Dept. of Fish and Wildlife v. Crook County ( 2021 )


Menu:
  •                                       625
    Argued and submitted August 20, reversed and remanded November 17, 2021
    OREGON DEPARTMENT
    OF FISH AND WILDLIFE,
    Respondent,
    v.
    CROOK COUNTY
    and West Prineville Solar Farm, LLC,
    Petitioners.
    Land Use Board of Appeals
    2020114; A176344
    504 P3d 68
    Petitioners West Prineville Solar Farm LLC (Solar Farm) and Crook County
    seek judicial review of an order of the Land Use Board of Appeals (LUBA) that
    remands to Crook County its decision approving Solar Farm’s application made
    under ORS 215.446 for a midsize solar facility. Petitioners assert that LUBA mis-
    construed what ORS 215.446 requires by concluding that a mitigation plan must
    include submittal requirements set out in OAR 635-415-0020(8). Respondent
    Oregon Department of Fish and Wildlife (ODFW) argues that the text of ORS
    215.446 requires that all the rules of its mitigation policy, including OAR 635-
    415-0020(8), apply to mitigation plans. Held: Counties approve applications made
    under ORS 215.446 and, because OAR 635-415-0020(8) concerns ODFW’s own
    approval process, LUBA erred in concluding that Solar Farm’s mitigation plan
    must include OAR 635-415-0020(8)’s submittal requirements.
    Reversed and remanded.
    John R. Eisler argued the cause and filed the brief for
    petitioner Crook County.
    Merissa A. Moeller argued the cause for petitioner West
    Prineville Solar Farm, LLC. Also on the brief were Timothy
    L. McMahan, Crystal S. Chase, Max M. Yoklic, and Stoel
    Rives LLP.
    Denise G. Fjordbeck, Assistant Attorney General, argued
    the cause for respondent. Also on the brief were Ellen F.
    Rosenblum, Attorney General, and Benjamin Gutman,
    Solicitor General.
    John Maxwell Greene filed the brief amicus curiae for
    Renewable Northwest.
    626             Dept. of Fish and Wildlife v. Crook County
    Damien R. Hall and Ball Janik LLP, and Elaine R. Albrich
    and Davis Wright Tremaine LLP filed the brief amicus cur-
    iae for Oregon Solar Energy Industries Association.
    Ellen H. Grover, Megan K. Beshai, and Karnopp Petersen
    LLP filed the brief amicus curiae for Community Renewable
    Energy Association.
    Before Tookey, Presiding Judge, and James, Judge, and
    Aoyagi, Judge.
    JAMES, J.
    Reversed and remanded.
    Cite as 
    315 Or App 625
     (2021)                                             627
    JAMES, J.
    Petitioner West Prineville Solar Farm, LLC (Solar
    Farm) applied to petitioner Crook County for approval of a
    modification to an existing conditional use permit (CUP) for
    a solar photovoltaic facility, seeking to increase the facility
    size from 320 acres to 654 acres on nonarable land. Solar
    Farm’s permit-modification application was made under
    ORS 215.446, which is a recently enacted statute that pro-
    vides standards regarding wildlife mitigation for counties
    to apply when determining whether to authorize midsize
    solar facilities, i.e., solar facilities sized between 321 acres
    and 1,920 acres. Crook County approved the application, but
    the Oregon Department of Fish and Wildlife (ODFW or the
    department) appealed that decision to the Land Use Board
    of Appeals (LUBA), contending that Solar Farm failed to
    include in its mitigation plan information called for in OAR
    635-415-0020(8). LUBA agreed with ODFW, and petition-
    ers assert on judicial review that LUBA misconstrued what
    ORS 215.446 requires by concluding that it requires a mit-
    igation plan to include the OAR 635-415-0020(8) submittal
    requirements. We agree with petitioners that LUBA erred
    in its construction of ORS 215.446. With a construction of
    ORS 215.446 that correctly reflects the legislature’s intent,
    we reverse and remand the matter to LUBA.
    BACKGROUND AND PROCEDURAL HISTORY
    Legal Framework. In 2019, the legislature passed
    House Bill (HB) 2329, which was codified as ORS 215.446.
    Or Laws 2019, ch 650, § 4.1 ORS 215.446 provides standards
    for applicants seeking to develop midsize renewable energy
    facilities. Generally speaking, midsize renewable energy
    facilities are solar facilities that use a certain number of
    acres, depending on the type of land on which the applicant
    seeks to build, or geothermal or wind energy generation
    facilities that have a certain megawatt generating capacity.
    ORS 215.446(1)(c). As relevant here, an applicant seeking to
    develop a solar facility on nonarable land can avail itself of
    the application process under ORS 215.446 for sites that use
    1
    The definitional section of ORS 215.446 was amended in 2021, Or Laws
    2021, ch 60, § 1, but the changes are not relevant to the issues here and we use
    the current version of the statute.
    628               Dept. of Fish and Wildlife v. Crook County
    more than 320 acres but not more than 1,920 acres. ORS
    215.446(1)(c)(A)(iii).
    Before ORS 215.446 was enacted, the Energy
    Facility Siting Council (EFSC) was solely responsible for
    permitting solar energy facilities that use more than 320
    acres of nonarable land. ORS 469.300 (2019), amended by Or
    Laws 2019, ch 650, § 1. The renewable energy industry did
    not consider it financially feasible to develop midsize renew-
    able energy facilities under the EFSC permitting process,
    which in their view is lengthy, cumbersome, and expensive.
    See, e.g., Audio Recording, Joint Subcommittee on Natural
    Resources, HB 2329, June 10, 2019, at 38:42 (comments
    of Morrow County representative Don Russell, https://
    olis.oregonlegislature.gov (accessed Nov 12, 2021)). The
    industry was familiar with developing smaller scale solar
    facilities—320 acres or less—through a process in which
    counties were the permitting authority, and HB 2329 was
    advanced as an approach that would allow counties the
    authority to permit midsize renewable energy facilities. Yet,
    as it was for the EFSC permitting process, ODFW would
    have a role regarding protections for wildlife.
    That desire for a faster and more responsive per-
    mitting process is embodied in subsections (2) and (3) of
    ORS 215.446:
    “(2) An application for a land use permit to estab-
    lish a renewable energy facility must be made under ORS
    215.416. An applicant must demonstrate to the satisfaction
    of the county that the renewable energy facility meets the
    standards under subsection (3) of this section.
    “(3) In order to issue a permit, the county shall require
    that the applicant:
    “(a)(A) Consult with the State Department of Fish
    and Wildlife, prior to submitting a final application to the
    county, regarding fish and wildlife habitat impacts and any
    mitigation plan that is necessary;
    “(B) Conduct a habitat assessment of the proposed
    development site;
    “(C) Develop a mitigation plan to address signifi-
    cant fish and wildlife habitat impacts consistent with
    Cite as 
    315 Or App 625
     (2021)                                            629
    the administrative rules adopted by the State Fish and
    Wildlife Commission for the purposes of implementing
    ORS 496.012; and
    “(D) Follow administrative rules adopted by the State
    Fish and Wildlife Commission and rules adopted by the
    Land Conservation and Development Commission to imple-
    ment the Oregon Sage-Grouse Action Plan and Executive
    Order 15-18.”
    Hence, in enacting ORS 215.446, the legislature
    placed in the hands of counties an alternative permitting
    process for proposed midsize solar facilities. Developers can
    still seek permitting for midsize solar facilities under the
    EFSC process. ORS 215.446(2). Under ORS 215.416, a county
    must approve permits that fit within the county’s compre-
    hensive plan and zoning ordinances. ORS 215.416(4)(a).
    Moreover, a county has 150 days from the completion of
    an application to make its determination. ORS 215.427(1).
    Typically, permitting by EFSC takes much longer.
    As for mitigation of impacts to wildlife, an applicant
    seeking a solar facility permit under ORS 215.446 must do
    three things: (1) consult with ODFW about the impacts the
    proposed site will have on fish and wildlife, and if neces-
    sary, develop a mitigation plan; (2) conduct a habitat assess-
    ment; and (3) “[d]evelop a mitigation plan to address sig-
    nificant fish and wildlife habitat impacts consistent with
    the administrative rules adopted by the State Fish and
    Wildlife Commission for the purposes of implementing ORS
    496.012.”2
    ORS 496.012, also known as the state’s Wildlife
    Policy, declares that “wildlife shall be managed to prevent
    serious depletion of any indigenous species and to provide the
    optimum recreational and aesthetic benefits for present and
    future generations of the citizens of this state.” To advance
    the Wildlife Policy, the Fish and Wildlife Commission has
    adopted rules, chapter 635, division 415, which are known
    as ODFW’s Mitigation Policy. See OAR 635-415-0000 (“The
    purpose of these rules is to further the Wildlife Policy (ORS
    496.012) * * * of the State of Oregon through the application
    2
    If sage grouse are involved, ORS 215.446(3)(a)(D), an applicant must do a
    fourth thing.
    630                    Dept. of Fish and Wildlife v. Crook County
    of consistent goals and standards to mitigate impacts to fish
    and wildlife habitat caused by land and water development
    actions.”); OAR 635-415-0010 (“It is the fish and wildlife
    habitat mitigation policy of the Oregon Department of Fish
    and Wildlife to require or recommend, depending upon the
    habitat protection and mitigation opportunities provided by
    specific statutes, mitigation for losses of fish and wildlife
    habitat resulting from development actions.”).
    Two of the Mitigation Policy’s rules in particular
    are implicated here: OAR 635-415-0025 and OAR 635-415-
    0020. OAR 635-415-0025 sets out six habitat categories,
    with “Habitat Category 1” as the most protective category
    (for irreplaceable and essential habitat, the mitigation goal
    is no loss of habitat) and “Habitat Category 6” as the least
    protective (habitat that has low potential to become essen-
    tial habitat for wildlife and where the mitigation goal is to
    minimize impacts to wildlife). Habitat Categories 3 and 4
    are habitats that are essential or important for wildlife.3 For
    both habitat categories, ODFW must act to achieve the mit-
    igation goals by “recommending or requiring”:
    “(A) Avoidance of impacts through alternatives to the
    proposed development action; or
    “(B) Mitigation of impacts, if unavoidable, through reli-
    able in-kind,[4] in-proximity habitat mitigation to achieve
    no net loss in either pre-development habitat quantity or
    quality. Progress towards achieving the mitigation goals
    and standards shall be reported on a schedule agreed to in
    the mitigation plan performance measures. The fish and
    wildlife mitigation measures shall be implemented and
    completed either prior to or concurrent with the develop-
    ment action.”
    OAR 635-415-0025(4). That is, Habitat Categories 3 and 4
    have mitigation goals of “no net loss” of habitat.5
    3
    ODFW has the view that Habitat Categories 3 and 4 apply to the proposed
    site. West Prineville agrees that Habitat Category 4 applies. In any event, all
    parties agree that the applicable mitigation standard is achieving “no net loss” of
    habitat.
    4
    “Out-of-kind” or “off-proximity” mitigation is not permitted for Habitat
    Category 3.
    5
    “Net Loss” means “a loss of habitat quantity and/or habitat quality result-
    ing from a development action despite mitigation measures having been taken.”
    OAR 635-415-0005(22).
    Cite as 
    315 Or App 625
     (2021)                                631
    OAR 635-415-0020 begins by describing the actions
    that ODFW is authorized to undertake. For ODFW’s own
    development actions that impact fish and wildlife habitat,
    the department must “provide mitigation consistent with
    the goals and standards of OAR 635-415-0025.” OAR 635-
    415-0020(1) (emphasis added). For instances when ODFW
    has “statutory authority to require mitigation as a condi-
    tion of a permit or order,” the department must “require
    mitigation consistent with the goals and standards of OAR
    635-415-0025.” OAR 635-415-0020(2) (emphasis added). For
    “other than” ODFW actions, when “[f]ederal or state envi-
    ronmental laws or land use regulations authorize or require
    mitigation for impacts to fish and wildlife,” the department
    must “recommend mitigation consistent with the goals and
    standards of OAR 635-415-0025.” OAR 635-415-0020(3)(a)
    (emphasis added).
    Depending on what ODFW is authorized by stat-
    ute to do, it may recommend or require mitigation of hab-
    itat impacts of a development action based on a number of
    considerations: (a) the location, physical and operational
    characteristics, and duration of the proposed development
    action; (b) the alternatives to the proposed development
    action; (c) the fish and wildlife species and habitats that
    will be affected by the proposed development action; and
    (d) the nature, extent, and duration of impacts expected to
    result from the proposed development action. OAR 635-415-
    0020(4)(a) - (d).
    In addition to those considerations, and of particu-
    lar relevance to LUBA’s conclusions in its final order, OAR
    635-415-0020(8) provides:
    “In addition to any other information that may be
    required by law, a written mitigation plan prepared for the
    Department shall:
    “(a) Include the information required in OAR 635-415-
    0020(4)(a) - (d); and
    “(b) Describe the mitigation actions which shall be
    taken to achieve the fish and wildlife habitat mitigation
    goals and standards of OAR 635-415-0025; and
    “(c) Describe and map the location of [t]he development
    action and mitigation actions including the latitude and
    632               Dept. of Fish and Wildlife v. Crook County
    longitude, township, range, section, quartersection and
    county; and
    “(d) Complement and not diminish mitigation provided
    for previous development actions; and
    “(e) Include protocols and methods, and a reporting
    schedule for monitoring the effectiveness of mitigation
    measures. Monitoring efforts shall continue for a dura-
    tion and at a frequency needed to ensure that the goals
    and standards in OAR 635-415-0025 are met, unless the
    Department determines that no significant benefit would
    result from such monitoring; and
    “(f) Provide for future modification of mitigation mea-
    sures that may be required to meet the goals and standards
    of OAR 635-415-0025; and
    “(g) Be effective throughout the project life or the
    duration of project impacts whichever is greater.
    “(h) Contain mitigation plan performance measures
    including:
    “(A) Success Criteria. The mitigation plan must clearly
    define the methods to meet mitigation goals and standards
    and list the criteria for measuring success;
    “(B) Criteria and a timeline for formal determination
    that the mitigation goals and standards have been met;
    “(C) Provisions for long-term protection and manage-
    ment of the site if appropriate;
    “(D) A reporting schedule for identifying progress
    toward achieving the mitigation goals and standards and
    any modification of mitigation measures. Mitigation goals
    and standards must be achieved within a reasonable time
    frame to benefit the affected fish and wildlife species.”
    Procedural History. Solar Farm consulted with
    ODFW before submitting its mitigation plan to the county’s
    planning commission. Solar Farm, having used ODFW’s
    COMPASS Habitat Mapping Tool (COMPASS), character-
    ized the site as Habitat Category 6. Although Solar Farm
    assessed the proposed site as having “low habitat quality”
    for big game, it nevertheless acquiesced to ODFW’s view
    that the land was a higher quality of habitat (a combination
    of Habitat Categories 4 and 5) and agreed to a 1:1 mitigation
    Cite as 
    315 Or App 625
     (2021)                                              633
    ratio (for every acre impacted by the development, one acre
    of mitigation would be required). Solar Farm’s mitigation
    plan (the V2 Plan) included two options, summarized as
    follows:6
    •     Option 1. Because western juniper has signifi-
    cantly expanded its range and encroached land-
    scapes dominated by shrubs and herbaceous veg-
    etation and negatively affects ecosystems, a “final
    mitigation plan will be prepared” before construc-
    tion of the proposed solar facility to cull encroach-
    ing juniper at some location in Crook County, which
    would ultimately provide forage for big game. The
    to-be-developed final mitigation plan would include,
    among other things, success criteria, durability
    measures, and a reporting schedule.
    •     Option 2. A one-time payment to the Deschutes
    Land Trust (or a similar land trust) to aid its Crook
    County conservation initiatives. The amount of the
    payment would be determined by a formula used for
    other similar solar facility projects in the surround-
    ing area.
    ODFW and the Department of Land Conservation
    and Development (DLCD) jointly submitted comments to the
    county’s planning commission about Solar Farm’s V2 Plan.
    The agencies asserted that the V2 Plan was insufficiently
    specific about the needed measures to achieve “no net loss”
    to mitigate impact to wildlife. To begin with, the agencies
    disagreed with Solar Farm’s assessment of the habitat as
    Category 6 and asserted that Solar Farm mistakenly used
    COMPASS. The agencies expressed their belief that the
    project needed a site-specific assessment and, based on what
    they knew of the site, classified the additional 334 acres as
    Habitat Category 3 or Habitat Category 4 (OAR 635-415-
    0025(3) and (4)), given its importance for a variety of wildlife,
    including reptiles, small mammals, and migratory birds.
    6
    The V2 Plan also proposed a third mitigation option, which were unspecified
    alternative mitigation measures to be developed “in consultation” with ODFW,
    subject to that agency’s “reasonable approval.” The agencies recommended that
    Option 3 be omitted from final approval, to which the county agreed.
    634                 Dept. of Fish and Wildlife v. Crook County
    With that in mind, the agencies made recommen-
    dations. They were of the view that Option 1—juniper
    removal—was inadequate, among other things, because it
    lacked the informational requirements set out in ORS 635-
    415-0020(8), including assurances that mitigation actions
    will offset adverse impacts and the identification of a spe-
    cific mitigation site. As to Option 2, the agencies, citing
    OAR 635-415-0020(8)(c) (requiring description and map of
    the mitigation action), recommended the inclusion of a spe-
    cific project area for which the one-time mitigation payment
    would benefit. They also recommended that Solar Farm pro-
    vide documentation that Deschutes Land Trust was willing
    to accept responsibility for the mitigation measures that the
    one-time payment contemplated.
    The county’s planning commission approved the
    modification of the CUP. ODFW appealed the decision to the
    Crook County Court.7 The county court held a hearing on the
    application and concluded that Options 1 and 2 were specific
    enough to ensure appropriate mitigation for the proposed
    solar-facility site. The county court noted that the applicant
    and ODFW agreed that a 1:1 ratio of mitigating one acre
    for every acre of solar facility development was appropriate,
    characterizing the mitigation plan as a “no net loss” mitiga-
    tion standard, but recognized that there was disagreement
    between the applicant and ODFW on the implementation
    of the “no net loss” standard. The county court, however,
    found that there was substantial evidence that V2 Plan
    addressed significant fish and wildlife habitat impacts and
    was consistent with the Mitigation Policy. Moreover, the
    county court, relying on OAR 660-033-0130(38)(j) (a set of
    DLCD rules that set standards for approval of solar facili-
    ties on nonarable land of 320 acres or less), concluded that
    Solar Farm’s V2 Plan was “appropriate.” OAR 660-033-0130
    (38)(j)(G) (providing, in part, that, “[w]here the applicant
    and the resource management agency cannot agree on what
    mitigation will be carried out, the county is responsible for
    determining appropriate mitigation, if any, required for the
    7
    The Crook County Court is the governing body for Crook County and is
    comprised of a county judge and two county commissioners. ORS 203.111; ORS
    376.005.
    Cite as 
    315 Or App 625
     (2021)                                                   635
    facility” (emphasis added)).8 In the county court’s view, the
    mitigation options were in line with mitigation approaches
    taken by other solar facilities in the area and consistent
    with the county court’s prior decisions.
    ODFW petitioned for LUBA review of the county’s
    decision, arguing that the county court improperly con-
    strued ORS 215.446(3)(a)(C) when it determined that the
    V2 Plan satisfied that statute’s requirements. It argued
    that the V2 Plan failed to meet the Mitigation Policy’s defi-
    nition of “mitigation plan” because it failed to “thoroughly
    describe the manner in which” implementing the no net loss
    standard would occur. OAR 635-415-0005(18). ODFW also
    argued that the V2 Plan failed to satisfy the requirements of
    OAR 635-415-0020(8), specifically the information required
    by OAR 635-415-0020(8)(c), (g), (h)(A), (h)(B), and (h)(D).
    Without that information, ODFW asserted, the V2 Plan was
    not consistent with the Mitigation Policy and did not sup-
    port a conclusion that its implementation would result in no
    net loss of habitat quality and quantity.
    Solar Farm responded with its view that ORS
    215.446(3)(a)(C) did not require that a mitigation plan be
    consistent with all of the provisions of the Mitigation Policy,
    in particular, the requirements set out in OAR 635-415-
    0020(8). The county court, according to Solar Farm, was
    not required to determine consistency with OAR 635-415-
    0020(8), because that rule is limited to situations in which
    ODFW is the permitting authority.
    LUBA agreed with ODFW, concluding that the
    plain language of ORS 215.446(3)(a)(C) requires a miti-
    gation plan that “is consistent with” all of the Mitigation
    Policy’s provisions, including those set out in OAR 635-415-
    0020(8). LUBA reasoned that, because all of the rules in the
    Mitigation Policy state that they implement ORS 496.012,
    those rules are “ ‘adopted * * * for the purposes of imple-
    menting ORS 496.012.’ ” (Quoting ORS 215.446(3)(a)(C).)
    LUBA stated that Solar Farm’s construction of ORS 215.446
    (3)(a)(C) “essentially inserts the phrase ‘it deems applicable’
    8
    Petitioners do not argue on review that the DLCD rules that apply to solar
    facility projects that are 320 acres or less also apply to solar facility applications
    and review for projects made under ORS 215.446.
    636              Dept. of Fish and Wildlife v. Crook County
    after the phrase ‘administrative rules adopted by the State
    Fish and Wildlife Commission for the purposes of imple-
    menting ORS 496.012.’ ” LUBA added that the “legislature
    did not limit the universe of rules with which an applicant
    must demonstrate consistency to only those rules that the
    county determines apply.” Additionally, LUBA concluded
    that it was not persuaded by Solar Farm’s additional argu-
    ments concerning context, namely, that ORS 496.446(2) pro-
    vides that an “applicant must demonstrate to the satisfaction
    of the county” that the proposed facility meets the standards
    set out in subsection (3). (Emphasis added.) LUBA said that
    that subsection does not permit the county to determine
    which of the Mitigation Policy’s rules apply.
    With that decided, LUBA also concluded that the
    V2 Plan failed to meet OAR 635-415-0020(8)(g)’s require-
    ment that a mitigation plan be “effective throughout the
    project life or the duration of the project impacts whichever
    is greater” and OAR 635-415-0020(8)(h)’s requirement that
    a mitigation plan include certain performance measures.
    Moreover, LUBA concluded that the county’s findings nei-
    ther adequately explained the justification for the approval
    of the V2 Plan, ORS 215.416(9), nor adequately responded to
    specific issues raised by ODFW. LUBA remanded the deci-
    sion to the county. Petitioners now seek judicial review of
    LUBA’s order.
    STANDARD OF REVIEW
    ORS 197.850(9) requires us to “reverse or remand”
    LUBA’s order if it is “unlawful in substance,” which occurs
    if it “represent[s] a mistaken interpretation of the applicable
    law.” Mountain West Investment Corp. v. City of Silverton, 
    175 Or App 556
    , 559, 30 P3d 420 (2001). The issue on review—
    what ORS 215.446 requires of a mitigation plan—reduces
    to a matter of statutory construction, and we therefore
    review LUBA’s opinion for legal error. To do so, we use the
    PGE/Gaines methodology, which requires us to examine
    the relevant text of ORS 215.446 in context, along with any
    relevant legislative history or other aids to construction.
    State v. Gaines, 
    346 Or 160
    , 171-72, 206 P3d 1042 (2009);
    Trautman/Conte v. City of Eugene, 
    280 Or App 752
    , 758, 383
    P3d 420 (2016) (“Because LUBA’s legal conclusions involve
    Cite as 
    315 Or App 625
     (2021)                            637
    an issue of statutory construction, we apply the principles
    of statutory construction set out in PGE v. Bureau of Labor
    and Industries, 
    317 Or 606
    , 610-12, 
    859 P2d 1143
     (1993), as
    modified by [Gaines, 
    346 Or at 171-72
    .]). When we interpret
    terms that are not defined by statute, we typically resort to
    dictionary definitions to discern their “plain, natural, and
    ordinary meaning.” PGE, 
    317 Or at 611
    . Further, when our
    review involves statutory construction, we must interpret
    statutory provisions correctly, regardless of how the par-
    ties have asserted their interpretations. Gunderson, LLC v.
    City of Portland, 
    352 Or 648
    , 662, 290 P3d 803 (2012) (citing
    Stull v. Hoke, 
    326 Or 72
    , 77, 
    948 P2d 722
     (1997)).
    DISCUSSION
    Solar Farm, on judicial review, raises five assign-
    ments of error. In its first assignment of error, Solar Farm
    argues that LUBA erred by requiring “strict compliance”
    with the Mitigation Policy. In its second assignment, Solar
    Farm contends that LUBA erred by concluding that ORS
    215.446 requires “strict compliance” with the Mitigation
    Policy as ODFW interprets it. In its third assignment, Solar
    Farm argues that LUBA erred by concluding that the V2 Plan
    failed to satisfy ORS 215.446 and remanding the county’s
    approval of the V2 Plan. Solar Farm, in its fourth and fifth
    assignments of error, argues in the alternative—in the event
    we agree with LUBA’s construction of ORS 215.446—that
    LUBA interpreted OAR 635-415-0020(8) in such a way so as
    to allow ODFW to dictate the manner of evidence required
    to satisfy that rule, and that LUBA erred by making its own
    findings whether the requirements of OAR 635-415-0020(8)
    were satisfied. Crook County also weighs in, arguing that
    LUBA erred in concluding that the items set out in OAR
    635-415-0020(8) were mandatory approval criteria for mid-
    size solar facility applicants. In addition to briefing from
    petitioners, three industry groups, Community Renewable
    Energy, Oregon Solar Energy, and Renewable Northwest,
    have supplied amicus briefing to argue that LUBA miscon-
    strued ORS 215.446. ODFW defends LUBA’s construction
    of ORS 215.446, mainly by arguing that the text of that
    statute plainly means that all of the Mitigation Policy rules
    apply to applicants.
    638              Dept. of Fish and Wildlife v. Crook County
    Before we begin our analysis, we pause to make two
    points to help frame the parties’ dispute. First, the parties’
    clash over the construction of ORS 215.446 reflects simpler
    arguments that the parties have asserted from the begin-
    ning of this dispute. For petitioners’ part, they view ODFW’s
    efforts—by insisting that certain rules of the Mitigation
    Policy apply, pressing its interpretation of the rules, and
    asserting that the V2 Plan failed to satisfy them—as an
    attempt to usurp the decisional authority of the county. As
    for ODFW, the department views the V2 Plan as lacking
    because it is merely “a plan to submit a plan” and fails to
    adequately convey how the impacts of Solar Farm’s solar
    facility on wildlife will be mitigated. And, because the
    county has approved Solar Farm’s application, when the
    final mitigation plan is ultimately submitted to the county,
    there will be no forum or opportunity for state agencies or
    other concerned parties to object to it.
    Second, Solar Farm advances a theme that LUBA
    has demanded “strict compliance” with the Mitigation Policy
    and ODFW’s interpretation of it. Although that character-
    ization is somewhat understandable given LUBA’s view of
    ORS 215.446 and its agreement with many of ODFW’s posi-
    tions, those are Solar Farm’s words, not LUBA’s. The crux of
    LUBA’s decision is that ORS 215.446(3)(a)(C)—requiring a
    mitigation plan to “address significant fish and wildlife hab-
    itat impacts consistent with” the Mitigation Policy—requires
    an applicant to include the informational requirements
    described in OAR 635-415-0020(8). Petitioners’ arguments
    and assignments of error flow from that key conclusion by
    LUBA, and, consequently, we confine our review to deciding
    whether that conclusion was correct and addressing how a
    mitigation plan submitted for ORS 215.446 compliance is
    consistent with the Mitigation Policy. We begin with a dis-
    cussion of the relevant significant terms contained in ORS
    215.446.
    “To the satisfaction of the county.” Approval of an
    application by the county is central to the approval frame-
    work under ORS 215.446. The purpose of the statute was
    to provide county approval as an alternative to EFSC
    permitting for midsize renewable energy facilities. ORS
    Cite as 
    315 Or App 625
     (2021)                                      639
    215.446(2) provides that applications “for a land use per-
    mit to establish a renewable energy facility must be made
    under ORS 215.416,” which sets out notice and related pro-
    cedural requirements for county action on permits that are
    subject to discretionary approval. See Flowers v. Klamath
    County, 
    98 Or App 384
    , 386, 
    780 P2d 227
    , rev den, 
    308 Or 592
     (1989). Further, subsection (2) provides that an “appli-
    cant must demonstrate to the satisfaction of the county that
    the renewable energy facility meets the standards under
    subsection (3) of this section.” When those two sentences are
    considered together, it is plainly evident that the county is
    the decisionmaker for a permit allowing a renewable energy
    facility under ORS 215.446 and that an applicant prepares
    a mitigation plan for the county’s approval.
    “Consistent with.” As stated earlier, ORS 215.446
    (3)(a)(C) provides that a county must require an applicant to
    “[d]evelop a mitigation plan to address significant fish and
    wildlife habitat impacts consistent with the administrative
    rules adopted by the State Fish and Wildlife Commission
    for the purposes of implementing ORS 496.012[.]”
    As to the ordinary meaning of “consistent with,” we turn
    to the term’s dictionary definition. “Consistent” is defined
    as “marked by agreement and concord <opinions consistent
    with each other> : coexisting and showing no noteworthy
    opposing, conflicting, inharmonious, or contradictory qual-
    ities or trends : compatible—usually used with with.”9 That
    is, “consistent with” connotes that two things are concordant
    with each other and that they lack noteworthy conflicting
    elements or qualities. That meaning alone, however, does
    not answer the question of what the legislature intended
    when it provided that mitigation plans are to be prepared as
    part of an application under ORS 215.446 and, specifically,
    whether the legislature intended that a mitigation plan
    includes the information set out in OAR 635-415-0020(8).
    LUBA construed the phrase “[d]evelop a mitiga-
    tion plan to address significant fish and wildlife impacts
    9
    Merriam-Webster Unabridged Dictionary, https://unabridged.merriam-
    webster.com/unabridged/consistent (accessed Oct 24, 2021) (definition of
    consistent).
    640              Dept. of Fish and Wildlife v. Crook County
    consistent with the administrative rules” of the Mitigation
    Policy to mean all of rules of the Mitigation Policy, includ-
    ing OAR 635-415-0020(8). It reasoned that to do otherwise
    would essentially insert the phrase “as applicant deems
    applicable” after the phrase “administrative rules adopted
    by [ODFW] for the purposes of implementing ORS 496.012.”
    See ORS 174.010 (“In the construction of a statute, the office
    of the judge is simply to ascertain and declare what is, in
    terms or in substance, contained therein, not to insert what
    has been omitted, or to omit what has been inserted.”).
    However, Solar Farm and the county do not arrive with-
    out reason to their view that the applicable “administrative
    rules” do not include OAR 635-415-0020(8). Rather, petition-
    ers assert that context and the legislative history of ORS
    215.446 compel that view. We turn to those arguments.
    Context. Although we agree with LUBA that “con-
    sistent with” the rules of ODFW’s mitigation policy does not
    mean that an applicant or the county approving the applica-
    tion for a solar facility gets to determine which rules apply,
    we proceed to explain that, once ORS 215.446 is considered
    in relation to how the rules of the Mitigation Policy operate
    as a whole, compliance with those items set out in OAR 635-
    415-0020(8) is not a requirement of the application process
    under ORS 215.446.
    The informational requirements set out in OAR
    635-415-0020(8) are prefaced by the statement that, “[in]
    addition to any other information that may be required by
    law, a written mitigation plan prepared for the Department
    shall [contain the information set out in paragraphs
    (a) - (h)].” (Emphasis added.) In other words, subsection (8)
    plainly indicates that the information required under that
    rule is for when an application is prepared for ODFW. An
    application made under ORS 215.446 is prepared for the
    county. To be sure, under ORS 215.446(3)(a), an applicant
    must consult with ODFW before it submits its application to
    the county, which is the approving entity, but that provision
    cannot be understood to say that an applicant’s mitigation
    plan is prepared for ODFW. A construction of ORS 215.446
    that says that an applicant must comply with the informa-
    tion requirements set out in OAR 635-415-0020(8) would
    Cite as 
    315 Or App 625
     (2021)                              641
    need to substitute “the county” in place of “the Department.”
    That substitution strikes a discordant note by requiring
    application of that rule when it was adopted by the Fish and
    Wildlife Commission for the purpose of ODFW’s own use
    when the department is the permitting authority.
    Additionally, OAR 635-415-0020(8) is a rule that
    sets out a circumstance for when ODFW requires certain
    information for mitigation plans. That is not the case here,
    where the development action is neither ODFW’s own action
    nor is it an action in which ODFW has statutory authority to
    require mitigation measures. See OAR 635-415-0020(1), (2).
    Rather, ODFW’s own rule—OAR 635-415-0020(3)—states
    that the department must “recommend mitigation consis-
    tent with the goals and standards of OAR 635-415-0025”
    when the two foregoing scenarios do not apply and a state
    environmental law or land use regulation, like ORS 215.446,
    requires mitigation for impacts to fish and wildlife.
    Other rules contained in the mitigation policy allow
    for ODFW to recommend or require a mitigation action
    (depending on the statutory authority that requires a mit-
    igation plan). See OAR 635-415-0025(1) - (6); OAR 635-415-
    0020(4) (requiring ODFW to consider certain factors when
    it is making a recommendation or requiring something for a
    development action). To us, that suggests that, because OAR
    635-415-0020(8) speaks to situations in which something is
    required, it is not a rule of the mitigation policy that applies
    to all situations in which ODFW is involved in furthering
    the state’s wildlife policy and applications that require mit-
    igation plans.
    Accordingly, rules in the Mitigation Policy cre-
    ate different obligations for applicants depending whether
    ODFW is requiring mitigation, based on statutory author-
    ity, or whether ODFW is recommending mitigation to other
    permitting authorities. Here, ORS 215.446 provides that a
    county is the permitting authority. When the legislature
    enacted ORS 215.446, those distinctions were in place.
    There is nothing in the text of ORS 215.446 that suggests
    that the legislature intended to modify those distinctions.
    Therefore, the phrase “the administrative rules adopted by
    the State Fish and Wildlife Commission for the purposes of
    642               Dept. of Fish and Wildlife v. Crook County
    implementing ORS 496.012,” ORS 215.446(3)(a)(C), refers to
    rules in which ODFW is not the permitting authority, and
    those rules do not include OAR 635-415-0020(8).
    Legislative history. EFSC was formerly the sole per-
    mitting authority for solar facilities 320 acres or greater in
    size. The proponent of HB 2329, Representative Ken Helm,
    was asked during a meeting of the Joint Subcommittee
    on Natural Resources if counties would be using the same
    wildlife mitigation criteria as EFSC used. Representative
    Helm responded, “The bill intends that, yes.” Audio Record-
    ing, Joint Subcommittee on Natural Resources, HB 2329,
    June 10, 2019, at 23:24 (comments of Rep Ken Helm),
    https://olis.oregonlegislature.gov (accessed Nov 12, 2021).
    Representative Helm also explained that HB 2329 created
    an approval process—different from the county approval
    process for smaller solar facilities—“in which the county
    would administrate the approval process, but this bill
    includes particular requirements that mirror the EFSC
    criteria—not necessarily the process, but the criteria.” Audio
    Recording, Joint Subcommittee on Natural Resources, HB
    2329, June 10, 2019, at 21:40 (comments of Rep Ken Helm)
    https://olis.oregonlegislature.gov (accessed Nov 12, 2021).
    The relevant EFSC criteria to which Helm referred is set
    out in OAR 345-022-0060:
    “To issue a site certificate, the Council must find that
    the design, construction and operation of the facility, tak-
    ing into account mitigation, are consistent with:
    “(1) The general fish and wildlife habitat mitigation
    goals and standards of OAR 635-415-0025(1) through (6) in
    effect as of February 24, 2017[.]”
    EFSC’s rule does not require the OAR 635-415-0020(8)
    submittal information. To impose the additional submittal
    requirements of OAR 635-415-0020(8) for ORS 215.446 per-
    mitting would impose procedural hurdles for applications
    made under ORS 215.446 above those required for EFSC
    permitting. The legislative history indicates that that was
    not the legislature’s intent.
    Consequently, although all the rules of the Mitigation
    Policy have the purpose of implementing ORS 496.012—the
    Cite as 
    315 Or App 625
     (2021)                             643
    Wildlife Policy—not all the rules are applicable when ODFW
    is not the permitting authority. With the text, context, and
    legislative history of ORS 215.446 considered together, sub-
    section (3)(a)(C) does not require an applicant to include
    the information set out in OAR 635-415-0020(8). Given the
    framework of the Mitigation Policy, in which certain rules
    are intended for ODFW’s own approval process, nothing in
    ORS 215.446 suggests that ODFW requirements or submit-
    tal rules meant for ODFW’s approval were intended by the
    legislature to apply to the county approval process for mid-
    size renewable energy facilities. LUBA’s order, however, con-
    cluded that the submittal information set out in OAR 635-
    415-0020(8), which is information that must be provided in
    applications prepared for ODFW, are requirements that an
    applicant must include to demonstrate to the county’s satis-
    faction under ORS 215.446 that the mitigation plan is con-
    sistent with the Mitigation Policy. That conclusion is unlaw-
    ful in substance, and we therefore reverse and remand the
    petition to LUBA.
    The parties’ arguments focus on the role of OAR
    635-415-0020(8), and we have concluded that ORS 215.446
    does not require an applicant to include that rule’s sub-
    mittal requirements. Left open, however, is the question of
    what “consistent with” the Mitigation Policy does require.
    Given the limited nature of the parties’ arguments, we do
    not endeavor to provide a conclusive, all-encompassing con-
    struction of what a mitigation plan prepared for an applica-
    tion under ORS 215.446 requires, but we do offer the follow-
    ing observations, as relevant to issues the parties raise on
    review that LUBA will consider on remand.
    Petitioners contend that an ORS 215.446 applica-
    tion for a solar facility must include a mitigation plan that
    applies the goals and standards of OAR 635-415-0025. That
    view is largely correct, but we highlight elements of OAR
    635-415-0025 and other provisions of the Mitigation Policy
    that must be considered when a county makes a determina-
    tion that a mitigation plan is “consistent with” the Mitigation
    Policy.
    First, the Mitigation Policy defines “Mitigation Plan”
    (ORS 215.446(3)(a)(C) requires that an applicant must
    644                  Dept. of Fish and Wildlife v. Crook County
    develop a “mitigation plan” consistent with the Mitigation
    Policy) as
    “a written plan or statement that thoroughly describes
    the manner in which the impact of a development action
    will be reduced or eliminated over time, avoided, and/or
    minimized; and the affected environment, including fish
    and wildlife habitat, monitored, restored, rehabilitated,
    repaired and/or replaced or otherwise compensated for in
    accordance with OAR 635-415-0010 of these rules.”
    OAR 635-415-0005(18) (emphases added). The emphasized
    terms—“thoroughly describes the manner” and “will be”—
    indicates that specificity and definiteness are required for a
    mitigation plan to be consistent with the Mitigation Policy.
    That is, the term “will be” connotes a definiteness of future
    action and the term “thorough” connotes that the mitigation
    plan requires completeness and attention to detail.10 When
    a county assesses whether a mitigation plan is “consistent
    with” the Mitigation Policy, it must determine whether the
    plan has those qualities.
    Also notable are the standards set out for each
    Habitat Category. OAR 635-415-0025. Petitioners have
    accepted that the goals for Habitat Categories 3 and 4—“no
    net loss” in both cases—are appropriate criteria for Solar
    Farm’s mitigation plan. (For example, the mitigation goal
    for Habitat Category 4 “is no net loss in either existing hab-
    itat quantity or quality.” OAR 635-415-0025(4)(a).) In addi-
    tion to a goal, each Habitat Category has a directive. For
    instance, Habitat Category 4 directs ODFW to
    “achieve the mitigation goal for Category 4 habitat by rec-
    ommending or requiring:
    “(A) Avoidance of impacts through alternatives to the
    proposed development action; or
    “(B) Mitigation of impacts, if unavoidable, through
    reliable in-kind or out-of-kind, in-proximity or off-proximity
    habitat mitigation to achieve no net loss in either pre-
    development habitat quantity or quality. Progress towards
    10
    “Thorough” means “marked by completeness: such as * * * carried through
    to completion especially with full attention to details : complete <a thorough
    search>[.]” Merriam-Webster Unabridged Dictionary, https://unabridged.merriam-
    webster.com/unabridged/thorough (accessed Oct 24, 2021).
    Cite as 
    315 Or App 625
     (2021)                                               645
    achieving the mitigation goals and standards shall be
    reported on a schedule agreed to in the mitigation plan
    performance measures. The fish and wildlife mitigation
    measures shall be implemented and completed either prior
    to or concurrent with the development action.”
    OAR 635-415-0025(4)(b). We note two things here. First, an
    ODFW recommendation furthers the Mitigation Policy by
    seeking a mitigation plan that has (if an alternative develop-
    ment action is unavoidable) “reliable in-kind or out-of-kind,
    in-proximity or off-proximity habitat mitigation to achieve
    no net loss.” OAR 635-415-0025(4)(b) (emphasis added). The
    Mitigation Policy therefore calls for reliable “no net loss”
    mitigation, i.e., a mitigation measure “fit to be relied on.”11
    Second, an ODFW recommendation to further “no net loss”
    mitigation reflects that, under the Mitigation Policy, a mit-
    igation plan includes a schedule of performance measures.
    Finally, we observe that OAR 635-415-0020(4) pro-
    vides that ODFW’s recommendations for mitigation of a
    development action’s impact must be based, among other
    things, on the “location, physical and operational charac-
    teristics, and duration of the proposed development action”
    and the “nature, extent, and duration of impacts expected
    to result from the proposed development action.” OAR 635-
    415-0020(4)(a), (d). The OAR 635-415-0020(4) considerations
    illustrate that the Mitigation Policy includes, regardless
    of ODFW’s particular role, durational considerations as to
    the development action and the mitigation efforts. Ignoring
    those considerations would allow for mitigation measures
    that fail to accommodate the impact on habitat for the full
    life of a renewable energy facility.
    With that said, we return to the meaning of “con-
    sistent with.” A mitigation plan prepared for ORS 215.446
    approval must be concordant with the Mitigation Policy and
    not show any substantive conflicting elements. Although a
    mitigation plan need not follow the submittal requirements
    set out in OAR 635-415-0020(8), there are other require-
    ments of the Mitigation Policy that a mitigation plan must
    11
    Merriam-Webster Unabridged Dictionary, https://unabridged.merriam-
    webster.com./unabridged/reliable (accessed Oct 24, 2021) (definition of reliable).
    646             Dept. of Fish and Wildlife v. Crook County
    satisfy, including the ones that we have highlighted above.
    On remand, LUBA will consider those in the first instance.
    Reversed and remanded.
    

Document Info

Docket Number: A176344

Judges: James

Filed Date: 11/17/2021

Precedential Status: Precedential

Modified Date: 10/10/2024