Adelsperger v. Elkside Development LLC , 371 Or. 61 ( 2023 )


Menu:
  • No. 12               May 18, 2023                    61
    IN THE SUPREME COURT OF THE
    STATE OF OREGON
    RON Adelsperger;
    Sally Adelsperger; Walter Arnold; Sandy Arnold;
    Larry Brewer; Marilyn Brewer;
    James Brown; Lonna Brown;
    Bill Burgess; Jane Burgess; Shirley Calkins;
    Jerry Christensen, aka Gerald Christenson;
    Cindy Christensen, aka Cynthia Evans-Christenson;
    Russell Cobb; Norma Cobb; Ron Ellis; Sallie Ellis;
    Amy Flickenger Pierpoint, aka Amy Flickenger-Pierpoint;
    Glen Pierpoint; Mike Fredrickson; Tresea Fredrickson;
    David Fulcer; Sarah Fulcer;
    Jack Gibson; Sharon Sue Gibson, aka Sue Gibson;
    Mary Gray; Rudolph Hanna; Brenda Hanna;
    Gerald Hastings, aka Jerry Hastings;
    Shirley House; Michael Huntley; Gloria Huntley;
    Rodney Hyde, aka Rod Hyde; Patricia Hyde;
    Johnnie Issacs, aka Johnnie Isaacs;
    Rowina Issacs, aka Rowena Isaacs;
    Don Johnson, aka Donald Johnson; Linda Johnson;
    Robert Kasmar; Linda Kasmar;
    Kraig Knutson; Barbara Knutson;
    Tom Kuntz; Brenda Kuntz;
    Richard Mathis; Linda Mathis;
    Gary McCord; Marie McCord;
    David McReynolds; Joseph Moore; Geraldine Moore;
    Adam Morgan; Vicky Morgan, aka Victoria Morgan;
    Thomas Noel; William Oar;
    Donald Partridge, aka Don Partridge;
    Lucille Partridge, aka Lucy Partridge;
    Craig Pedersen; Cheryl Pedersen;
    David Smith; Carol Smith;
    William Thomas, aka Bill Thomas; Jackie Thomas;
    Fred Waidtlow; Linda Waidtlow;
    Gary Wayman; Charlotte Wayman;
    David Weberg; Jeanne Weberg;
    Forrest Wheeler; and Jane Wheeler,
    Petitioners on Review,
    v.
    62                     Adelsperger v. Elkside Development LLC
    ELKSIDE DEVELOPMENT LLC,
    Successor in Interest to Osprey Point RV Park, LLC,
    and Barnett Resorts, LLC, an Oregon Limited Liability
    Company, dba Osprey Point RV Resort,
    Defendants,
    and
    Chris BARNETT
    and Stefani Barnett,
    Respondents on Review.
    (CC 19CV14756) (CA A174502) (SC S069449)
    On review from the Court of Appeals.*
    Argued and submitted January 18, 2023.
    Ronald L. Sperry III, Johnson & McKinney DBA DC
    Law, Roseburg, argued the cause and filed the brief for peti-
    tioners on review. Also on the brief was Dan G. McKinney.
    Elizabeth W. Armitage, Frohnmayer, Deatherage,
    Jamieson, Moore, Armosino & McGovern, P.C., Medford,
    argued the cause and filed the brief for respondents on
    review. Also on the briefs was Tracy M. McGovern.
    Before Flynn, Chief Justice, and Duncan, Garrett, DeHoog,
    Bushong, and James, Justices.**
    JAMES, J.
    The decision of the Court of Appeals is affirmed in part,
    affirmed in part by an equally divided court, and reversed
    in part. The judgment of the circuit court is affirmed in part,
    affirmed in part by an equally divided court, and reversed
    in part, and the case is remanded to the circuit court for
    further proceedings.
    Bushong, J. concurred in part and dissented in part and
    filed an opinion, in which Garrett and DeHoog, JJ., joined.
    ______________
    * Appeal from Coos County Circuit Court, Andrew E. Combs, Judge. 
    317 Or App 666
    , 504 P3d 1 (2022).
    ** Nelson, J., resigned February 25, 2023, and did not participate in the
    decision of this case.
    Cite as 
    371 Or 61
     (2023)   63
    64                       Adelsperger v. Elkside Development LLC
    JAMES, J.
    This case comes to us upon the grant of summary
    judgment. Elkside Development LLC (Elkside) owned and
    operated the Osprey Point RV Resort in Lakeside, Oregon.
    Part of Elkside’s business model involved selling member-
    ship contracts that conferred free use of the campground,
    among other benefits. In April 2017, Barnett Resorts, LLC,
    an Oregon limited liability company operated by member-
    managers Stefani Barnett and Chris Barnett, purchased
    Elkside. Shortly after the purchase, Stefani Barnett and
    Chris Barnett sent a letter to all campground members,
    identifying them as “owners” of the resort, and indicating
    that they would not honor Elkside’s membership contracts.
    Plaintiffs—a group of 71 people who, collectively, were
    party to 39 membership contracts with Elkside—brought
    suit alleging a variety of claims against Stefani Barnett
    and Chris Barnett individually, and against the company,
    Barnett Resorts, LLC. Three of those claims have formed
    the basis of the parties’ arguments on appeal. For our pur-
    poses, they can be categorized as (1) a breach of contract
    claim; (2) an intentional interference with contract claim;
    and (3) a statutory claim of elder abuse, based on the fact
    that the majority of the membership contracts had been held
    by plaintiffs over the age of 65.1
    As to the claims against Stefani Barnett and Chris
    Barnett individually, the trial court granted summary judg-
    ment for defendants, relying on ORS 63.165 and our opinion
    in Cortez v. Nacco Materials Handling Group, 
    356 Or 254
    ,
    280, 337 P3d 111 (2014).2 ORS 63.165(1) provides:
    “The debts, obligations and liabilities of a limited liabil-
    ity company, whether arising in contract, tort or otherwise,
    are solely the debts, obligations and liabilities of the limited
    liability company. A member or manager is not personally
    1
    The other claims are variations, or attendant to, the three main categories
    of claims. For example, the first claim for relief seeks a declaratory judgment as
    to the existence of a contract. The third claim seeks the appointment of a trustee.
    2
    The trial court allowed a breach of contract claim, and an elder abuse
    claim, against Barnett Resorts, LLC, to proceed, and the jury returned a verdict
    in favor of plaintiffs. Those claims form the basis of another pending appeal—
    Adelsperger v. Elkside Development LLC, 
    322 Or App 809
    , 523 P3d 142 (2022).
    Cite as 
    371 Or 61
     (2023)                                               65
    liable for a debt, obligation or liability of the limited liabil-
    ity company solely by reason of being or acting as a member
    or manager.”
    Plaintiffs appealed, arguing that the trial court
    erred in its understanding of ORS 63.165. Plaintiffs argued,
    in part, that whether ORS 63.165 shielded the Barnetts
    from liability required considering whether their actions
    were entirely in support of the LLC, or whether they were,
    instead, in furtherance of a non-LLC individual motive. The
    Court of Appeals heard oral argument, and then affirmed
    without opinion. We allowed review and now reverse in part
    the decision of the Court of Appeals and the judgment of
    the trial court: Specifically, we reverse as to the elder abuse
    claim, affirm as to the breach of contract claim, and affirm
    the intentional interference claim by an equally divided
    court.
    OVERVIEW
    The contours of summary judgment review are set
    by the operative complaint and the specific arguments for
    summary judgment advanced by a party. Under ORCP 47 C,
    the party opposing summary judgment has the burden of
    producing evidence on any issue “raised in the motion” as
    to which that party would have the burden of persuasion
    at trial. Two Two v. Fujitec America, Inc., 
    355 Or 319
    , 324,
    325 P3d 707 (2014). But a party does not have the burden
    of producing evidence on an issue that is not raised in the
    motion. 
    Id. at 325
    .
    Once the parameters of what is, and is not, at issue
    in summary judgment are identified, we will affirm the trial
    court’s judgment if we agree that “there is no genuine issue
    as to any material fact and * * * the moving party [was] enti-
    tled to a judgment as a matter of law.” ORCP 47 C; see also
    Robinson v. Lamb’s Wilsonville Thriftway, 
    332 Or 453
    , 455, 31
    P3d 421 (2001) (describing that standard on review). No issue
    of material fact exists if, viewing the evidence in the light
    most favorable to the nonmoving party—here, plaintiffs—
    “no objectively reasonable juror could return a verdict for
    the adverse party on the matter that is the subject of the
    motion for summary judgment.” ORCP 
    47 C. 66
                     Adelsperger v. Elkside Development LLC
    In accord with that standard, we begin by setting
    forth, in greater detail, plaintiffs’ allegations in the first
    amended complaint, as well as defendants’ framing of the
    basis for summary judgment. Plaintiffs’ second claim for
    relief alleged a breach of contract claim against Elkside,
    Barnett Resorts, LLC, and the Barnetts individually, claim-
    ing that they had “breached the membership camping con-
    tract and guarantee with each Plaintiff by denying Plaintiffs
    the contractual right to the use of the Resort facilities set
    forth in the membership camping contracts.” They further
    alleged that Elkside “breached the contracts by assigning
    its obligations to [Barnett Resorts, LLC] without permission
    or release from Plaintiffs. [Barnett Resorts, LLC] thereafter
    denied the Plaintiffs’ rights under the membership camping
    contracts.”
    Plaintiffs’ fourth claim for relief alleged a statutory
    elder abuse claim, asserting that both the Barnetts individ-
    ually, as well as Barnett Resorts, LLC, had a “responsibil-
    ity to honor the membership campground contracts of the
    Elderly Plaintiffs” and had “acquired a property right of the
    Elderly Plaintiffs (ORS 124.110[(1)](a)) or [held] in trust the
    annual dues and property rights of the Elderly Plaintiffs
    (ORS 124.110[(1)](b)).” The claim then alleged that both
    Barnett Resorts, LLC and the individual defendants had
    “acted in bad faith in refusing to honor the property rights
    and knew or should have known that the Elderly Plaintiffs
    had the rights in the membership camping contracts and
    the rights to use the Resort.”
    Finally, plaintiffs’ sixth claim for relief alleged
    intentional interference with contractual relations against
    both Barnett Resorts, LLC and the Barnetts individually.
    That claim was specifically raised as an alternative claim
    to the breach of contract, “in the event Defendants Barnett
    are found not to be a contractual successor to [Elkside] and
    bound as a contracting party to the membership camping
    contracts.” In that alternative, plaintiffs alleged that the
    Barnetts intentionally interfered with the contractual rela-
    tionship “between Plaintiffs and [Elkside] by acquiring the
    Resort with knowledge of the existence of the membership
    camping contracts and thereafter denying the Plaintiffs
    access to Resort facilities.”
    Cite as 
    371 Or 61
     (2023)                                           67
    Defendants’ arguments for summary judgment were
    undifferentiated by the individual claims in the complaint.
    Instead, defendants raised a unitary argument, against all
    claims and on behalf of all defendants equally, that primar-
    ily relied on the assertion that defendants had purchased
    property, not a business. Defendants challenged the recor-
    dation of the membership contracts, arguing that alleged
    failure to record prevented the contracts from encumbering
    the property. Without recordation, defendants argued, the
    membership camping contracts were retail installment con-
    tracts pursuant to ORS 94.989(2). Defendants argued that
    they had not purchased the contracts, only the land of the
    mobile home park. Those arguments encompassed almost
    the entirety of the summary judgment motion but were not
    the basis for the trial court’s ruling and are not the subject
    of this appeal.
    The argument that did form the basis of the trial
    court’s partial grant of summary judgment occurs in the
    final two paragraphs of the summary judgment motion:
    “Members of a limited liability company are personally lia-
    ble only to the same extent and in the same manners as
    shareholders of a professional corporation. ORS 63.074(2).
    A member is not liable for the acts or debts of an LLC
    merely by reason of being a member. ORS 60.151(2).
    “Plaintiffs have asserted claims against Barnett
    Resorts, LLC, but also against Chris and Stefani Barnett
    as the owners and operators of Barnett Resorts. It is axiom-
    atic that an LLC owner or member is not liable for a claim
    against the LLC. Indeed, the purpose of organizing and
    carrying out business in an LLC, rather than some other
    form, is to avoid such liability. Barnett Resorts, LLC is the
    sole owner and operator of Osprey Point. Chris and Stefani
    Barnett are entitled to judgment as a matter of law.”
    As to the claims against the Barnetts individually,
    the trial court granted summary judgment for defendants,
    relying on ORS 63.165 and our opinion in Cortez, 
    356 Or at 280
    . As the trial court reasoned:
    “The general rule regarding the liability of members
    and managers of limited liability companies in Oregon was
    explained in Cortez[, 
    356 Or at 280
    ,] as follows:
    68                   Adelsperger v. Elkside Development LLC
    “ ‘ORS 63.165 immunizes members and managers of an
    LLC from vicarious liability for the debts, obligations,
    and liabilities of that LLC. LLC members and manag-
    ers, however, remain personally liable for their acts and
    omissions to the extent those acts or omissions would
    be actionable against the member or manager if that
    person were acting in an individual capacity.’
    “The court finds in the instant matter that of the six
    claims alleged by plaintiffs’ in their first amended com-
    plaint, that none of those claims allege acts or omissions
    by defendants Chris Barnett or Stefani Barnett that would
    provide a basis for imposing personal liability on either.
    Chris Barnett and Stefani Barnett formed Barnett Resorts,
    LLC on February 27, 2017; Barnett Resorts LLC purchased
    the property on April 28, 2017; and Barnett Resorts LLC
    has been the owner of the property ever since. For these
    reasons, the court finds that defendants Chris Barnett and
    Stefani Barnett are entitled to summary judgment on all of
    plaintiffs’ claims.”
    On appeal, defendants raise a number of argu-
    ments in defense of the trial court’s ruling; however, many
    of those arguments are unpreserved. Defendants argue that
    plaintiffs’ claims for elder abuse fail because defendants did
    not withhold money or property under ORS 124.110(1)(a)
    or (b). That argument was developed at trial, on the claims
    against Barnett Resorts, LLC that survived, but that was
    not an argument before the summary judgment court.
    Similarly, defendants argue that, as to the intentional
    interference claim, plaintiffs failed to provide evidence of
    an improper means or motive. That also was not an argu-
    ment before the summary judgment court. As set forth
    above, the arguments on summary judgment were limited,
    and the sole basis of the court’s grant of summary judgment
    was ORS 63.165. Accordingly, that is the singular issue we
    address.
    With that background now set, we turn to Cortez,
    where we noted that the Oregon legislature patterned ORS
    63.165 off the Uniform Limited Liability Company Act
    (ULLCA) (1996) and adopted verbatim subsections 303(a)
    and (b) from that uniform act. We noted that a comment to
    that section included the following statement:
    Cite as 
    371 Or 61
     (2023)                                          69
    “ ‘A member or manager is responsible for acts or omissions
    to the extent those acts or omissions would be actionable in
    contract or tort against the member or manager if that per-
    son were acting in an individual capacity. Where a mem-
    ber or manager delegates or assigns the authority or duty
    to exercise appropriate company functions, the member or
    manager is ordinarily not personally liable for the acts or
    omissions of the officer, employee, or agent [of the LLC] if
    the member or manager has complied with the duty of care
    set forth in Section 409(c).’ ”
    Cortez, 
    356 Or at
    267-68 (citing ULLCA § 303 comment
    (1996) (brackets in Cortez)). Accordingly, we held that “mem-
    bers and managers remain personally liable for the actions
    that they take on behalf of an LLC to the same extent that
    they would be liable ‘if [they] were acting in an individual
    capacity.’ ” Id. at 268 (brackets in Cortez). We therefore turn
    to applying that principle to each of the three claims at issue
    here. We begin with plaintiffs’ elder abuse claim, then pro-
    ceed to consider the breach of contract claim, and conclude
    with the intentional interference with contract claim.
    ELDER ABUSE
    ORS 124.100(2) provides that “[a] vulnerable person
    who suffers injury, damage or death by reason of physical
    abuse or financial abuse may bring an action against any
    person who has caused the physical or financial abuse or
    who has permitted another person to engage in physical or
    financial abuse.” As used in the Oregon Revised Statutes,
    the term “person” is generally defined to include “individ-
    uals, corporations, associations, firms, partnerships, lim-
    ited liability companies and joint stock companies.” ORS
    174.100(7) (so providing unless context or specific statutory
    definition provides otherwise). By its terms, then, an action
    for elder abuse can lie against a corporate abuser, as well as
    those people who have “permitted” the corporation to abuse
    the elderly person.
    To what extent, if at all, ORS 63.165 operates to
    preclude a claim for elder abuse, under ORS 124.100(2), is a
    question of statutory interpretation. We approach such ques-
    tions with the “paramount goal” to discern the intention of
    the legislature. State v. Gaines, 
    346 Or 160
    , 171, 206 P3d
    70                 Adelsperger v. Elkside Development LLC
    1042 (2009). In pursuing that goal, we give primary weight
    to the text and context of the disputed statutory terms. 
    Id.
    As we emphasized in Gaines, “there is no more persuasive
    evidence of the intent of the legislature than the words by
    which the legislature undertook to give expression to its
    wishes.” 
    Id.
     (internal quotation marks omitted).
    ORS 124.100(2), by its terms, contemplates direct
    liability in tort for an individual who permits another—
    including a corporation—to commit elder abuse. The parties
    have provided us no legislative history that would contra-
    dict the plain text, and our review of the history of ORS
    124.100(2) shows no indication that the legislature sought to
    exclude from direct liability those who permitted abuse by a
    corporate actor.
    As part of construing the text and context of a stat-
    ute, we also look to case law construing the statute at issue.
    See Sherman v. Dept. of Human Services, 
    368 Or 403
    , 411-
    12, 492 P3d 31 (2021) (so demonstrating). In imposing direct
    liability for those who permit another to commit elder abuse,
    ORS 124.100(2) bears similarity to the statute at issue in
    Cortez. There, we considered a workplace safety statute that
    imposed obligations on a person who “retains the right to
    control the manner or method in which the risk-producing
    activity was performed.” 
    356 Or at 273
    . The plaintiff in
    Cortez was injured while working for a lumber mill owned
    by an LLC and sued the member-manager of the LLC,
    arguing that the member-manager was a person subject to
    the statute. 
    Id. at 256
    . The member-manager argued that,
    under ORS 63.165(1), it could not be held personally liable
    for harm arising out of the LLC’s business operations based
    on “merely having the authority to require the LLC to pre-
    vent a workplace accident.” 
    Id. at 263
    .
    We held that ORS 63.165(1) did not shield the
    member-manager of an LLC from liability for failing to sat-
    isfy the statutory safe-workplace obligations. We reasoned
    that “ORS 63.165(1) immunizes [the LLC member] only
    from vicarious liability for the LLC’s obligations,” and not
    from liability for its own omissions if, having retained con-
    trol, the person failed to provide, or to require the LLC to
    provide, a safe workplace. 
    Id. at 264
    .
    Cite as 
    371 Or 61
     (2023)                                                    71
    Later, in Kinzua Resources v. DEQ, 
    366 Or 674
    , 468
    P3d 410 (2020), we considered two additional statutes—
    ORS 459.205 and ORS 459.268—which imposed obligations
    on the permit holder for the proper closure of a landfill. We
    construed the landfill permit statutes with ORS 63.165(1)
    and concluded that individual liability for LLC member-
    managers was permissible:
    “The commission contends that ORS 63.165(1) permits it
    to impose liability based on [the] petitioners’ own failure
    to perform obligations with which they were individu-
    ally charged in their capacity as persons ‘controlling’ the
    landfill.
    “We agree with the commission that ORS 459.205 and
    ORS 459.268 impose obligations directly on each person
    ‘controlling’ a landfill and that liability for the person’s own
    failure to satisfy those obligations is direct liability, which
    ORS 63.165(1) does not prevent.”
    Kinzua Resources, 
    366 Or at 687
    .
    Like the statutes at issue in Cortez and Kinzua
    Resources, ORS 124.100(2) creates liability for those that
    perpetrate elder abuse, as well as those who permit others
    to perpetrate elder abuse.3 That liability is not vicarious; it
    is direct. In such an instance, ORS 63.165(1) is not a bar to
    asserting a claim for a statutory violation of ORS 124.100(2)
    against a member-manager of an LLC, when the LLC is
    alleged to be the entity that directly perpetrated the elder
    abuse. The trial court erred in granting summary judgment
    as to this claim.
    BREACH OF CONTRACT
    We turn now to plaintiffs’ second claim for relief—
    breach of contract. Here, we agree with the trial court
    that there is no evidence that the Barnetts, acting in their
    individual capacity, breached the contract. As we explain,
    the trial court was therefore correct to preclude this claim
    according to ORS 63.165.
    3
    We are not called upon here to delineate the boundaries of what constitutes
    permission under the statute.
    72                 Adelsperger v. Elkside Development LLC
    It is well established, both in Oregon and elsewhere,
    that generally speaking, but with some exceptions, privity
    of contract is an essential prerequisite to a breach of con-
    tract claim. See, e.g., Davis v. Homasote Company, 
    281 Or 383
    , 386, 
    574 P2d 1116
     (1978); DAFCO LLC v. Stewart Title
    Guar. Co., 
    156 Idaho 749
    , 754, 331 P3d 491, 496 (2014) (“It
    is axiomatic in the law of contract that a person not in priv-
    ity cannot sue on a contract.” (Quoting Wing v. Martin, 
    107 Idaho 267
    , 272, 
    688 P2d 1172
    , 1177 (1984).)); Danielkiewicz
    v. Whirlpool Corp., 426 F Supp 3d 426, 432 (ED Mich 2019)
    (citing the same); Yucyco, Ltd. v. Republic of Slovenia, 984 F
    Supp 209, 215 (SD NY 1997) (stating that a plaintiff “may
    not assert a cause of action to recover damages for breach
    of contract against a party with whom it is not in privity” of
    contract); Cent. Con. Co. v. Paradise Valley Utility, 
    634 P2d 346
    , 348 (Wyo 1981) (“[P]rivity of contract is an essential
    element [for] a cause of action on a contract[.]” (Internal quo-
    tation marks omitted.)).
    Here, the parties do not dispute that the Barnetts,
    individually, are not signatories to the contracts at issue. The
    membership contracts existed between Elkside and plaintiffs.
    The purchase of Osprey Point was accomplished through a
    contract between Elkside and Barnett Resorts, LLC. To the
    extent that the Barnetts took any action in that contract for-
    mation, they did so solely as agents of the LLC. Accordingly,
    and as the parties effectively acknowledged at oral argument,
    the Barnetts, individually, are not in privity with any of the
    plaintiffs or Elkside as to the contracts at issue.
    Under ORS 63.165, member-managers remain per-
    sonally liable for their acts or omission only to the extent
    that “those acts or omissions would be actionable against
    the member or manager if that person were acting in an
    individual capacity.” Cortez, 
    356 Or at 280
    . That concept pre-
    sumes that “those acts or omissions” could have been under-
    taken by a person in their individual capacity. In this case,
    the Barnetts lack privity with Elkside or plaintiffs. Absent
    certain circumstances not present here, such as issues of
    implied warranty, a nonparty to a contract cannot bring
    suit for breach of that contract, and in reverse, parties to a
    contract cannot bring suit against a third-party for breach
    of the contract. Thus, as alleged by plaintiffs, any “acts or
    Cite as 
    371 Or 61
     (2023)                                   73
    omissions” by the Barnetts with respect to the contract could
    not possibly have been undertaken in their individual capac-
    ities. As such, the trial court did not err in granting sum-
    mary judgment as to the breach of contract claim against
    defendants Stefani Barnett and Chris Barnett individually.
    INTENTIONAL INTERFERENCE
    Finally, we turn to plaintiffs’ sixth claim, inten-
    tional interference with contractual relations. “A mere
    breach of contract cannot be sued on as a tort, but for tor-
    tious acts, independent of the contract, a man may be sued
    in tort, though one of the consequences is a breach of his
    contract.” Harper v. Interstate Brewery Co., 
    168 Or 26
    , 37-38,
    
    120 P2d 757
     (1942) (citing Stock v. City of Boston, 149 Mass
    410, 
    21 NE 871
    , 872, 14 Am St Rep 430 (1889)). Intentional
    interference with economic or contractual relations is the
    name we give to tortious conduct, independent of a contract,
    that brings about a breach of that contract.
    To state a claim for intentional interference with
    economic or contractual relations, a party must allege each
    of the following elements: (1) the existence of a professional
    or business relationship, (2) intentional interference by
    the third party with the relationship, (3) that the inter-
    ference was accomplished through improper means or for
    an improper purpose, (4) the interference caused damage
    to the economic relationship, and (5) damages. McGanty v.
    Staudenraus, 
    321 Or 532
    , 535, 
    901 P2d 841
     (1995); Straube
    v. Larson, 
    287 Or 357
    , 360-61, 
    600 P2d 371
     (1979); Wampler
    v. Palmerton, 
    250 Or 65
    , 73-76, 
    439 P2d 601
     (1968); see Lewis
    v. Oregon Beauty Supply Co., 
    302 Or 616
    , 621, 
    733 P2d 430
    (1987), overruled in part on other grounds by McGanty, 
    321 Or 532
     (complaint must allege “[e]ither the pursuit of an
    improper objective of harming plaintiff or the use of wrong-
    ful means that in fact cause injury to plaintiff’s contractual
    or business relationships”); see also Sheets v. Knight, 
    308 Or 220
    , 237, 
    779 P2d 1000
     (1989), overruled in part on other
    grounds by McGanty, 
    321 Or 532
     (holding same); Top Service
    Body Shop v. Allstate Ins. Co., 
    283 Or 201
    , 205, 
    582 P2d 1365
    (1978) (holding same).
    In applying that rule here, it is important to call
    attention to how the claim was pleaded in this instance.
    74                 Adelsperger v. Elkside Development LLC
    Plaintiffs asserted an intentional interference claim as an
    alternative to their breach of contract claim. As plaintiffs
    stated in the first amended complaint, the claim was trig-
    gered only “in the event Defendants Barnett are found not
    to be a contractual successor to [Elkside] and bound as a
    contracting party to the membership camping contracts.”
    As such, the claim would only exist if it was determined
    that Barnett Resorts, LLC was not a successor in interest to
    Elkside and did not assume the obligations of Elkside’s con-
    tracts with the plaintiffs. Further, plaintiffs did not allege
    that the Barnetts, individually, had interfered with Barnett
    Resorts, LLC’s contract. Rather, the claim asserted that
    Barnett Resorts, LLC, and the Barnetts individually, inter-
    fered as third parties to a contract between plaintiffs and
    Elkside. That interference was alleged to be accomplished
    by “acquiring the Resort with knowledge of the existence of
    the membership camping contracts and thereafter denying
    the Plaintiffs access to Resort facilities.”
    So framed, ORS 63.165 is not an obvious bar.
    Both individuals and corporations can be liable for inten-
    tional interference in economic and contractual relations.
    In the situation presented here, when both the LLC and its
    member-manager are alleged to have acted tortiously vis-à-
    vis a contract between third parties, the individual liability
    of the member-manager under ORS 63.165 turns upon prin-
    ciples of agency—whether the member-manager acted upon
    individual motives, and for individual benefit, or merely
    acted as an agent of the corporation, in furtherance of a cor-
    porate motive. “So long as the officer or employee acts within
    the general range of his authority intending to benefit the
    corporation, the law identifies his actions with the corpora-
    tion.” Wampler, 
    250 Or at 76-77
    .
    Before the trial court and the Court of Appeals,
    plaintiffs argued that the trial court erred in failing to con-
    sider whether a genuine issue of material fact existed as
    to whether the Barnetts interfered in furtherance of per-
    sonal motives, or merely in their capacity as agents of the
    LLC. Plaintiffs were correct. The trial court’s grant of sum-
    mary judgment—based solely on ORS 63.165, without con-
    sideration of whether the Barnetts were acting within their
    authority for the benefit of the corporation, or for individual
    Cite as 
    371 Or 61
     (2023)                                   75
    motives—was misplaced, and the trial court erred. See, e.g.,
    Bova v. City of Medford, 
    262 Or App 29
    , 43, 324 P3d 492,
    rev den, 
    356 Or 516
     (2014) (reversing grant of summary
    judgment based on an incorrect statutory interpretation).
    Our holding here is narrow and confined to the par-
    ticularities of the parties’ arguments and the trial court’s
    reasoning. ORS 63.165 was the argument raised in defen-
    dants’ summary judgment motion as to the elder abuse
    and intentional interference claim, and the sole basis of
    the trial court’s ruling. No opinion is offered as to whether
    summary judgment might be appropriate on some alter-
    native grounds. As discussed, the alternative arguments
    presented on appeal were not before the trial court, and no
    party has invoked a “right for the wrong reasons” rationale.
    See Outdoor Media Dimensions Inc. v. State of Oregon, 
    331 Or 634
    , 659-60, 20 P3d 180 (2001) (setting out conditions
    for affirmance under a “right for the wrong reasons” basis);
    State v. Rogers, 
    330 Or 282
    , 295, 4 P3d 1261 (2000) (“The
    ‘right for the wrong reason’ principle establishes that appel-
    late courts may examine legal arguments not relied on by a
    trial court to determine if those arguments provide a basis
    for affirmance.”). The foregoing analysis is simply that, on
    this record, ORS 63.165 did not bar plaintiffs’ claim such
    that summary judgment was required.
    It is worth noting that the claims that survived sum-
    mary judgment here, against Barnett Resorts, LLC, pro-
    ceeded through verdict, and that verdict is now the subject
    of a different appellate proceeding—Adelsperger v. Elkside
    Development LLC, 
    322 Or App 809
    , 523 P3d 142 (2022). It is
    certainly possible that the ultimate resolution of the issues
    presented in that case may ultimately affect the claims at
    issue here. As the dissent notes, whether this decision will
    have a meaningful affect upon the parties is a prudential
    concern. See, e.g., City of Damascus v. State of Oregon, 
    367 Or 41
    , 68 n 13, 472 P3d 741 (2020) (“We express no opinion
    here regarding the circumstances in which advisory opin-
    ions may or may not be unconstitutional * * *. The point is
    that there are prudential and jurisprudential reasons to
    avoid unnecessarily deciding legal issues that may be pre-
    sented in a case, if the case can be appropriately resolved on
    more limited grounds.”). However, at this point in time, that
    76                       Adelsperger v. Elkside Development LLC
    case has not reached finality, and we will not prognosticate
    its future. The dissent would hold the decision in this case,
    to avoid “piecemeal litigation of related claims.” However, it
    is not prudent to intentionally delay issuance of a decision
    in this matter to await an unknown outcome when no lower
    court has consolidated the cases, and no party has moved
    for the cases to be consolidated, nor asked this court to hold
    a decision in abeyance. The ultimate applicability of that
    other case to the claims here is left to the sound wisdom of
    the trial court upon remand.
    The decision of the Court of Appeals is affirmed
    in part, affirmed in part by an equally divided court,
    and reversed in part. The judgment of the circuit court is
    affirmed in part, affirmed in part by an equally divided
    court, and reversed in part, and the case is remanded to the
    circuit court for further proceedings.
    BUSHONG, J., concurring in part, dissenting in
    part.
    I agree with the majority’s disposition of the elder
    abuse and breach of contract claims, and I join in the major-
    ity opinion on those claims.1 I write separately, however, to
    explain my preferred approach as a procedural matter as
    to the elder abuse and intentional interference claims, and
    relatedly, why I disagree with the majority’s disposition of
    the intentional interference claim. I would await the final
    appellate disposition of Adelsperger v. Elkside Development
    LLC, 
    322 Or App 809
    , 523 P3d 142 (2022) (Adelsperger II),
    recently decided by the Court of Appeals and involving simi-
    lar claims from these same plaintiffs,2 before addressing the
    elder abuse and intentional interference claims in this case.
    In my view, we should not be addressing those claims at
    this stage of the proceeding, because they are intertwined
    with the issues decided in Adelsperger II. The final disposi-
    tion of those issues may, in the end, transform the majority
    1
    For ease of reference, I use the term “majority opinion” throughout this
    opinion in referring to the opinion authored by Justice James. However, that
    opinion is not truly a “majority” opinion as to the intentional interference claim,
    which we are affirming by an equally divided court.
    2
    The Court of Appeals denied petitions for reconsideration in Adelsperger II
    on March 31, 2023. On May 5, plaintiffs petitioned this court for review of the
    Court of Appeals’ disposition of their elder abuse claim.
    Cite as 
    371 Or 61
     (2023)                                                   77
    opinion into an advisory opinion that has no practical effect
    on the parties. At the very least, deciding those issues now
    unnecessarily continues the piecemeal litigation of related
    claims.3
    In reversing the trial court’s summary judgment
    ruling on the two noted claims against defendants Stefani
    and Chris Barnett (the Barnetts), the majority opinion con-
    cludes that ORS 63.165 does not shield them individually
    from liability for elder abuse or intentional interference
    with contract. On the elder abuse claim, the majority opin-
    ion concludes that ORS 63.165 is not a bar to asserting the
    claim against the Barnetts individually simply because the
    entity alleged to have “directly perpetrated the elder abuse”
    is the LLC and not its individual members. 371 Or at 72.
    But, in Adelsperger II—which involves the same claims as
    asserted by these same plaintiffs against Barnett Resorts,
    LLC—the Court of Appeals determined that plaintiffs had
    failed to prove at trial that the LLC had perpetrated elder
    abuse. Adelsberger II, 
    322 Or App at 827
    .
    Similarly, the majority opinion acknowledges that
    the intentional interference claim “would only exist if it was
    determined that Barnett Resorts, LLC was not a successor
    in interest to Elkside [Resorts LLC] and did not assume the
    obligations of Elkside’s contracts with the plaintiffs.” 371 Or
    at 74. But again, in Adelsperger II, the Court of Appeals con-
    cluded that sufficient evidence at trial had supported the
    jury’s conclusion that Barnett Resorts, LLC had been a suc-
    cessor in interest and thus had assumed the obligations of
    Elkside’s contracts with the plaintiffs. 
    322 Or App at 819-20
    .
    If the Court of Appeals’ resolution in Adelsperger II
    of those claims as to the LLC becomes final, then the major-
    ity opinion’s resolution of the issues in this case—whether
    the trial court properly granted summary judgment to the
    Barnetts under ORS 63.165 on those same two claims—
    would amount to an advisory opinion that has no practical
    effect on the parties. And if the Court of Appeals’ resolution
    of those claims in Adelsperger II does not become final—that
    is, if we allow plaintiffs’ pending petition for review—then
    3
    My views expressed in this opinion do not apply to the breach of contract
    claim addressed in the majority opinion.
    78                 Adelsperger v. Elkside Development LLC
    deciding now that the Barnetts might be liable on those
    claims and deciding later whether the Court of Appeals cor-
    rectly resolved those claims against the LLC would continue
    the piecemeal litigation of these related claims.
    We typically seek “to avoid piecemeal litigation of
    multiple claims likely to involve related facts.” Thompson v.
    Coughlin, 
    329 Or 630
    , 637, 
    997 P2d 191
     (2000). And there are
    prudential reasons to avoid unnecessarily deciding issues
    that may not have any practical effect on the parties. See
    City of Damascus v. State of Oregon, 
    367 Or 41
    , 68 n 13, 472
    P3d 741 (2020) (“We express no opinion here regarding the
    circumstances in which advisory opinions may or may not be
    unconstitutional[.] * * * Our point is that there are prudential
    and jurisprudential reasons to avoid unnecessarily deciding
    legal issues that may be presented in a case, if the case can
    be appropriately resolved on more limited grounds.”).
    The majority opinion acknowledges that final res-
    olution of the claims against the LLC may affect the ulti-
    mate disposition of the claims against the Barnetts. 371 Or
    at 75. The majority opinion also acknowledges that, depend-
    ing upon how the claims against the LLC are ultimately
    resolved, today’s decision may not have any meaningful
    effect on the parties. Id. at 75-76. Nevertheless, it concludes
    that it would not be prudential to await the final resolution
    of the claims against the LLC. Id.
    The majority justifies that conclusion by treating
    Adelsperger II as a different “case” that has not been consol-
    idated with this case, concluding that the “ultimate applica-
    bility of that other case” to the claims here should be left to
    the trial court. Id. at 76. But there is no “other case”; there
    is one action commenced by filing a complaint that ulti-
    mately resulted in splintered appeals, each of which were
    assigned different case numbers. See ORCP 3 (“[A]n action
    shall be commenced by filing a complaint with the clerk of
    the court.”). The claims addressed by the majority opinion
    and by the Court of Appeals in Adelsperger II were asserted
    in the same complaint filed in the same action.
    I suggest that, under the circumstances, the pru-
    dential decision would be to await final resolution of the
    Cite as 
    371 Or 61
     (2023)                                     79
    claims against the LLC, and then resolve all the remaining
    claims asserted in this action at once.
    In addition, I disagree with the majority’s disposi-
    tion of the intentional interference claim for a reason that
    further highlights why we should not be deciding that alter-
    native claim at all. The majority opinion called attention to
    how this claim was pleaded—as an alternative to the breach
    of contract claim—and framed the issue as whether ORS
    63.165 barred a claim asserting that the Barnetts individu-
    ally (and the LLC) interfered with contracts between plain-
    tiffs and Elkside. 371 Or at 74.
    The majority then concludes that ORS 63.165 is not
    “an obvious bar” to the claim because, under Wampler v.
    Palmerton, 
    250 Or 65
    , 74-77, 
    439 P2d 601
     (1968), the claim
    hinges on whether “the Barnetts were acting within their
    authority for the benefit of the corporation, or for individ-
    ual motives[.]” 371 Or at 74-75; see also id. at 74 (citing test
    under Wampler); id. (applying test).
    However, the circumstances presented here are dif-
    ferent from those presented in Wampler, and the majority’s
    application of the Wampler test for determining individ-
    ual liability of corporate officials in this context is flawed.
    The plaintiff in Wampler alleged that the individual defen-
    dants—the president and a business advisor of Diamond
    Lake Lumber Company (Diamond Lake)—were liable for
    interfering with a logging contract between the plaintiff
    and Diamond Lake. A jury ruled in favor of the plaintiff,
    and the individual defendants appealed. 
    250 Or at 67-68
    .
    This court first noted that, “[i]n the usual interfer-
    ence with a contract situation, the person interfering is a
    complete stranger to the contractual relationship.” 
    Id. at 74
    .
    But Wampler added a “complicating ingredient * * * where
    the party induced to breach its contract is a corporation and
    the third person who induces the breach is not a stranger,
    but is a person who, by reason of his position with the corpo-
    ration, owes a duty of advice and action to the corporation.”
    
    Id.
     The interest protected by an interference with contract
    claim “is the interest of the plaintiff in not having his con-
    tract rights interfered with by intermeddling strangers.”
    80                 Adelsperger v. Elkside Development LLC
    
    Id. at 77
    . Thus, “so long as the person inducing the breach
    of a corporate contract is an officer or employe[e] acting for
    the benefit of the corporation and within the scope of his
    authority, the plaintiff cannot show that this interest was
    invaded and therefore cannot maintain an interference with
    contract action.” 
    Id.
    “On the other hand,” the Wampler court explained,
    “there is no reason to protect corporate officers or employe[e]s
    who authorize, direct and participate in tortious conduct by
    their corporate principal.” 
    Id.
     “If the corporation commits a
    tort as a result of such intentional action on the part of its
    officers or employe[e]s, these agents are also responsible.”
    
    Id.
     Thus, whether there was a jury question as to the lia-
    bility of the individual defendants in Wampler depended on
    “whether there [was] evidence that defendants were guilty
    of engaging in tortious conduct upon behalf of the corpora-
    tion.” 
    Id. at 78
    . The Wampler court reviewed the evidence
    at trial, noting first that “there is no direct evidence of any
    bad motive or intent” in almost all cases “in which intent
    is in issue.” 
    Id. at 80
    . As a result, it was necessary for the
    court “to ascertain whether there [was] sufficient circum-
    stantial evidence” of bad motive or intent. 
    Id.
     Finding none
    in the trial court record, the court concluded that “[t]he trial
    court erred in failing to grant the defendants’ motion for a
    directed verdict.” 
    Id. at 82
    .
    Cases decided after Wampler have made it clear
    that an intentional interference with contract claim requires
    proof of “the pursuit of an improper objective of harming
    plaintiff or the use of wrongful means that in fact cause
    injury to plaintiff’s contractual or business relationships.”
    Lewis v. Oregon Beauty Supply Co., 
    302 Or 616
    , 621, 
    733 P2d 430
     (1987); see also Sheets v. Knight, 
    308 Or 220
    , 237,
    
    779 P2d 1000
     (1989), abrogated in part on other grounds by
    McGanty v. Staudenraus, 
    321 Or 532
    , 
    901 P2d 841
     (1995)
    (plaintiff must plead and prove that defendant, “either with
    an improper objective or through improper means, purpose-
    fully interfered with the plaintiff’s contractual relation-
    ship with some third party, thereby causing the plaintiff
    damage”). Thus, under Wampler and subsequent cases, for
    a corporate officer to be liable for intentionally interfering
    with a contract entered into by the corporation, the officer
    Cite as 
    371 Or 61
     (2023)                                   81
    must have authorized, directed, and participated in the cor-
    poration’s tortious conduct, that is, conduct that not only
    amounted to a breach of contract but that was taken for
    improper motives or through improper means.
    This case is different from Wampler because plain-
    tiffs’ claim here is that the Barnetts may be individually
    liable for interfering with contracts between plaintiffs and
    Elkside. In other words, this case involves “the usual inter-
    ference with contract situation” where the persons alleged to
    have interfered with the contract—here, the Barnetts—are
    strangers to the contractual relationship with which they
    allegedly interfered. Thus, it is not clear that Wampler even
    applies here. Moreover, even assuming that Wampler is on
    point, applying the Wampler test would seem to require the
    court to review the summary judgment record to determine
    whether it contains direct or circumstantial evidence that
    the Barnetts acted with “bad motive or intent” in causing
    Barnett Resorts, LLC to tortiously interfere with the con-
    tracts between plaintiffs and Elkside.
    The majority opinion does not (1) explain why
    the Wampler test applies in this context; (2) explain why
    “individual motives”—not “bad motives or intent”—would
    be enough to meet the Wampler test in this context; or
    (3) review the summary judgment record to determine
    whether it contains evidence of both individual motives and
    “bad motive or intent” sufficient to avoid summary judg-
    ment. Instead, it just concludes that the trial court erred
    by granting summary judgment “without consideration of
    whether the Barnetts were acting within their authority for
    the benefit of the corporation, or for individual motives[.]”
    371 Or at 74-75.
    My disagreement with how the majority opinion
    disposes of the intentional interference claim highlights
    the reasons why we should not be reversing the trial court’s
    decision to grant summary judgment on that claim—pled as
    an alternative to plaintiffs’ breach of contract claim—at this
    stage of the proceedings. Accordingly, I dissent from that
    part of the majority opinion.
    Garrett and DeHoog, JJ., join in this concurring
    and dissenting opinion.
    

Document Info

Docket Number: S069449

Citation Numbers: 371 Or. 61

Judges: James

Filed Date: 5/18/2023

Precedential Status: Precedential

Modified Date: 10/24/2024