Northwest and Intermountain Power Producers v. PGE ( 2020 )


Menu:
  •                                        110
    Argued and submitted September 24, 2019, petition for judicial review dis-
    missed as moot December 23, 2020
    NORTHWEST AND INTERMOUNTAIN
    POWER PRODUCERS COALITION,
    Community Renewable Energy Association,
    Renewable Energy Coalition, and
    The Public Utility Commission of Oregon,
    Respondents,
    v.
    PORTLAND GENERAL
    ELECTRIC COMPANY,
    Petitioner.
    Public Utility Commission of Oregon
    UM1805; A167707
    480 P3d 981
    In 2005, the Public Utility Commission of Oregon (PUC) issued Order 05-584.
    In that order, it adopted a policy requiring standard contracts for purchase of
    electricity from qualifying facilities to, among other things, set fixed prices for
    the purchase of electricity for the first 15 years of every 20-year contract. Order
    05-584 arguably left ambiguous whether the fixed-price term ran from the date
    of contract execution or from the first day of power supply. Following the order,
    the price term in Portland General Electric’s (PGE) standard contracts ran from
    the date of contract execution, and complainants initiated an action to require
    PGE’s fixed-price terms to run from the first day of power supply. On review, the
    PUC declined to interpret PGE’s already approved contracts but clarified that
    Order 05-584 required fixed-price terms to run from the date of power supply.
    PGE petitioned for judicial review of the PUC’s decision, but, during the judicial-
    review proceeding, the PUC promulgated OAR 860-029-0120, which requires
    that fixed-price terms commence from the date of power supply. Complainants
    contend that the PUC’s rulemaking has rendered this appeal moot. Held: The
    PUC’s rulemaking mooted the appeal; no ruling on any of the issues PGE raised
    before the Court of Appeals would have had a practical effect on PGE’s rights or
    obligations.
    Petition for judicial review dismissed as moot.
    Anna M. Joyce argued the cause for petitioner. Also
    on the briefs were Dallas S. DeLuca, Anit K. Jindal, and
    Markowitz Herbold PC.
    Nadia H. Dahab argued the cause for respondents
    Northwest and Intermountain Power Producers Coalition,
    Community Renewable Energy Association, and Renewable
    Cite as 
    308 Or App 110
     (2020)                          111
    Energy Coalition. Also on the answering brief were Steven
    C. Berman, Keil M. Mueller, Stoll Stoll Berne Lokting &
    Shlachter PC, Irion A. Sanger, and Sanger Law PC. Also
    on the supplemental brief were Steven C. Berman, Keil M.
    Mueller, Stoll Stoll Berne Lokting & Shlachter PC, Irion A.
    Sanger, and Sanger Thompson PC.
    Jordan R. Silk, Assistant Attorney General, argued
    the cause for respondent The Public Utility Commission of
    Oregon. On the answering brief were Ellen F. Rosenblum,
    Attorney General, Benjamin Gutman, Solicitor General, and
    Keith L. Kutler, Assistant Attorney General. On the supple-
    mental brief were Ellen F. Rosenblum, Attorney General,
    Benjamin Gutman, Solicitor General, and Jordan R. Silk,
    Assistant Attorney General.
    Before Lagesen, Presiding Judge, and DeVore, Judge, and
    Powers, Judge.
    LAGESEN, P. J.
    Petition for judicial review dismissed as moot.
    112 Northwest and Intermountain Power Producers v. PGE
    LAGESEN, P. J.
    This dispute about certain contracts to buy and
    sell electric power is before us on Portland General Electric
    Company’s (PGE) petition for judicial review under ORS
    183.482 of a final order of the Public Utility Commission of
    Oregon (PUC). We conclude that it has become moot by vir-
    tue of subsequent rulemaking by the PUC. Accordingly, we
    dismiss the petition.
    At the core of this case are the PUC’s requirements
    for standard contracts for the purchase of electricity from
    operators known as “qualifying facilities” or “QFs.” In 2005,
    to implement the Public Utility Regulatory Policies Act, 16
    USC § 824a-3, the PUC issued Order 05-584. In that order,
    the PUC adopted a policy requiring standard contracts for
    purchase of electricity from QFs to (1) have 20-year terms,
    (2) set fixed prices for the purchase of electricity for the first
    15 years of the term, and (3) provide for market prices for
    the last five years of the contract term.
    What Order 05-584 arguably left ambiguous was
    the start date for the period of 15 years of fixed prices: Did it
    run from the date of contract execution or did it start when
    the QF became operational and began supplying power
    under the contract? Although Order 05-584 prescribed stan-
    dard terms for contracts with QFs, it did not prescribe a
    standard form for such contracts.
    Following the issuance of Order 05-584, some power
    companies provided in their standard contracts with QFs
    that the 15-year fixed-price period commenced when the QF
    became operational and began to supply power. PGE appar-
    ently took a different approach.1 Its standard contracts, in
    its view, allowed for the 15-year period to start on the date
    of contract execution. All of PGE’s standard contracts were
    filed with, and approved by, the PUC.
    1
    We say “apparently” because the parties dispute how PGE’s previous stan-
    dard contracts should be read. The PUC did not reach the issue in this proceed-
    ing, noting only that “PGE’s approved standard contract filings * * * may have
    limited the availability of fixed prices to the first fifteen years measured from
    contract execution,” and, further, that if the contracts did in fact do so, “PGE
    cannot be found to have been in violation of our orders” because the PUC had
    approved those contracts.
    Cite as 
    308 Or App 110
     (2020)                                                113
    In December 2016, the Northwest and Intermountain
    Power Producers Coalition, the Community Renewable
    Energy Association, and the Renewable Energy Coalition
    (collectively, complainants) initiated this complaint proceed-
    ing against PGE under ORS 756.500. They requested that
    (1) the PUC order PGE “to cease and desist * * * openly dis-
    puting that it must offer 15 years of fixed prices from the
    QF’s operation date,” which is what complainants alleged
    the PUC orders required; (2) the PUC declare that PGE’s
    standard contract “requires payment by PGE at fixed
    prices for 15 years after the QF’s operation date rather
    than merely 15 years after the time of contract execution,
    unless express language is inserted by the QF that demon-
    strates a contrary intent”; (3) in the alternative to the first
    two forms of relief requested, order “PGE to file revised
    standard contracts clearly stating that the 15 years of fixed
    prices run from the commercial operation date”; and (4) the
    PUC order any additional relief “deem[ed] necessary” by the
    PUC.
    Although it took a series of three orders,2 the PUC
    ultimately resolved the case by leaving the past murky and
    making the future clear.
    As for the past, the PUC declined to interpret PGE’s
    previously approved standard contracts. Consequently, it
    did not determine the date on which the 15-year fixed-price
    term began under them. Relatedly, the PUC declined to
    determine whether PGE’s past standard contracts complied
    with Order 05-584, explaining that the agency’s approval of
    them meant that PGE could not be found to be in violation
    of its orders.
    As for the future, the PUC explained how things
    should work going forward. It clarified that its policy in Order
    05-584 should be understood “to explicitly require standard
    2
    After the PUC issued the final order on review, Order No. 17-256, one of the
    complainants requested rehearing or reconsideration and, in Order No. 17-465,
    the PUC denied that request but “amend[ed] and clarif[ied] Order No. 17-256.”
    Then, PGE requested rehearing or reconsideration and, in Order No. 18-079, the
    PUC denied that request but again made clarifying statements. For purposes of
    this opinion, general references to the order on review are to Order No. 17-256, as
    amended and clarified in the two later orders.
    114   Northwest and Intermountain Power Producers v. PGE
    contracts, on a going-forward basis, to provide for 15 years
    of fixed prices that commence when the QF transmits power
    to the utility.” The PUC stated further that “PGE should
    promptly file revisions to Schedule 201 which shall include
    a revised standard contract PPA with language consistent
    with our requirement that the 15-year term of fixed prices
    commences when the QF transmits power to the utility.”
    Ultimately, the PUC ordered two things: (1) the dismissal
    of the complaint; and (2) “[w]ithin five business days of the
    date of this order, [PGE] shall file revisions to Schedule 201
    of its tariffs consistent with this order.”
    Following the PUC’s rejection of two requests for
    reconsideration, which resulted in some revisions and clar-
    ifications to the order on review, PGE filed this judicial-
    review proceeding under ORS 183.482. PGE raises two
    assignments of error. First, PGE argues that the PUC’s
    decision to direct PGE “to alter the start date for the 15-year
    period of fixed prices for all future PGE standard contracts
    with QFs” represents a change in policy that is not “sup-
    ported by substantial reason.” Second, PGE contends that
    the PUC acted outside “the range of discretion delegated to
    the agency by law,” and inconsistently with past practice,
    when, in the context of a complaint proceeding under ORS
    756.500, it announced what PGE views as a new policy. For
    relief, PGE requests that the PUC’s order be vacated and
    remanded.
    Meanwhile, before complainants filed their answer-
    ing briefs in this matter, the PUC promulgated administra-
    tive rules to address timing issues with the required con-
    tract terms for power purchase agreements with QFs. The
    pertinent rule, OAR 860-029-0120(3), provides:
    “Qualifying facilities have the unilateral right to select
    a purchase term of up to 20 years for a power purchase
    agreement. Qualifying facilities electing to sell firm out-
    put at fixed-prices have the unilateral right to a fixed-price
    term of up to 15 years.”
    For purposes of the provision, a “purchase term” is “the
    period of a power purchase agreement during which the
    qualifying facility is selling its output to the public utility.”
    OAR 860-029-0010(26). Additionally, a “fixed-rate term,”
    Cite as 
    308 Or App 110
     (2020)                                           115
    something that all parties agree is synonymous with a
    “fixed-price term,”3 means,
    “for qualifying facilities electing to sell firm energy or firm
    capacity or both, the period of a power purchase agreement
    during which the public utility pays the qualifying facil-
    ity avoided cost rates determined either at the time of con-
    tracting or at the time of delivery.”
    OAR 860-029-0010(16).
    Complainants then filed their answering brief
    in this matter. They argue that the administrative rules
    mooted the issues raised by PGE because the rules super-
    sede any policy statement made by the PUC in the order on
    review. Complainants argue further that, if the proceeding
    is not moot, then the PUC’s decision is not erroneous. In its
    answering brief, the PUC argues that the matter is moot for
    a different reason: PGE complied with the directive to sub-
    mit revised contracts and did not seek judicial review of the
    PUC orders approving those revised contracts. This means,
    according to the PUC, that resolution of PGE’s contentions
    will not have a practical effect on its rights because it cannot
    affect those approved standard contracts.
    Because the PUC did not address the effect of its
    own administrative rules in its initial brief to us, following
    oral argument, we requested supplemental briefing from
    the parties on that point; we viewed it as important to have
    the agency’s take on how its own act of rulemaking might
    displace any policy announcement it made in the order on
    review. In its supplemental brief, the PUC explains that it
    interprets its new rules to require the 15-year fixed-price
    period to start on the date a QF becomes operational and
    begins supplying power, not on the date of contract execu-
    tion. The PUC argues that, for this additional reason, this
    proceeding is moot. In their supplemental brief, complain-
    ants generally agree with the PUC’s take, echoing the posi-
    tion taken in their earlier brief.
    In its supplemental brief, PGE disagrees with the
    PUC’s interpretation of its rules to require the 15-year
    3
    The parties’ agreement on that point is consistent with the PUC’s rules,
    which define the word “rate” to include “price.” OAR 860-029-0010(28).
    116   Northwest and Intermountain Power Producers v. PGE
    fixed-price term to commence when the QF becomes oper-
    ational, arguing that it does not plausibly account for their
    text, context, and, in particular, rulemaking history. PGE
    argues further that neither the rules, nor the fact that it
    filed new standard contracts, make this proceeding moot.
    In its view, vacating and remanding the order could provide
    grounds for withdrawing the new standard contracts that it
    filed; PGE suggests that we would have the authority in this
    proceeding to order the PUC to take action in the contract-
    approval proceedings under ORS 183.486(1)(b). PGE also
    suggests that a favorable decision by us could affect 60
    power purchase agreements that it entered into with QFs
    between the entry of the final order on review and the effec-
    tive date of the administrative rules. According to PGE, “If
    the Commission’s policy was invalid, that calls into question
    the terms of a standard [power purchase agreement] issued
    to comply with that invalid policy.”
    Having considered the parties’ arguments on the
    point, we conclude that the PUC’s rulemaking has mooted
    this proceeding. “An appeal becomes moot when a decision
    ‘will no longer have a practical effect on the rights or obli-
    gations of a party.’ ” City of Cave Junction v. State of Oregon,
    
    289 Or App 216
    , 222-23, 410 P3d 306 (2017) (quoting State v.
    Walraven, 
    282 Or App 649
    , 654, 385 P3d 1178 (2016)). Here,
    the issues raised by PGE are (1) whether the PUC acted out-
    side the boundaries of its authority by prospectively clari-
    fying agency policy in a complaint proceeding under ORS
    756.500; and (2) whether substantial reason supports the
    PUC’s determination that the policy announced in Order
    05-584 required the 15-year fixed-price term to start upon
    delivery of power.
    The PUC’s act of formal rulemaking has mooted
    the first issue because, whether or not the PUC had the
    authority to announce policy in the context of a complaint
    proceeding, its act of rulemaking has superseded any pol-
    icy announced. Even if the PUC should have engaged in
    rulemaking or some other formal process to announce what
    it did in the order on review, as PGE contends it should have,
    it has now done so, thereby rendering academic the question
    of whether it is procedurally proper for the PUC to do what
    Cite as 
    308 Or App 110
     (2020)                               117
    it did in terms of announcing prospective policy in an order
    issued in a complaint proceeding.
    As for the substantial reason issue, that is also aca-
    demic at this point. As of now, the PUC’s rules set forth its
    current policy for the fixed-price terms of power purchase
    agreements with QFs. That is so regardless of what party is
    right about how those rules should be interpreted (a point we
    do not resolve); one way or another, the rules, not the order
    on review, are the current source of the PUC’s articulation
    of its policy on the point. If PGE believes that the rules allow
    for standard contracts containing terms different from the
    ones that it filed in response to the order on review, then
    it can seek approval of new standard contracts under the
    terms of the rules. An order from us directing the PUC to
    vacate its approval of the standard contracts that PGE filed
    in accordance with the order would not alter what is now the
    case: Going forward, PGE’s standard contracts must satisfy
    the administrative rules, which the PUC is bound to follow.
    See Harsh Investment Corp. v. State Housing Division, 
    88 Or App 151
    , 157, 
    744 P2d 588
     (1987), rev den, 
    305 Or 273
     (1988)
    (having promulgated administrative rules, an agency must
    follow them).
    That PGE opted to enter into 60 power purchase
    agreements between the time the order on review was
    entered and the effective date of the rules, apparently using
    the standard form contract that it was ordered to file, does
    not render this proceeding justiciable. PGE asserts that a
    ruling in its favor would call the terms of those contracts
    into question, and that is why this proceeding is not moot.
    But there has never been any question that Order 05-584
    allowed for power purchase agreements with QFs in which
    the 15-year fixed-price term started to run when the QF
    started to deliver power. The only question was whether
    Order 05-584 also allowed for power purchase agreements
    where the 15-year fixed-price term started earlier, upon con-
    tract execution. In other words, there is no basis to think
    that the executed power purchase agreements conflict with
    Order 05-584 by having the 15-year fixed-price term start
    when the QF becomes operational, or to otherwise question
    the validity of any such terms.
    118 Northwest and Intermountain Power Producers v. PGE
    Beyond that, there is no nonspeculative basis to
    conclude that a ruling in PGE’s favor on the issues raised
    would provide it with grounds for avoiding power purchase
    agreements that it executed of its own accord with QFs that
    are not parties to this proceeding. That is, even if we were
    to rule that the PUC somehow overstepped its authority or
    acted without substantial reason in clarifying in the order
    on review how the 15-year fixed-price terms were to operate,
    there is no nonspeculative basis to think that PGE would be
    entitled to avoid the bargains that it made with nonparties
    to this proceeding, even if PGE would have preferred to have
    made those bargains on different terms.
    Petition for judicial review dismissed as moot.
    

Document Info

Docket Number: A167707

Judges: Lagesen

Filed Date: 12/23/2020

Precedential Status: Precedential

Modified Date: 10/10/2024