Golden Rule Farms v. Water Resources Dept. ( 2022 )


Menu:
  •                                       43
    Argued and submitted February 10, affirmed July 27, 2022
    GOLDEN RULE FARMS, INC.,
    Petitioner,
    v.
    OREGON WATER RESOURCES DEPARTMENT,
    Respondent.
    Oregon Water Resources Department
    G16867, G17578;
    A172879 (Control), A172880
    515 P3d 908
    Petitioner applied for extensions of two groundwater permits under ORS
    537.630 and OAR 690-315-0040. The Oregon Water Resources Department
    (OWRD) issued proposed final orders denying those extensions and advising that
    petitioner was entitled to protest the denials as allowed under OAR 690-315-
    0100 and OAR 690-315-0060. Petitioner did not initiate the protest procedure
    and OWRD issued final orders denying each extension. Petitioner petitioned
    OWRD to reconsider its final orders, which ORWD did not act on, resulting in
    the petition being denied by operation of law. Petitioner initiated this judicial
    review proceeding under ORS 183.482. After petitioner initiated this review,
    OWRD withdrew its final orders under ORS 183.482(6), then issued orders on
    reconsideration in which it modified several findings of fact. Held: The Court of
    Appeals affirmed because petitioner failed to exhaust administrative remedies
    by employing the protest procedure. To the extent that the protest procedure was
    not available to challenge the modified findings on reconsideration, petitioner’s
    arguments fail on the merits.
    Affirmed.
    Sara Kobak argued the cause for petitioner. Also on the
    briefs were Elizabeth E. Howard, Shonee Langford, and
    Schwabe, Williamson & Wyatt, P.C.
    Inge D. Wells, Assistant Attorney General, argued the
    cause for respondent. Also on the brief were Ellen F. Rosenblum,
    Attorney General, and Benjamin Gutman, Solicitor General.
    Lisa A. Brown filed the brief amicus curiae for WaterWatch
    of Oregon.
    Before Ortega, Presiding Judge, and Lagesen, Chief Judge,
    and Powers, Judge.
    44               Golden Rule Farms v. Water Resources Dept.
    LAGESEN, C. J.
    Affirmed.
    Cite as 
    321 Or App 43
     (2022)                                45
    LAGESEN, C. J.
    Petitioner holds multiple groundwater permits in
    Harney County. This case involves two of those permits.
    When petitioner failed to complete construction of the wells
    authorized by the relevant permits or apply the water to
    beneficial use by the deadlines specified in the permits, peti-
    tioner applied for extensions under ORS 537.630 and OAR
    690-315-0040. The Oregon Water Resources Department
    (OWRD) issued final orders denying those extensions and
    petitioner initiated this judicial review proceeding under
    ORS 183.482. After petitioner initiated this proceeding,
    OWRD withdrew its final orders under ORS 183.482(6), and
    then issued orders on reconsideration in which it modified
    several findings of fact. We affirm because petitioner failed
    to exhaust administrative remedies and to the extent peti-
    tioner challenges the modified findings on reconsideration,
    those challenges fail.
    The relevant facts are mostly procedural and not
    disputed. Any substantive facts are drawn from the uncon-
    tested factual findings in the orders on review. Klein v.
    BOLI, 
    317 Or App 138
    , 506 P3d 1108, rev den, 
    369 Or 705
    (2022).
    As noted, this case involves two groundwater per-
    mits: G-17441 and G-17100. Both are for groundwater within
    the Greater Harney Valley Groundwater Area of Concern
    (GHVGAC). OWRD issued Permit G-17441 in 2015, autho-
    rizing “the use of up to 2.0 cfs of water from three wells in
    Malheur Lake Basin for irrigation use on 160 acres.” The
    permit superseded a prior permit for which construction
    had not been completed. When G-17441 was issued, the com-
    pletion date for construction and application of water was
    October 1, 2018. Permit G-17100 had a similar trajectory.
    OWRD issued G-17100 on October 31, 2013. It authorized
    the use of up to 4 cfs of water from two wells in Malheur
    Lake Basin for irrigation of 320 acres. It specified a com-
    pletion date for construction and “complete application of
    water” by October 31, 2018. Between the dates the permits
    issued and the specified completion dates, no action was
    taken to begin construction on the wells authorized by the
    permits.
    46            Golden Rule Farms v. Water Resources Dept.
    In March 2017, petitioner submitted Permit Amend-
    ment T-12609 to OWRD. That application sought to amend
    both permits at issue in this case. With respect to both, it
    sought to change the place of use and places of appropriation
    authorized under the permits to other locations within the
    GHVGAC. In September 2018, OWRD notified petitioner by
    letter that it could not process the application “without an
    active completion date” for Permits G-17441 and G-17100.
    It advised that petitioner needed to seek—and obtain—
    approval of extensions of time for those permits for OWRD to
    approve the amendment application. OWRD did not receive
    a response to its September letter and denied the amend-
    ment application on November 7, 2018, on the ground that
    petitioner was “unable to complete the application of the
    water to beneficial use” as required under the permits and
    “[w]ithout current dates for complete application of water,”
    OWRD could not approve the amendment.
    On November 19, 2018, petitioner submitted the
    extension requests at issue in this case, seeking to extend
    the completion dates of both permits to October 1, 2019. After
    a notice-and-comment period, OWRD issued proposed final
    orders denying both requested extensions in April 2019. The
    proposed final orders advised that petitioner was entitled to
    protest the denials as allowed under OAR 690-315-0100 and
    OAR 690-315-0060 by filing a written protest with OWRD
    by May 31, 2019. Petitioner did not protest either proposed
    final order and, on June 14, 2019, OWRD issued final orders
    denying each extension. In the final orders, as it had in
    the proposed final orders, OWRD determined that “[t]he
    applicant has not demonstrated good cause for the permit
    extension pursuant to ORS 537.630, 539.010(5) and OAR
    690-315-0040(2).”
    Almost two months later, petitioner petitioned OWRD
    to reconsider its final orders. It asserted that OWRD “did
    not act in good faith or in a timely manner during the
    review process” of permit amendment T-12609 and that, but
    for OWRD’s alleged failure to act in good faith, petitioner
    would not have required extensions. OWRD did not act on
    the petition, and it was deemed denied by operation of law.
    ORS 183.482(1).
    Cite as 
    321 Or App 43
     (2022)                                47
    Petitioner sought judicial review. After petitioner
    filed its opening brief, OWRD withdrew the final orders for
    reconsideration under ORS 183.482(6) and filed orders on
    reconsideration that modified several factual findings but
    otherwise adhered to the original orders denying the exten-
    sions. Petitioner then filed a supplemental brief, in which it
    challenged several of the modified findings.
    On review, petitioner argues that, in determining
    that it did not demonstrate “good cause” for the permit
    extensions, OWRD “acted contrary to statute and outside of
    the range of its permissible discretion.” Petitioner contends
    that OWRD should not have considered its failure to com-
    plete construction of the wells authorized by the permits
    because petitioner “sought the extensions solely to apply
    the groundwater to beneficial use under the permits,” and
    was not seeking to build the wells. Petitioner also argues
    that OWRD erred when it did not take into account “its
    own unexplained 14-month delay in processing” the permit
    amendments requested in T-12609, pointing to the require-
    ment in ORS 537.630(2) that OWRD must consider the
    extent to which “other governmental requirements relating
    to the project have significantly delayed completion of con-
    struction or perfection of the right.” ORS 537.630(2). Finally,
    petitioner asserts that various factual findings, including
    some of the modified findings included in OWRD’s orders on
    reconsideration, are not supported by substantial evidence.
    OWRD responds that petitioner’s contentions are
    not reviewable because petitioner did not exhaust admin-
    istrative remedies by employing the protest procedure, and
    also because petitioner did not preserve the issues by rais-
    ing them with OWRD in the first instance. OWRD other-
    wise argues that its order reflects a proper understanding
    of ORS 537.630(2), and that its findings are supported by
    substantial evidence.
    With one exception, we agree with OWRD that peti-
    tioner failed to exhaust administrative remedies and that
    that failure precludes review of the bulk of petitioner’s
    arguments to us. As the Supreme Court has explained, “[t]he
    general doctrine of exhaustion of administrative remedies
    is judicially created, a creature of the common law, and is
    48             Golden Rule Farms v. Water Resources Dept.
    employed by the courts * * * in the interest of orderly pro-
    cedure and good administration.” Tuckenberry v. Board of
    Parole, 
    365 Or 640
    , 646, 451 P3d 227 (2019). In general,
    where, as here, an agency provides a process for raising
    issues to it, the doctrine requires a party to present the
    issue to the agency through that process before a court
    will consider it. 
    Id.
     Pertinent to this case, “[a] party does
    not exhaust his administrative remedies simply by stepping
    through the motions of the administrative process without
    affording the agency an opportunity to rule on the substance
    of the dispute. Exhaustion of administrative remedies is not
    accomplished through the expedience of default.” Mullenaux
    v. Dept. of Revenue, 
    293 Or 536
    , 541, 
    651 P2d 724
     (1982).
    OWRD has a well-established administrative pro-
    cess through which applicants and others “adversely affected
    or aggrieved” by a proposed order on an extension request
    can “protest” the order with the agency. OAR 690-315-0060.
    That process enables a person to supply “a detailed descrip-
    tion of how the proposed final order is in error or deficient
    and how to correct the alleged error or deficiency,” OAR 690-
    315-0060(2)(d), along with any applicable legal authority
    supporting the claim of error. OAR 690-315-0060(2)(e). It is
    undisputed that petitioner was given notice of that process,
    yet petitioner failed to use it to raise the issues that petitioner
    now seeks to raise in this court. We would, of course, have
    the discretion to “relax or set aside” the exhaustion require-
    ment should the circumstances warrant it, Tuckenberry, 365
    Or at 647. But petitioner has offered no convincing reason as
    to why we should do that here.
    Petitioner suggests that, notwithstanding its fail-
    ure to invoke the protest process, we should conclude that
    petitioner adequately exhausted administrative remedies
    by filing a petition for reconsideration later. We often have
    concluded that a party cannot preserve an issue for appeal
    by raising it for the first time in a motion for reconsider-
    ation when the party had an opportunity to raise it earlier.
    Sugiyama v. Arnold, 
    294 Or App 546
    , 549-50, 431 P3d 466
    (2018). We think it appropriate to apply an analogous princi-
    ple in the exhaustion context, at least where, as here, a peti-
    tioner failed to invoke the designated process for presenting
    issues to the agency, and the agency exercises its discretion
    Cite as 
    321 Or App 43
     (2022)                                49
    not to act on a subsequent petition for reconsideration. We
    likewise are not persuaded by petitioner’s related sugges-
    tion that it need not have exhausted its administrative
    remedies through the protest process, as distinct from the
    reconsideration process, because administrative rules, not
    statutes, are the source of the protest requirement for orders
    on extensions. Having been provided with a well-defined
    process to raise its issues to OWRD in the first instance,
    it was incumbent on petitioner to use that process, absent
    unusual circumstances.
    This conclusion—that petitioner failed to exhaust
    administrative remedies—disposes of the issues raised
    in the opening brief, which could have been raised in the
    protest process. But it does not complete the resolution of
    this case. As noted, after petitioner filed its opening brief
    in this matter, OWRD withdrew its final orders under ORS
    183.482(6) and filed revised orders in this court in which it
    modified several factual findings. Petitioner then filed a sup-
    plemental brief contesting some of those findings. As should
    be evident, those modifications occurred when the protest
    process was no longer available to petitioner. Consequently,
    petitioner had no opportunity to raise any challenges to the
    modified findings through the protest process. Rather, this
    proceeding presents petitioner’s first opportunity to chal-
    lenge those modifications; petitioner had no administrative
    remedies available to exhaust. That means the exhaustion-
    of-administrative-remedies doctrine does not apply to bar
    review of petitioner’s challenges to the modifications.
    As for the merits of petitioner’s challenges to the
    modified findings, we conclude that those findings are sup-
    ported by substantial evidence—that is, that “the record,
    viewed as a whole, would permit a reasonable person to
    make” those findings, ORS 183.482(8)(c).
    Affirmed.
    

Document Info

Docket Number: A172879

Judges: Lagesen

Filed Date: 7/27/2022

Precedential Status: Precedential

Modified Date: 10/10/2024