Warren v. Smart Choice Payments, Inc. , 306 Or. App. 634 ( 2020 )


Menu:
  •                                       634
    Argued and submitted May 17, 2019, affirmed September 23, 2020
    Jason WARREN,
    Plaintiff-Respondent,
    v.
    SMART CHOICE PAYMENTS, INC.;
    Wholesale Merchant Processing, Inc.;
    North American Processing Solutions, LLC;
    and Todd McCartney,
    Defendants-Appellants.
    Washington County Circuit Court
    17CV05531; A166758
    475 P3d 444
    Defendants appeal from a trial court order denying their petition to compel
    arbitration after plaintiff sued them for breach of contract, unjust enrichment,
    and fraud. Defendants contend that the court erred by (1) concluding that a 2008
    agreement between the parties with an arbitration clause was superseded by a
    2009 agreement that did not require arbitration and (2) deciding in the alterna-
    tive that, if the 2008 agreement survived, its arbitration clause was unconscion-
    able and therefore unenforceable. Held: The Court of Appeals concluded that the
    2009 agreement superseded the 2008 agreement and did not require arbitration
    of the dispute. As a result, the court did not reach the trial court’s alternative
    conclusion that the 2008 arbitration clause was unconscionable.
    Affirmed.
    Beth L. Roberts, Judge.
    Kevin J. Jacoby argued the cause and filed the briefs for
    appellants. Also on the reply brief was Colin P. Mackenzie.
    Michael A. Cox argued the cause for respondent. Also on
    the brief was Law Office of Michael A. Cox.
    Before Armstrong, Presiding Judge, and Tookey, Judge,
    and Shorr, Judge.
    SHORR, J.
    Affirmed.
    Cite as 
    306 Or App 634
     (2020)                             635
    SHORR, J.
    Defendants appeal from a trial court order denying
    their petition to compel arbitration. Defendants assign error
    to the trial court’s denial, contending that the court erred
    in (1) concluding that a 2008 agreement with an arbitration
    clause was superseded by a 2009 agreement that did not
    require arbitration and (2) deciding, in the alternative, that,
    if the 2008 agreement survived, its arbitration clause was
    unconscionable and unenforceable. We conclude that the
    court did not err when it concluded that the 2009 agreement
    superseded the 2008 agreement and did not require arbitra-
    tion of this dispute. As a result, we do not reach the court’s
    alternative conclusion that the 2008 arbitration clause is
    unconscionable. We, therefore, affirm.
    We begin with the background to this dispute.
    The facts relevant to our resolution of the arbitration issue
    on appeal are uncontested. The underlying dispute arose
    between plaintiff Jason Warren, on one side, and defen-
    dant Todd McCartney and entities owned or controlled by
    McCartney, on the other side. Plaintiff was initially hired
    in March 2007 by defendant McCartney’s wholly-owned
    company, Wholesale Merchant Services, Inc. The parties
    entered into a “Contract of Employment” in March 2007
    that was executed by plaintiff and defendant McCartney on
    behalf of Wholesale Merchant Services. Plaintiff was iden-
    tified as an employee in the agreement. There is no clause
    mandating arbitration of any disputes in the March 2007
    agreement.
    Plaintiff was hired to sell or lease credit card pro-
    cessing equipment and services to potential business cus-
    tomers; was provided “leads” for potential business and
    directed to make sales calls on those businesses; and was
    asked to relocate from Oregon to Sacramento, California.
    Plaintiff alleges that he was promised commissions on sales
    of any equipment to merchants and also promised future
    commissions or “residuals” when those merchants made
    ongoing payments for credit-card processing services.
    At some point prior to May 2008, defendant
    McCartney asked plaintiff to enter into a new agree-
    ment with a different entity McCartney owned, defendant
    636                        Warren v. Smart Choice Payments, Inc.
    Wholesale Merchant Processing, Inc. Plaintiff and Wholesale
    Merchant Processing entered into an agreement in May
    2008 (the 2008 agreement). Unlike the prior agreement, the
    agreement identified plaintiff as an independent contractor
    rather than an employee. The 2008 agreement provided a
    section for payment of fees, which stated that, “[d]uring any
    period of time in which this Agreement remains in full force
    and effect, compensation to Independent Contractor will be
    paid as set forth” in an attached schedule. Significant to this
    dispute, the 2008 agreement included a dispute resolution
    provision, which spelled out the parties’ obligation to try to
    resolve any disagreement, and was immediately followed by
    an arbitration clause, which provided, in relevant part:
    “All disputes that cannot be resolved pursuant to the
    internal issue resolution process identified above will be
    submitted to and settled by final and binding arbitration.
    The arbitration will take place in Portland, Oregon, and
    will apply the governing law of this Agreement. The final
    and binding arbitration will be performed by a panel of
    three arbitrators in accordance with and subject to the
    Commercial Arbitration Rules of the AAA then in effect.
    * * * The decision of the arbitrators will be final and bind-
    ing, and judgment on the award may be entered in any
    court of competent jurisdiction.”
    The 2008 agreement also contained a provision that the dis-
    pute resolution and arbitration provisions, among others,
    “shall survive termination of this Agreement.”1
    Plaintiff maintains that he agreed to enter into
    that new agreement based on the condition that any “resid-
    uals” resulting from ongoing merchant accounts would be
    1
    We note that, in addition to, or perhaps despite, that arbitration clause, the
    2008 agreement also curiously contained the following jurisdiction and venue
    provision, which provides, in relevant part:
    “The parties hereby agree that any suit to enforce any provision of this
    Agreement or arising out of or based upon this Agreement or the business
    relationship between the parties hereto shall be brought in federal or state
    court in Portland, Oregon. Each party hereby agrees that such courts shall
    have exclusive personal jurisdiction and venue with respect to such party,
    and each party hereby submits to the exclusive personal jurisdiction and
    venue of such courts.”
    Based on our analysis later in this opinion that the later 2009 agreement super-
    seded the 2008 arbitration clause, we do not need to address this potential conflict
    between the arbitration and litigation-venue provisions in the 2008 agreement.
    Cite as 
    306 Or App 634
     (2020)                               637
    “vested” and earned even if he was terminated from his
    position. Although there were some substantive changes to
    the agreement, plaintiff’s job duties did not change after
    that agreement except in the fact that he now reported to
    Wholesale Merchant Processing.
    In November 2009, Wholesale Merchant Processing
    and plaintiff entered into a new agreement (the 2009 agree-
    ment). Plaintiff became a sales manager for Wholesale
    Merchant Processing and worked out of an Oregon office.
    The 2009 agreement identified plaintiff as an employee
    again. It did not specifically define plaintiff’s wages or com-
    pensation, but noted that the “compensation or other mon-
    ies paid or to be paid to [plaintiff] by Wholesale Merchant
    Processing” is consideration for plaintiff’s employment.
    Notable for this dispute, the 2009 agreement had a
    broad integration clause, which provided:
    “There are no terms, conditions or obligations made or
    entered into by the parties other than as contained herein.
    This agreement, upon execution, shall supersede any
    and all other employment and compensation agreements
    between the Corporation and the Employee.”
    Also important to this opinion, there was no arbitration
    clause in the 2009 agreement. In fact, the agreement
    included several provisions that indicated that the parties
    anticipated that disputes “under” or “arising out of” or to
    “enforce” the 2009 agreement would be resolved through a
    “lawsuit,” “suit,” or sometimes “action,” but never referenced
    arbitration. The mandated venue for any such “suit” was
    Multnomah County.
    Later, in 2014, plaintiff began to work with defen-
    dants Smart Choice Payments, Inc., and North American
    Processing Solutions, LLC. Plaintiff has never had an arbi-
    tration agreement with either entity.
    In February 2017, plaintiff filed an action in
    Washington County against defendants. Plaintiff alleged
    that he had been terminated in September 2015 and had
    not been paid the “future” commissions and residuals that
    defendants had promised to pay him when defendants
    received ongoing payments for merchant-processing services
    638                 Warren v. Smart Choice Payments, Inc.
    and equipment that plaintiff or his team had originally
    arranged to sell or rent to defendants’ customers. Plaintiff
    alleged claims for breach of contract, unjust enrichment, and
    fraud. As to the breach of contract claim, plaintiff alleged
    the promises that were breached, but did not make clear
    whether he was claiming defendants’ breach of a particular
    written or oral agreement. Plaintiff later filed an amended
    complaint that continued to identify the promises that were
    breached but did not identify a particular contract, such as
    the 2008 or 2009 agreement or some other agreement. After
    that filing, defendants deposed plaintiff. Plaintiff testified
    that the 2008 agreement provided at least a “portion” of the
    support for his claim that he had been promised to be paid
    future commissions and residuals for the sales and rentals
    that he had arranged to make to defendants’ customers.
    Defendants then petitioned to stay the litigation and
    compel arbitration, contending that plaintiff’s claims arose
    out of the 2008 agreement between Wholesale Merchant
    Services and plaintiff, and, therefore, the claims were sub-
    ject to arbitration under the 2008 agreement’s arbitration
    clause. Plaintiff opposed the petition, contending, among
    other things, that the 2008 agreement’s arbitration clause
    was superseded by the same parties’ 2009 agreement that
    does not provide for arbitration but anticipates potential lit-
    igation. Plaintiff also contended that, if the 2008 agreement
    controlled, it was a contract of adhesion and the arbitration
    clause was unconscionable. As noted above, the trial court
    agreed with both of plaintiff’s arguments and denied the
    petition to compel arbitration and stay the litigation.
    We turn to the legal arguments before us and the
    standard of review. On appeal, the parties reprise the argu-
    ments that they made in the trial court. We review the denial
    of a petition to compel arbitration for legal error. Lumm v.
    CC Services, Inc., 
    290 Or App 39
    , 43, 414 P3d 454 (2018).
    We begin with a brief background on the law gov-
    erning arbitration agreements. As a general rule, arbitra-
    tion agreements that involve interstate commerce are sub-
    ject to federal arbitration law and state contract law. Section
    2 of the Federal Arbitration Act (FAA), in relevant part,
    provides:
    Cite as 
    306 Or App 634
     (2020)                                              639
    “A written provision in * * * a contract evidencing a trans-
    action involving commerce to settle by arbitration a contro-
    versy thereafter arising out of such contract or transaction,
    or the refusal to perform the whole or any part thereof, or
    an agreement in writing to submit to arbitration an exist-
    ing controversy arising out of such a contract, transaction,
    or refusal, shall be valid, irrevocable, and enforceable, save
    upon such grounds as exist at law or in equity for the revo-
    cation of any contract.”
    
    9 USC § 2
    . “Moreover, section 2 is ‘a congressional decla-
    ration of a liberal federal policy favoring arbitration agree-
    ments, notwithstanding any state substantive or procedural
    policies to the contrary.’ ” Gozzi v. Western Culinary Institute,
    Ltd., 
    276 Or App 1
    , 4-5, 366 P3d 743, adh’d to as modified on
    recons, 
    277 Or App 384
    , 371 P3d 1222 (2016) (quoting Moses
    H. Cone Hospital v. Mercury Constr. Corp., 
    460 US 1
    , 24, 
    103 S Ct 927
    , 
    74 L Ed 2d 765
     (1983)). The parties do not dispute
    that section 2 of the FAA governs the arbitration clause at
    issue in the 2008 agreement.
    Section 2 “create[d] a body of federal substantive
    law, which was applicable in state and federal courts.”
    Buckeye Check Cashing, Inc. v. Cardegna, 
    546 US 440
    , 445,
    
    126 S Ct 1204
    , 
    163 L Ed 2d 1038
     (2006) (brackets in orig-
    inal; internal quotation marks omitted). As we explained
    in Lumm after summarizing the relevant United States
    Supreme Court case law, an arbitration agreement may be
    invalidated “based on generally applicable contract defenses
    like fraud or unconscionability, but not on legal rules that
    apply only to arbitration or that derive their meaning from
    the fact that an agreement to arbitrate is at issue.” 
    290 Or App at 44
     (internal quotation marks omitted).
    As noted, the trial court agreed with plaintiff’s
    argument that the 2009 agreement superseded the 2008
    agreement’s arbitration clause and did not require arbitra-
    tion of this dispute. Defendants’ arguments to the contrary
    are threefold, and we address each in turn.2
    First, defendants contend that the trial court erred
    in concluding that the 2009 agreement superseded the 2008
    2
    We note that defendants do not contend that only the arbitrator and not the
    trial court has the authority to decide whether this dispute is arbitrable. As a
    result, we do not reach that issue.
    640                  Warren v. Smart Choice Payments, Inc.
    agreement as it relates to the arbitration clause because the
    2009 agreement does not specifically state that any prior
    arbitration agreements are superseded and is “silent as to
    arbitration.” As we explain below, that argument ignores
    the clear text of the 2009 agreement, which provides that
    it “shall supersede any and all other employment and
    compensation agreements between the Corporation and
    the Employee.” Indeed, defendants concede that the 2008
    agreement is a compensation agreement. That concession
    is appropriate because the 2008 agreement has a section
    addressing the payment of fees to plaintiff and references a
    schedule with a “compensation plan.” The 2008 agreement
    is a compensation agreement.
    Plaintiff contends that the 2009 agreement is a
    partially integrated writing that supersedes inconsistent
    terms in prior agreements, including those in the 2008
    agreement. Plaintiff notes that the 2009 agreement, which
    anticipates the possibility of litigation and does not require
    arbitration, is inconsistent with the 2008 agreement’s arbi-
    tration clause. Defendants agree that the 2009 agreement is
    a partial integration. Defendants contend, however, that the
    2009 agreement is “silent as to arbitration” and, therefore,
    is not inconsistent with and does not supersede the 2008
    arbitration clause.
    We assume for this appeal, as the parties do, that
    the 2009 agreement is a partial integration. “A partially
    integrated writing is one that the parties intended to be a
    final expression as to the terms in the writing, but not as
    to all the terms of their agreement.” Abercrombie v. Hayden
    Corp., 
    320 Or 279
    , 288, 
    883 P2d 845
     (1994) (emphasis in
    original). As the Supreme Court has stated,
    “[a] partial integration may not be contradicted, but it may
    be supplemented by evidence of prior consistent, additional
    terms. A partially integrated writing supersedes or dis-
    charges all prior agreements, written or oral, to the extent
    that the prior agreements are inconsistent with the partial
    integration.”
    
    Id. at 289
     (citations omitted). The terms of the 2009 agree-
    ment do not include an arbitration clause, but anticipate
    the possibility of a “lawsuit” or “suit” or “action” to resolve
    Cite as 
    306 Or App 634
     (2020)                                              641
    disagreements. Venue for such a “suit” was in Multnomah
    County. Those terms, individually and collectively in the
    agreement, unambiguously indicate that disputes will be
    resolved by litigation in court and not through a less formal
    proceeding before an arbitrator or arbitration panel. The
    terms of the 2009 agreement are entirely inconsistent with
    and supersede the 2008 arbitration clause. Those terms are
    not silent as to arbitration, as defendants claim, but are
    inconsistent with arbitration.3
    We turn to defendants’ second argument, that the
    2008 arbitration clause was not superseded because the
    2008 agreement provides that the dispute resolution and
    arbitration sections of that agreement, among several other
    sections, “shall survive termination of this [a]greement.”
    Defendants’ second argument fails for the same reason as
    its first. To the extent that defendants contend that the arbi-
    tration section survives the 2008 agreement, that obligation
    is entirely inconsistent with the 2009 integration clause,
    which states that there are no other obligations between the
    parties and that the 2009 agreement supersedes all prior
    agreements. As discussed above, an ongoing arbitration
    agreement is also inconsistent with the terms of the 2009
    agreement that does not discuss arbitration and anticipates
    that litigation in court will be used to resolve disputes.
    Defendants’ third and final argument is that, if we
    conclude that the compensation terms of the 2008 agree-
    ment survive, we must also conclude that the 2008 arbitra-
    tion clause survives. They further contend that, if we were
    to do otherwise, we would disfavor arbitration agreements
    in violation of federal law. We do not decide which terms of
    the two compensation agreements control or what evidence
    may be admitted to prove plaintiff’s employment compensa-
    tion terms. That issue is not before us and was not litigated
    in the trial court. Indeed, the specific compensation sched-
    ule to the 2008 agreement is not part of our record. Further,
    the 2009 agreement has no defined compensation terms
    3
    Both parties rely on case law from federal and other state jurisdictions.
    Those cases are dependent on the particular initial and superseding agreements
    at issue as well as the agreements’ specific arbitration and integration clauses.
    Although instructive, they do not persuade us either way in interpreting the
    agreements before us under Oregon law.
    642                  Warren v. Smart Choice Payments, Inc.
    outside of a general reference that the consideration for the
    agreement includes “compensation or other monies paid or
    to be paid to [plaintiff] by Wholesale Merchant Processing.”
    There is no record in the trial court yet of plaintiff’s compen-
    sation terms, and the court did not decide what terms con-
    trol. That issue remains to be decided based on the factual
    record developed on remand.
    Defendants, nevertheless, contend that it would dis-
    favor arbitration and hold arbitration clauses to more exact-
    ing scrutiny in violation of the FAA if the arbitration clause
    in the 2008 agreement were superseded and not carried for-
    ward with the compensation terms that defendants contend
    were bound up with the arbitration clause. In other words,
    defendants contend that, if the 2008 arbitration clause is
    superseded, then any 2008 agreed compensation terms are
    similarly superseded because they must be placed on equal
    footing under federal arbitration law.
    Plaintiff contends that, because the 2009 agree-
    ment is not fully integrated and not in conflict with the 2008
    agreement as to compensation, any evidence of compensa-
    tion in 2008 remains relevant to what the parties agreed
    as to compensation in 2009. That is, plaintiff contends that,
    because the 2009 agreement left the precise compensation
    terms undefined, the 2008 agreement can at least be used
    as evidence for determining what promises were made to
    him regarding compensation at that time.
    We reject defendants’ final argument as well. As we
    observed earlier, an arbitration agreement may be invali-
    dated “based on generally applicable contract defenses like
    fraud or unconscionability, but not on legal rules that apply
    only to arbitration or that derive their meaning from the
    fact that an agreement to arbitrate is at issue.” Lumm, 
    290 Or App at 44
     (internal quotation marks omitted). The rules
    surrounding integrated agreements and integration clauses
    derive from the parol evidence rule, which is a substantive
    rule in contract law. Abercrombie, 
    320 Or at 286
    . Those
    rules reflect long-established and generally applicable con-
    tract principles. See Hatley v. Stafford, 
    284 Or 523
    , 530, 
    588 P2d 603
     (1978) (tracing the roots of the parol evidence rule,
    now adopted by statute, back to the law governing contracts
    Cite as 
    306 Or App 634
     (2020)                             643
    made under the “King’s seal,” which made the document
    uncontestable). They are not legal rules that apply to or tar-
    get only arbitration clauses or derive their particular mean-
    ing from the fact that an arbitration agreement is at issue.
    Although we do not decide the compensation terms between
    the parties, we conclude that our application of the parol evi-
    dence rule and its rules regarding integrated agreements
    are generally applicable contract principles and do not
    require us to conclude that the 2009 agreement supersedes
    the 2008 agreement’s compensation terms, whatever they
    may be, merely because we conclude that the 2009 agree-
    ment is in conflict with and supersedes the 2008 arbitration
    clause.
    In sum, we reject each of defendants’ arguments
    and conclude that the trial court did not err when it denied
    defendants’ petition to arbitrate this dispute.
    Affirmed.
    

Document Info

Docket Number: A166758

Citation Numbers: 306 Or. App. 634

Judges: Shorr

Filed Date: 9/23/2020

Precedential Status: Precedential

Modified Date: 10/10/2024