Innovative Business Technologies, L.L.C. v. Ohio State Univ. ( 2021 )


Menu:
  • [Cite as Innovative Business Technologies, L.L.C. v. Ohio State Univ., 
    2021-Ohio-2403
    .]
    INNOVATIVE BUSINESS                                    Case No. 2018-01403JD
    TECHNOLOGIES, LLC
    Judge Dale A. Crawford
    Plaintiff
    DECISION
    v.
    THE OHIO STATE UNIVERSITY
    Defendant
    I. Introduction
    {¶1} Plaintiff Innovative Business Technologies, LLC (IBT) brings claims of
    breach of contract and tortious interference with a contract against Defendant The Ohio
    State University (OSU). The parties’ dispute stems from two contracts concerning two
    projects at OSU’s College of Engineering: Active Directory (AD) Project, and System
    Center Configuration Management (SCCM) Project.
    {¶2} The case proceeded to a bench trial on issues of liability and damages. At
    the conclusion of trial, the Court determined that IBT proved by a preponderance of the
    evidence that OSU breached the parties’ two contracts. The Court also determined that
    OSU is liable for damages that are proximately caused by its breaches. The Court
    ordered the parties to submit briefing on the issues of damages and attorney fees. The
    Court, however, took the issue of IBT’s claims for tortious interference with a contractual
    relationship under advisement pending a review of submitted deposition evidence.
    {¶3} Following the trial OSU submitted a filing labeled “Memorandum In
    Opposition To An Award Of Attorney Fees And To IBT’s Last-Minute Damage Claim
    and Review Of IBT’s Damage Claim.” And following the trial IBT submitted a post-trial
    brief and a Notice of Filing.          In the Notice of Filing IBT represents that it filed the
    followingdocuments: (1) Trial Transcript with Exhibits, (2) Deposition of Marsha Henfer
    Case No. 2018-01403JD                        -2-                                DECISION
    with Exhibits, (3) Deposition of Stacy Spear with Exhibits, (4) Affidavit of Shaina Thorpe
    with Exhibits, and (5) Affidavit of Beth Lashuk with Exhibits. A review of the docket,
    however, discloses that the documents identified in IBT’s Notice of Filing were not
    contemporaneously filed with IBT’s Notice.
    II. IBT has not proven by a preponderance of the evidence that OSU tortiously
    interfered with IBT’s contracts with its subcontractors.
    {¶4} IBT is required to establish its claims of tortious interference with a contract
    by a preponderance of the evidence. See Weishaar v. Strimbu, 
    76 Ohio App.3d 276
    ,
    282, 
    601 N.E.2d 587
     (8th Dist.1991). A preponderance of the evidence “is defined as
    that measure of proof that convinces the judge or jury that the existence of the fact
    sought to be proved is more likely than its nonexistence.” State ex rel. Doner v. Zody,
    
    130 Ohio St.3d 446
    , 
    2011-Ohio-6117
    , 
    958 N.E.2d 1235
    , ¶ 54. Under Ohio law the
    elements of the tort of tortious interference with a contract “are (1) the existence of a
    contract, (2) the wrongdoer’s knowledge of the contract, (3) the wrongdoer’s intentional
    procurement of the contract’s breach, (4) the lack of justification, and (5) resulting
    damages.” Fred Siegel Co., L.P.A. v. Arter & Hadden, 
    85 Ohio St.3d 171
    , 176, 
    707 N.E.2d 853
     (1999), citing Kenty v. Transamerica Premium Ins. Co., 
    72 Ohio St. 3d 415
    ,
    
    650 N.E.2d 863
     (1995), paragraph two of the syllabus.
    {¶5} Based on the submitted evidence, the Court finds that OSU did not
    intentionally procure the breach of IBT’s contracts with IBT’s subcontractors—Syllogistic
    Group or LenMar Project Solutions—as alleged by IBT. Thus, IBT has not proven all
    the required elements of the tort of tortious interference with a contract and,
    consequently IBT has failed to prove by a preponderance of the evidence that OSU
    tortiously interfered with IBT’s contracts with Syllogistic Group or LenMar Project
    Solutions. The Court holds that IBT is not entitled to relief on its claims of tortious
    interference with a contract.
    Case No. 2018-01403JD                     -3-                                DECISION
    III. IBT is entitled to damages and prejudgment interest for OSU’s breach of
    the parties’ contracts.
    {¶6} At trial the Court found that OSU is liable for IBT’s lost profit of
    approximately $8,000. IBT asserts, however, that “the amount due and payable to IBT
    for the breach of contract claims is the $439,840 service cost due under the AD
    Contract, along with waiting time for five resources under the AD Contract and two
    resources under the SCCM Contract through the end the Contracts in March 2018 of
    $1,710,140. The resulting total amount due to IBT is $2,149,980 plus attorney’s fees
    and costs.”
    {¶7} OSU challenges IBT’s calculation of the amount due and payable. OSU
    contends that IBT’s unwillingness to engage in good faith settlement discussions bars
    recovery. OSU further contends that before trial (1) IBT was offered more than this
    Court awarded at trial, (2) IBT refused to negotiate in good faith, and (3) IBT insisted
    that the case should go to trial. OSU reasons that, if IBT had accepted OSU’s offer or
    continued to negotiate, it would not have incurred attorney fees in the weeks leading up
    to and through trial.
    {¶8} In Allen, Heaton & McDonald, Inc. v. Castle Farm Amusement Co., 
    151 Ohio St. 522
    , 
    86 N.E.2d 782
     (1949), the Ohio Supreme Court discussed the concept of
    damages resulting from a breach of contract. The Ohio Supreme Court held, “Where a
    plaintiff sues on a contract to recover the amount he would have received for the full
    performance thereof which was prevented by a defendant's breach, he seeks in effect to
    recover as damages the profit from performance of the contract that defendant's breach
    prevented him from earning.” Castle Farm Amusement Company at paragraph two of
    the syllabus. The Ohio Supreme Court further held, “In such a case, plaintiff has the
    burden of alleging and proving not only (a) what he would have received under the
    contract from the performance so prevented, but also (b) what such performance would
    have cost him (or the value to him of relief therefrom).    Unless he proves both of
    Case No. 2018-01403JD                        -4-                                  DECISION
    thosefacts, he cannot recover as damages the profits he would have earned from full
    performance of the contract.” 
    Id.
     at paragraph three of the syllabus. Accord ABLE
    Roofing v. Pingue, 10th Dist. Franklin No. 10AP-404, 
    2011-Ohio-2868
    , ¶ 24, quoting
    Restatement (Second) of Contracts (1981), Section 347 (injured party has a right to
    damages as measured by (a) the loss in the value to him of the other party's
    performance caused by its failure or deficiency, plus (b) any other loss caused by the
    breach, less (c) any cost or other loss that he has avoided by not having to perform).
    {¶9} Based on the submitted evidence, the Court finds that OSU paid IBT
    $74,300 for the SCCM Project, which was the agreed price for the SCCM Project. IBT
    thus received the benefit of its bargain for the SCCM Project. IBT is therefore not
    entitled to damages for OSU’s breach of the contract for the SCCM Project.
    {¶10} Based on the parties’ representations to the Court and evidence submitted,
    and for reasons that the Court announced at trial, the Court finds that IBT is entitled to
    damages for lost profits in the amount of $8,385.00 for OSU’s breach of the contract for
    the AD project, which the Court determines as follows:
    $219,810.00 (IBT’s projected total profits)
    -   $211,424.45 (IBT’s actual profits received)
    $   8,385.55 (Difference between projected total profits and actual profits)
    See generally Charles R. Combs Trucking, Inc. v. Internatl. Harvester Co., 
    12 Ohio St.3d 241
    , 
    466 N.E.2d 883
     (1984), paragraph two of the syllabus (holding that lost
    profits “may be recovered by the plaintiff in a breach of contract action if: (1) profits were
    within the contemplation of the parties at the time the contract was made, (2) the loss of
    profits is the probable result of the breach of contract, and (3) the profits are not
    Case No. 2018-01403JD                            -5-                                       DECISION
    remoteand speculative and may be shown with reasonable certainty”); see also JLJ Inc.
    v. Rankin & Houser, Inc., 2d Dist. Montgomery No. 23685, 
    2010-Ohio-3912
    , ¶ 21.1
    {¶11} R.C. 2743.18 governs an award of prejudgment interest on a judgment
    rendered against the state. R.C. 2743.18(A)(1) provides, “Prejudgment interest shall be
    allowed with respect to a civil action on which a judgment or determination is rendered
    against the state for the same period of time and at the same rate as allowed between
    private parties to a suit.” (Emphasis added.) See R.C. 1343.03 (interest when rate is
    not stipulated). In Royal Elec. Constr. Corp. v. Ohio State Univ., 
    73 Ohio St.3d 110
    ,
    116, 
    652 N.E.2d 687
     (1995), the Ohio Supreme Court stated, “[I]n determining whether
    to award prejudgment interest pursuant to R.C. 2743.18(A) and 1343.03(A), a court
    need only ask one question: Has the aggrieved party been fully compensated?” In
    Royal Electric Construction Corporation the Ohio Supreme Court held:
    In a case involving breach of contract where liability is determined
    and damages are awarded against the state, the aggrieved party is
    entitled to prejudgment interest on the amount of damages found due by
    the Court of Claims. The award of prejudgment interest is compensation to
    the plaintiff for the period of time between accrual of the claim and
    1In JLJ Inc. v. Rankin & Houser, Inc., 2d Dist. Montgomery No. 23685, 
    2010-Ohio-3912
    , ¶ 21, the
    Second District Court of Appeals stated:
    “‘As a general rule, an injured party cannot recover damages for breach of contract
    beyond the amount that is established by the evidence with reasonable certainty, and
    generally, courts have required greater certainty in the proof of damages for breach of
    contract than in tort.’ * * * The damages awarded for a breach of contract should place
    the injured party in as good a position as it would have been in but for the breach. Such
    compensatory damages, often termed ‘expectation damages,’ are limited to actual loss,
    which loss must be established with reasonable certainty.” Textron Fin. Corp. v.
    Nationwide Mut. Ins. Co. (1996), 
    115 Ohio App.3d 137
    , 144, 
    684 N.E.2d 1261
    . We have
    noted, however, that a trial court “enjoys a certain degree of latitude in ‘structuring
    damage awards in a manner most appropriate to the case before it.’” Davis v. Sun
    Refining and Marketing Co. (1996), 
    109 Ohio App.3d 42
    , 59, 
    671 N.E.2d 1049
     (citation
    omitted).
    Case No. 2018-01403JD                       -6-                              DECISION
    judgment, regardless of whether the judgment is based on a claim which
    was liquidated or unliquidated and even if the sum due was not capable of
    ascertainment until determined by the court. (R.C. 2743.18[A] and
    1343.03[A], construed and applied.)
    (Emphasis added.) 
    Id.
     at syllabus. In accordance with Royal Electric Construction
    Corporation, IBT therefore is entitled to prejudgment interest on the amount of damages
    on IBT’s claims of breach of contract.
    {¶12} Based on the submitted evidence, the Court holds that IBT is entitled to
    $8,385.55 in damages for lost profits for OSU’s breaches of contract, plus prejudgment
    interest at the statutory rate as of June 23, 2017 (the date that OSU called IBT about
    terminating the parties’ contracts). See United States Playing Card Co. v. Bicycle Club,
    
    119 Ohio App.3d 597
    , 609, 
    695 N.E.2d 1197
     (1st Dist.1997) (finding that prejudgment
    interest is to be calculated from the date of a breach until the date the trial court’s
    judgment was entered); see also R.C. 1343.03(A) and 5703.47.
    IV. IBT is entitled to an award of attorney fees under the parties’ contracts.
    {¶13} OSU disputes that it contractually agreed to an award of attorney fees.
    OSU maintains that, according to Sections 7 and 12 of the General Terms and
    Conditions contained in the parties’ contracts, OSU agreed that IBT may “seek”
    damages, including attorney fees.
    {¶14} Both of the parties’ contracts contain General Terms of Conditions,
    Sections 7 and 12, whose provisions are identical. Section 7 provides,
    PAYMENT TERMS - The Project Initiation Service Fees are due 14 days
    prior to the Initialization/Kick-off meeting for the Project. All remaining
    payments are to be made according to the “Payment Schedule on page 7
    of this contract/Agreement. Charges resulting from changes to the SOW
    will be due in advance of commencing services. All invoiced work will be
    Case No. 2018-01403JD                       -7-                               DECISION
    due upon receipt of invoice ACH payment is the preferred method of
    payment. If payment due to IBT is not received within 15 days from due
    date IBT shall be entitled to seek all amounts due it in law or in equity
    including court costs, and reasonable attorney fees (including but not
    limited to pre-litigation, representation through appeals and post-trial
    motions) which may be incurred by IBT in the collection of any invoices
    not paid in full by Customer.
    (Emphasis added.) Section 12 states,
    LAW OF AGREEMENT - The parties agree that the laws of the State of
    Ohio shall govern any dispute arising from or related to this agreement.
    The parties further agree that entry into this agreement constitutes
    irrevocable consent that the exclusive venue for any such dispute shall be
    solely in the state or county courts in and for Franklin County, Ohio.
    Litigation in federal court is precluded by agreement of the parties hereto.
    The parties acknowledge and agree that they have had the opportunity to
    review this agreement, its terms and conditions, with counsel of their
    choice prior to executing same. IBT reserves all rights to seek reasonable
    attorneys’ fees in all proceedings, trials, investigations, appearances,
    appeals, arbitrations, and in any bankruptcy proceeding or administrative
    proceeding as the prevailing party.
    (Emphasis added.)
    {¶15} Contract interpretation presents a question of law. City of St. Marys v.
    Auglaize Cty. Bd. of Commrs., 
    115 Ohio St.3d 387
    , 
    2007-Ohio-5026
    , 
    875 N.E.2d 561
    , ¶
    38. Contracts “are to be interpreted so as to carry out the intent of the parties, as that
    intent is evidenced by the contractual language.” Skivolocki v. E. Ohio Gas Co., 
    38 Ohio St.2d 244
    , 
    313 N.E.2d 374
     (1974), paragraph one of the syllabus. Common words
    in a written instrument “will be given their ordinary meaning unless manifest absurdity
    Case No. 2018-01403JD                        -8-                                 DECISION
    results, or unless some other meaning is clearly evidenced from the face or overall
    contents of the instrument.” Alexander v. Buckeye Pipeline Co., 
    53 Ohio St.2d 241
    ,
    241, 
    374 N.E.2d 146
     (1978), paragraph two of the syllabus.
    {¶16} To construe Sections 7 and 12 as meaning that OSU promised that IBT
    may “seek” damages is tantamount to concluding that OSU offered no consideration
    because a plaintiff generally can always “seek” damages, including an award of attorney
    fees, in a contractual dispute. See McGlone v. Motorist Mut. Ins., 3d Dist. Crawford No.
    3-2000-25, 
    2001-Ohio-2188
    , 
    2001 Ohio App. LEXIS 1626
    , *10 (April 5, 2001) (“[a]n
    illusory promise is a promise that lacks consideration and thus, is unenforceable”).
    Courts generally disfavor interpretations of contracts that render contracts illusory or
    unenforceable, and courts generally prefer a meaning, which gives the contract vitality.
    See Thomas v. Am. Elec. Power Co., 10th Dist. Franklin No. 03AP-1192, 2005-Ohio-
    1958, ¶ 32. The Court determines that under Sections 7 and 12 the parties intended
    that IBT, as a prevailing party, is entitled to reasonable attorney fees for the amount
    owed to IBT. When a state entity contractually agrees to an attorney fees provision, this
    Court should enforce the contractual provision.          See Georgalis v. Cloak Factory
    Condominium Unit Owners’ Assn., 8th Dist. Cuyahoga No. 109300, 
    2021-Ohio-66
    , ¶ 34
    (observing that that the Ohio Supreme Court has made clear that courts should not
    rewrite contracts).
    {¶17} The Court finds that IBT is entitled to an award of reasonable attorney fees
    from the time during pretrial negotiations that OSU offered to resolve the parties’ dispute
    for $8,385.55, or an amount more than $8,385.55. Plaintiff shall prepare an affidavit
    reflecting reasonable attorney fees for services rendered to Plaintiff from the time during
    pretrial negotiations that OSU offered $8,385.55, or an amount more than $8,385.55.
    Plaintiff shall file such affidavit with the Court within 10 days of the date of this entry.
    And Plaintiff shall serve OSU with the affidavit that Plaintiff shall prepare.
    Case No. 2018-01403JD                       -9-                                DECISION
    {¶18} If the parties agree to the amount of attorney fees owed to IBT, then the
    parties shall inform the Court of the parties’ agreement within 14 days of the date of this
    entry. However, if the parties cannot agree on the amount of attorney fees to which IBT
    is due, then the parties shall notify the Court within 14 days of the date of the entry. If
    the parties are unable to reach an agreement on the amount of attorney fees that are
    due, then the Court will schedule an evidentiary hearing to determine the amount of
    attorney fees to which IBT is entitled.
    DALE A. CRAWFORD
    Judge
    Filed May 17, 2021
    Sent to S.C. Reporter 7/14/21
    

Document Info

Docket Number: 2018-01403JD

Judges: Crawford

Filed Date: 5/17/2021

Precedential Status: Precedential

Modified Date: 7/15/2021