’s recommendation.
    The court thereafter issued a decision, dated April 16, 2009, wherein it adopted the
    magistrate’s decision that the damage to plaintiff’s property was permanent, but
    disallowed the award of $949,300 in interest costs. The court reasoned that plaintiff’s
    decision to repair and reopen the RecPlex was at his own risk and expense, and that
    any award of interest charged upon sums borrowed to finance the repair of the RecPlex
    was in error. The court summarized that the loss of market value of the property was
    the extent of defendant’s liability and the limit of plaintiff’s recovery. Accordingly, the
    court entered judgment in the reduced amount of $3,286,144.
    {¶ 5} The parties then filed cross-appeals to the Tenth District Court of Appeals.
    On December 15, 2009, the appeals court affirmed this court’s decision on liability, but
    reversed and remanded the case for further determination on the issue of damages.
    The court held that the damage to plaintiff’s property should have been deemed to be
    temporary because, in order to prevent or minimize future flooding events, plaintiff had
    built an approximately six-foot-high dike around the property after the 2003 flood. The
    court explained that “[t]he injury to [plaintiff’s] property was temporary because it was
    repairable, and the owners took measures to alleviate the risk of further flooding.” Case
    Leasing & Rental, Inc. v. Ohio Dept. of Natural Resources, Franklin App. No. 09AP-498,
    
    2009-Ohio-6573
    , ¶40. Therefore, the appeals court concluded that the proper measure
    of damages was “the reasonable cost of repair, plus reasonable compensation for the
    loss of the use of the property” and remanded the case “for a determination of damages
    for a temporary injury to the property.” Id. at ¶41.
    {¶ 6} Upon review of the evidence, testimony, and the arguments of counsel,
    the court makes the following determination.
    {¶ 7} Plaintiff is now claiming damages in the total amount of $5,201,911.
    Defendant asserts that plaintiff’s damages are minimal, if any, and puts forth essentially
    one argument in support of that proposition: a reassertion of its previous contention that
    plaintiff lacks standing to assert its damages claims. Those arguments were presented
    at the liability trial and were rejected in the court’s subsequent written decision.2 The
    determination of that issue was not assigned as error in ODNR’s appeal to the Tenth
    District, nor was it addressed in that court’s decision. To the contrary, the appeals court
    held that plaintiff was “entitled” to damages. Thus, in accordance with the law of the
    case doctrine, the court again rejects defendant’s arguments as to any alleged lack of
    standing. It is well-settled that “the decision of a reviewing court in a case remains the
    law of that case on the legal questions involved for all subsequent proceedings in the
    case at both the trial and reviewing levels.” Nolan v. Nolan (1984), 
    11 Ohio St.3d 1
    , 3.
    The Supreme Court of Ohio has further explained that “ the rule is necessary to ensure
    consistency of results in a case, to avoid endless litigation by settling the issues, and to
    preserve the structure of superior and inferior courts as designed by the Ohio
    Constitution.” 
    Id.
     citing State ex rel. Potain v. Mathews (1979), 
    59 Ohio St.2d 29
    , 32.
    Nonetheless, the doctrine is not a substantive rule of law, but rather, is a rule of
    practice that should not be applied to achieve unjust results. 
    Id.
     citing Gohman v. St.
    Bernard (1924), 
    111 Ohio St. 726
    , 730, reversed on other grounds. (Additional citations
    omitted.)
    {¶ 8} Based upon the foregoing, the court accepts as settled that plaintiff has
    standing to pursue his damages claims. However, the second branch of defendant’s
    argument is that, even if plaintiff’s standing is established, his recovery is limited to the
    2
    Specifically, the court held that: “[d]efendant has argued that plaintiff lacks standing to assert its claims
    because it did not own the property at the time of the July 2003 flood. The court finds that argument to be
    without merit inasmuch as plaintiff financed the purchase and received a mortgage on the property as
    security. Ohio law permits mortgagees to sue third parties for damage to their security interest. City of
    Toledo v. Brown (1936), 
    130 Ohio St. 513
    , 519. See also Trip Agency, Inc. v. R. G. Akkihal (Nov. 4,
    1991), Lawrence App. No. 1790; RFC Capital Corp. v. Earthlink, Inc., Franklin App. No. 03AP-375, 2004-
    Ohio-7046. Moreover, at the time of the flood, the purchasers had made only one payment of $100,000
    on the $3,000,000 they financed, and they had no insurance on the property. They threatened to file
    bankruptcy if plaintiff pursued them for the balance of the mortgage. Plaintiff never released the
    mortgage and the property was conveyed back to it on September 1, 2003.” Case Leasing & Rental, Inc.
    v. Ohio Dept. of Natural Resources, Ct. of Cl. No. 2005-08034, 
    2008-Ohio-3411
    , fn.2.
    amount that his mortgage interest was impaired. Again, that issue was not assigned as
    error to the Court of Appeals nor addressed in its decision. To the contrary, the appeals
    court specifically defined the measure of damages for temporary injury to property.
    Thus, the law of the case precludes further review of the issue and the court finds that
    application of the doctrine does not achieve an unjust result in this case.
    {¶ 9} Accordingly, the court turns to analysis of plaintiff’s damages claims as
    directed by the Court of Appeals. It is axiomatic that plaintiff bears the burden of proof
    on damages. Henderson v. Spring Run Allotment (1994), 
    99 Ohio App.3d 633
    , 641. In
    making its determination, the court’s “essential inquiry is whether the damages sought
    are reasonable.” Martin v. Design Const. Servs., Inc., 
    121 Ohio St.3d 66
    , 
    2009-Ohio-1
    ,
    ¶25.
    I. REPAIR AND RESTORATION
    {¶ 10} As discussed in this court’s liability and damages decisions, the 2003 flood
    devastated plaintiff’s property.   Plaintiff contracted with Shinn Brothers, Inc. for the
    majority of the labor involved in repairing and restoring the RecPlex to its pre-flood
    condition. The cost for those services was $1,446,675.61. Plaintiff also alleges that he
    paid an additional $89,607 to other vendors for restoration services and expenses. All
    of the expenses were documented in Plaintiff’s Exhibit 10, which was prepared by
    plaintiff’s daughter, Cheri Kraska. There was no credible testimony or other evidence to
    contradict the documented amounts. The court concludes that plaintiff has proven by a
    preponderance of the evidence that he incurred $1,536,282.61 ($1,446,675.61 +
    $89,607) for this portion of the repair and restoration efforts. The court finds that the
    costs are reasonable in light of both the extent of the damage sustained to the property
    and the intensive labor involved in its reconstruction. Accordingly, plaintiff is entitled to
    compensation for the requested amount.
    {¶ 11} In addition to the work provided by Shinn Brothers, Inc., plaintiff alleges
    that he also utilized services provided by RecPlex employees, Case Leasing, Inc.
    employees, and      independent contractors.     Plaintiff alleges that from July 1, 2003
    through September 2003, RecPlex employees were solely engaged in repair and
    restoration activities; however, in October 2003, portions of the RecPlex reopened and
    some employees returned to their usual duties while continuing to assist with restoration
    work.    Plaintiff and Kraska then began a process whereby they estimated the
    percentage of the employees’ work week spent on restoration activities and followed-up
    by interviewing the respective employees to confirm the accuracy of the estimates.
    The results of that process are documented in Plaintiff’s Exhibit 12, also generated by
    Kraska, which shows that RecPlex employees were paid $104,229.90 for their
    continued restoration services. The work performed by the independent contractors
    and employees of Case Leasing, Inc., was calculated in the same manner as the
    RecPlex employees’ services, and was documented as $302,932.66.3                        Plaintiff is
    seeking compensation in the total amount of $381,540 for these expenses.
    {¶ 12} The court finds that plaintiff failed to prove by a preponderance of the
    evidence that he is entitled to compensation for the total amount claimed for these
    additional labor expenses.        There is no documentary evidence as to the services
    provided, the hourly rate of the RecPlex or Case Leasing employees, the type of work
    that they ordinarily performed for their employers, or how their talents or the cost of their
    services would compare to the cost of hiring outside labor for the various tasks
    performed.     Likewise, there is no documentary evidence as to the amount of work
    performed by the independent contractors or why their work was necessary in addition
    to that provided by Shinn Brothers, Inc. and the others previously discussed. The court
    finds that neither the documentation nor the testimony presented provide a reasonably
    certain basis for an award of the claimed amount. Accordingly, the court shall award
    compensation only for the RecPlex employees’ labor expense in the amount of
    $5,503.47, for the period from July 2003 to September 30, 2003, when the facility was
    completely closed and there was no work other than repair and restoration to perform.
    {¶ 13} Plaintiff also seeks an award of $500,000 for repair of the nine-hole golf
    course that previously existed on the property. Plaintiff concedes that he did not rebuild
    the course and that, even though a dike was constructed around the RecPlex property,
    it does not protect the entire 21 acres upon which the facility is situated. As a result,
    3
    Although the total of the two amounts equals $407,162.56, plaintiff asserts that he arrived at the
    requested amount after deducting $19,200 of labor expenses that were also included in the $1,536,283
    plaintiff cannot prevent future flooding to the golf course portion of his property. The
    court finds that it would be unreasonable to award damages for a restoration that has
    not actually been performed, and for which it would make little economic sense to
    pursue. Therefore, no award shall be granted for future repair of the golf course.
    {¶ 14} Finally in this category, plaintiff seeks damages in the amount of $551,119
    for personal property inside the RecPlex that was repaired and put back into use. This
    court’s previous award for that amount was not assigned as error on appeal. However,
    defendant now contests an award for such damages, based upon its lack of standing
    arguments and the documentation offered to support those contentions. Again, the law
    of the case doctrine precludes further debate of the issue, and there was no testimony
    or other evidence that persuades the court that application of the doctrine would
    achieve an unjust result. Accordingly, the court concludes that plaintiff is entitled to
    compensation for the claimed amount of $551,119.4
    {¶ 15} In summary, judgment shall entered in the total amount of $2,092,905.08
    ($1,536,282.61 + $5,503.47 + $551,119) for plaintiff’s costs of repair and restoration.
    As noted by the Court of Appeals on remand, “evidence of diminution of the market
    value is relevant in deciding whether the actual costs of repair and restoration are
    reasonable.”      Case Leasing, supra, at ¶43.              The court concludes that the amount
    awarded is reasonable based upon its previous finding that the diminution of market
    value for the property was $2,735,000.
    II. INTEREST ON LOANS
    {¶ 16} Plaintiff is seeking recovery for the cost of interest paid on $5,000,000 in
    loans, all of which were allegedly obtained to restore and repair the RecPlex to its pre-
    flood operating conditions. The amount of those loans and the interest associated with
    each is set forth in Plaintiff’s Exhibits 2 and 13. As stated by the Court of Appeals on
    amount documented in Plaintiff’s Exhibit 10. According to the court’s calculations, $407,162.56 - $19,200
    equals $387,962.56.
    4
    As a result of such determination, both plaintiff’s August 23,2010 “motion to certify a partial judgment”
    and defendant’s September 9, 2010 “motion for relief from judgment” are DENIED as moot. Additionally,
    plaintiff’s September 17, 2010 motion for leave to file a reply in support of its motion to certify a partial
    judgment, defendant’s October 7, 2010 motion for leave to file a reply in support of its motion for relief
    remand, “interest on loans taken out to restore the property can be a reasonable cost of
    repair.” Id. at ¶46. (Emphasis added.)
    {¶ 17} Plaintiff’s first loan was obtained from Markle Bank in the form of a
    $1,000,000 note which was later increased (in March 2004) to $2,500,000. Following
    the first damages trial, the magistrate recommended an award of $949,300 for interest
    accrued on that loan from its inception to February 11, 2009, the date of decision.5
    Plaintiff is now seeking an award of $952,561 for interest that has continued to accrue
    on the loan through the date of the second trial, plus $74 per day thereafter. Further,
    plaintiff seeks an award of $260,000, for interest that his brother would have earned on
    a $1.9 million certificate of deposit (CD) that was used to pay down the principal of this
    loan.
    {¶ 18} Plaintiff has submitted evidence detailing the interest and principal
    payments made over time and the various interest rates that have been applied.
    Defendant has not refuted those amounts, but rather the extent to which the proceeds
    were used for restoration. What is problematic for the court is that plaintiff chose not
    just to restore the facility to a condition suitable for sale, but to reopen the RecPlex
    business and to incur continued expenses for that purpose. It is undisputed that the
    business was not profitable for at least the two years before the flood, and generated
    only $22,099 in net income in the months prior to the July 2003 flood. (Defendant’s
    Exhibits K, L, M, N, and Q.) It is apparent from the evidence that plaintiff eventually
    began to struggle to repay the loan, to the extent that the bank allowed “interest only”
    payments for a period of time, charged frequent late fees, and eventually cashed the
    CD that plaintiff’s brother had pledged to secure the loan.
    {¶ 19} Upon review of the evidence submitted, the court is unable to reconcile
    what amount of interest is attributable to proceeds of the loan used solely for
    restoration, what amount is attributable to plaintiff’s efforts to keep the business in
    operation, and what amount is            attributable to plaintiff’s inability to make timely
    from judgment, and plaintiff’s October 13, 2010 motion to strike defendant’s reply memorandum are
    DENIED as moot.
    5
    As noted previously, the court modified the magistrate’s recommendation to disallow an award for
    interest costs; it did not comment on the reasonableness of the amount or the manner in which it was
    calculated.
    payments on the loan. In short, the court is forced to conclude that the total amount of
    interest sought for repayment of this loan is unreasonable, and that defendant cannot
    be held liable for interest incurred as a result of plaintiff’s decision to reopen a non-
    profitable business, or his inability to meet his obligations.            Therefore, based upon
    plaintiff’s failure of proof, and his lack of credibility on this issue, the court shall award
    only the amount of interest paid through July 9, 2007, when regular payments were
    being made. Using the figures contained in Plaintiff’s Exhibit 13, the court calculates
    that amount to be $520,603.44.6 For these same reasons, no award shall be granted
    for the $260,000 claimed for reimbursement of interest owed to plaintiff’s brother.
    {¶ 20} As to the remaining loans, the court also finds that plaintiff failed to prove
    by a preponderance of the evidence that the proceeds of the additional loans were
    utilized for   restoration efforts, or that the amount of the loans was reasonable as
    compared to the cost of restoration or the diminution of the property’s market value.
    Therefore, no award shall be granted for the claimed interest on the additional loans.
    III. LOSS OF USE OF THE RECPLEX
    {¶ 21} According to the testimony, plaintiff calculated this element of damages by
    relying upon a net income figure of $56,164 for the year 2008, when he asserts that the
    RecPlex had returned to a level of operation comparable to pre-flood business
    conditions. Based upon audited financial statements, plaintiff then applied that figure in
    calculating the net income that the RecPlex would have earned in the years from 2003
    through 2007, but for the flood. For example, plaintiff contends that for the four months
    of the last quarter of 2003, the RecPlex should have received a net revenue of $14,041
    ($56,164/4). However, because the business lost $49,000, plaintiff calculated the loss
    of use for those months as $63,041 ($14,041 + $49,000). The same method was used
    to calculate a loss of use for the years 2004 through 2007. The total amount sought for
    this element of damages is $348,198.                 All of the calculations and supporting
    documentation are set forth in Plaintiff’s Exhibit 14.
    6
    The calculation began at $13,020.83 paid on April 3, 2004, and ended with the $13,937.52 paid on July
    9, 2007.
    {¶ 22} Defendant counters that plaintiff is not entitled to any loss-of-use
    damages, again based largely upon its lack of standing arguments. Those arguments
    were previously addressed and rejected. Defendant further contends that, based upon
    the reported net operating losses for the RecPlex in the years prior to and following the
    flood (Defendant’s Exhibits K, L, M, N, and Q), plaintiff has not suffered any
    compensable loss of use.
    {¶ 23} Neither party has offered any case law in support of the method used in
    the evaluation of these damages. However, it has consistently been held that: “‘[t]he
    value of the use of the property is measured according to the purpose for which the
    property is held. If the injured property is held for rental purposes, then the “value of the
    use” is the diminution in the property’s rental value.’ Reeser v. Weaver Bros., Inc.
    (1992), 
    78 Ohio App.3d 681
    , 686, 
    605 N.E.2d 1271
    , citing Klein v. Garrison (1951), 
    91 Ohio App. 418
    , 420-427, 
    108 N.E.2d 381
    . Loss or decrease in rental value would not
    be a reliable basis upon which to estimate damages if the property is not held for rental
    purposes, rather, loss of the value of use would be the measure of damages. Id.”
    Weber v. Obuch, Medina App. No. C.A.05CA0048-M, 2005-Ohio- 6993, ¶25.
    (Emphasis added.) The case law provides no guidance as to how to determine a value
    of use for a multi-dimensional business such as the RecPlex. Nonetheless, Ohio law
    makes clear that a party cannot recover purely speculative damages.              Id. at ¶28.
    (Additional citations omitted.)
    {¶ 24} Based upon the evidence and the available case law, the court finds that
    plaintiff’s loss of revenue calculations are a purely speculative means upon which to
    base an award for any loss of value of use. In light of the minimal profitability of the
    business, and as a result of the lack of credible evidence, the court concludes that
    plaintiff failed to prove by a preponderance of the evidence that he sustained a
    compensable loss of use of the property. Therefore, no award shall be granted for this
    component of plaintiff’s alleged damages.
    {¶ 25} In conclusion, the court finds that plaintiff is entitled to damages in the
    amount of $2,613,508.52, consisting of $2,092,905.08 ($1,536,282.61 + $5,503.47 +
    $551,119) for repair and restoration, and $520,603.44 for interest costs. Judgment shall
    be entered in that amount plus $25 for reimbursement of the filing fee.
    Court of Claims of Ohio
    The Ohio Judicial Center
    65 South Front Street, Third Floor
    Columbus, OH 43215
    614.387.9800 or 1.800.824.8263
    www.cco.state.oh.us
    CASE LEASING & RENTAL, INC.
    Plaintiff
    v.
    OHIO DEPARTMENT OF NATURAL
    RESOURCES
    Defendant
    Case No. 2005-08034
    Judge Joseph T. Clark
    JUDGMENT ENTRY
    This case was tried to the court on the issue of plaintiff’s damages. The court
    has considered the evidence and, for the reasons set forth in the decision filed
    concurrently herewith, judgment is rendered in favor of plaintiff in the amount of
    $2,613,533.52, which includes the filing fee paid by plaintiff. Court costs are assessed
    against defendant. The clerk shall serve upon all parties notice of this judgment and its
    date of entry upon the journal.
    _____________________________________
    JOSEPH T. CLARK
    Judge
    cc:
    Jeremy M. Grayem                    Kevin L. Murch
    250 West Street, 7th Floor          Matthew T. Green
    Columbus, Ohio 43215                Stephen P. Samuels
    250 West Street
    Columbus, Ohio 43215
    Randall W. Knutti
    Assistant Attorney General
    150 East Gay Street, 18th Floor
    Columbus, Ohio 43215-3130
    LH/cmd
    Filed March 3, 2011
    To S.C. reporter March 22, 2011
    

Document Info

Docket Number: 2005-08034

Judges: Clark

Filed Date: 3/3/2011

Precedential Status: Precedential

Modified Date: 10/30/2014