Development Northwest, Inc. v. Zhiryada ( 2023 )


Menu:
  • No. 642             December 6, 2023                   427
    This is a nonprecedential memorandum opinion
    pursuant to ORAP 10.30 and may not be cited
    except as provided in ORAP 10.30(1).
    IN THE COURT OF APPEALS OF THE
    STATE OF OREGON
    DEVELOPMENT NORTHWEST, INC.,
    an Oregon corporation,
    dba Wolcott Plumbing,
    Plaintiff-Appellant,
    v.
    Valeriy ZHIRYADA,
    an individual;
    Valentina Zhiryada, an individual;
    and NORTHWEST FREIGHT, LLC,
    a Washington limited liability company,
    Defendants-Respondents,
    and
    VALLEY PACIFIC CONSTRUCTION, INC.,
    an Oregon corporation;
    and KEITH MINTER, INC.,
    an Oregon corporation,
    dba Jade Smith Paving,
    Defendants.
    Multnomah County Circuit Court
    19CV13524; A176707
    Christopher J. Marshall, Judge.
    Argued and submitted September 6, 2023.
    Thomas M. Christ argued the cause and filed the briefs
    for appellant. Also on the briefs was Sussman Shank LLP.
    Geoffrey B. Silverman argued the cause and filed the
    brief for respondents. Also on the brief was The Law Office
    of Geoffrey B. Silverman, LLC.
    Before Shorr, Presiding Judge, and Mooney, Judge, and
    Pagán, Judge.
    428               Development Northwest, Inc. v. Zhiryada
    SHORR, P. J.
    Reversed and remanded as to plaintiff’s lien foreclosure
    claim; otherwise affirmed.
    Nonprecedential Memo Op: 
    329 Or App 427
     (2023)                               429
    SHORR, P. J.
    Following a bench trial, plaintiff appeals from a
    judgment dismissing its claim for construction lien foreclo-
    sure. In a single assignment of error, plaintiff asserts that
    the trial court erred in dismissing plaintiff’s lien foreclosure
    claim because, according to plaintiff, the construction work
    invoices that plaintiff presented to defendant were due and
    payable and defendant failed to tender adequate payment
    such that defendant could avoid the enforcement of plain-
    tiff’s construction lien. We agree and conclude that the trial
    court erred in holding that defendant’s proffered check was
    an unconditional and adequate payment to plaintiff. Rather,
    defendant’s check was improperly conditioned on plaintiff’s
    potential release of a construction lien for plaintiff’s work
    on defendant’s property for which plaintiff had not yet been
    paid. As a result, we reverse and remand for further pro-
    ceedings on the construction lien claim.1
    The dispute arose out of plumbing subcontract
    work plaintiff provided to defendant on a major commercial
    construction project. Defendant contracted with a primary
    contractor, E&M Constructors, which subsequently subcon-
    tracted with plaintiff. The contract between defendant and
    E&M Constructors provided for defendant to pay subcon-
    tractors directly.
    Following the completion of its work, plaintiff sent
    two invoices to defendant: one for “finishing work” in the
    amount of $13,050; and one for “Change Order 6 work” for
    the plumbing work on a truck washing installation, in the
    amount of $39,530. Both invoices were sent on December 19,
    2018, and had a due date of January 10, 2019. On February
    12, 2019, defendant sent plaintiff a check for $13,050, along
    with a lien waiver form that stated:
    “The undersigned acknowledges receipt of a progress
    payment in the amount of $13,050.00 and in consideration
    of such payment, does hereby release any rights to collection,
    mechanics lien, stop notice, or bond right that the undersigned
    1
    Plaintiff also brought breach of contract and quantum meruit claims, which
    were tried to a jury. The jury found in plaintiff’s favor on the breach of contract
    claim. The merits of that claim have not been challenged on appeal. We therefore
    affirm those portions of the judgment resulting from the jury’s verdict.
    430                     Development Northwest, Inc. v. Zhiryada
    has on the above-referenced job, not just claims paid by this
    check, to the following extent. This release covers a progress
    payment for labor, service, equipment, or materials fur-
    nished to Northwest Freight project through __________[2]
    only and does not cover any retentions retained before or
    after the release date; extras furnished before the release
    date for which payment has not been received; extras or
    items furnished after the release date. Rights based upon
    work performed or items furnished under a written change
    order which has been fully executed by the parties prior to
    the release date are covered by this release unless specifi-
    cally reserved by the claimant in this release.
    “* * * * *
    “NOTICE: THIS DOCUMENT WAIVES RIGHTS
    UNCONDITIONALLY AND STATES THAT YOU HAVE
    BEEN PAID FOR GIVING UP THESE RIGHTS. THIS
    DOCUMENT IS ENFORCEABLE AGAINST YOU IF
    YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID.
    IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL
    RELEASE FORM.”
    (Uppercase in original; emphases added.).
    Plaintiff declined to sign the form because it did not
    specifically reserve rights for plaintiff to be paid for work
    associated with the Change Order 6 invoice. Plaintiff con-
    tacted its attorney, and obtained an alternative waiver form,
    which acknowledged the $13,050 payment on the finishing
    work invoice and released plaintiff’s lien on the property for
    that work and up to that amount, but reserved all rights,
    including lien rights, on the unpaid Change Order 6 invoice.
    Plaintiff’s attorney emailed the alternative waiver to defen-
    dant owner Valentina Zhiryada, stating:
    “Last week [plaintiff] received a check for $13,050.00
    and a form of unconditional waiver, copies of which are
    attached. [Plaintiff] construes your tender of the $13,050.00
    payment as being conditioned on [plaintiff] signing and
    returning the unconditional waiver. [Plaintiff] is unwilling
    to sign the unconditional waiver, because it is not condi-
    tioned on the check clearing and also includes language
    that may result in [plaintiff] waiving or adversely affecting
    2
    The blank was not filled in. In previous versions of the form accompanying
    prior payments, a date was hand-written into the blank.
    Nonprecedential Memo Op: 
    329 Or App 427
     (2023)                             431
    its lien rights for other amounts owed to [plaintiff] on this
    project.
    “Also attached [is] a ‘Waiver of Right to Lien - Unsigned
    (2-16-19)’, which [plaintiff] is willing to sign and return
    to you when it deposits the $13,050.00 check. However,
    we need your written confirmation (your reply e-mail is
    sufficient) that * * * this lien waiver is acceptable to you.
    * * * If I do not receive your confirming e-mail by close of
    business on 2/20/19, [plaintiff] will conclude the waiver of
    right to lien is not acceptable to you, and in that event the
    $13,050.00 check will be mailed back to you.”
    Zhiryada replied that she understood the parties to still
    be in negotiations about the Change Order 6 invoice, and
    otherwise responded to the email as follows: “I need You to
    sign a Waiver that I sent You together with my Check #1307
    for $13,050.00 and email it back to Me, please.” Plaintiff did
    not cash the check. Instead, it returned the check to defen-
    dant, recorded its lien with the county, and filed this action
    to foreclose the lien.
    The lien foreclosure claim was tried to the court. The
    trial court concluded that defendant’s $13,050 check was “an
    unconditional tender” and that “[t]he payment for the fin-
    ishing work was not conditional on the execution of the lien
    waiver[.]” Because the check was “good tender” that plain-
    tiff rejected, the trial court concluded that the tender cut
    off consequences of nonpayment, and plaintiff was therefore
    not entitled to foreclose on the lien for the $13,050 invoice.
    The court further determined that, under the terms of the
    subcontract, completion of a lien waiver for the $13,050 pay-
    ment was a condition precedent for payment of the follow-
    ing invoice for the Change Order 6 work, and that, because
    plaintiff had not accepted payment and executed such a lien
    waiver, the Change Order 6 invoice was not presently due
    and was therefore not subject to foreclosure. The trial court
    thus entered judgment in favor of defendant.3
    3
    The trial court later entered a supplemental judgment awarding plain-
    tiff attorney fees based on plaintiff prevailing before the jury on its breach of
    contract claim. Defendant has appealed that supplemental judgment, which is
    before us in a separate appeal that we affirm today in Development Northwest,
    Inc. v. Zhiryada (A178102), 
    329 Or App 439
     (2023) (nonprecedential memoran-
    dum opinion).
    432                Development Northwest, Inc. v. Zhiryada
    The issues as presented by the parties on appeal are
    whether defendant tendered adequate unconditional pay-
    ment for the finishing work invoice and whether the Change
    Order 6 invoice was due and payable. We review the trial
    court’s legal conclusions for legal error and its factual find-
    ings to determine whether those findings are supported by
    any evidence in the record. Vukanovich v. Kine, 
    268 Or App 623
    , 633, 342 P3d 1075, adh’d to as modified on recons, 
    271 Or App 133
    , 349 P3d 567 (2015).
    We agree with plaintiff that the trial court erred
    in concluding that defendant’s $13,050 check was uncon-
    ditional. Under lien foreclosure law, a property owner may
    demand that a contractor waive all lien rights “as to mate-
    rials or supplies for which payment has been made.” ORS
    87.025(5). Under that law, a property owner may not demand
    a lien waiver from a contractor who has not been paid for
    that work unless the “language of the waiver [brings] home
    to the supplier what he is releasing.” Portland Elec. & Plum.
    v. Simpson, 
    59 Or App 486
    , 490, 
    651 P2d 172
     (1982), adh’d to
    on recons, 
    61 Or App 266
    , 
    656 P2d 394
    , rev den, 
    294 Or 682
    (1983). Otherwise, the “person making payment is entitled
    to a waiver of a lien only as to materials or supplies already
    paid for.” 
    Id.
    Defendant was, thus, permitted to demand a
    broader release, but plaintiff was not obligated to, and in
    fact did not, agree to that broader language. Oregon sub-
    scribes to the objective theory of contracts, which provides
    that the existence and terms of a contract are determined by
    objective evidence of the parties’ communications and acts.
    Rhoades v. Beck, 
    260 Or App 569
    , 572, 320 P3d 593 (2014).
    We conclude that the parties’ objective actions demonstrate
    that defendant’s offer of the $13,050 check was conditioned
    on plaintiff signing defendant’s broadly stated lien waiver
    form, and that plaintiff declined to agree to that broad lien
    waiver language. The check and the waiver form were sent
    together. The form stated: “The undersigned acknowledges
    receipt of a progress payment in the amount of $13,050.00
    and in consideration of such payment, does hereby release
    any rights * * * not just claims paid by this check to the fol-
    lowing extent.” (Emphases added.) The remainder of the
    Nonprecedential Memo Op: 
    329 Or App 427
     (2023)                             433
    form includes a blank that does not identify or limit the
    date through which the release covers and does not other-
    wise identify which work the payment covers. The form thus
    indicated that the payment, while being made in exchange
    for the work completed, was also being offered in exchange
    for plaintiff’s unconditional waiver of all lien rights. Even to
    the extent that defendant’s form could be ambiguous as to
    the extent of the release, which defendant does not argue,
    plaintiff’s attorney then proposed a more limited release to
    clarify that plaintiff would release a lien for the finishing
    work reflected in the finishing work invoice, in the amount
    of $13,050. Plaintiff’s counsel then explicitly stated in his
    email to defendant that plaintiff construed the check “as
    being conditioned on [plaintiff] signing and returning the
    unconditional waiver.” Defendant did nothing to dispel that
    assumption, and indeed responded that plaintiff needed
    to sign the broad waiver that was sent with the check.
    Defendant did not address plaintiff’s proffered alternative
    and more limited waiver.
    We conclude that the only reasonable objective
    interpretation of those acts, none of which are factually
    disputed, is that the check was not an unconditional pay-
    ment, but was instead conditioned on plaintiff signing the
    broadly worded lien waiver form sent by defendant. Plaintiff
    was not obligated to accept the broad waiver under ORS
    87.025, and it did not do so. Defendant takes the position on
    appeal that plaintiff could have cashed the check outright
    without signing any waiver, or could have amended the
    waiver by indicating it was reserving its rights with respect
    to the Change Order 6 work; however, those options were
    not communicated to plaintiff at the time the dispute arose,
    and defendant’s actions and statements viewed objectively
    demonstrate otherwise. The trial court therefore erred in
    concluding that the check was unconditional and was there-
    fore adequate tender that plaintiff rejected.4
    4
    The trial court’s additional conclusion that payment was not due on the
    Change Order 6 invoice was premised on its erroneous conclusion regarding the
    conditional nature of the $13,050 check. We therefore do not need to address
    the parties’ further dispute about plaintiff’s obligation to provide lien waivers
    as a condition precedent for future payments, because defendant did not tender
    unconditional payment for the finishing work invoice.
    434                      Development Northwest, Inc. v. Zhiryada
    Because defendant failed to tender adequate pay-
    ment for either invoice, both of which were due and payable,
    the trial court erred in dismissing plaintiff’s lien foreclosure
    claim.5
    Reversed and remanded as to plaintiff’s lien fore-
    closure claim; otherwise affirmed.
    5
    As the trial court noted, there was no controversy regarding the timeliness
    of the filing of the liens and the service of related notices. On remand, the trial
    court will need to make fact findings regarding the precise amount of the lien
    foreclosure.
    

Document Info

Docket Number: A176707

Judges: Shorr

Filed Date: 12/6/2023

Precedential Status: Non-Precedential

Modified Date: 10/16/2024