Merrill v. Hexter , 52 Or. 138 ( 1908 )


Menu:
  • Mr. Justice Moore

    delivered the opinion of the court.

    1. It is contended by plaintiff’s counsel that cross-bills have been abolished by statute; that the affirmative relief which the defendants sought against the plaintiff is not germane to the original bill; and that the facts thus alleged in the answer are not pleaded as a counterclaim in equity, for which reasons the trial court erred in entertaining the cross-bill and in granting relief based thereon. Cross-bills have been abolished, except in an action at law, where the defendant is entitled to relief arising out of facts requiring the interposition of a court of equity and material for his defense, when he may, upon filing his answer therein, also as plaintiff file a complaint in equity in the nature of a cross-bill, which shall stay the proceedings at law; and the case thereafter shall proceed as a suit in equity. Section 391, B. & C. Comp. Our statute regulating the practice in suits in equity contains the following provision: "The counterclaim of the defendant shall be one upon which a suit might be maintained by the defendant against the plaintiff in the suit; and in addition to the cases specified in the subdivisions of Section 74, it is sufficient if it be connected with the subject of the suit.” Section 402, B. & C. Comp. In construing the section last mentioned it was held in Dodd v. Dodd, *14314 Or. 338 (13 Pac. 509), that, in a suit for a divorce, the defendant might, in an answer in the way of á counterclaim, demand and obtain affirmative relief, when it appears that such party is entitled to a decree. This decision removed the doubt which the statute abolishing cross-bills had Created, as to the right of a defendant in a suit in equity to invoke affirmative relief. In Maffett v. Thompson, 32 Or. 546 (52 Pac. 565: 53 Pac. 854), Mr. Justice Wolverton, referring to what is now codified as Section 402, B. & C. Comp., says: “In so far as it was designed to afford affirmative relief, the counterclaim here provided for, takes the place of the cross-bill under the chancery practice as it formerly prevailed. In Dove v. Hayden, 5 Or. 500, it was ruled that a counterclaim in equity could not be interposed by a defendant, unless his answer to the complaint admitted the plaintiff’s claim stated therein, or some part thereof. In that case, however, it is stated that the cause of suit did not arise out of a contract, nor was the defense connected with the subject of the suit. The rule thus announced was followed in Le Clare v. Thibault, 41 Or. 601 (69 Pac. 552), in which it was determined that the matters set forth in the second separate defense, did not arise out of the contract set forth in the complaint as the foundation of the plaintiff’s claim, except in one particular, and in that instance it was not connected with the subject-matter of'the suit. In the case at bar the separate defense interposed arises out of the contract entered into by the parties, and is intimately connected with the cause of suit stated in the complaint. The defendants’ admission in the answer of their execution of the contract was a sufficient acknowledgment of the plaintiff’s claim, as set forth in the complaint, to give the court jurisdiction of the defense, and though that part of the answer under consideration is denominated a cross-complaint, as classed under the ancient chancery practice, neither the court nor the adverse party was misled thereby, and hence no error was committed as alleged.

    *1442. It is insisted by plaintiff’s counsel that the testimony conclusively shows, that the defendants never tendered any part of the $50,000 as a condition precedent to the execution of a deed to the premises, and, this being so, no foundation exists for the specific performance of the terms of the contract, in decreeing which an error was committed. It will be remembered that it was the plaintiff who initiated this suit, and that the defendants, having been made adverse parties, answered, setting forth the facts constituting their defense and alleged right to equitable relief. They also averred that the plaintiff notified them that she would not accept the offer of the stipulated consideration for the premises, or execute to them a deed therefor. In such case no actual tender in money of the consideration was necessary. Guillaume v. K. S. D. Land Co., 48 Or. 400 (86 Pac. 883: 88 Pac. 586) ; West v. Washington Ry. Co., 49 Or. 436 (90 Pac. 666).

    3. Considering the case on its merits, the plaintiff, as a witness in her own behalf, testified that she was receiving from Langman, $125 a month for a lease of the storeroom and basement, and could have obtained from other tenants a like sum per month for the use of the premises,' but she demised the same to the defendants for a term of five years at only $100 a month, relying upon their covenants to keep the rooms in a sanitary condition, and to make, at their own expense, the improvements specified, which they represented would entail an outlay of about $3,000; that the defendants neglected to keep the premises in a sanitary condition, and in operating their meat market they permitted foul-odors to emanate, the inhaling of which made the witness and her tenants ill; and that the defendants refused to make any of the improvements specified, and, when requested by her to do so, replied that the contract did not specify any time within which the betterments should be made. The testimony of other witnesses shows, that *145complaint of the unsanitary condition of the meat market was made to the health officer; that he examined the leased premises, and notified the proprietors that changes in the management thereof should be made; and that the defendants always complied therewith. It also appears that one Saturday, evening, during warm weather, the scavenger, whose duty it was to remove garbage, neglected to call at the defendants’ place of business for the accumulated refuse, and on the next day offensive smells therefrom were discharged. Wm. Beutelspaeher, a deputy health officer, as plaintiff’s witness, testified that, complaint having been made of the condition of the meat market, he visited it, and notified the defendants of certain changes that should be made in the management of their business, with which directions they complied, and on cross-examination this witness states that the defendants’ butcher shop is as cleanly as any in the city. The defendant Strause testified that, when the lease was executed, the plaintiff had no knowledge of the improvements to the premises which he and his partner, the co-defendant Hexter, contemplated, until the latter informed her that some changes were desired, and particularly that a cold storage plant should be installed, whereupon she informed them that they must bear the expense incident thereto, and a stipulation to that effect was made a part of the contract, but no time was specified within which the work should be done; that it was thereafter discovered that the foundation of the basement was so deep that drainage therefrom could not be made into the sewer, and for that reason the inauguration of the refrigerator process was deferred until they could secure a title to the lot agreed to be conveyed to them; that the reduction of $25 a month in the rent reserved did not form any part of the consideration to make the improvements specified; that the defendants were ready, able, and willing, within the 60 days limited therefor, to pay the plaintiff $25,000, and to execute to her a mortgage *146of the premises to secure the remainder of the consideration, but she preferred that the entire sum should be paid at once, and desired to retain possession of all the lot, except the storeroom and basement, until such payment was made rather than to accept the mortgage bearing the low rate of interest; and that at. her suggestion, the lease and contract were so prepared. This witness further testified that about April 1,1906, the plaintiff was notified that the money agreed to be paid for the lot was ready and she was requested to procure an abstract of the title to the premises, which she, from time to time, promised to secure, until July 25th of that year, when this suit was commenced. The testimony of this witness is corroborated by that of Hexter, who also states that, when the first bargain to purchase the property was made, the price agreed to be paid therefor was considered as being very high, but because of their inability to secure another desirable location for a meat market, and by reason of the low rate of interest which they expected to pay for five years, on one half of the consideration, the agreement was consummated.

    It is argued by plaintiff’s counsel that, though the contract does not, in express terms, specify the time within which the improvements were to have been made, the rules of law applicable to the interpretation of such agreements imply that the work should have been done within a reasonable time, which had fully expired long prior to the commencement of this suit, and that the defendants’ failure to keep the demised premises in a healthful condition, constituted such breaches of the agreement as to justify the plaintiff’s action in taking advantage of the clause of the contract which permitted her, in case of such default, to revoke the option to purchase the premises, and, having done so, the trial court erred in refusing to grant the relief prayed for in the complaint. In a note to Section 1297 of Pomeroy’s Equity Jurisprudence (3 ed.) it is said: “Equity distinguishes *147between those terms and stipulations which are of the essence of a contract, and those which are not, and does not permit the defendant to set up a breach of the latter as complete bar to all relief, or a sufficient reason for wholly refusing to execute the agreement. In these cases no action at law can be maintained; but equity, if the contract is otherwise a proper pne, will compel a performance, with such compensations or allowances as may be just to the parties.”

    The reduction of $25 a month which the plaintiff made to the defendants on account of the rent when she leased the storeroom and basement to them did not, in our opinion, form the consideration for the stipulation to make the specified improvements. The defendants severally testified tliat they were prepared to pay the plaintiff the sum of $25,000 within the 60 days first limited therefor, and would have done so, but, at her request, they accepted a lease of the premises for the term of five years. It appears that several buildings have been erected on the lot, the rent from which was to be paid to the plaintiff until the deed was delivered to the defendants. By executing the lease to them the plaintiff surrendered her right to $1,000 a year, the interest on the remainder of the purchase price at 4 per cent per annum, which, with the reduction in the rent, is equivalent to a diminution of $108.33 a month. Whether or not the value of the plaintiff’s occupation of her home, and the money which she received from tenants for the use of rooms in her buildings, were equal to the relinquishments indicated, do not appear from the testimony; but we believe the receipt of such rents and the possession of the building which had for many years been her residence constituted the consideration for executing the lease in question. “Where the length of the lease,” says Mr. Justice Lewis, in Wilson v. Owens, 1 Ind. T. 163 (38 S. W. 976), “is fixed by the agreement, but the time within which the improvements are to be made is not *148stated, it is not perceived why the ordinary rule of law that performance must be had within a reasonable time, should not apply. What would be a reasonable time must depend upon the character of the improvements, and the various circumstances surrounding the parties and the subject-matter of the contract. These considerations may be readily apprehended, arid are to be kept in mind in determining what is a reasonable time for the making of the improvements stipulated.”

    4. The discovery made by the defendants, after the lease was executed, that the floor of the basement, which they stipulated to relay in concrete, was lower than the sewer, in consequence of which it would have been extremely difficult to install a cold storage plant, is a fact to be considered, from which it would appear that a change in the structure of the building was required before the cement work could have profitably been done; and hence the securing of a deed to the premises prior to making the improvements affords evidence of business acumen. In view of this circumstance the defendants’ offer, made about April 1, 1906, to pay the-entire consideration for the lot, does not, in our opinion, make their delay of less than eight months in complying with the terms of the agreement so unreasonable as to authorize a forfeiture of their rights under the contract.

    5. It will be remembered that a complaint having been made of the alleged unsanitary condition of the defendants’ meat market, Beutelsp'acher, a deputy health officer of Portland, visited their place of business, and, as plaintiff’s witness, testified on cross-examination that he found it as cleanly conducted as any butcher shop in the city. At one time in the summer, however, the scavenger neglected to call for the garbage on Saturday evening, and on the next day odors, arose from the refuse which, Strause testified, was immediately removed.

    6. A careful examination of the testimony convinces^ us that there was not such a violation by the defendants *149of their covenants as to authorize a cancellation of the contract, and that, in decreeing a specific performance thereof, no error was committed.

    [96 Pac. 865.]

    It follows that the decree is affirmed.

    Affirmed.

Document Info

Citation Numbers: 52 Or. 138, 94 P. 972, 1908 Ore. LEXIS 102

Judges: Bean, Moore

Filed Date: 4/14/1908

Precedential Status: Precedential

Modified Date: 11/13/2024